Electromagnetic Transient Analysis On 500kV and 230kV Ecuador Transmission Project (VER6) - revTE-1
Electromagnetic Transient Analysis On 500kV and 230kV Ecuador Transmission Project (VER6) - revTE-1
Electromagnetic Transient Analysis On 500kV and 230kV Ecuador Transmission Project (VER6) - revTE-1
ii
7. Conclusion.......................................................................................................54
iii
1. System parameter
The 500kV and 230kV transmission lines and substations of the project to be
designed in Ecuador are shown in Fig System parameter.1.
+10
EL INGA substation: 600/600/200MVA ,500/230 -10 1.25%/34.5kV,on-load
voltage regulation,Ud1-2≤12.5%,Ud1-3≤30%,Ud2-3≤15%,YN0yn0d1.
+8
SAN RAFAEL substation: 450/450/150MVA ,500/230 -8 1.25%/34.5kV,on-
Parameters of 500kV and 230kV transmission line are shown in Tab System
1
parameter.1 and Tab System parameter.2.
avera
ge Number
Condu
height Wire of location of
earth ctor
Line conductor of spacing complete transpositio
wire arrang
condu (m) transposi n tower
ement
ctor( tion
m)
San
4×ACAR GJ-100+ 20km+40k
Rafael - horizo
1100 MCM OPGW- 20 12.5 1 m+40km+2
The ntal
18/19 100 0km
Inga
3×ACAR GJ-100+ 26km+53k
Inga – horizo
1100 MCM OPGW- 20 12.5 1 m+53km+2
Tisaleo ntal
18/19 100 7km
17km+33k
Tisaleo
3×ACAR GJ-100+ m+33km+3
– horizo
1100 MCM OPGW- 20 12.5 2 3km+33km
Chorrill ntal
18/19 100 +33km+18k
os
m
average
earth height of bundle spacing
Line conductor
wire conduct (mm)
or(m)
SAN RAFAEL– 2×ACAR 750 GJ-55+
15 400
JIVINO MCM 18/19 OPGW-55
TISALEO– 2×ACAR 750 GJ-55+
15 400
TOTORAS MCM 18/19 OPGW-55
JIVINO – 2×ACAR 750 GJ-55+
15 400
SHUSHUFINDI MCM 18/19 OPGW-55
Parameters of shunt reactors and neutral reactors for 500kV transmission lines
are shown in Tab System parameter.3. The neutral reactor of the shunt reactor shall be
determined in the manner that the secondary arc current and the recovery voltage shall
be minimized in case of single-phase earth fault and that the neutral overvoltage of the
small reactor shall not be excessively high.
Tab System parameter.3 Parameter of 500kV shunt reactor and neutral reactor
Three-phase
Rated Impedance
Installation rated neutral
Line voltage value
position capacity( reactor(Ω)
(kV) (Ω)
Mvar)
Line side of 500/ 2500+2×10%
30 8333.33
SAN RAFAEL 3 2500-10%
SAN RAFAEL-EL Line side of EL 500/ 2500+2×10%
30 8333.33
INGA INGA 3 2500-10%
Bus bar of EL 500/ neutral
30 8333.33
INGA 3 grounded
Line side of EL 500/ 800+2×10%
90 2777.78
EL INGA – INGA 3 800-10%
TISALEO Line side of 500/ 2500+2×10%
30 8333.33
TISALEO 3 2500-10%
Line side of 500/ 2500+2×10%
30 8333.33
TISALEO – TISALEO 3 2500-10%
CHORRILLOS Line side of 500/ 500+2×10%
120 2083.33
CHORRILLOS 3 500-10%
3
2. Secondary arc current and recovery voltage
The value of secondary-arc currents and recovery voltages are the key factor for
the speed of self-extinguishing of the arc, and are decisive for time of single-phase
reclosing of CB, which affect the single-phase successfully reclosing probability of
CB.
The neutral reactor of the shunt reactor shall be determined in the manner that
the secondary arc current and the recovery voltage shall be minimized in case of
single-phase earth fault and that the neutral overvoltage of the small reactor shall not
be excessively high.
Take 500kV SAN RAFAEL-EL INGA transmission line for example, the power
frequency overvoltage, secondary arc current and recovery voltage corresponding to
different value of small reactance is shown in Tab Secondary arc current and recovery
voltage.4.As the value of neutral reactance is larger, secondary arc current and
recovery voltage is smaller, and the power frequency overvoltage is larger. In order to
make the neutral reactance power frequency overvoltage is less than the rated voltage
of MOA (72kV), the value of neutral reactance should be limited to no greater than
4
2500Ω, so the value of neutral reactance of 500kV SAN RAFAEL - EL INGA line is
chosen 2500Ω.
Tab Secondary arc current and recovery voltage.4 the power frequency overvoltage,
secondary arc current and recovery voltage corresponding to different value of small
reactance(1p.u.= 2 ×550/ 3)
5
Tab Secondary arc current and recovery voltage.5 Secondary-arc current and recovery
Tap
position neutral recovery Secondry-arc
Operation
Line of reactance voltage(k current
mode
neutral (Ω) Vrms) (A rms)
reactance
+20% 3000 30.86 10.95
+10% 2750 32.51 11.49
34.34
12.07
(Fig
(Fig
Secondary
JUN 2015 Secondary
0 2500 arc current
arc current
and
and recovery
recovery
voltage.3)
SAN voltage.2)
RAFAEL-EL -10% 2250 36.37 12.70
INGA +20% 3000 29.64 10.50
+10% 2750 31.22 11.00
OCT 2015
0 2500 33.02 11.58
-10% 2250 35.03 12.21
+20% 3000 29.76 10.54
+10% 2750 31.36 11.05
DIC 2016
0 2500 33.16 11.32
-10% 2250 35.17 12.26
100
[kV]
75
50
25
0
-25
-50
-75
-100
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2015-6P.pl4; x-var t) v:X0093C
Fig Secondary arc current and recovery voltage.2 Max transient recovery voltage after
secondary-arc extinction(first peak value 41.7kVp)
6
20
[A]
15
10
5
0
-5
-10
-15
-20
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2015-6P.pl4; x-var t) c: -X0093C
Fig Secondary arc current and recovery voltage.3 Secondary-arc current relevant to max
transient recovery voltage(first peak value 17.06Ap)
2.3 500kV EL INGA – TISALEO transmission line
Tab Secondary arc current and recovery voltage.6 Secondary-arc current and recovery
Tap
position neutral recovery Secondry-arc
Operation
Line of reactance voltage(k current
mode
neutral (Ω) Vrms) (A rms)
reactance
+20% 960/3000 2.61 0.64
+10% 880/2750 6.65 1.62
11.46
2.75
(Fig
(Fig
EL INGA – Secondary
DIC 2016 Secondary
TISALEO 0 800/2500 arc current
arc current
and
and recovery
recovery
voltage.5)
voltage.4)
-10% 720/2250 16.97 4.00
7
35.00
[kV]
26.25
17.50
8.75
0.00
-8.75
-17.50
-26.25
-35.00
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12GPnew.pl4; x-var t) v:X0228B
Fig Secondary arc current and recovery voltage.4 max transient recovery voltage after
secondary-arc extinction(first peak value 6.7kVp)
4
[A]
3
-1
-2
-3
-4
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12GPnew.pl4; x-var t) c: -X0228B
Fig Secondary arc current and recovery voltage.5 secondary-arc current relevant to max
transient recovery voltage(first peak value 3.9Ap)
2.4 500kV TISALEO – CHORRILLOS transmission line
8
Tab Secondary arc current and recovery voltage.7 Secondary-arc current and recovery
