FIDIC EPC Contract Example
FIDIC EPC Contract Example
FIDIC EPC Contract Example
Engineering, Procurement
& Construction Contract
23-11-2012/JOH
1 EPC Contract
Engineering, Procurment & Construction Contract
1. GENERAL PROVISION
2. THE EMPLOYER
3. THE EMPLOYER’S ADMINISTRATION
4. THE CONTRACTOR
5. DESIGN
6. STAFF AND LABOUR
7. PLANT, MATERIALS AND WORKMANSHIP
8. COMMENCEMENT, DELAYS AND SUSPENSION
9. OPERATION TEST RUN AND TESTS BEFORE
TAKING-OVER
10. EMPLOYER’S TAKING-OVER
11. DEFECTS LIABILITY
12. TESTS AFTER COMPLETION
13. VARIATION AND ADJUSTMENTS
14. CONTRACT PRICE AND PAYMENT
15. TERMINATION BY EMPLOYER
16. SUSPENSION AND TERMINATION BY CONTRACTOR
17. RISK AND RESPONSIBILITY
18. INSURANCE
19. FORCE MAJEURE
20. CLAIMS DISPUTES AND ARBITRATION
23-11-2012/JOH
2 EPC Contract
SCHEDULE 1
23-11-2012/JOH
3 EPC Contract
APPENDIX 1 - EMPLOYER’S REQUIREMENTS
23-11-2012/JOH
5 EPC Contract
APPENDIX 1 - EMPLOYER’S REQUIREMENTS
23-11-2012/JOH
6 EPC Contract
APPENDIX 1 - EMPLOYER’S REQUIREMENTS
23-11-2012/JOH
7 EPC Contract
APPENDIX 2 – FORM OF PERFORMANCE BOND
23-11-2012/JOH
8 EPC Contract
APPENDIX 3 – FORM OF WARRANTY BOND
23-11-2012/JOH
9 EPC Contract
APPENDIX 4 – OPERATION TEST RUN
CONDITIONS
The four (4) weeks Test Run period shall take place within
ninety (90) days following issuance of the last Certificate of
Start-Up Acceptance. Within the aforesaid timeframe the
Contractor is entitled to utilise the period before start of the
Test Run for tuning and adjustments at full discretion of the
Contractor.
The Operation Test Run period will be four (4) weeks during
which time the seventy-two (72) hours uninterrupted Fiberline
Capacity Test Run shall take place according to criteria specified
in Appendix 5.
During the four weeks Operation Test Run period the average
production measured at the baling lines of the Pulp Dryer shall
be at least seventy percent (70 %) of the Fiber Line design rate
(2 700 ADt/d).
23-11-2012/JOH
10 EPC Contract
APPENDIX 4 – OPERATION TEST RUN
CONDITIONS
During the Operation Test Run period, excluding the Fiber Line
Capacity Test Run period, an unlimited number of interruptions
attributable to the Contractor are permitted. There are neither
any limitations regarding the durations of the interruptions.
Should the average production requirement (52 920 ADt) during
the Operation Test Run be not fulfilled the verification period will
be shifted ahead until the requirement is met. However, the
Operation Test Run shall be carried out within six (6) months
from the Start-Up of the Plant.
The Parties shall not less than one (1) month prior to the
scheduled Operation Test Run, draw up an advance plan for
carrying out the Operation Test Run of the Plant. Requirement
of material and personnel for the Operation Test Run shall be
defined in the plan in detail.
23-11-2012/JOH
11 EPC Contract
APPENDIX 5 – FIBER LINE CAPACITY TEST RUN
CONDITIONS
After the Operation Test Run and Fiber Line Capacity Test Run
has been accepted, a Taking-Over Certificate will be issued.
The Taking-Over Certificate means minutes prepared by the
Contractor and signed by the Employer in accordance with the
Employer’s Requirements, confirming that the requirements
stipulated for Taking-Over have been met and list possible faults
and defects still detected in the Plant and that the Plant has been
taken over in accordance with the EPC Contract. Faults and
defects (category 3 items on the Punch List) that are not decisive
for the normal Continuous Commercial Operation of the Plant
shall not prevent the signing of the inspection minutes and the
approval of the Fiber Line Capacity Test Run provided that the
Contractor agrees to rectify the faults and defects listed in the
minutes as soon as possible or within an agreed time.
EPS PACKAGES
1.Woodhandling Plant (Metso)
2.Cooking Plant (Metso)
3.Fiberline (Metso)
4.Pulp Dryer (Metso)
5.Evaporation (Metso)
6.Recovery Boiler (Metso)
7.Power Boiler (Metso)
8.Recausticizing (Metso)
9.Lime Kiln (Metso)
23-11-2012/JOH
13 EPC Contract
APPENDIX 7 – PERFORMANCE TEST
PROCEDURES AND PROTOCOL
EPS PACKAGES
1.Woodhandling Plant (Metso)
2.Cooking Plant (Metso)
3.Fiberline (Metso)
4.Pulp Dryer (Metso)
5.Evaporation (Metso)
6.Recovery Boiler (Metso)
7.Power Boiler (Metso)
8.Recausticizing (Metso)
9.Lime Kiln (Metso)
23-11-2012/JOH
14 EPC Contract
APPENDIX 8 – FORM OF ADVANCE PAYMENT
GUARANTEE
23-11-2012/JOH
15 EPC Contract
APPENDIX 9 – SCHEDULE OF PAYMENTS
23-11-2012/JOH
16 EPC Contract
APPENDIX 10 – DISPUTE ADJUDICATION
AGREEMENT
1. Definitions
2. General Provisions
3. Warranties
4. General Obligations of the Member
5. General Obligations of the Employer and the
Contractor
6. Payment
7. Default of the Member
8. Default of the Member
23-11-2012/JOH
17 EPC Contract
APPENDIX 11 – PROCESS AREAS