Intern Report
Intern Report
Intern Report
BY
KOO YE LIANG
Begin a report submitted to
INTI INTERNATIONAL UNIVERSITY
As a requirement for
BSC. (Hons) in Quantity Surveying (BQSI)
(Semester: JAN 2018)
1
ACKNOWLEDGEMENT
The internship opportunity I had with Peck Chew Piling was a great chance for me in
learning and professional development. Therefore, I consider myself as a very lucky
individual as I was provided with this opportunity to be a part of it. I am also grateful for
having a chance to meet so many wonderful people, collogue and professionals who led
me though this internship period.
First, I would like to thanks to my internal supervisor who is Miss Suhaida. She is the
one give the fully supported and encourage to me during the internship period. Without
her patient to guide me, it would be more difficult for me to complete my report as well.
Besides that, I would like to thank her, although she did not come to supervise my
practical training condition due to venue problems, she will give me some time to reply
my email.
However, I would like to thanks to my colleagues in Peck Chew Piling who always teach
me and assist me throughout my internship period. They always show me how to do the
work and they are willing to share their working experience to me.
In addition, I would like to thanks to INTI International University for providing me this
opportunity to have a real practice and allow me to expose myself in construction
industry to gain more and more knowledge, internship is a very interesting subject and i
hope that duration of internship could be longer.
Finally, I would like to thanks to my family and friends who always support me in
everything and will always encourage me when I faced difficulties. I am very thankful
and appreciate to them who help me throughout my internship period.
2
Declaration
3
ABSTRACT
In this report, I did separated in to 4 main chapters which are Chapter 1 - Introduction to
internship, Chapter 2 - Company Profile (Background Information, Organization Chart,
Completed Project, Ongoing Project, Upcoming Project, Corporate Structure and Board
of Directors), Chapter 3 - Body of Content, would described the tasks and job I was
assigned throughout the internship period and appendix attached a lot of appendix as a
supporting document. Besides, in Chapter 4 - Conclusion, I did summarize what had
learned during the internship period and some recommended for internship program from
my opinion. Lastly, Chapter 5 the reference.
4
Table Of Content
Chapter 1- Introduction
2.2 Mission.........................................................................................................................10
2.3 Vision...........................................................................................................................10
3.3.1 Introduction..............................................................................................................22
5
Chapter 4
4.0 Conclusion...................................................................................................................28
Appendix...........................................................................................................................29
Chapter 5
5.0 Reference.....................................................................................................................38
6
CHAPTER 1 – INTRODUCTION
Internship program allows students to expose themselves into real industry and gain
additional knowledge, specifically to achieve the following objectives:
12 To improve and gain teamwork and relationships with other staff in a company.
7
1.2 INTRODUCTION OF INTERNSHIP
Internship is the one of the course structure under Inti International University with the
aims to allow students to explore themselves in the real working environment and gain
extra knowledge. It also enables students to set up their future path and get prepare for
the industry. As a student of (Hons) in Quantity Surveying (BQSI), I am required to
complete 16 weeks (4 months, 8th Jan – 27th April) of internship in a construction related
company.
To complete my internship program, I decided and get the chance to join in Peck Chew
piling (M) Sdn Bhd, which are located at Lot 233, jalan pantas pam minyak BHP Sg
Rengit ke kg baru osman saat, Pengerang, Johor as a trainee. Besides that, the reason I
choose this company because I believe this company can help me to gain extra
knowledge of being as a professional Quantity Surveyors. This experience can be a useful
guideline for my future study and career as a Quantity Surveyor.
My employer is Mr. Lean Lai Ming, who is the Project Manager of Peck Chew Piling
company(Johor), and my external supervisor is Miss Radin Marina. Apart of that, my
working hour is start from 8:00am until 5:00pm on every Monday to Saturday and no
working on Sunday. My lunch break is start from 12:00pm until 1:00pm (1 hour). During
these 16 weeks of internship period, I was taught on the details measurement skill,
preparation of work program, understanding the content of contract document, assist in
handover of document, the details in piling construction.