Tap
position neutral recovery Secondry-arc
Operation
Line of reactance voltage(k current
mode
neutral (Ω) Vrms) (A rms)
reactance
+20% 3000/600 11.16 3.41
+10% 2750/550 15.51 4.66
20.38
6.03
(Fig
(Fig
TISALEO – Secondary
DIC 2016 Secondary
CHORRILLOS 0 2500/500 arc current
arc current
and
and recovery
recovery
voltage.7)
voltage.6)
-10% 2250/450 25.86 7.53
60
[kV]
40
20
-20
-40
-60
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12GPnew.pl4; x-var t) v:X0164A
Fig Secondary arc current and recovery voltage.6 max transient recovery voltage after
secondary-arc extinction(first peak value 11.74kVp)
9
9
[A]
6
-3
-6
-9
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12GPnew.pl4; x-var t) c: -X0164A
Fig Secondary arc current and recovery voltage.7 secondary-arc current relevant to max
transient recovery voltage(first peak value 8.53Ap)
2.5 230kV SAN RAFAEL – JIVINO transmission line
10
Tab Secondary arc current and recovery voltage.8 Secondary-arc current and recovery
recovery Secondry-arc
Operation
Line voltage(k current
mode
Vrms) (A rms)
29.77
9.67
(Fig
(Fig
Secondary
Double Secondary
DIC 2016 arc current
SAN RAFAEL circuit arc current
and
– JIVINO and recovery
recovery
voltage.9)
voltage.8)
Single
DIC 2016 25.99 8.71
circuit
Tab Secondary arc current and recovery voltage.9 Secondary-arc current and recovery
recovery Secondry-arc
Operation
Line Type of fault voltage(k current
mode
Vrms) (A rms)
Same
SAN Two-phase phase DIC 2016 40.99 13.64
RAFAEL grounding fault
– of two Variant
JIVINO circuit phase DIC 2016 36.17 11.59
fault
90
[kV]
75
60
45
30
15
0
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12-230kVGP逆相序.pl4; x-var t) v:X0248C
Fig Secondary arc current and recovery voltage.8 max transient recovery voltage after
secondary-arc extinction(first peak value 84.36kVp)
11
15
[A]
10
-5
-10
-15
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12-230kVGP逆相序.pl4; x-var t) c: -X0248C
Fig Secondary arc current and recovery voltage.9 secondary-arc current relevant to max
transient recovery voltage(first peak value 13.68Ap)
2.6 230kV TISALEO – TOTORAS transmission line
12
Tab Secondary arc current and recovery voltage.10 Secondary-arc current and recovery
recovery Secondry-arc
Operation
Line voltage(k current
mode
Vrms) (A rms)
30.26
1.53
(Fig
(Fig
Secondary
Double Secondary
DIC 2016 arc current
TISALEO – circuit arc current
and
TOTORAS and recovery
recovery
voltage.11)
voltage.10)
Single
DIC 2016 28.40 1.49
circuit
Tab Secondary arc current and recovery voltage.11 Secondary-arc current and recovery
recovery Secondry-arc
Operation
Line Type of fault voltage(k current
mode
Vrms) (A rms)
Same
Two-phase phase DIC 2016 41.41 2.15
TISALEO
grounding fault
–
of two Variant
TOTORAS
circuit phase DIC 2016 36.76 1.84
fault
90
[kV]
75
60
45
30
15
0
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12-230kVGP逆相序.pl4; x-var t) v:X0070C
Fig Secondary arc current and recovery voltage.10 max transient recovery voltage after
13
secondary-arc extinction(first peak value 85.60kVp)
2.500
[A]
1.875
1.250
0.625
0.000
-0.625
-1.250
-1.875
-2.500
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file 2016-12-230kVGP逆相序.pl4; x-var t) c: -X0070C
Fig Secondary arc current and recovery voltage.11 secondary-arc current relevant to max
transient recovery voltage(first peak value 2.17Ap)
14
3. Power frequency temporary overvoltage
The above three kinds of temporary power frequency overvoltage are assumed
the three-phase circuit breaker of the no-fault line side has not been tripping, That is
to say still connected to the substation busbar with power supply.
The action sequence of failure process decided by relay protection is shown in
Tab Power frequency temporary overvoltage.12.
type 0s 60ms
K0 tripping of 3 phases /
K1 single-phase grounding tripping of 3 phases
K2 two-phase grounding tripping of 3 phases
15
Tab Power frequency temporary overvoltage.13 Power frequency overvoltage of 500kV
600
[kV]
340
80
-180
-440
-700
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12GPnew 工频波形.pl4; x-var t) v:X0119A v:X0119B v:X0119C
Fig Power frequency temporary overvoltage.12 DIC 2016, two-phase grounding tripping of
3 phases at SAN RAFAEL side (Phase B:first peak 331kVp)
16
600
[kV]
340
80
-180
-440
-700
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12GPnew 工频波形.pl4; x-var t) v:X0117A v:X0117B v:X0117C
Fig Power frequency temporary overvoltage.13 DIC 2016, two-phase grounding tripping of
3 phases at EL INGA side (Phase B:first peak 320kVp)
17
600
[kV]
340
80
-180
-440
-700
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12GPnew工频波形.pl4; x-var t) v:X0228A v:X0228B v:X0228C
Fig Power frequency temporary overvoltage.14 DIC 2016, two-phase grounding tripping of
3 phases at EL INGA side (Phase B:first peak 320kVp)
600
[kV]
340
80
-180
-440
-700
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12GPnew工频波形.pl4; x-var t) v:X0151A v:X0151B v:X0151C
Fig Power frequency temporary overvoltage.15 DIC 2016, two-phase grounding tripping of
3 phases at TISALEO side (Phase B:first peak 443kVp)
3.3 500kV TISALEO – CHORRILLOS transmission line
18
Tab Power frequency temporary overvoltage.15 Power frequency overvoltage of 500kV
600
[kV]
400
200
-200
-400
-600
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12GPnew工频波形.pl4; x-var t) v:X0164A v:X0164B v:X0164C
Fig Power frequency temporary overvoltage.16 DIC 2016, two-phase grounding tripping of
3 phases at TISALEO side (Phase B:first peak 443kVp)
600
[kV]
400
200
-200
-400
-600
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12GPnew工频波形.pl4; x-var t) v:X0246A v:X0246B v:X0246C
Fig Power frequency temporary overvoltage.17 DIC 2016, two-phase grounding tripping of
19
3 phases at CHORRILLOS side (Phase B:first peak 377kVp)
Power frequency
Fault and
Operatio Fault overvoltage (p.u.)
Line tripping
n mode type SAN
side JIVINO
RAFAEL
K0 0.94 0.93
SAN
K1 0.99 0.90
RAFAEL
Double K2 0.93 0.77
circuit K0 0.97 0.97
DIC
JIVINO K1 0.94 1.08
2016
K2 0.88 1.08
K0 1.00 1.01
Single
JIVINO K1 0.99 1.11
circuit
K2 0.97 1.13
Maximum 1.00 1.13
300
[kV]
200
100
-100
-200
-300
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12-230kVGP波形.pl4; x-var t) v:X0247C v:X0247A v:X0247B
20
Fig Power frequency temporary overvoltage.18 DIC 2016, two-phase grounding tripping of
3 phases at JIVINO side (Phase B:first peak 148kVp)
Power frequency
Fault and
Operatio Fault overvoltage (p.u.)
