SCHEDULE - A
1. The Site
1.1 The project road starts from Sangareddy (near Kandi village) (498+250 Km of
NH-65 (old NH-9)) and ends at Km 44+757 (existing chainage) of NH-161. The
entire project road runs through Sangareddy district. The site shall include
land, buildings, structures & road works as described in Annex – 1 of this
Schedule – A
1.2 The dates of handing over the Right of Way to the Contractor are specified in
Annex-II of this Schedule-A.
1.3 An inventory of the Site including land, buildings, structures, road works, trees
and any other immovable property on, or attached to, the site shall be
prepared jointly by the Authority Representative and the Contractor, and such
inventory shall form part of the memorandum referred to in clause 10.3.1 of
the agreement.
1.4 Additional land required for construction of works specified in the Change of
Scope Order issued under clause 16.2.3 of this Agreement shall be acquired in
accordance with the provisions of Clause 10.3.6 of this Agreement. Upon
acquisition, such land shall form part of the Site and vest in the Authority.
1.5 The proposed alignment plans of the Project Highway are specified in Annex-III
which shall be followed by the Contractor with minimum finished roadway level
(FRL) as indicated in the alignment plan.
Annex – I: Site
(Schedule-A)
Site
1. Site: The project road starts from Sangareddy (near Kandi village) (498+250 Km of
NH-65(old NH-9)) and ends at Km 44+757 (existing chainage) of NH-161. The land,
carriageway and structures comprising the Site are described below.
2. Land: The Site of the Project Highway comprises the land as described below:
Type of Structure
No. of Spans
Sr. Existing Width
Super with span Remarks
No. Chainage Foundation Sub Structure (m)
Structure length (m)
(Km)
RCC Pier, RCC
1 5.770 - RCC Slab 3x5.8 8.60
abutment
- RCC Pier, RCC
2 25.630 RCC Slab 5x6.8 8.50
abutment
- RCC Pier, RCC
3 35.970 RCC Slab 3x8.1 7.40
abutment
- RCC Pier, RCC
4 37.700 RCC Slab 5x6.8 8.50
abutment
Type of Structure
No. of Spans
Sr. Existing Width
Super with span Remarks
No. Chainage Foundation Sub Structure (m)
Structure length (m)
(Km)
- RCC Pier, RCC
5 44.600 RCC Slab 3x5 8.50
abutment
8. Railway level crossings: The Site includes the following railway level crossings:
11. Bus bays: The details of bus bays on the Site are as follows:
Length
Sr. No. Chainage (Km) Left Hand Side Right Hand side
(m)
Nil
12. Truck Lay byes: The details of truck lay byes are as follows:
Sr. No. Chainage (Km) Length (m) Left Hand Side Right Hand side
Nil
14. Minor junctions: The details of the minor junctions are as follows:
Sr. Leads to
Existing Chainage(Km) Junction
No. Left Right
1 9.780 4-Legged Fasalwadi Fasalwadi
2 9.920 3-Legged - Side road
3 9.960 3-Legged Side road -
4 10.220 3-Legged Side road -
5 10.050 3-Legged Side road -
6 12.120 3-Legged - Village Road
7 12.190 3-Legged Village Road -
8 12.650 3-Legged Village Road -
9 13.350 3-Legged Village Road -
10 13.900 4-Legged Village Road Village Road
11 14.090 3-Legged - Village Road
12 14.620 3-Legged - Village Road
13 14.730 3-Legged Village Road -
14 14.850 3-Legged - Village Road
15 15.310 3-Legged Village Road -
16 15.720 3-Legged - Varnarpur
17 15.850 3-Legged - Varnarpur
18 17.750 3-Legged Singur -
19 19.810 3-Legged - Korpol Road
20 19.830 3-Legged Sultanpur -
21 12.100 3-Legged Sultanpur -
22 21.070 3-Legged Sarafpally -
23 23.180 3-Legged Chowtkur -
25 27.190 3-Legged - Almaipet
26 28.330 3-Legged - Chandampet
27 28.390 3-Legged Pocharam X Road -
15. Bypasses: The details of the existing road sections proposed to be bypassed are
as follows:
Annex-II
(Schedule-A)
The dates on which the Authority shall provide Right of Way to the Contractor on
different stretches of the Site are stated below:
Note: The Authority shall provide the Right of Way on no less than 90% (Ninety per
cent) of the total length of Project Highway on Appointed date in compliance to
Clause 8.2 of EPC Contract Agreement.