8
CHAPTER 2 COMPANY PROFILE
2.1 Introduction to Company
Logo of company
Peck Chew Piling (M) Sdn. Bhd. formerly know as Tan Pek Chu Piling which founded in
1975 by Mr. Tan Pek Chu at Johor Bahru that carry out timber and bakau piling using A-
Frame. We are then cooperated in 2004 at central region Malaysia and actively involve in
foundation con-struction works for various type of building or for infra-structure across
peninsular Malaysia. Now, East Malaysia operation office is functioning since 2010.
In line with company fast growing, we are now equipped with big scale Bored Piles
machines from BAUER, SOILMEC and JINTAI with up to 1800mm diameter and 54.0m
meter depth.
Under the directorship of Board of Director, who has been actively involved in
foundation con-struction field for more than 30 years, with their in-depth knowledge,
experience and wide con-tacts in this industry, we trust that the company will be lifted to
another platform as comparing to other player in this industry.
We had been in the forefront of many others piling contractor in general piling works. As
Today, we had completed projects with total value more than one (1) billion
(RM1,000,000,000.00). (Peck Chew Piling Administrator. 2018)
9
2.2Mission
To construct a wide range of foundation works, service and guarantee
performance at an affordable price.
To be the piling & construction company of choice by providing customer-driven
multitechnology solution.
.To continual improve our service through implementing and achieving ISO
9001:2008 (Quality Management System) certificate(Peck Chew Piling
Administrator. 2018)
2.3Vision
Build and sustain a leading position in the delivery of excellent services in each of
our core businesses.
Enhance the quality of life through projects and activities that are socially,
culturally and environmentally responsible.
Nurture a corporate culture that emphasizes the pursuit of excellence. (Peck Chew
Piling Administrator. 2018)
10
2.4Company Organization chart
1)Concrete Pile
Pre-cast pre-stressed concrete piles are commonly used in the pile market. We drive
concrete piles on more than ninety percent of our jobs. The pre-cast pile is one of the
most cost effective pile types due to material cost, custom pile lengths, and availability.
Recently we had involved in Pile Jack-In Technology which using Hydraulic Jack-In
Machine.
The cost of concrete pile varies based on design loads, dimensions, and length,
but typically a concrete pile is more cost effective.
11
After the completion of an indicator program pile lengths can be customized to
site specific soil conditions prior to ordering production pile avoiding costly
material waste.
Concrete piles can be ready to drive in most cases in fourteen days, as opposed to
steel piles which can require a mill rolling taking six to eight weeks.
2)Bored Pile
Heave situations can be accommodated with permanent sleeves, void formers, and
a choice of slip-plane liners.
Piles can be installed through adverse ground conditions using temporary casings
or bentonite.
3)Micro Pile
Also known as “Pin piles” or “Minipiles”, Micropiles are small diameter high
capacity pipe piles.
They are typically specified in short threaded lengths and installed through
various drilling techniques.
The addition of grout and threaded bar reinforce the pile in lateral, tensile, and
compressive loading.
4)Sheet Pile
The shape or geometry of a section lends to the structural strength. In addition, the soil in which
the section is driven has numerous mechanical properties that can affect the performance. Sheet
piling is classified in two construction applications, permanent and temporary. A permanent
12
application is “stay-in-place” where the sheet pile wall is driven and remains in the ground. A
temporary application provides access and safety for construction in a confined area.
5)H-pile
H-Piles are dimensionally square structural beams that are driven in the ground for deep
foundation applications. Most soils at or near surface do not have the mechanical
properties to support large buildings. As you go deeper into the earth’s geology, there are
layers (bearing strata) capable of doing so. H-Piles are manufactured and designed to
transfer structural loads to these good bearing soils.