Line tripping
n mode type TOTORA
side TISALEO
S
K0 0.99 0.99
TISALE
K1 1.05 0.96
O
Double K2 1.06 0.90
circuit K0 0.99 0.99
TOTOR
K1 0.96 1.02
AS
DIC K2 0.87 0.90
2016 K0 0.98 0.98
TISALE
K1 1.03 0.98
O
Single K2 1.02 0.94
circuit K0 1.00 1.00
TOTOR
K1 1.00 1.03
AS
K2 0.99 1.04
Maximum 1.06 1.04
21
300
[kV]
200
100
-100
-200
-300
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12-230kVGP波形.pl4; x-var t) v:X0070C v:X0070A v:X0070B
Fig Power frequency temporary overvoltage.19 DIC 2016, two-phase grounding tripping of
3 phases at TISALEO side (Phase B:first peak 223kVp)
250.0
[kV]
187.5
125.0
62.5
0.0
-62.5
-125.0
-187.5
-250.0
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12-230kVGP波形.pl4; x-var t) v:X0265C v:X0265A v:X0265B
Fig Power frequency temporary overvoltage.20 DIC 2016, two-phase grounding tripping of
3 phases at TOTORAS side (Phase B:first peak 183kVp)
22
4. Switching overvoltage
23
Tab Switching overvoltage.19 overvoltage of energizing no-load line of SAN RAFAEL-EL
closing resistor(Ω)
line overvoltage
300 400 500 600
maximum phase to
ground 2% 1.20 1.17 1.13 1.15
overvoltage(p.u.)
SAN RAFAEL-EL
maximum phase to
INGA(OCT 2015) 1.94 1.92 1.90 1.88
phase overvoltage(p.u.)
Calculate closing
0.160 0.176 0.187 0.195
resistor energy (MJ)
maximum phase to
ground 2% 1.19 1.18 1.18 1.18
overvoltage(p.u.)
EL INGA–TISALEO maximum phase to
1.99 1.94 1.95 1.99
phase overvoltage(p.u.)
Calculate closing
0.179 0.190 0.198 0.202
resistor energy (MJ)
maximum phase to
ground 2% 1.23 1.19 1.19 1.21
overvoltage(p.u.)
TISALEO–
maximum phase to
CHORRILLOS 2.04 1.93 1.96 1.99
phase overvoltage(p.u.)
Calculate closing
0.235 0.249 0.256 0.260
resistor energy (MJ)
Required value of closing resistor energy(MJ)
E=t×U2/R(U is 2 times of phase to ground 10.8 8.1 6.5 5.4
working voltage,t is turn-on time)
24
shown in Fig4.1.
Tab Switching overvoltage.20 Overvoltage of switching on no-load line from SAN RAFAEL
phase to phase
2% phase to ground MOA
overvoltage( p Shunt closing
overvoltage (p.u.) Energy(MJ)
Operation Side of .u.) Reactor resistor
Line
mode energizing SAN SAN SAN Neutral energy
maxim
EL EL EL
RAFA RAFA RAFAE (p.u.) (kJ)
INGA um INGA INGA
EL EL L
JUN 2015 EL INGA 1.17 1.12 1.17 1.99 1.95 <0.01 <0.01 0.22 181
SAN 1.08 1.17 1.17 1.87 1.92 <0.01 <0.01 0.23 176
SAN OCT 2015 RAFAEL
RAFAEL- EL INGA 1.16 1.06 1.16 1.96 1.88 <0.01 <0.01 0.22 180
EL INGA SAN 1.04 1.12 1.12 1.81 1.88 <0.01 <0.01 0.23 178
DIC 2016 RAFAEL
EL INGA 1.10 1.03 1.10 1.84 1.80 <0.01 <0.01 0.22 178
600
[kV]
380
160
-60
-280
-500
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file OCT_2015-SGIGHdc.pl4; x-var t) v:X0123A v:X0123B v:X0123C
Fig Switching overvoltage.21 OCT 2015, max 2% phase to ground overvoltage energizing
from SAN RAFAEL side(Phase A: first peak 484kVp, Phase B: first peak 445kVp, Phase
C: first peak 523kVp)
phase to phase
2% phase to ground MOA Shunt closing
overvoltage( p
Operation Side of overvoltage (p.u.) Energy(MJ) Reactor resistor
Line .u.)
mode energizing Neutral energy
EL TISAL maxim EL TISAL EL TISALE
(p.u.) (kJ)
INGA EO um INGA EO INGA O
EL INGA – EL INGA 1.05 1.18 1.18 1.78 1.94 <0.01 <0.01 0.22 190
DIC 2016
TISALEO TISALEO 1.15 1.07 1.15 2.00 1.87 <0.01 <0.01 0.23 184
500
[kV]
280
60
-160
-380
-600
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file DIC_2016-IGTSHdc.pl4; x-var t) v:X0163A v:X0163B v:X0163C
Fig Switching overvoltage.22 DIC 2016, max 2% phase to ground overvoltage energizing
from EL INGA side(Phase A: first peak 417kVp, Phase B: first peak 400kVp, Phase C: first
peak 370kVp)
4.2.4 500kV TISALEO – CHORRILLOS transmission line
Under the condition of installing closing resistor(8 ms for 400 Ω) of circuit
breaker of transmission line, Tab Switching overvoltage.22 shows the calculation
results of no-load line closing overvoltage for TISALEO – CHORRILLOS line.
It is can be drawn from the results that, when switching on no-load line, the
maximum phase to ground 2% overvoltage is 1.19p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 1.93p.u.. The maximum energy of
MOA is smaller than 0.01MJ. Max energy absorbed by the closing resistor is 249kJ.
The max 2% phase to ground overvoltage energizing from TISALEO side is shown in
Fig Switching overvoltage.23.
26
Tab Switching overvoltage.22 Overvoltage of switching on no-load line from TISALEO –
phase to phase
2% phase to ground MOA
overvoltage( p Shunt closing
overvoltage (p.u.) energy(MJ)
Operation Side of .u.) Reactor resistor
Line
mode energizing CHOR CHOR Neutral energy
TISAL maxim TISAL TISALE CHORR
RILL RILLO (p.u.) (kJ)
EO um EO O ILLOS
OS S
TISALEO TISALEO 1.11 1.18 1.19 1.89 1.93 <0.01 <0.01 0.22 249
– 1.15 1.06 1.15 1.88 1.79 <0.01 <0.01 0.22 226
DIC 2016 CHORRIL
CHORRIL
LOS
LOS
500
[kV]
280
60
-160
-380
-600
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file DIC_2016-TSCSHdc.pl4; x-var t) v:X0166A v:X0166B v:X0166C
Fig Switching overvoltage.23 DIC 2016, max 2% phase to ground overvoltage energizing
from TISALEO side(Phase A: first peak 467kVp, Phase B: first peak 431kVp, Phase C:
first peak 445kVp)
4.2.5 230kV SAN RAFAEL – JIVINO transmission line
Without closing resistor of circuit breaker of transmission line, Tab Switching
overvoltage.23 shows the calculation results of no-load line closing overvoltage for
230kV SAN RAFAEL – JIVINO line.
It is can be drawn from the results that, when switching on no-load line, the
maximum phase to ground 2% overvoltage is 2.03p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 3.40p.u.. The maximum energy of
MOA is smaller than 0.04MJ. The max 2% phase to ground overvoltage energizing
from SAN RAFAEL side is shown in Fig Switching overvoltage.24.
27
Tab Switching overvoltage.23 Overvoltage of switching on no-load line from SAN RAFAEL
– JIVINO(1.0p.u.= 2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
overvoltage (p.u.) energy(MJ)
Operation Side of .u.)