Annex-III
(Schedule-A)
Alignment Plans
The existing alignment of the project highway shall be modified as per the enclosed
alignment plan. The profile of enclosed alignment plan of the project highway shall be
modified by the contractor at the following locations:
A. The length of service/slip roads proposed in clause 2.8 of schedule B shall also
be incorporated by the contractor in the profile of the project highway.
Annex-IV
(Schedule-A)
Environment Clearances
The project highway is less than 100 km length and does not involve additional Right
of Way or land acquisition more than 40m on existing alignment and 60m on
Bypass/Realignments. Therefore, as per MOEF notification No. S.O.2559(E) dated
22.08.2013, environmental clearance is not required.
SCHEDULE - B
(See Clause 2.1)
Rehabilitation and augmentation shall include Four Lane with Paved shoulders
configuration as described in Annex-I of this Schedule-B and in Schedule-C.
Annex-I
(Schedule-B)
1.1 The Project Highway shall follow the existing alignment unless otherwise
specified by the Authority and shown in the alignment plans specified in Annex
III of Schedule-A. Geometric deficiencies, if any, in the existing horizontal and
vertical profiles shall be corrected as per the prescribed standards for
plain/rolling terrain to the extent land is available.
Four-Laning with paved shoulders shall be undertaken. The paved carriageway
shall be as specified in the Para 2.11 of this Annex-I of Schedule-B.
Except as otherwise provided in this Agreement, the width of the paved
carriageway and cross-sectional features shall conform to paragraph 1.2.1
above.
2.1 General: Geometric design and general features of the Project Highway shall
be in accordance with Section 2 of the Manual.
2.2 Design Speed: The design speed shall be the minimum design speed of 80 km
per hour for plain/rolling terrain.
2.3.1 In the following sections, where improvement of the existing road geometrics
to the prescribed standards is not possible, the existing road geometrics shall
be improved to the extent possible within the given right of way and proper
road signs and safety measures shall be provided:
2.3.3 Bypasses: The existing road shall be bypassed to the standards as specified in
the manual at the following locations:
2.4 Right of Way: Details of the Right of Way are given in Annex II of
Schedule-A.
(b) In open country, paved shoulders of 1.5 m width shall be provided and balance
2.0m width shall be covered with approved material.
(c) Design and specifications of paved shoulders shall conform to the requirements
specified in paragraphs 5.10 of the Manual.
2.7.1 Lateral and Vertical clearances at over passes shall be as per paragraph 2.11 of
the Manual.
2.7.2 Lateral clearance: The width of the opening at the Overpasses shall be as
follows:
2.8.1 Service Road: Service Roads shall be constructed at the locations and for the
lengths indicated below:
Design Chainage
Sr. Length (km) Width
(Km) Side Remarks
No. (m)
From To LHS RHS
1 0.700 1.100 0.400 0.400 7.0 Both Bypass
2 2.100 2.650 0.550 0.550 7.0 Both Bypass
3 11.820 12.150 0.330 0.330 7.0 Both Built-up section
4 17.450 18.120 0.670 0.670 7 Both Bypass
5 26.600 27.210 0.610 0.610 7.0 Both Bypass
6 27.850 28.350 0.500 0.500 7.0 Both Bypass
7 29.660 29.950 0.290 0.290 7.0 Both Bypass
8 30.800 31.000 0.200 0.200 7.0 Both Bypass
9 31.790 34.450 2.660 2.660 7.0 Both Bypass
10 36.600 36.900 0.300 0.300 7.0 Both Bypass
Sub Total on each
6.510 6.510
side (km)
Total (km) 13.020
Note: The length of slip ins and slip outs to connect the service road to main
carriageway shall also be constructed in addition to length given in above table.
2.8.2 Slip Road: Slip roads shall be constructed at the locations and for the lengths
indicated below:
2.9.1 Interchange
1 Loop 1 410 As per fig. 2.4 X 3– lane section Design of the Loops
shall be carried out
3– lane section as per trumpet plan
2 Loop 2 390 As per fig. 2.4 Y provided in Annex-II
Note: The Ramps for Loop1 & Loop2 shall also be constructed by the contractor as per
Trumpet plan provided in Annexure II.
