Unit 4 - Power System Operation and Control
Unit 4 - Power System Operation and Control
Data acquisition and remote control is performed by the computer system called SCADA,
which forms the front end of EMS. The EMS communicates with generating, transmission
and distribution systems through SCADA systems.
Energy Management
Automatic generation control and economic dispatch minimize the production cost and
transmission cost. Commit the number of units to be operated to minimize the cost and
schedule hydro-thermal plants properly have come under energy management.
Fig: 7.1
Energy management system consists of energy management, AGC, security control, SCADA,
load management, as shown in fig: 7.1.
8. Maintenance scheduling.
Load Management
Remote Terminal Unit (RTU) installed at distribution substations, can provide status and
measurements for distribution substation. RTU can monitor switches, interrupters, control
voltage, customer meter reading, etc.
8. Service restoration.
12. To control customer load through appliance switching (Heater) and indirectly
through voltage control.
Fig.7.2 shows the schematic diagram showing the information flow between
various functions to be performed in an operation control centre computer system.
The system gets information about the power system from remote terminal units
(RTU) that encodes measurement transducer outputs and opened / closed status
information into digital signals that are transmitted to the operations centre over
communication circuits. The control centre can transmit control information such as
raise / lower commands to the speed changer and in turn to generators and open /
close commands to circuit breakers (CBs). The information coming into the control
centre is breaker / switch status indications and analog measurements.
2. AGC (called Load Frequency Control (LFC)) maintains frequency and net
power interchange –action repeated at 2-6 sec interval.
3. Economic Dispatch Control (EDC) distributes the load among the units such
that fuel cost is minimum – executed at 5-10 minutes intervals.
In order to run the state estimator, we must know how the transmission lines are connected to
the load and generator buses. This information is called as network topology. Since the
breakers and switches in any substation can cause the network topology to change, a program
must be provided that reads the telemetred breaker / switch status indicators and restructures
the model of the system. The network topology programs must have a complete description
of each substation and how the transmission lines are attached to the substation equipment.
Bus sections that are connected to the other bus sections through closed breakers or switches
are designed as belonging to the same electrical bus. Thus, the number of electrical buses and
the manner in which they are interconnected can be changed in the model to reflect breaker
and switch status changes on the power system itself.
The electrical model of the transmission system is sent to the state estimation program
together with the analog measurements. The output of the state estimator consists of all
voltage magnitudes and phase angles, transmission line MW and MVAR flows and bus loads
and generation calculated from the line flows. These quantities, together with the electrical
model, provide the basis for the economic dispatch program, contingency anaylsis program
and generator corrective action program.
Since the complete electrical model of the transmission system is available, we can directly
calculate bus penalty factors, participation factors, optimal voltages, etc.
NOTE:
Contingency Analysis: Many of the problems that occur on a power system can cause
serious trouble within such a quick time period that the operator cannot take action fast
enough. This will cause cascading failures. Due to this aspect of system operation, modern
operations, computers are equipped with contingency analysis programs that model possible
system‟s troubles before they arise. These programs are based on a model of the power
system and are used for study of outage events and alarm the operators of any potential
overloads or out of the limit voltages. We are considering line outages and generator outages
separately.
The practice of all communication links between equipment and the control centre could
be interrupted and still, electric service is being maintained. The generating plant in the
system remains synchronized to the transmission network and maintains its existing power
output level even without signals received from control centre.
Monitoring
An energy control centre fulfils the function of coordinating their response of the system
elements in both normal operation and emergency conditions. The burden of repetitious
control in normal situations is delegated to the digital computer and selective monitoring is
performed by human operators. The digital computer is used to process the incoming stream
of data to detect abnormalities and then alarm the human operator via lights, buzzers and
CRT presentations. Many lower level or less serious cases of exceeding normal limits are
routinely handled by digital computer. A more serious abnormality detected by the digital
computer may cause suspension of normal control functions.
Data acquisition provides operators and computer control systems with status and
measurement information needed to supervise overall operations. Security control analyses
the consequences of faults to establish operating conditions.
Data acquisition and remote control is performed by computer system called supervisory
control and data acquisition (SCADA) systems. A SCADA system consists of a master
station and remote terminal unit (RTU). Master station communicates information to the
RTU for observing and controlling plants. RTU‟s are installed at generating station or
transmission substation or distribution substation. RTUs transmitting status of the device and
measurements to master station and receive control commands from the master station.