H-Piles are also used in conjunction with sheet piles to add lateral stiffness and bending
resistance where loads exceed the capacity of sheet piles alone. (Peck Chew Piling
Administrator. 2018)
13
Concrete Pile Bored Pile
H-pile
14
2.5.2 Pile Installation Method
If installation is to be carried out using pile-hammer, then the following factors should be
taken in to consideration:
The hydraulic jack in piling system utilizes a patented hydraulic grip jacking technique in
which piles are injected into the ground at a maximum pile jacking capacity of 800 tones.
Due to the fact that only the most minimal emission of noise, vibration and pollution
occurs during the pile injection process, this system meets even the most stringent
environmental protection requirements around the world.
It also has many other advantages, such as a superior mobility, an excellent jacking
ability, high levels of operational accuracy and a 100% quality check on all injected piles.
Currently, we have hydraulic jacking machines of various capacities ranging from 160
tones to 600 tones.
4)PRE-BORING
The method is especially effective on soft ground and enables to install a variety of bored
piles of various diameters that are able to penetrate a multitude of soil conditions. Still,
for successful operation of rotary auger the soil must be reasonably free of tree roots,
cobbles, and boulders, and it must be self-supporting.
During operation little soil is brought upwards by the auger that a lateral stress is
maintained in the soil and voiding or excessive loosening of the soil minimize. However,
15
if the rotation of the auger and the advance of the auger is not matched, resulting in
removal of soil during drilling-possibly leading to collapse of the side of the hole. (Peck
Chew Piling Administrator. 2018)
Vibratory Pre-boring
16
2.5.3 Engineering Testing
Also known as pile static load test. Pile load test are usually carried out that one or some
of the following reasons are fulfilled:
To obtain back-figured soil data that will enable other piles to be designed.
To confirm pile lengths and hence contract costs before the client is committed to
overall job costs.
To counter-check results from geotechnical and pile driving formulae
To determine the load-settlement behavior of a pile, especially in the region of the
anticipated working load that the data can be used in prediction of group
settlement.
The maintained load test (MLT), Kent ledge or adjacent tension piles or soil anchors are
used to provide a reaction for the test load applied by jacking(s) placed over the pile
being tested. (Peck Chew Piling Administrator. 2018)
High Strain Dynamic Pile Testing is used to provide data on strain or force and
acceleration of a pile under an impact force. The data is used to evaluate the bearing
capacity and the structural integrity of the pile as well as hammer performance, pile
stresses and soil characteristics, such as soil damping coefficients and quake values. Pile
integrity, which is accurately evaluated on site, would allow the engineer to accept or
reject the pile immediately.
Actual driving stresses and hammer performance data obtained during pile monitoring
can be used to reduce the risk of pile damage. Piles no longer have to be overdriven
resulting in lower foundation cost.
17
probably not be at the site all the time to witness the pile installation. It is also to ensure
that the installed piles can function as designed. (Peck Chew Piling Administrator. 2018)
18
2.5.4 Provide of machinery and equipment
3) Hydraulic Hammer
4)Compressor
19
2.6 Previous Project of company
20
CHAPTER 3 BODY OF COMPANY
3.1 Job description
The job scope that I have involved during my internship period had been summarized as
below:
a)Project Phase 1 Dialog 1E
1.Sending piling record
2.Mark on plan
3.Prepare RFI(request for inspection)
4.Sending RFI
5.Type the claim summary
b)Project P28B, Rapid pengerang
1. Site inspection
2.Helping surveyor to peg pile point
3.Prepare summary of piling record
4.Estimating cost
5.Sending RFI to CCSM office
c)Project Metex
1. Inspect pile testing
2. Prepare piling claim summary
d)New office Pengerang PCP
1. Prepared work program
e) Forest city
1. Translate contract document
21
3.2 INTRODUCE FORMAT AND SOFTWARE USED BY THE COMPANY
In this part I will describe format and software used by this company to ensure
understanding is always there. Normally, we will use Microsoft Excel, AutoCAD,
Microsoft Word, and Microsoft Project to complete our construction, measurement and
claiming job.
3.3.1 INTRODUCTION
This chapter will describe tasks I have been carried out in each of projects, project scope
that I had involve and also the explain in details of the project.