Line
mode energizing SAN SAN SAN
JIVIN maxim
RAFAE RAFAE JIVINO RAFAE JIVINO
O um
L L L
SAN 1.47 1.74 1.85 2.36 3.04 <0.01 0.02
Double
SAN DIC 2016 RAFAEL
circuit
RAFAEL JIVINO 1.68 1.36 1.72 2.56 2.12 <0.01 <0.01
–JIVINO Single SAN 1.66 1.79 2.03 2.72 3.40 <0.01 0.04
DIC 2016
circuit RAFAEL
400
[kV]
250
100
-50
-200
-350
-500
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file 2016-12RFJVH-Idc.pl4; x-var t) v:X0217A v:X0217B v:X0217C
Fig Switching overvoltage.24 DIC 2016, max 2% phase to ground overvoltage energizing
from SAN RAFAEL side(Phase A: first peak 366kVp, Phase B: first peak 352kVp, Phase
C: first peak 406kVp)
4.2.6 230kV TISALEO – TOTORAS transmission line
Without closing resistor of circuit breaker of transmission line, Tab Switching
overvoltage.24 shows the calculation results of no-load line closing overvoltage for
TISALEO – TOTORAS line.
It is can be drawn from the results that, when switching on no-load line, the
maximum phase to ground 2% overvoltage is 1.82p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 3.28p.u.. The maximum energy of
MOA is smaller than 0.01MJ. The max 2% phase to ground overvoltage energizing
from TISALEO side is shown in Fig Switching overvoltage.25.
28
Tab Switching overvoltage.24 Overvoltage of switching on no-load line from TISALEO –
TOTORAS(1.0p.u.= 2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
Operation Side of overvoltage (p.u.) energy(MJ)
Line .u.)
mode energizing
TISAL TOTO maxim TISAL TOTOR TISALE TOTORA
EO RAS um EO AS O S
TISALEO 1.65 1.71 1.82 2.64 3.26 <0.01 <0.01
Double
TISALEO DIC 2016 TOTORA 1.73 1.09 1.76 3.11 1.85 <0.01 <0.01
circuit
– S
TOTORA TISALEO 1.70 1.74 1.81 2.94 3.17 <0.01 <0.01
Single
S DIC 2016 TOTORA 1.74 1.13 1.76 3.28 1.88 <0.01 <0.01
circuit
S
400
[kV]
300
200
100
-100
-200
-300
-400
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file 2016-12TATTHdc.pl4; x-var t) v:X0218A v:X0218B v:X0218C
Fig Switching overvoltage.25 DIC 2016, max 2% phase to ground overvoltage energizing
from TISALEO side(Phase A: first peak 363kVp, Phase B: first peak 191kVp, Phase C:
first peak 331kVp)
phase to phase
2% phase to ground
overvoltage( p MOA 能量(MJ) Shunt closing
overvoltage (p.u.)
Operation Side of .u.) Reactor resistor
Line
mode energizing SAN SAN SAN Neutral energy
EL maxim EL EL
RAFA RAFA RAFAE (p.u.) (kJ)
INGA um INGA INGA
EL EL L
JUN 2015 EL INGA 1.22 1.13 1.22 1.98 1.92 <0.01 <0.01 0.18 169
SAN 1.09 1.07 1.12 1.83 1.89 <0.01 <0.01 0.17 168
SAN OCT 2015 RAFAEL
RAFAEL- EL INGA 1.06 1.08 1.08 1.90 1.84 <0.01 <0.01 0.17 172
EL INGA SAN 1.01 1.04 1.04 1.78 1.81 <0.01 <0.01 0.17 173
DIC 2016 RAFAEL
EL INGA 1.03 1.03 1.03 1.80 1.76 <0.01 <0.01 0.17 178
500
[kV]
280
60
-160
-380
-600
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file JUN_2015-IGSGCdc.pl4; x-var t) v:X0119A v:X0119B v:X0119C
Fig Switching overvoltage.26 JUN 2015, max 2% phase to ground overvoltage single-phase
reclosing of CB from EL INGA side(Phase A: first peak 439kVp, Phase B: first peak 55kVp,
Phase C: first peak 442kVp)
30
4.3.2 500kV EL INGA – TISALEO transmission line
Under the condition of installing closing resistor(8 ms for 400 Ω) of circuit
breaker of transmission line, Tab Switching overvoltage.27 shows the calculation
results of single-phase reclosing of CB overvoltage for EL INGA – TISALEO line.
It is can be drawn from the results that, when single-phase reclosing of CB, the
maximum phase to ground 2% overvoltage is 1.07p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 1.90p.u.. The maximum energy of
MOA is smaller than 0.01MJ. Max energy absorbed by the closing resistor is 159kJ.
The max 2% phase to ground single-phase reclosing of CB overvoltage from EL
INGA side is shown in Fig Switching overvoltage.27.
TISALEO(1.0p.u.= 2 *550/ 3 )
phase to phase
2% phase to ground MOA Shunt closing
overvoltage( p
Operation Side of overvoltage (p.u.) energy(MJ) Reactor resistor
Line .u.)
mode energizing Neutral energy
EL TISAL maxim EL TISAL EL TISALE
(p.u.) (kJ)
INGA EO um INGA EO INGA O
EL INGA EL INGA 1.04 1.07 1.07 1.76 1.82 <0.01 <0.01 0.16 159
– DIC 2016 1.02 1.05 1.05 1.90 1.82 <0.01 <0.01 0.16 152
TISALEO
TISALEO
500
[kV]
375
250
125
-125
-250
-375
-500
0.00 0.03 0.06 0.09 0.12 [s] 0.15
(file DIC_2016-IGTSCdc.pl4; x-var t) v:X0163A v:X0163B v:X0163C
Fig Switching overvoltage.27 DIC 2016, max 2% phase to ground overvoltage single-phase
reclosing of CB from EL INGA side(Phase A: first peak 433kVp, Phase B: first peak 36kVp,
Phase C: first peak 428kVp)
4.3.3 500kV TISALEO – CHORRILLOS transmission line
Under the condition of installing closing resistor(8 ms for 400 Ω) of circuit
31
breaker of transmission line, Tab Switching overvoltage.28 shows the calculation
results of single-phase reclosing of CB overvoltage for TISALEO – CHORRILLOS
line.
It is can be drawn from the results that, when single-phase reclosing of CB, the
maximum phase to ground 2% overvoltage is 1.09p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 1.86p.u.. The maximum energy of
MOA is smaller than 0.01MJ. Max energy absorbed by the closing resistor is 219kJ.
The max 2% phase to ground single-phase reclosing of CB overvoltage from
TISALEO side is shown in Fig Switching overvoltage.28.
CHORRILLOS(1.0p.u.= 2 *550/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p Shunt closing
overvoltage (p.u.) energy(MJ)
Operation Side of .u.) Reactor resistor
Line
mode energizing CHOR CHOR Neutral energy
TISAL maxim TISAL TISALE CHORR
RILL RILLO (p.u.) (kJ)
EO um EO O ILLOS
OS S
TISALEO TISALEO 1.07 1.09 1.09 1.81 1.86 <0.01 <0.01 0.16 219
– 1.01 1.02 1.02 1.81 1.74 <0.01 <0.01 0.16 203
DIC 2016 CHORRIL
CHORRIL
LOS
LOS
500
[kV]
375
250
125
-125
-250
-375
-500
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file DIC_2016-TSCSCdc.pl4; x-var t) v:X0243A v:X0243B v:X0243C
Fig Switching overvoltage.28 DIC 2016, max 2% phase to ground overvoltage single-phase
reclosing of CB from TISALEO side(Phase A: first peak 418kVp, Phase B: first peak
417kVp, Phase C: first peak 34kVp)
4.3.4 230kV SAN RAFAEL – JIVINO transmission line
32
Without closing resistor of circuit breaker of transmission line, Tab Switching
overvoltage.29 shows the calculation results of single-phase reclosing of CB
overvoltage for SAN RAFAEL – JIVINO line.
