20110145-Ng Piping Hazards
20110145-Ng Piping Hazards
20110145-Ng Piping Hazards
O
ver the last 10 years, several industrial accidents Many individuals who manage or perform gas piping
related to natural gas piping problems have taken repairs lack the knowledge needed to do so safely. Some
more than a dozen lives, injured hundreds of people, in purchasing or maintenance functions think that all
and cost the companies involved billions of dollars. Many piping is the same; they do not understand that repairing
more significant incidents and fires involved commercial and or installing an air or water line is quite different from
even residential facilities. working on a gas line.
One of the most recent cases described on the U.S. This problem is especially relevant in the current
Chemical Safety and Hazard Investigation Board’s (CSB) economy, with many companies choosing the lowest bidder
website (www.csb.gov) is the June 2009 explosion at a food for repair projects. In the past, contractors apprenticed pipe-
plant in Garner, NC (1). A new piece of equipment was being fitters by directly training them and sharing their experience.
installed and a natural gas line was being re-energized for In addition, many businesses that provided training related to
light-off. Four people were killed and more than 40 others gas piping risks no longer have the resources to do so. Very
were sent to the hospital with injuries when the blast knocked few communities regulate who is qualified to perform gas
down walls and caused the roof to collapse. Investigators piping work, and local building inspectors rarely see projects
concluded that the gas line was purged into the building, and beyond low-pressure residential jobs.
that led to the accident. As a result, the state of North Caro- NFPA 54 explains how to safely perform gas piping
lina now prohibits the purging of gas lines into buildings. repairs, purging, and pressure testing. Unfortunately, many
Another purging incident in February 2010 killed six who should be familiar with NFPA don’t even know that it
workers and injured 50 others at an energy plant under exists, don’t have time to read it, or don’t interpret it cor-
construction in Middletown, CT. The CSB determined that rectly. Another problem is that NFPA 54 does not go into
the explosion was most likely caused during a routine gas detail about the reintroduction of natural gas after repairs.
purging procedure (2). The accumulating gas reached an Even the newest changes require some amount of interpreta-
ignition source, where welding and other work were being tion depending on the project size and scope. In addition,
performed nearby, setting off the blast that leveled much of many nuances of repair can only be learned through experi-
the facility. ence and practical examples.
The National Fire Protection Association (NFPA) has This article fills some of the gaps that are not explicitly
adopted sweeping changes to NFPA 54, the “National Fuel covered in NFPA 54 and summarizes some important les-
Gas Code” (3), to protect against these kinds of incidents. sons learned that can help prevent devastating natural gas
The changes were deemed important enough to be added accidents. It reviews ten common hazards associated with
as a tentative interim amendment (TIA) to the standard (see the installation and repair of natural gas piping and provides
www.nfpa.org for the complete changes). insights on how to avoid them. These tips and techniques
Copyright © 2011 American Institute of Chemical Engineers (AIChE) CEP January 2011 www.aiche.org/cep 45
Safety
should be incorporated into a comprehensive documented is much more effective to find and repair leaks in reasonably
procedure for natural-gas piping purging, piping system sectionalized piping, possibly hundreds of feet at a time.
design, and equipment start-up. Other important considerations during the planning pro-
cess include:
Inadequate design and planning • Where are isolation points and how will isolation be
A safe gas piping installation or repair job involves six safely achieved?
basic steps: • Will the utility be involved? What will be required of
Pre-repair the utility? What does the utility require of the facility?
1. Planning • Is there an overall plan and does everyone involved
2. Isolation understand it?
3. Pre-repair purging • Is there enough nitrogen to handle the purging require-
Making the repair ments? Does everyone involved understand nitrogen hazards?
4. Pressure testing • Where will the purge stream be sent?
5. Post-repair purging • Have reintroduction and start-up been discussed,
6. Reintroduction and light-off including their unique hazards?
Before any work can be performed, significant planning
is needed to ensure the job is completed safely. Proper plan- Improper isolation (an often-tragic mistake)
ning includes: The U.S. Occupational Safety and Health Administra-
• procedures: What specific written procedures of the tion’s (OSHA) lockout/tagout standard (OSHA 1910.147)
work to be done and processes to be used will provide a (4) governs the isolation of hazardous energy sources. Much
step-by-step understanding for everyone involved? has been written about this issue, and most facilities comply
• people: What is the knowledge and skill level of the with it when isolating electrical equipment. For gas piping,
staff to be involved? Is training needed? however, proper isolation is much less common. Even some
• design: Has a thorough review of the design been sites that place locks on all electrical disconnects may close
completed to ensure that everything to be installed meets a gas valve, but not lock it.
