MSIL Training On VSA Check Sheet
MSIL Training On VSA Check Sheet
MSIL Training On VSA Check Sheet
1
- November is observed as Quality Month every year in MSIL.
Theme Focus :
- Drive Quality in all aspects of business by reviewing rules, training
rules and adhering to defined rules
Quality System
3
Importance of Quality Systems
Quality Problems
System
Non
Adherence
70%
4
Importance of Quality Systems
Serious Quality Problem due to System Non Adherence
System failure
Adherence to Process :-
- Process Control standard (PCS)
- Maruti Inspection Standard (MIS-P)
Adherence to System:-
- Vendor Quality Assurance Manual (VQM)
Quality Systems Assessment by MSIL
MSIL QA-VSA conduct System Audit at Tier 1
Supplier periodically.
Total Clause in Check Sheet: 14
No. of Check Points: 79
Scoring:
Score Criteria
O (Circle) +3 System defined & Implemented
∆ (Traingle) 0 Minor deficiency either in system definition or implementation
X (Cross) -3 Major deficiency either in system definition or implementation
Green
19%
Red
Yellow 18%
63%
14
Clause 1 – Production Preparation
S Sub Clause S Check Point Requirement
No No
2 Regarding 1 Do you implement follow-up to Master Timing plan as per APQP matrix
management / control the schedule and progress Customer events (sample approval, trial
implementatio of production preparation items? dates, SOP at customer end) and
n by production vendor's events (sample submission,
preparation pilot lot submission, SOP)
plan / report Plan Vs Actual updation
(master plan) Micro timing plan matching with
MACRO plan (wrt timing)
Capturing delays in plan v/s actual in
timing plans.
3 Defect 2 Do you review and improve Procedure for FMEA with CFT
prevention on FMEA or Matrix diagrams when approach
the stage of any critical issue occurs after Rating of FMEA as per AIAG
process design SOP?
guidelines and having back up
by using
data for rating. Allocation of
FMEA/Matrix
diagram severity, occurrence & detection as
per AIAG manual
Cut off criteria for taking action as
per latest AIAG manual (actions to
be taken for top 3 RPN processes)
Review of FMEA as per decided
criteria and at decided frequency
• What is It?
FAILURE MODE AND EFFECTS ANALYSIS
(PROCESS FMEA)
Process Step
• Objective or Purpose
Classification
Occurrence
Current Current
Detection
/ Function
Severity
Potential Potential Potential
RPN
Process Process
Failure Effect(s) Causes(s)
Mode of Failure of Failure Controls Controls
6
Clause 1 – Production Preparation
S
Sub Clause S No Check Point Requirement
No
Regulation ② How do you define items required Special controls (increased
2 for special control during initial inspection, increased sample size etc.
initial production control? Do you set at all stages - incoming, in-process &
production stricter inspection methods than the final)
control ordinal inspection?
Scope:
Initial flow control is applicable for newly developed parts or
parts developed after engineering change or after process
change.
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Control period:
For newly developed parts – 3 months or 3000parts (whichever is
later)
For ECN/PCN parts – 1 month or 1000parts
(whichever is later)
ECN PCN
SOP SOP SOP
IFC
IFC
IFC
Production preparation ECN PCN
IMPORTANT!
Always ensure implementation of
IFC in new part & post-SOP
ECN/PCN cases!
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Roles & Responsibility:
Choose responsible information receiver
Choose responsible person who takes countermeasures for defects
Overall
Responsible
Equipment/
Quality Assurance Manufacturing & Delivery
Tools/Jigs
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Special control during IPC period:
Increased or tightened inspection across all inspection stages within the process
Incoming, in-process, doubled inspection for FG parts (Addition Firewall/ IPC station)
Monitoring of Process capability for each product and process
OK . NG
OK . NG
OK . NG
IMPORTANT!
OK . NG
It is necessary to deploy stringent
checks at respective inspection OK . NG
stages
OK . NG
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
OK . NG
1 Customer complaints 0 OK . NG
Result of Initial Production Control OK . NG Initial control checks can be terminated YES . NO
If No, IPC period extended by _______ days, reason for extension ____________________________________________________________
___________________________________________________________________________________________________________________
(please use new sheet for extension period)
End of IPC (Termination)
ENGG PROD PUR PE HOD - QA
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Countermeasure:
Checkpoint when any defect occurs
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasure >> Exit
Clause 2 – Initial Production Control
Initial control period termination conditions:
Initial production control period can be terminated in case if following targets
are achieved:
Zero customer complaints
Zero Firewall/ IPC station defects
Inhouse rejection ppm (less than annual target)
Process capability Cpk>1.67 (or Process performance Ppk)
Effective implementation of countermeasure for production preparation issues
Effective implementation of countermeasure for issues observed during Initial production
control period
This means that the production can be resumed as per normal controls as specified in control plan.
