1 Total motorised & Non motorized Vehicle. Per Day ( as per traffic survey conducted and fore casting according to specifications of
SP - 72 , 2007 & IRC : 108 )
Total 279
3 Average Traffic During Non Harvesting Season (Considered half of the total Traffic in
T = 140
peak Season )
4 Average Increase in Traffic During Harvesting Season (Total Traffic in peak season -
Traffic During Non Harvesting Season) nT = 140
6 It is presumed that road will open for traffic after 0.5 yrs. ADT = 180
therefore AADT after 0.5 yrs by considering 6% growth rate ADT = AADT x (1+0.06) n