In a computer aided data acquisition scheme, the steady state reading can be acquired
simultaneously from various instrument locations and can be saved for future analysis. The
transients may be in the form of voltage or current fluctuations. In a real power system, the
transient may result in the failure of components and it is sometimes difficult to trace the
origin of disturbance. Using a Data Acquisition System, the transients can be reduced and
analysed.
For generation.
5. Security monitoring: The on-line process using real-time data for analyzing the
effects of outages contingencies on the steady state performance of the system.
6. State estimation: It is the process of estimating the state. When based on system
monitoring data, it produces best estimates of the power system state.
The supervisory control and data acquisition system allows a few operators to monitor the
generation and HV transmission system.Consistent with principles of high reliability and fail
safe features,electric utilities have almost universally applied a redundant set of dual digital
computers for functions of remote data acquisition control,energy management and system
security.Both computers have their own core memory and drive an extensive number of
input-output devices such as printers,teletypes, magnetic tape drive,disks and so on.
Usually one computer, the on-line units,is monitoring and controlling the power system.The
backup computer maybe executing off-line batch programs such as load forecasting or hydro-
thermal allocation. The on–line computer periodically updates a disk memory shared between
two computers.
Upon a fail over or switch-in status command, stored information of common disk is inserted
in the memory of the on-line computer.
The information used by the online computer has a maximum age of update cycle(typically
30 sec).the fig gives block diagram of typical digital computer control and monitoring for
power system.
All of the peripheral equipment is interfaced with the computer through input-output
microprocessors that have been programmed to communicate,as well as preprocess the
analog information,check for limits,convert to another system of units and so on.
The microprocessors can transfer data in and out of computer memory withoutinterrupting
the central processing unit.As a result of these precautions,for all critical hardware
functions,there is often a guaranteed 99.8% or more availability.software also allows for
multilevel hardware failures and initialization of application programs,if failures
occur.critical operations and functions are maintained during either preventive or corrective
maintainence.
Besides hardware, new digital code to control the system may be compiled and tested in the
backup computer then switched to on-line status.The digital computers are usually employed
in a fixed cycle operating mode, with priority interrupts wherein the computer periodically
performs a list of operations.The most critical functions have the fastest scan cycle.Typically
, the following categories are scanned every 2 seconds.
All status points such as switchgear position,substation loads and voltages,transformer
tap positions and capacitor banks.
Tie-line flows and interchanges schedules.
Generator loads,voltages, operating limits and boiler capacity.
Telemetry verification to detect failures and errors in the remote bilateral
communication links between the digital computer and the remote equipment.
The turbine-generators are often commanded to new power levels every 4 seconds,sharing
the load adjustments based on each unit‟s response capability in MW/min.The absolute
power output of each unit‟s capability is typically adjusted every 5 min by the computer
executing an economic dispatch program to determine the base power settings.
Most low-priority programs may be executed on demand by the operator for study purposes
or to initialize the power system. An operator may also alter the digital computer code in the
execution if a parameter changes in the system.The computer software compiler and data
handlers are designed to be versatile and readily accept operator inputs.
Type2: medium sized power systems (plant control center),power station HVDC link,
distribution systems.
Type 3: regional control center, distribution systems in large urban areas,several hydro power
stations with cascade control.
Type 4: national and regional control center, distribution systems in large urban areas,several
hydro power stations with cascade control.
Automatic generation control and economic load dispatch are two process or principle areas
of generation control on large interconnected power systems.Automatic Generation
Control(AGC) is as online cmp[uter control that maintains the overall system frequency and
the net tie-line load exchange between the power companies in the interconnection as in fig.
Economic load dispatch is also an on-line compute control, whose function is to supply the
existing system load demands from all the currently operating generators in the most
economical manner in terms of minimal fuel cost.The “boundaries” of an area are the points
on the tie-lines where a utility‟s ownership,maintainence and loss accounting ends and those
of its neighbor begins.There are very few isolated power systems that are not connected to
neighbours by means of tie-lines.
Tie –lines allow a local or “pool” exchange and sale of power between the power
companies on a predetermined schedule.
Tie-lines allow areas experiencing disturbances to draw on other areas for help.
Tie-lines provide a long distance transmission line for the sale and transfer of power.
Interconnections are made so that operating areas can share generation and load.This sharing
is normally on a scheduled basis as forced by the AGC.
Such unscheduled interchanges persist until the distributed area can either itself fully respond
to its local requirement, or until normal schedules are reset so that contribution is taken out
of the unscheduled class and put into the scheduled class.