Announcement >> IFC Activity plan >> Target Monitoring >> Countermeasures >> Exit
Clause 3
(4M Change Management)
Clause 3 –Change Management
S S No
Sub Clause Check Point Requirement
No
3.1 Definition and 1 Do you define List of changes that can occur
implementatio unexpected change in process related to 4M.
n of changing (unusual) and planned Distribution of changes into
management change clearly? planned and unplanned
Major Observation:-
4M changes related to man, method and material not
identified clearly.
No clarity on planned and unplanned.
4M
Change
Unplanned
Changes
S S No
Sub Clause Check Point Requirement
No
Major Observation:-
In-house and
Brainstorming Past Defect
customer end
session History
standards
Training
4 M CHANGE CONDITIONS & ACTIONS
Process : Injection Molding, Assembly & Ultrasonic welding
Action Plan
Retroactive
Set up approval
S 4M Inspection
Change Change Detail Cut off criteria in case of Abnormal Situations
No Category (checking of
(checking of parts
parts before &
after change)
after change)
Any da ma ge i n mol d l i fter/i ns erts or hol e After mol d recti fi ca ti on pa rts to be checked for a ppea ra nce &
bl ock i n pa rt a ffected di mens i ons by QA & i f found OK then a l l ow for
Yes Yes producti on.
If any major repair or modification is carried out in mold then
customer approval is required before start of production.
Valve Gate : 5 pa rts . to be checked for pa rt wei ght & vi s ua l l y fo
Ai r pres s ure l ow/hi gh Yes -
a ppea ra nce.
Expected 1. Use of alternate source material from
Yes - Thorough inspection & customer approval is required
(Pl a nned) approved source*
Unexpected 1. Use of alternate source material from Not allowed & Customer approval required. All material to be
Yes Yes
(Unpl a nned) unapproved source* rejected.
3 Ma teri a l
1.) I mmedi a tel y check & get veri fy the s us pected or a ffected l ot
BOP Pa rts Bi n/Trol l ey fa l l en down Yes -
Abnorma l by QA or dema nd for new ok l ot.
Condi ti on
Any cus tomer compl a i nt recei ved or Check & s egrega te the whol e l ot l yi ng a t BAPL for the concerned
Yes Yes
Wa rra nty i s s ue recei ved i s s ue
1. Modification of Jigs/fixtures*
2. Process Change*
Expected Customer approval required & relevant documents to be
3. Proces Sequence Change* Yes -
(Pl a nned) submitted as per MSIL requirements.
4. Sub Supplier Process Change *
5. Despatch Packing Change*
4 Method
Check & s egrega te the whol e l ot l yi ng a t BAPL for the concerned
Abnorma l Any intermittent short shot or molding
Yes Yes i s s ue & i f s hi pped to a s s y l i ne then check & i nform to a s s y & QA
Condi ti on defect
for concerned i s s ue.
Abnorma l
FG Bi n/Trol l ey fa l l en down /da ma ge Yes - Al l Pa rts to be checked whi ch a re l yi ng i n tha t trol l ey/bi n
Condi ti on
Remarks
This is a live sheet, if any employee observe any new abnormal or unplanned change condions then he can request for addition of the check
point in this sheet.
Clause 3 –Change Management
S S No
Sub Clause Check Point Requirement
No
3.1 Definition and 3 Do you record product Inspection report of parts after
implementatio quality check results to change occurrence
n of changing ensure traceability? Records of batch code for
management traceability
4 Do you retroactively Comparison of parts before
check about product and after breakdown
quality when unexpected
change occurs?
Major Observation:-
Report contains part checked and found ok.
Content of inspection is not available.
Parts produced before breakdown (Retroactive parts) are not
checked.
Change item to be
recorded in
standard format
Clause 3 –Change Management
Clause 3 –Change Management
Clause 3 –Change Management
Abnormal conditions Criteria
Process Flow
Layout
Graph
Defect due to 4 M 50
change parts 600 parts 12000 Vehicles
X 1000X
Major Observation:-
4.1 Procedure to 2 Do you mention defined Mention both process & product
make process both characteristics of characteristic on control plan?
control quality and production
standards(QA control on the process
process control standards?
charts)
Observation (4.1.2)
Gaps in Standard management
All process characteristics not mentioned in control plan
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
Observation (4.1.3)
Gaps in Standard management
Poka Yoke, Limit sample reference not available in PCS
Clause 4 – Standard Management
PART ASSY ( Write part number of the VENDOR Write your company's name
NAME INDL
assembly)
( Write part number of the Process Control Standard Write serial no of Write total no. of pages
assembly) each page
(Write M UL, part number of Write A for and A and F for Functional parts
the assembly) MODEL
PART ASSY at the end of Part Number Write name (s) of mode (s) for
which this part is supplied
Page No.