It is can be drawn from the results that, when single-phase reclosing of CB, the
maximum phase to ground 2% overvoltage is 1.95p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 2.50p.u.. The maximum energy of
MOA is smaller than 0.03MJ. The max 2% phase to ground single-phase reclosing of
CB overvoltage from SAN RAFAEL side is shown in Fig Switching overvoltage.29.
phase to phase
2% phase to ground MOA
overvoltage( p
overvoltage (p.u.) energy(MJ)
Operation Side of .u.)
Line
mode energizing SAN SAN SAN
JIVIN maxim
RAFAE RAFAE JIVINO RAFAE JIVINO
O um
L L L
SAN 1.43 1.73 1.81 2.23 2.48 <0.01 <0.01
Double
SAN DIC 2016 RAFAEL
circuit
RAFAEL JIVINO 1.60 1.34 1.60 2.35 2.03 <0.01 <0.01
–JIVINO Single SAN 1.64 1.78 1.95 2.33 2.50 <0.01 0.03
DIC 2016
circuit RAFAEL
400
[kV]
300
200
100
-100
-200
-300
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file 2016-12RFJVC-Idc.pl4; x-var t) v:X0219A v:X0219B v:X0219C
Fig Switching overvoltage.29 DIC 2016, max 2% phase to ground overvoltage single-phase
reclosing of CB from SAN RAFAEL side(Phase A: first peak 176kVp, Phase B: first peak
181kVp, Phase C: first peak 33kVp)
4.3.5 230 kV TISALEO – TOTORAS transmission line
33
Without closing resistor of circuit breaker of transmission line, Tab Switching
overvoltage.30 shows the calculation results of single-phase reclosing of CB
overvoltage for TISALEO – TOTORAS line.
It is can be drawn from the results that, when single-phase reclosing of CB, the
maximum phase to ground 2% overvoltage is 1.80p.u., along with transmission line.
The maximum phase to phase overvoltage of line is 2.61p.u.. The maximum energy of
MOA is smaller than 0.01MJ. The max 2% phase to ground single-phase reclosing of
CB overvoltage from TISALEO side is shown in Fig Switching overvoltage.30.
TOTORAS(1.0p.u.= 2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
Operation Side of overvoltage (p.u.) energy(MJ)
Line .u.)
mode energizing
TISAL TOTO maxim TISAL TOTOR TISALE TOTORA
EO RAS um EO AS O S
TISALEO 1.62 1.73 1.79 2.34 2.56 <0.01 <0.01
Double
TISALEO DIC 2016 TOTORA 1.72 1.08 1.73 2.59 1.80 <0.01 <0.01
circuit
– S
TOTORA TISALEO 1.69 1.74 1.80 2.48 2.54 <0.01 <0.01
Single
S DIC 2016 TOTORA 1.73 1.12 1.74 2.61 1.82 <0.01 <0.01
circuit
S
400
[kV]
300
200
100
-100
-200
-300
0.00 0.05 0.10 0.15 0.20 0.25 [s] 0.30
(file 2016-12TATTC-Idc.pl4; x-var t) v:X0212A v:X0212B v:X0212C
Fig Switching overvoltage.30 DIC 2016, max 2% phase to ground overvoltage single-phase
reclosing of CB from TISALEO side(Phase A: first peak 198kVp, Phase B: first peak
195kVp, Phase C: first peak 39kVp)
34
4.4 Failure rate calculation
failure rate
line
(times per energizing operation)
500kV SAN RAFAEL-EL INGA 1.539385×10-10
500kV EL INGA–TISALEO 1.543006×10-8
500kV TISALEO–CHORRILLOS 7.643719×10-9
230kV SAN RAFAEL – JIVINO 4.485060×10-8
230kV TISALEO – TOTORAS 1.386822×10-8
During live working on transmission line, using the single phase closing
operation of CB is stopped and the three phases CB at the both ends of the line with
live working will be tripped when single phase ground occurs. The action sequence of
tripping is shown in Tab Switching overvoltage.32.
The three phases tripping voltage determines the risk probability of live working.
The three phases tripping voltage also occurs when single phase closing is
unsuccessful due to permanent grounding fault. The tripping voltage of the latter is
less than the former.
Tab Switching overvoltage.32 action sequence of fault tripping
time Operating procedure
0s Live working on transmission line
20ms Single-phase grounding fault occurs
100ms three phases CB nearest fault are tripping at first
120ms Three phases CB at remote end are Tripping
140ms Clearing the single-phase grounding fault
35
4.5.1 500kV SAN RAFAEL-EL INGA transmission line
Tab Switching overvoltage.33 shows the calculation results of fault tripping
overvoltage for SAN RAFAEL-EL INGA line.
It is can be drawn from the results that the maximum phase to ground 2%
overvoltage is 1.37p.u., along with transmission line. The maximum phase to phase
overvoltage of line is 1.99p.u.. The maximum energy of MOA is smaller than 0.01MJ.
The max 2% phase to ground fault tripping overvoltage from EL INGA side is shown
in Fig Switching overvoltage.31.
phase to phase
2% phase to ground MOA
overvoltage( p Shunt
overvoltage (p.u.) energy(MJ)
Operation .u.) Reactor
Line fault side
mode SAN SAN SAN Neutral
ELmaxim EL EL
RAFA RAFA RAFAE (p.u.)
INGA um INGA INGA
EL EL L
SAN 1.29 1.19 1.29 1.96 1.93 <0.01 <0.01 0.33
JUN 2015 RAFAEL
EL INGA 1.37 1.22 1.37 1.99 1.97 <0.01 <0.01 0.33
SAN SAN 1.27 1.21 1.27 1.93 1.89 <0.01 <0.01 0.30
RAFAEL- OCT 2015 RAFAEL
EL INGA EL INGA 1.29 1.32 1.32 1.95 1.98 <0.01 <0.01 0.31
SAN 1.26 1.21 1.26 1.87 1.82 <0.01 <0.01 0.32
DIC 2016 RAFAEL
EL INGA 1.17 1.33 1.33 1.92 1.95 <0.01 <0.01 0.31
600
[kV]
380
160
-60
-280
-500
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(fileFig
DIC_2016-IGSGJdc.pl4; x-var t) v:X0021A
Switching overvoltage.31 DIC 2016,v:X0021B
max 2%v:X0021C
phase to ground overvoltage of fault
tripping from EL INGA side(start from the ground fault moment, Phase A: first peak
507kVp, Phase B: first peak 66kVp, Phase C: first peak 446kVp)
36
4.5.2 500kV EL INGA – TISALEO transmission line
Tab Switching overvoltage.34 shows the calculation results of fault tripping
overvoltage for EL INGA – TISALEO line.
It is can be drawn from the results that the maximum phase to ground 2%
overvoltage is 1.37p.u., along with transmission line. The maximum phase to phase
overvoltage of line is 2.08p.u.. The maximum energy of MOA is smaller than 0.01MJ.
The max 2% phase to ground fault tripping overvoltage from EL INGA side is shown
in Fig Switching overvoltage.32.
phase to phase
2% phase to ground MOA Shunt
overvoltage( p
Operation overvoltage (p.u.) energy(MJ) Reactor
Line fault side .u.)
mode Neutral
EL TISAL maxim EL TISAL EL TISALE
(p.u.)