applicable codes and best practices? The isolation of lubricated plug valves, which account for
• resources: What resources will be required? When will 60–80% of the manual shut-off valves in natural-gas piping
they be needed? systems, requires special attention. These valves have a small
• hazards: What possible hazard assessments and abate- gap between the plug and the valve body. If a sealant is not
ment steps need to be performed at this stage? applied annually, as required by code and the manufacturer,
Planning also needs to include a review of isolation gas will leak past the plug even when the valve is in the
points, including existing valves and flanges, the pos- closed position. Many facilities have never sealed their lubri-
sible need to install flanges, and areas where blanks can be cated plug valves. Hence, closing or locking out a valve in
installed. According to NFPA 54, pressure testing cannot be this condition does not necessarily isolate the energy source.
carried out against valves if there is a pressurized substance Isolation must ensure that all active gas-filled parts of
on the other side of the valve. The engineer will need to the system are safely separated from open sections of pipe
evaluate the entire gas piping system to determine where the and/or the areas to be repaired. Most people think of isola-
system can be sectionalized for proper testing. tion as valves. However, even when they are in the closed
It is helpful to have (at a minimum) a schematic repre- position, valves may leak, especially if they have not been
sentation of the facility’s gas piping systems on hand during serviced properly. Because of this, the safest approach is to
planning. A schematic typically shows major line sizes, use blinds or double-block-and-bleed valves for isolation.
valves, and equipment. A detailed natural gas piping draw- A double-block-and-bleed system consists of three valves
ing depicts much more detail and may include isometric in series — the two end valves are closed and the middle
representations of some of the piping. If neither is available valve is open and vented to a safe place. If a valve leaks, the
for use during the planning stage, a schematic representation leaked gas can exit through the vent rather than pressurize the
will need to be prepared (detailed piping drawings for a large downstream valve and create a more serious hazard.
facility could take weeks to make). Effective isolation protects not only personnel from the
Planning is vital because it allows piping sections to be hazard of natural gas, but it also protects components in fuel
designed to be somewhat reasonable in length for testing trains from the elevated pressures that may be encountered
and evaluation. For example, if the system does not hold during pressure tests. Valves that are left open or leak in the
pressure during pressure testing of all of the plant piping, the closed position can overpressure and permanently damage
entire plant will need to be searched to locate a small leak. It delicate components such as regulators and pressure switches.
46 www.aiche.org/cep January 2011 CEP Copyright © 2011 American Institute of Chemical Engineers (AIChE)
Improper purge points
Purge points are pipe nipples installed at strategic loca- Purge Endpoint Vent
(<1% LEL, <1% O2) reached to a
tions in the piping system for the purpose of introducing or safe
removing nitrogen and natural gas at various stages of the Purge location
process. These are generally 1-in. Sch. 80 nipples (which Closed
Inlet Valve Closed
are thicker and stronger than common Sch. 40 pipes) with PV1
Copyright © 2011 American Institute of Chemical Engineers (AIChE) CEP January 2011 www.aiche.org/cep 47
Safety
48 www.aiche.org/cep January 2011 CEP Copyright © 2011 American Institute of Chemical Engineers (AIChE)
does not occur after three light-off attempts, stop the pro- require the installation of a blind on equipment that will
cess. Shut off all the gas and perform a dry light-off purge be out of service for months to avoid the possibility of gas
to move any accumulated flammables out of the firebox. leaks through valves.
If light-off is still not achieved after six or more attempts, This is a compliance issue. NFPA 54 is a code — not a
verify the level of gas entering the fuel train to see what standard — and it has the force of law in many jurisidic-
concentration was reached. If it is too low, more purging tions. The newest changes state that any natural-gas piping
is needed. system larger than 2 in. in diameter or operating at pres-
Automatic fuel valves should be leak-checked within sures over 2 psig needs to follow the directives of the code.
30 days of major gas piping repairs. Considerable slag and In many cases, this is a game changer and the maintenance
debris in piping systems can be found after major repairs and plant service people must be aware of this.
and construction. This is also a time to clean strainers and
sediment traps. Taking lessons learned to heart
You should now have a heightened awareness of the
Human error — the greatest risk of all issues involved in gas piping repairs and equipment com-
The most important factor in avoiding gas piping and missioning. If you are involved in this activity on a regular
equipment recommissioning issues is human error. Human basis, you may be able to put some of the advice presented
error can be minimized by changing cultures — that is, here into practice immediately. If you have only casual
through training and discipline. contact with gas piping repair, please share what you have
Training includes reaching out to maintenance depart- learned with those who routinely service or maintain gas-
ments and anyone involved in this process and teaching fired equipment. This is a very specialized area that many
them how to correctly perform gas piping repairs. The take for granted and that has proven to be anything but
trade unions that provide training for pipefitters do not nec- straightforward and simple. CEP
Copyright © 2011 American Institute of Chemical Engineers (AIChE) CEP January 2011 www.aiche.org/cep 49