To maintain a net interchange of power with its neighbours an AGC uses real power flow
measurements of all tie-lines emanating from the area and subtracts the scheduled
interchange to calculate an error value.The net power interchange, together with a
gain,b(MW/Hz),the frequency bias, as a multiplier on the frequency is called area control
error.
ACE = ∑ PK + PS + 10b(f act –f 0) in MW
Where,
The interchange power PS is generally scheduled for periods of the day and is changed as
“blocks” of MWhr are bought or sold to neighbouringutilities.A positive ACE or positive net
exchange of power represents a flow out of the area.
MASTER STATION:
Master unit is provided with a digital computer with associated interfacing devices and
hardware to receive information from RTU, process data and display salient information to
the operator as in fig.
1. Process computer
2. CRT display
3. Printer
4. Data logger
5. Computer graphics
6. Control console
7. Keyboard
8. Alarm panel
9. Instrument panel
10. Modem
11. Multiplexer
REMOTE TERMINAL UNIT :
The RTU‟s are installed at the selected power stations and substations.
1. Transducers
2. A/D converters and D/A converters.
3. Serial interface
4. Modems
5. Multiplexers
6. Front end computer
7. Control relays
The analog quantities like voltage,MW,MVAR and frequency measured at stations are
converted into DC voltage or current signals, through transducers and fed to the A/D
converters which converts the analog signals into digital form suitable for transmission.The
digital signal is fed to the front end computer and modems through serial interface.MODEM
sends the information to the master unit through multiplexer.MODEM will also receive
commands from the master units to control the station equipments through the control
relays.In addition to measure quantities, status of various devices is informed to master
station.
The master station scans the RTU sequentially and gathers information on the system
operating condition i.e, voltage, current, line flows, generation,output etc., as well as
equipment status.Computer, using real time data can check operating limits of various
quantities and give an alarm to operator if overloading or any other abnormal condition is
detected.The system real time information is presented to the operator through CRT(cathode
ray tube), computer graphic terminals, alarm panel, alarm printers etc, so that the affected
operator can supervise minute byminute,system operating conditions and take control action
to prevent the system disturbances whenever emergency conditions and system status at
specified interval is printed by data loggers.
Alarm functions
Control and indication
Control of position of devices
Data collections
Protective functions
Control and monitoring functions
OTHER FUNCTIONS OF SCADA AND EMS are
A Power system in the manual operating condition may face a contingency condition,
such as a generating unit may go out of order, an important line may be tripped off, and the
demand may undergo a large from the forecasted value and so on. Although many such
contingencies can occur, only those having a high probability of occurrence are to be
considered and such contingencies are known as credible contingencies. A system operator
would like to analyze the effect of such credible contingencies to obtain secure operation.
Thus, the analysis of credible contingencies goes to enhance the security of operation.
A power system is said to be secured if there is neither any occurrence of overloading of any
equipment nor transient instability due to a set of credible contingencies.
Example of contingencies
Non-credible contingency: Three phase electrical faults, multiple generating unit failures,
double line failure, abnormal conditions caused by severe weather
conditions/lightning/storm/equipment malfunction.
Measurements Schemes
Measurement vector [Z] consists of all the measurement made.
Let [ Z ] be the measurement vector which has the dimension nn.
Let nm be the number of measurements.
Each quantity being measured is a non-linear function of the state variables.
[ Z I ] = Fi[X], i=1,2,…………,nm
There are five standard measurement schemes. They are:
1. Measurement of P at all the buses except the reference bus and Q at all the buses.
nm = 2 nb – 1 = ns
2. Measurement of P, Q and V at all the buses.
nm = 3 nb
3. Measurement of P and Q at both ends of each element of the transmission network.
nm = 4 nl
where nl = Number of elements.
4. Measurement of P and Q at both ends of each element of the transmission network
plus measurement of voltage magnitudes at all the buses.
nm = 4 nl + nb
5. Measurement of P, Q, V at all buses plus measurement of P and Q at both ends of
each element of the transmission network
nm = 3 nb + 4 nl
Sometimes, any non-standard scheme of measurements are also possible, so, number of
measurements should be greater than number of state variables.
nm > ns
Three cases:
Case (i) If nm = ns
Number of equations = Number of state variables
∴ Solution is unique.
There is no redundancy in the measured data, the effect of measurement reliability or
measurement noise cannot be taken into account. This scheme is not adopted normally.