INGA EO um INGA EO INGA O
EL INGA – EL INGA 1.37 1.16 1.37 2.08 2.05 <0.01 <0.01 0.32
DIC 2016
TISALEO TISALEO 1.24 1.29 1.29 1.98 2.02 <0.01 <0.01 0.32
600
[kV]
340
80
-180
-440
-700
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file DIC_2016-IGTSJdc.pl4; x-var t) v:X0233A v:X0233B v:X0233C
Fig Switching overvoltage.32 DIC 2016, max 2% phase to ground overvoltage of fault
tripping from EL INGA side(start from the ground fault moment, Phase A: first peak
488kVp, Phase B: first peak 43kVp, Phase C: first peak 476kVp)
4.5.3 500kV TISALEO – CHORRILLOS transmission line
Tab Switching overvoltage.35 shows the calculation results of fault tripping
overvoltage for TISALEO – CHORRILLOS line.
It is can be drawn from the results that the maximum phase to ground 2%
overvoltage is 1.50p.u., along with transmission line. The maximum phase to phase
37
overvoltage of line is 2.35p.u.. The maximum energy of MOA is smaller than 0.01MJ.
The max 2% phase to ground fault tripping overvoltage from TISALEO side is shown
in Fig Switching overvoltage.33.
phase to phase
2% phase to ground MOA Shunt
overvoltage( p
Operation overvoltage (p.u.) energy(MJ) Reactor
Line fault side .u.)
mode Neutral
TISAL CHORR maxim TISAL CHORRI TISALE CHORRIL
(p.u.)
EO ILLOS um EO LLOS O LOS
TISALEO – TISALEO 1.50 1.20 1.50 2.35 2.31 <0.01 <0.01 0.31
CHORRIL DIC 2016 1.16 1.29 1.29 1.98 2.01 <0.01 <0.01 0.33
CHORRILLOS
LOS
700
[kV]
440
180
-80
-340
-600
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file DIC_2016-TSCSJdc.pl4; x-var t) v:X0182A v:X0182B v:X0182C
Fig Switching overvoltage.33 DIC 2016, max 2% phase to ground overvoltage of fault
tripping from TISALEO side(start from the ground fault moment, Phase A: first peak
507kVp, Phase B: first peak 586kVp, Phase C: first peak 295kVp)
4.5.4 230kV SAN RAFAEL – JIVINO transmission line
Tab Switching overvoltage.36 shows the calculation results of fault tripping
overvoltage for SAN RAFAEL – JIVINO line.
It is can be drawn from the results that the maximum phase to ground 2%
overvoltage is 1.36p.u., along with transmission line. The maximum phase to phase
overvoltage of line is 2.09p.u.. The maximum energy of MOA is smaller than 0.01MJ.
The max 2% phase to ground fault tripping overvoltage from JIVINO side is shown in
Fig Switching overvoltage.34.
38
Tab Switching overvoltage.36 fault tripping overvoltage(1.0p.u.= 2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
overvoltage (p.u.) energy(MJ)
Operation .u.)
Line fault side
mode SAN SAN SAN
JIVIN maxim
RAFAE RAFAE JIVINO RAFAE JIVINO
O um
L L L
SAN 1.22 1.17 1.22 1.79 1.77 <0.01 <0.01
Double
DIC 2016 RAFAEL
SAN circuit
JIVINO 1.23 1.22 1.23 1.81 1.87 <0.01 <0.01
RAFAEL
SAN 1.09 1.03 1.11 1.72 1.67 <0.01 <0.01
–JIVINO Single
DIC 2016 RAFAEL
circuit
JIVINO 1.35 1.31 1.36 1.97 2.09 <0.01 <0.01
300
[kV]
200
100
-100
-200
-300
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12JVRFJ-I0.1dc.pl4; x-var t) v:X0213A v:X0213B v:X0213C
Fig Switching overvoltage.34 DIC 2016, max 2% phase to ground overvoltage of fault
tripping from JIVINO side(start from the ground fault moment, Phase A: first peak
194kVp, Phase B: first peak 187kVp, Phase C: first peak 206kVp)
4.5.5 230kV TISALEO – TOTORAS transmission line
Tab Switching overvoltage.37 shows the calculation results of fault tripping
overvoltage for TISALEO – TOTORAS line.
It is can be drawn from the results that the maximum phase to ground 2%
overvoltage is 1.43p.u., along with transmission line. The maximum phase to phase
overvoltage of line is 2.01p.u.. The maximum energy of MOA is smaller than 0.01MJ.
The max 2% phase to ground fault tripping overvoltage from TISALEO side is shown
in Fig Switching overvoltage.35.
39
Tab Switching overvoltage.37 fault tripping overvoltage(1.0p.u.= 2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
Operation overvoltage (p.u.) energy(MJ)
Line fault side .u.)
mode
TISAL TOTO maxim TISAL TOTOR TISALE TOTORA
EO RAS um EO AS O S
Double TISALEO 1.43 1.19 1.43 1.80 1.80 <0.01 <0.01
DIC 2016
TISALEO – circuit TOTORAS 1.20 1.20 1.25 1.92 1.88 <0.01 <0.01
TOTORAS Single TISALEO 1.21 1.22 1.22 1.86 1.85 <0.01 <0.01
DIC 2016
circuit TOTORAS 1.22 1.27 1.27 2.01 2.01 <0.01 <0.01
300
[kV]
200
100
-100
-200
-300
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12TATTJ0.1dc.pl4; x-var t) v:X0021A v:X0021B v:X0021C
Fig Switching overvoltage.35 DIC 2016, max 2% phase to ground overvoltage of fault
tripping from TISALEO side(start from the ground fault moment, Phase A: first peak
286kVp, Phase B: first peak 225kVp, Phase C: first peak 27kVp)
4.6 Two phase grounding faults at 230kV double circuit line
The two phases back flashover of the double circuit line take place simultaneity
due to strong lightning stroking a tower top. The two phases grounding fault could be
at one circuit or each one phase of two circuit.
The action sequence of fault tripping is shown in Tab Switching overvoltage.38.
Tab Switching overvoltage.38 action sequence of two phase grounding fault
time Operating state
0s Transmission line is in operation
20ms Two-phase grounding at two circuit
100ms Tripping the fault side of two circuit (six phase)
2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
overvoltage (p.u.) energy(MJ)
Type of Operation .u.)
Line fault side
fault mode SAN SAN SAN
JIVIN maxim
RAFAE RAFAE JIVINO RAFAE JIVINO
O um
L L L
Same SAN 1.21 1.12 1.21 1.68 1.66 <0.01 <0.01
phase DIC 2016 RAFAEL
SAN
fault JIVINO 1.16 1.61 1.61 1.89 2.04 <0.01 <0.01
RAFAEL –
Variant SAN 1.23 1.09 1.23 1.74 1.71 <0.01 <0.01
JIVINO
phase DIC 2016 RAFAEL
fault JIVINO 1.15 1.61 1.61 2.49 1.88 <0.01 <0.01
400
[kV]
300
200
100
0
-100
-200
-300
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12JVRFJ同名相dc.pl4; x-var t) v:X0292A v:X0292B v:X0292C
Fig Switching overvoltage.36 DIC 2016, max 2% phase to ground overvoltage of fault
tripping from JIVINO side(start from the ground fault moment, Phase B: first peak
242kVp, Phase C: first peak 183kVp)
4.6.2 230kV TISALEO – TOTORAS transmission line
Tab Switching overvoltage.40 shows the calculation results of two-phase
grounding of two circuit overvoltage for TISALEO – TOTORAS line.