(Write M UL, part number of
the assembly)
NUMBER INDL
Process Control Standard Control Inspectio Critical Control Sam pling R e c o rding
Process Description R e a m rk s
Machine Param ter Spec. Spec. n Method Characteri Incharge schem e/ Yes/ N o
Sl. No. stics frequency
Write check
Write the name of process/ Write For each For each Control Write A triangle Write Write if the For critical
Write frequency e.g.
operation e.g. incoming inspection, result of parameters
type, process control specificati briefly the should be R 100%. N=5
sequence
number
casting, machinging, plating etc. make w rite parameter on must method of marked if Am c=0. Start up Triangle to
checks are
recorded or
write action to
be taken in
control the W (I.e. check 5
checking
of the
For processes w hich are sub-
capacity
etc. of the parameter
w rite the
engineeri
be tighter
than the e.g. visual process P
pieces at the indicate Critical
not. It will be
better to also
case of
abnormally e.g.
process/ ti me of
mention the seggregation,
operation
contracted and for bought out
parts, w rite "sub-contracted"
machine s of both
products
ng standard w ith Go-
No Go
parameter
is critical
or
I
process
setting and
Process
way of scrap rework
used e.g. specificati specificati recording e.g. etc.
w ithing brackets below the Hydraulic (e.g. dia, on value on e.g. gauge, (See start if none is
defective).
Characteristics
name of report,
register, Z.R.
process name. Press 400 hardness w ith 250 + 7C, measurin legends N=3, c=0/Hr. chart etc.
Ton. etc) as tolerance 1.5 + 0.4 g w ith on bottom (I.e. check 3
For processes related to and w ell as or limits kg/cm2 45 micromete left pieces every
Functional items, w rite or process corner) hour and
e.g. 250, 55 r as per
continue if
respectively at the end of process (e.g. + 10C, 1.5 IS ….. none is
name. funace + 0.5 Etc. defective).
temp. kg/cm2 40- N=10, c=0;
Include sketch of the product pressure LOT (I.e.
60 HRC check 10
at each stage before and after etc.) pieces in each
each process lot and
accept the lot
if none is
defected).
R- Patrol Inspection Write briefly the reson for Date Prepared By Approved By
revision and referevce
AM - Automatic
Measurement Vendor
Legend for W- Operator
control P- Process Approval
Incharge I- Inspector
Write Revision Dates REV NO/DT Description Appd By MUL
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
Observation (4.2.1)
Gaps in Standard management
Retention period is not mentioned in procedure
Clause 4 – Standard Management
62
Clause 4 – Standard Management
S No Sub Clause S No Check Point Requirement
Observation (4.2.2)
Gaps in Standard management
Different process/ product characteristics in PCS, WI etc.
Clause 4 (Standard Management)
S No Sub Clause S No Check Point Requirement
4.2 Procedure to 3 Do you make use of lists Do you have the system to control
control to control preparation the revision details of any
standards and revision of document.
standards and share the
・Process updated information?
control
standards
・Inspection
specifications
・Operation
instructions
Observation (4.2.2)
Gaps in Standard management
Revision history not maintained properly.
Revision not captured in document.
Clause 5
(Education & Training)
Clause 5 – Education & Training
Training Process
Skill Development
Work on
Station
Clause 5 – Education & Training
Judgement
Clause 5 – Education & Training
S S No
Sub Clause Check Point Requirement
No
Name of the
Category
Operator
No Instructions
Line No. Process Name
Problem Required
Checked by Designation O X
Classificati Sub Item Plan
Item No. Check Point Remarks
on No. Actual
Coherence between specification mentioned in
1
Operation Operation Standards condition & actual condition.
A
Conditions Whether operator is immediately reading the "display
2
value" and recording them in the check sheet or not?
Operation Is the operation being carried out as per decided
B 1
Sequence operation sequence or not?
are Quality checks being carried out and the finding are
1
Quality recorded in the check sheet or not?
C
Checks Checks in of "Initial Product" and "Proper display" for
2
Initial Production are being carried out or not?
Equipment Checking of Machine and Equipments is being carried
D 1
Checks out and check sheets are duly filled or not?
Working condition checks are being carried out in
regard to device in which Fool proofing are being
1
incorporated, entries are made accordingly in the check
sheets or not?