3.3.2.1 Introduction
Phase 1B Phase 1C
22
PENGERANG INDEPENDENT TERMINALS, Phase 1 of PDT has a storage
capacity of approximately 1.3 million cubic meters (m3) on 150 acres of reclaimed land,
together with six deep-water berths at a cost of RM2.0billion. It has the capability to
handle the storage, blending and distribution of crude oil, petroleum, chemical and
petrochemical feedstock products, and by- product. (Dialog. 2018)
Phase 1 project is owned by Pengerang Independent Termainals Sdn Bhd (PITSB), a joint
venture between DIALOG(46%), Royal VOPAK(44%) and S.S.I (10%). It has been fully
completed and commenced operations in the second quarters of calendar year 2014.
PITSB welcomed its very first Very Large Crude Carrier (VLCC) on 16 March 2015. To
date it has welcomed more than 1100 vessels. (Dialog. 2018)
Phase 1 has the capacity to develop an additional 1 million m3 should the requirement
arise, as it has land available for further expansion. So our company will drive pile under
the tank in order to construct foundation to support the load of the tank. (Dialog. 2018)
First and foremost, the first things that I had do for this project is piling records scanning.
Although piling record scanning seen to be easy, but it is actually very important for us,
when there is any problem to that particular pile, so the scanning of piling record can be
used for refer as the original copy of piling record will send back to the client.
I also helping in key in the summary of piling record into claim summary, the data key by
me will allow the quantity surveyor to prepare bill of quantities and prepare claim. Other
than that, I also prepared Request for information (RFI) and send to the Dialog office.
The RFI is important as it act as a permit to allow construction work in progress. One RFI
can valid for three days.
I had prepare the daily report and mark on plan every day, daily report will be use to
ensure the quantity of pile that had been drive on the previous day and the total quantity
of pile that had been drive. I also do the mark on plan stated the penetration, date of drive,
set, and total length of pile in the drawing to ensure no missed of driven pile.
23
3.3.3 Project P28B, Rapid Pengerang
3.3.3.1 Introduction
Malaysian oil and gas company Petroliam Nasional Berhad (Petronas) is developing a
refinery and petrochemical integrated development project (RAPID) and other associated
facilities in Pengerang, Southern Johor, Malaysia, through a project called Pengerang
Integrated Complex (PIC). (Hydrocarbons Technology. 2018)
Launched in May 2012, PIC is part of the larger Pengerang Integrated Petroleum
Complex (PIPC) proposed by the Johor state government. Total investment for the PIPC
project is approximately MYR97bn ($27bn), of which the RAPID project costs
MYR57bn ($16bn) and the associated facilities require MYR40bn ($11bn).
(Hydrocarbons Technology. 2018)
A feasibility study along with site topographical survey and soil investigation work for
the project were completed in October 2011. Front-end engineering design (FEED) and
an environmental impact assessment studies have also been completed. (Hydrocarbons
Technology. 2018)
In April 2014, the Petronas board of directors approved the final investment decision
(FID) for the RAPID project. The refinery project is anticipated to be completed by early
24
2019. It is expected to employ 70,000 workers during construction and generate 4,000
new jobs upon completion. (Hydrocarbons Technology. 2018)
At about week 12 and 13 I had been ask by my employer to go to the site for inspection
and also experienced the construction work. I had learned more about construction of
piling works. For example I had know that how the jack in machine jack the pile into the
ground. Other than that, I also help to prepare the piling record which recording the
penetration of pile the total length of pile and also record pile break when breaking
occurred. When the pile was set, I will take the photo for the pile set reading on gauge.
This data will allow me to prepare a summary of piling record to the office to prepare
claim.
While construction work in progress, there is a land obstruction which cause by rock.
These rock causes the pile to break easily, so the employer of mine had told me to
estimate the additional cost that will be cause by the obstruction. While removal of
obstruction work is complete, I also help the surveyor to repeg the pile point.