Case (ii)
If nm < ns,
Number of equations < Number of state variables
∴ Solution is infinite.
This scheme is not possible to estimate the system state.
Case (iii)
If nm > ns,
Number of equations > Number of state variables
Number of iterations required for the Number of iterations required for the
convergence is independent of the convergence is dependent of the state
state system. of the system.
Fast decoupled load flow depend on It does not depend on X/R ration of
X/R ration of the transmission line. the transmission line.
Load Forecasting
The problem of load forecasting is that of estimating the future load demand of a given
power system. Depending upon the time period, it may be classified as very short term, short
term, medium term and long term technique. Very short term and short term load forecasting
are generally required by the system operators for the purpose of economic generation
scheduling and load dispatching. Medium term forecast helps in allocation of spinning
reserves. The long term load forecasting is essential for power system planning. The
construction of large generating plants takes many years. Therefore, the planner must
determine the generating needs well in advance. This influences the selection and sequence
of generation.
Unit Commitment
The unit commitment problem is to minimize system total operating costs while
simultaneously providing sufficient spinning reserve capacity to satisfy a given security level.
In unit commitment problems, we consider the following terms.
A short term load forecast.
System reserve requirements
System security
Startup costs for all units.
Minimum level fuel costs for all units.
Incremental fuel costs of units.
Maintenance costs
Emergency Control
Security problem will change with operational conditions. It depends not only upon the
reserve capacity in a given situation, but also upon the contingency of disturbances. In the
normal state, the system is secure, i.e., both equality and inequality constraints are satisfied.
If any contingency occurs, the system enters into alert state. Now, the security level falls
below threshold level and the system becomes insecure. If any overloads of generators or
transmission lines occur, the inequality constraints will alter and the system enters into an
emergency state. Now, disconnection of faulty section, rerouting of power, startup of reserve
generation, load shedding is done, then the power system is returned to the normal or alert
state. These control actions may be done form the central energy control centre.
State Estimation
For digital computer in short circuit computations, it is necessary to develop a systematic,
general computational procedure. State estimation techniques may be used for load
forecasting, economic dispatch and load frequency control. The main task of load frequency
control is to ensure that load disturbances do not cause an imbalance of real power.
The real-time system derives information from state estimates and upon detection of any
violation, security control calculations are needed for immediate implementation. Thus,
computing speed and reliability are of primary importance.
1. Normal State
A system is said to be in normal state if both load and operating constraints are
satisfied. It is one in which the total deemed on the system is met by satisfying all the
operating constraints (i.e., equality(E) and inequality(I) constraints).
2. Secure State
The normal state of the system is said to be secure state if all postulated contingency
states are found to be normal. A normal state of the system is said to be insecure if
one or more of the postulated contingency state consists of the constraint limits
violated. In this state, frequency and the bus voltage magnitude are within the normal
operating range. Current flows on all transmission lines are within the given ratings.
Transformers and generators are operated within their ratings and there is no load
shedding anywhere in the system. Reserve margin is sufficiently high to make the
system well secure.
3. Alert state
The normal state of the system is said to be alert state if one or more of the postulated
contingency states, consist of the constraint limits violated. When the system security
level falls below a certain level or the probability of disturbance increases, the system
may be in alert state. All equalities (E) and inequalities (I) are satisfied, but on the
event of a disturbance, the system may not have all the inequality constraints satisfied.
If a severe disturbance occurs, the system will push into emergency state. To bring
back the system to secure state, preventive control action is carried out.
4. Emergency state
The system is said to be in emergency state if one or more operating constraints are
violated, but the load constraint is satisfied. In this state, the equality constraints are
unchanged. The system will return to the normal (secure) or alert state by means of
corrective action, i.e., disconnection of faulted section or load shedding.
The generator still tracts the load and the system is still synchronized. But one or
several components are overloaded. As the components eventually fail, the system
will start disintegrate.
5. Extremis State
When the system is in emergency state, if no proper corrective action is taken in time,
then it goes to either serious emergency state or extremis state. In this, neither the
load nor the opening constraint is satisfied; this results in islanding. Also the
generating units are strained beyond their capacity. So, emergency control action is
done to bring back the system state either to the emergency state or normal state.
6. Restorative state
From this state, the system may be brought back either to alert state or secure state.
The latter is a slow process. Hence, in certain cases, first the system is brought back
to alert state and then to the secure state. This is using restorative control action.