Equipment Working conditions checks are also being carried out
E 2
Testing for Dies and Jigs or not?
Working condition checks are being carried out in
3 regard to "Inspection Equipments, Measurement
purpose tools, Devices, Gauges etc. or not?
Is the grinding and changeover of the Cutting Tools,
Changeov 1 Grinding Stone, Electrodes etc. being timely carried out
Clause 5 – Education & Training
S S No
Sub Clause Check Point Requirement
No
85
Clause 7 – Tier 2 Control
S S No
Sub Clause Check Point Requirement
No
Observation:-
Gaps in Selection check sheet
S
Sub Clause S No Check Point Requirement
No
Observation (7.2.1)
Gaps in Audits
Audit not planned/ Conducted for all supplier
Observations are not captured in Supplier selection check sheet
No Action plan/ Follow up for open observations
Observation (7.2.2)
Gaps in Development
Inspection Standard not decided with Sub Supplier.
Explanation of Part criticality not evident
Clause 7 – Tier 2 Control
S
Sub Clause S No Check Point Requirement
No
7.2 Management, 3 For outsourced process, Procedure for Supplier Part
quality do you control the development
evaluation and progress of production Monitoring of Part
instruction for preparation and development schedule
suppliers confirmed issues ? ,Capture the delay reasons
and make action plan to meet
the timeline
Monitor the Trial results at
supplier and prepare the
action plan based on CFT
approach.
Observation (7.2.3)
Gaps in Development
APQP Time plan Vs Actual not evident for Sub Supplier parts. Only
inspection reports available.
PPAP Approval not done / delayed
Clause 7 – Tier 2 Control
S Sub Clause S No Check Point Requirement
No
7.2 Management, 4 Do you make suppliers to Procedure to instruct suppliers
quality conduct initial about Initial flow control and
evaluation and production control and its monitoring.
instruction for decide department in
suppliers charge of conduct? Implement Initial Supply
control at supplier end as per
Procedure for new parts/
Change parts/ PCN cases.
Observation (7.2.4)
Gaps in Tier Initial flow control
IFC procedure not evident for Tier 2 Suppliers
Supplier Audit check sheet doesn’t contain related to IFC.
Clause 7 – Tier 2 Control
S Sub Clause S No Check Point Requirement
No
7.2 Management, 5 Regarding the parts Procedure to control the
quality which are shipped outsourced process where
evaluation and directly to the customers Delivery is done directly by
instruction for from outsourced Supplier to customer?
suppliers suppliers, do you have Adherence of Product Quality
method to assure checks as per procedure
product quality
performance?
Observation (7.2.4)
Gaps in Outsourced process
No Gaps .
Clause 7 – Tier 2 Control
S Sub Clause S No Check Point Requirement
No
7.2 Management, 6 Do you make outsourced Procedure for Change
quality suppliers to conduct approval request from
evaluation and initial parts and 4M suppliers & after getting
instruction for changing management change information how do
suppliers and is it possible to you manage the activities at
trace? suppliers end?
Check whether Suppliers is
recording the change
situations & ensuring parts
traceability.
Observation (7.2.4)
Gaps in Change management
Guidelines for changes is not prepared for Sub Suppliers.
Procedure for Change approval request from Sub Suppliers not
available.
Clause 8
(Handling abnormality in
quality)
Clause 8 – Handling abnormality in quality
S S No
Sub Clause Check Point Requirement
No
Major Observation:-
Major Observation:-
Major Observation:-
Major Observation:-
Major Observation:-
8.2 Prevention of 3 After corrective action are System for checking the
recurrence taken, do you conduct on- effectiveness of c/ms.
site checkup and evaluate
・Customer claims the effectiveness?
・In process failure
・Suppliers failure
Major Observation:-
Major Observation:-
Observation (5.1.1)
Gaps in 5S
Observation (5.1.2)
Gaps in 5S
Identification tag not available.
Similar parts kept together
Parts kept on floor, open environment etc.
Clause 9 – 5S Management
S No Sub Clause S No Check Point Requirement
Observation (5.1.3)
Gaps in 5S
Unidentified material at inspection table, Near machine etc.
Clause 9 – 5S Management
Observation (5.1.4)
Gaps in 5S
Lux level not defined as per IS: 6665
Lux level not monitored in B, C shift
No defined frequency & records for Lux monitoring.
Clause 9 – 5S Management
S No Sub Clause S No Check Point Requirement
5.2 Production 1 Do you keep condition Check condition of production
equipment's of production equipment's on shop floor. There
management equipment's, jigs and should be no equipment's
tools properly? damaged, clamps loose, oil
leakage from machine etc.