25
3.3.4 Project Metex
3.3.4.1 Introduction
Project Metex is a project that construct polis immigration, bungalow, hall, and office
which located at Kampung Lepau in Johor Bahru.
For this project I had inspect the Pile Driving Analyzer (PDA) testing of piling with my
colleague. The Pile Driving Analyzer (PDA) system is the most widely employed system
for Dynamic Load Testing and Pile Driving Monitoring in the world. High Strain
Dynamic Load Tests, also called PDA tests, assess the capacity of several piles in a
single day. Pile Driving Analyzer systems also evaluate shaft integrity, driving stresses,
and hammer energy when monitoring installation.
Other than that, I help in key in the summary of piling record into claim summary. This
would allow Quantity Surveyor to prepare claim to the client. I also help in prepare
transmittal for client acknowledgement.
Piling record scanning is also done by me to have a backup, so when problems occurred
on that particular pile, the piling record which had been scanned can be used as a
reference.
26
3.3.5 New office Pengerang PCP
3.3.5.1 Introduction
There is a new office which have a total of four level are being construct at bukit saga
near the area of Pengerang for our own company.
3.3.6.1 Introduction
Forest City real estate development in Gelang Patah, to be graced by Malaysia Prime
Minister Najib Razak and Sultan of Johor, Sultan Ibrahim Ismail. Forest City is expected
to create more than 220,000 jobs for the locals by the year 2035. Forest City, set to
be Southeast Asia’s largest mixed-use green development is now open to public for
previews and bookings, and have obtained many supportive incentives from the Federal
Government of Malaysia. Condominiums and high-rise coastal residences on Island 1 of
Forest City are exceptionally. (Forest City Johor 碧桂园森林城市. 2018)
In this project I had help the contract department to translate the contract document. Due
to the contractor are came from China, the contract document was in Chinese and I had
help them to translate the contract document from Chinese to Malay.
27
4.0 Conclusion
After these sixteen (16) weeks of internship in Peck Chew Piling (M) Sdn Bhd, I
have gained a lot of benefits and experience. Those knowledge and experience I gained
will helped me in future career and do better in my future work in construction.
Apart from that, the entire practical thing happen at work can let me recall back the
knowledge that I had learnt in university. However, through this internship period, I also
learn a lots of skills which are not taught in class such as time management, self-
discipline, work ethics, well managing the relationship between colleagues and others
details in construction.
Last but not least, I can say that I have gained a lot of benefits through this internship
and got to work with experience seniors makes whole training period goes smoothly and
give me a lots of unforgettable memories.
28
APPENDIX A
29
Figure A.1: Area LPS304 for project Dialog Phase 1 E
30
Figure A.3: Bill of Quantity for Claim
31
Figure A.5: Attending site meeting with colleague
32
Figure A.7 : P28B Rapid Site
33
Figure A.9: Help in prepare Piling Record for project P28B
34
Figure A.11: Site inspection for PDA testing
35
Figure A.13: PDA Report
36
Figure A.14: Schedule of work program for new office
37
5.0 REFERENCE
1. Administrator. 2018. Peck Chew Piling (M) Sdn. Bhd.. [ONLINE] Available
at: http://www.pc-piling.com/. [Accessed 27 April 2018].
2. Dialog. 2018. Dialog Group Berhad - Dialog Group Berhad. [ONLINE] Available
at: https://www.dialogasia.com/. [Accessed 27 April 2018].
3. Hydrocarbons Technology. 2018. Petronas RAPID Project, Southern Johor -
Hydrocarbons Technology. [ONLINE] Available at: https://www.hydrocarbons-
technology.com/projects/petronas-rapid-project-malaysia/. [Accessed 27 April 2018].
4. Forest City Johor 碧桂园森林城市. 2018. Forest City Johor 碧桂园森林城市 - Forest
City Johor By Country Garden Pacific View (CGPV) in Iskandar Malaysia, next to
Singapore – 碧桂园森林城市. [ONLINE] Available at: . [Accessed 27 April 2018].
38