It is can be drawn from the results that the maximum phase to ground 2%
overvoltage is 1.44p.u., along with transmission line. The maximum phase to phase
overvoltage of line is 1.90p.u.. The maximum energy of MOA is smaller than 0.01MJ.
41
The max 2% phase to ground fault tripping overvoltage from TISALEO side is shown
in Fig Switching overvoltage.37.
2 *245/ 3 )
phase to phase
2% phase to ground MOA
overvoltage( p
Type of Operation overvoltage (p.u.) energy(MJ)
Line fault side .u.)
fault mode
TISAL TOTO maxim TISAL TOTOR TISALE TOTORA
EO RAS um EO AS O S
Same TISALEO 1.44 1.15 1.44 1.75 1.74 <0.01 <0.01
phase DIC 2016 1.20 1.28 1.31 1.87 1.90 <0.01 <0.01
TOTORAS
TISALEO – fault
TOTORAS Variant TISALEO 1.43 1.19 1.43 1.76 1.78 <0.01 <0.01
phase DIC 2016 1.26 1.33 1.33 1.87 1.75 <0.01 <0.01
TOTORAS
fault
300
[kV]
200
100
-100
-200
-300
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file 2016-12TATTJ同名相dc.pl4; x-var t) v:X0021A v:X0021B v:X0021C
Fig Switching overvoltage.37 DIC 2016, max 2% phase to ground overvoltage of fault
tripping from TISALEO side(start from the ground fault moment, Phase B: first peak
225kVp, Phase C: first peak 287kVp)
4.7 Transformer energizing overvoltage of 500kV substation
43
Tab Switching overvoltage.43 Transformer energizing from EL INGA 500 kV side
overvoltage
(p.u)
inrush
500kV side 230kV side
Substation Operation mode current
Phase- Phase-
Phase- Phase- (kAp)
groun groun
phase phase
d d
One transformer already in
JUN operation,energizing
1.66 2.47 1.70 2.54 1.45
2015 another transformer with
no-load
Two lines of SAN RAFAEL-
EL INGA and 2 units of 1.70 2.66 1.72 2.72 1.24
OCT
CCS
2015
One line of SAN RAFAEL-
1.76 2.99 1.81 3.09 1.02
EL INGA EL INGA and 1 unit of CCS
Two lines of SAN RAFAEL-
EL INGA and 3 units of
1.69 2.49 1.71 2.53 1.79
CCS, EL INGA-TISALEO
DIC line in operation
2016 One line of SAN RAFAEL-
EL INGA and 1 unit of
1.75 2.97 1.80 3.05 1.03
CCS, EL INGA-TISALEO
line not in operation
800
[kV]
500
200
-100
-400
-700
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2015-10INGA合空变单机DC.pl4; x-var t) v:X0017B v:X0017C v:X0017A
44
1500
[A]
1000
500
-500
-1000
-1500
-2000
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2016-12INGA合空变DC.pl4; x-var t) c:X0021B-ELIN5B c:X0021C-ELIN5C c:X0021A-ELIN5A
Fig Switching overvoltage.39 maximum inrush current of 500kV side(Phase A: first peak
0.62kAp, Phase B: first peak 1.79kAp, Phase C: first peak 1.40kAp)
45
Tab Switching overvoltage.44 Transformer energizing from SAN RAFAEL 500 kV side
overvoltage
(p.u)
inrush
500kV side 230kV side
Substation Operation mode current
Phase- Phase-
Phase- Phase- (kAp)
groun groun
phase phase
d d
Two lines of CCS- SAN
RAFAEL and 2 units of CCS,
1.70 2.41 1.72 2.49 1.49
EL INGA-SAN RAFAEL
OCT lines are in operation
2015 One line of CCS- SAN
RAFAEL and 1 unit of CCS,
1.77 3.35 1.79 3.45 0.90
EL INGA-SAN RAFAEL
SAN lines are not in operation
RAFAEL Two lines of CCS- SAN
RAFAEL and 3 units of CCS,
1.71 2.42 1.72 2.49 1.60
EL INGA-SAN RAFAEL
DIC lines are in operation
2016 One line of CCS- SAN
RAFAEL and 1 unit of CCS,
1.77 3.39 1.79 3.50 0.96
EL INGA-SAN RAFAEL
lines are not in operation
800
[kV]
600
400
200
-200
-400
-600
-800
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2015-10RAFA合空变单机DC.pl4; x-var t) v:X0021B v:X0021C v:X0021A
46
1600
[A]
1200
800
400
-400
-800
-1200
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2016-12RAFA合空变DC.pl4; x-var t) c:X0018B-X0022B c:X0018C-X0022C c:X0018A-X0022A
Fig Switching overvoltage.41 maximum inrush current of 500kV side(Phase A: first peak
0.44kAp, Phase B: first peak 1.60kAp, Phase C: first peak 1.13kAp)
47
Tab Switching overvoltage.45 Transformer energizing from TISALEO 500 kV side
overvoltage
(p.u)
inrush
500kV side 230kV side
Substation Operation mode current
Phase- Phase-
Phase- Phase- (kAp)
groun groun
phase phase
d d
INGA-SAN RAFAEL lines
and TISALEO-CHORRILLOS
line are in operation, 3 1.70 2.42 1.72 2.49 1.48
transformers in EL INGA
and 3 units of CCS
one transformer in EL
INGA, INGA-SAN RAFAEL
lines and TISALEO- 1.72 2.70 1.73 2.76 1.04
CHORRILLOS line are not in
operation
DIC
TISALEO one transformer in EL
2016
INGA, one line of INGA-
SAN RAFAEL, one line of
CCS- SAN RAFAEL and 1 1.71 2.73 1.73 2.72 1.10
unit of CCS, TISALEO-
CHORRILLOS line is not in
operation
EL INGA- TISALEO line is
not in operation, TISALEO-
1.70 2.68 1.71 2.77 1.16
CHORRILLOS line is in
operation
800
[kV]
540
280
20
-240
-500
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2016-12TISALEO合空变1DC.pl4; x-var t) v:X0021B v:X0021C v:X0021A
Fig Switching overvoltage.42 maximum transformer energizing overvoltage of 500kV
side(Phase A: first peak 463kVp, Phase B: first peak 431kVp, Phase C: first peak
464kVp)
48
1500
[A]
1000
500
-500
-1000
-1500
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2016-12TISALEO合空变DC.pl4; x-var t) c:TISL5B-X0021B c:TISL5C-X0021C c:TISL5A-X0021A
Fig Switching overvoltage.43 maximum inrush current of 500kV side(Phase A: first peak
1.29kAp, Phase B: first peak 0.58kAp, Phase C: first peak 1.48kAp)
49
Tab Switching overvoltage.46 Transformer energizing from CHORRILLOS 500 kV side
overvoltage
(p.u)
inrush
500kV side 230kV side
Substation Operation mode current
Phase- Phase-
Phase- Phase- (kAp)
groun groun
phase phase
d d
TISALEO-CHORRILLOS
line ,TISALEO-EL INGA
line and two lines of EL 1.69 2.68 1.71 2.77 1.19
INGA-SAN RAFAEL are all
in operation, 3 units of CCS
TISALEO-CHORRILLOS
line ,TISALEO-EL INGA
line and one line of EL 1.69 2.68 1.71 2.77 1.15
INGA-SAN RAFAEL are all
in operation, 1 unit of CCS
TISALEO-CHORRILLOS
line in operation,
1.70 2.70 1.71 2.77 1.05
TISALEO-EL INGA line not
CHORRI DIC in operation
LLOS 2016 TISALEO-CHORRILLOS
line ,TISALEO-EL INGA
line are in operation, two
lines of EL INGA-SAN 1.69 2.66 1.71 2.74 1.14
RAFAEL are not in
operation, 3 transformers in
EL INGA
TISALEO-CHORRILLOS
line ,TISALEO-EL INGA
line are in operation, two
lines of EL INGA-SAN 1.69 2.67 1.71 2.75 1.12
RAFAEL are not in
operation, one transformer
in EL INGA
50
500
[kV]
240
-20
-280
-540
-800
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2016-12CHRS合空变无IG-TSdc.pl4; x-var t) v:X0021B v:X0021C v:X0021A
Fig Switching overvoltage.44 maximum transformer energizing overvoltage of 500kV
side(Phase A: first peak 760kVp, Phase B: first peak 440kVp, Phase C: first peak
432kVp)
1200
[A]
800
400
-400
-800
-1200
0.0 0.2 0.4 0.6 0.8 [s] 1.0
(file 2016-12CHRS合空变dc.pl4; x-var t) c:CHLS5B-X0021B c:CHLS5C-X0021C c:CHLS5A-X0021A
Fig Switching overvoltage.45 maximum inrush current of 500kV side(Phase A: first peak
1.04kAp, Phase B: first peak 0.76kAp, Phase C: first peak 1.19kAp)
51
5. Parameter selection of neutral reactor of shunt reactor
The maximum power frequency current I10 flowing through the neutral reactor
can be figured out on the basis of the maximum power frequency overvoltage of the
reactor neutral. And the continuous working current Ic=I10/10. Considering 50%
margin of I10, the max power frequency current and the capacity of neutral reactor is
shown in Tab Parameter selection of neutral reactor of shunt reactor of 500kV
transmission line.47.