Check that production
equipment should not be fixed
with temporary non-standard
methods like packing with
scrap, tied with cloth etc.
Observation (5.2.1)
Gaps in 5S
Unclean machine, Air
Oil leakage from machine.
Clause 9 – 5S Management
S No Sub Clause S No Check Point Requirement
5.2 Production 2 Do you keep condition Check condition of inspection
equipment's of inspection equipment's on shop floor. There
management equipment's properly to should be no equipment's
ensure accuracy? damaged, checking fixture
clamps loose, datum pins
missing etc.
Observation (5.2.2)
Gaps in 5S
Pin missing/ Damage on inspection fixture
Validation of fixture not done as per time
No defined frequency for Pin replacement
Clause 10
(Equipment/ Inspection
equipment's
management )
Maintenance of Inspection Equipment
113
Maintenance of Production Equipment
(Machine /die /tools /molds /jigs /fixtures)
Observation (10.1.1)
Gaps in Daily check sheet
Availability of Daily/ Periodic check sheet for all machines, dies,
tools
Objective values are not captured in Daily check sheet.
Actual verification not done just putting √ on check sheet.
Clause 10 – Maintenance
S No Sub Clause S No Check Point Requirement
Observation (7.2.1)
Observation (10.1.1)
Gaps in replacement
Observation (10.1.1)
Gaps in Calibration
Calibration plan vs Actual not adhered
No judgement is taken based on calibration reports
Clause 10 – Maintenance
S No Sub Clause S No Check Point Requirement
Observation (10.1.1)
Gaps in boundary Samples
Boundary sample not stored adequately.
Clause 11
(Implementation of
Standards)
Clause 11 – Implementation of Standards
S No Sub Clause S No Check Point Requirement
11.1 Production 1 Do you use easy All process & station should
equipment's expression (visualizer, have operation standard / work
management onomatopoeia ,etc.) for instructions available.
operation instructions? All work instructions should be
So that operator can well defined with pictorial
easily understand display of instructions and
process and critical check points.
points. It is preferrable to have work
instruction in local language so
that operators can easily
understand the content.
Observation (11.1.1)
Gaps in Implementation of Standards
Work instructions not available in English as well as regional
language.
Clause 11 – Implementation of Standards
S No Sub Clause S No Check Point Requirement
11.1 Production 2 Do you keep operation Work instructions should be
equipment's instructions on the kept at accessible place. For
management accessible place and Important information in work
post important quality instructions, highlighting is
points and critical recommended. .
operation points on the
place where operators
can see it easily?
Observation (11.1.2)
Gaps in Implementation of Standards
Clause 11 – Implementation of Standards
S No Sub Clause S No Check Point Requirement
11.1 Production 3 Do operators and Check that operators are
equipment's supervisors operate following the process as defined
management according to the in work instructions / OPS.
operation standards? Check that supervisor is
performing job as per his daily
work management sheet /
defined job responsibilities.
Observation (11.1.3)
Gaps in Implementation of Standards
Observation (11.1.4)
Gaps in Implementation of Standards
Observation (11.1.5)
Gaps in Implementation of Standards
Major Observations:-
Major Observations:-
Major Observations:-
Observation (13.1.1)
Gaps in Handling Management
Approved packaging standard not available for child parts.
Clause 13 – Handling Management
S No Sub Clause S No Check Point Requirement
13.1 Bins/ Trolley 2 Are the packaging style Check the bin / trolley and
Management & storage environment storage condition of work-in-
controlled with process, child parts and FG
consideration to parts. It should be able to
contamination control damage and
contamination to the parts.
Observation (13.1.2)
Gaps in Handling Management
Broken bins
Overloaded bins/ trolleys
Bins directly on shop floor
Clause 13 (Handling Management)
S No Sub Clause S No Check Point Requirement
13.1 Bins/ Trolley 3 Do you have system to System defined at supplier for
Management maintain Bins /Trolleys in identification and periodic
Good Condition. maintenance of damaged bins
/ trolleys.
Check if bins / trolleys are
cleaned before keeping FG
parts for despatch to customer.
Observation (13.1.3)
Gaps in Handling Management
Maintenance plan for Bins/ Trolleys
Adequate amount of bins as per production
Bins replacement time needs to be standardized.
Clause 13 (Handling Management)
13.1 Bins/ Trolley 4 Does the Packaging Check for the proper packing
Management method prevent condition of parts to avoid
Transportation damage damage during internal
movement and also during
dispatch to customer.
Observation (13.1.4)
Observation (14.1.3)
Gaps in Critical parts management
Details of Maru A parts Rework not captured