119.1(consider
800 12 116
EL INGA- 50% margin)
TISALEO 38.1 (consider
2500 4 40
50% margin)
52
38.1 (consider
2500 4 40
TISALEO – 50% margin)
CHORRILLOS 190.5 (consider
500 20 200
50% margin)
53
6. Induced current and voltage of 230kV double-circuit
line
For SAN RAFAEL – JIVINO line, it can be shown in the results that
maximum electrostatic induction voltage is 10.50kV; the maximum
electromagnetic induction voltage is 3.69kV; the maximum electrostatic
induction current is 2.78A; the maximum electromagnetic induction current is
126.48A.
54
disconnector.
55
Tab Induced current and voltage of 230kV double-circuit line.48 induced current and
Voltage of Voltage of
Status of Current of Current of
electrostatic electromagnetic
Dead line earthing electrostatic electromagnetic
induction( induction(kV
switches induction(A) induction(A)
kV) )
earthing
switches of
/ / / 122.53
both ends
closed
1st circuit of
earthing
SAN
switches of
RAFAEL – 10.50 / / /
both ends
JIVINO
opened
double-circuit
One
transmission
earthing
line
switch
/ 2.78 3.54 /
opened,
while other
is closed
earthing
switches of
/ / / 126.48
both ends
closed
2nd circuit of
earthing
SAN
switches of
RAFAEL – 10.04 / / /
both ends
JIVINO
opened
double-circuit
One
transmission
earthing
line
switch
/ 2.69 3.69 /
opened,
while other
is closed
Maximum 10.50 2.78 3.69 126.48
56
30
[kV]
20
10
-10
-20
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file RF-JV感应电压PI波形.pl4; x-var t) v:K0A v:K0B v:K0C
Fig Induced current and voltage of 230kV double-circuit line.46 electrostatic induction
voltage after grounding switch to cut off the capacitive current for SAN RAFAEL – JIVINO
line(Phase A: first peak 26.2kVp, Phase B: first peak 9.3kVp, Phase C: first peak
16.8kVp)
57
Tab Induced current and voltage of 230kV double-circuit line.49 induced current and
Voltage of Voltage of
Status of Current of Current of
electrostatic electromagnetic
Dead line earthing electrostatic electromagnetic
induction( induction(kV
switches induction(A) induction(A)
kV) )
earthing
switches of
/ / / 131.67
both ends
closed
1st circuit of earthing
TISALEO – switches of
9.95 / / /
TOTORAS both ends
double-circuit opened
transmission One
line earthing
switch
/ 0.42 0.59 /
opened,
while other
is closed
earthing
switches of
/ / / 135.68
both ends
closed
2nd circuit of earthing
TISALEO – switches of
9.80 / / /
TOTORAS both ends
double-circuit opened
transmission One
line earthing
switch
/ 0.41 0.62 /
opened,
while other
is closed
Maximum 9.95 0.42 0.62 135.68
58
30
[kV]
20
10
-10
-20
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file TS -TT 感应电压PI波形.pl4; x-var t) v:K0A v:K0B v:K0C
Fig Induced current and voltage of 230kV double-circuit line.47 electrostatic induction
voltage after grounding switch to cut off the capacitive current for TISALEO – TOTORAS
line(Phase A: first peak 25.9kVp, Phase B: first peak 9.4kVp, Phase C: first peak
16.8kVp)
59
Tab Induced current and voltage of 230kV double-circuit line.50 induced current and
Voltage of Voltage of
Status of Current of Current of
electrostatic electromagnetic
Dead line earthing electrostatic electromagnetic
induction( induction(kV
switches induction(A) induction(A)
kV) )
earthing
switches of
/ / / 124.75
both ends
closed
1st circuit of earthing
JIVINO – switches of
10.06 / / /
SHUSHUFINDI both ends
double-circuit opened
transmission One
line earthing
switch
/ 0.91 1.21 /
opened,
while other
is closed
earthing
switches of
/ / / 128.82
both ends
closed
2nd circuit of earthing
JIVINO – switches of
9.73 / / /
SHUSHUFINDI both ends
double-circuit opened
transmission One
line earthing
switch
/ 0.89 1.26 /
opened,
while other
is closed
Maximum 10.06 0.91 1.26 128.82
60
30
[kV]
20
10
-10
-20
0.0 0.1 0.2 0.3 0.4 [s] 0.5
(file JV-SSFD感应电压PI波形.pl4; x-var t) v:K0A v:K0B v:K0C
Fig Induced current and voltage of 230kV double-circuit line.48 electrostatic induction
voltage after grounding switch to cut off the capacitive current for JIVINO –
SHUSHUFINDI line(Phase A: first peak 26.0kVp, Phase B: first peak 9.4kVp, Phase C:
first peak 16.9kVp)
61
7. Conclusion
62
withstand voltage(LIWV) 325kV.
(8) The maximum transformer without load energizing overvoltage at 500kV side
among SAN RAFAEL substation, EL INGA substation, TISALEO substation
and CHORRILLOS substation is 1.77p.u., maximum inrush current is
1.79kAp. There is no resonance overvoltage during the transformer without
load energizing.
(9) The induced current and voltage of 230kV double-circuit lines are shown in
Tab Conclusion.51.
Voltage of Voltage of
Current of Current of
electrostatic electromagnetic
line electrostatic electromagnetic
induction( induction(kV
induction(A) induction(A)
kV) )
SAN RAFAEL
10.50 2.78 3.69 126.48
– JIVINO
TISALEO –
9.95 0.42 0.62 135.68
TOTORAS
JIVINO –
10.06 0.91 1.26 128.82
SHUSHUFINDI
63