Design
Sr. Length Typical Cross Section
Chainage(Km) Remarks
No. (Km) as per Manual
From To
1 Loop 1 0.410 2.4 X
Loops at Trumpet location
2 Loop 2 0.390 2.4 Y
3 -0.03 0.03 0.060 Fig 7.8 Trumpet
4 0.030 0.700 0.670 Fig 2.5 B Sangareddy Bypass From km
Design
Sr. Length Typical Cross Section
Chainage(Km) Remarks
No. (Km) as per Manual
From To
0.000 to km 8.300
5 0.700 1.100 0.400 Fig 2.3 A
6 1.100 1.575 0.475 Fig 2.5 B
7 1.575 1.591 0.016 Fig 7.8 VUP
8 1.591 2.100 0.509 Fig 2.5 B
9 2.100 2.650 0.550 Fig 2.3 A
10 2.650 4.094 1.444 Fig 2.5 B
11 4.094 4.106 0.012 Fig 7.8 LVUP
12 4.106 4.908 0.802 Fig 2.5 B
13 4.908 4.933 0.025 Fig 7.8 VUP
14 4.933 6.809 1.877 Fig 2.5 B
15 6.809 6.821 0.012 Fig 7.8 LVUP
16 6.821 7.444 0.623 Fig 2.5 B
17 7.444 7.456 0.012 Fig 7.8 LVUP
18 7.456 7.888 0.432 Fig 2.5 B
19 7.888 7.913 0.025 Fig 7.8 VUP
20 7.913 8.250 0.337 Fig 2.5 B
21 8.250 8.395 0.145 Fig 2.2 A
22 8.395 8.705 0.310 Fig 7.5 A Major Bridge
23 8.705 10.840 2.135 Fig 2.2 A
24 10.840 11.179 0.339 Fig 2.5 A
25 11.179 11.191 0.012 Fig 7.8 LVUP
26 11.191 11.520 0.329 Fig 2.5 A
27 11.520 11.820 0.300 Fig 2.2 A
28 11.820 12.150 0.330 Fig 2.6 A
29 12.150 16.840 4.690 Fig 2.2 A
30 16.840 17.094 0.254 Fig 2.6 B
31 17.094 17.106 0.012 Fig 7.8 LVUP
32 17.106 17.450 0.344 Fig 2.6 B
33 17.450 18.120 0.670 Fig 2.3 A
34 18.120 18.344 0.224 Fig 2.6 B
35 18.344 18.356 0.012 Fig 7.8 LVUP
36 18.356 18.720 0.364 Fig 2.6 B
37 18.720 20.400 1.680 Fig 2.2 A
Realignment from Km 20.700
38 20.400 20.750 0.350 Fig 2.5 A
to 21.700
39 20.750 20.869 0.119 Fig 2.5 B
40 20.869 20.881 0.012 Fig 7.8 LVUP
41 20.881 21.260 0.379 Fig 2.5 B
42 21.260 21.700 0.440 Fig 2.2 B
43 21.700 22.648 0.948 Fig 2.2 A
44 22.648 22.688 0.040 Fig 7.5 A Minor Bridge
45 22.688 25.650 2.962 Fig 2.2 A
25.9 to 37, Andole Jogipet
46 25.650 26.050 0.400 Fig 2.5 A
Bypass from km 25.900 to km
Design
Sr. Length Typical Cross Section
Chainage(Km) Remarks
No. (Km) as per Manual
From To
36.900
47 26.050 26.277 0.227 Fig 2.5 B
48 26.277 26.289 0.012 Fig 7.8 VUP
49 26.289 26.600 0.311 Fig 2.5 B
50 26.600 27.210 0.610 Fig 2.3 A
51 27.210 27.363 0.153 Fig 2.5 B
52 27.363 27.377 0.014 Fig 7.2B A Minor Bridge
53 27.377 27.850 0.473 Fig 2.5 B
55 27.850 28.265 0.415 Fig 2.3 A
56 28.265 28.285 0.020 Fig 7.2B A Minor Bridge
57 28.285 28.350 0.065 Fig 2.3 A
58 28.350 29.174 0.824 Fig 2.5 B
59 29.174 29.186 0.012 Fig 7.8 LVUP
60 29.186 29.660 0.474 Fig 2.5 B
61 29.660 29.950 0.290 Fig 2.3 A
62 29.950 30.223 0.273 Fig 2.5 B
63 30.223 30.237 0.014 Fig 7.2B A Minor Bridge
64 30.237 30.800 0.563 Fig 2.5 B
65 30.800 31.000 0.200 Fig 2.3 A
66 31.000 31.346 0.346 Fig 2.5 B
67 31.346 31.358 0.012 Fig 7.8 LVUP
68 31.358 31.397 0.039 Fig 2.5 B
69 31.397 31.433 0.036 Fig 7.2B A Minor Bridge
70 31.433 31.790 0.357 Fig 2.5 B
71 31.790 34.167 2.377 Fig 2.3 A
72 34.167 34.177 0.010 Fig 7.2B A Minor Bridge
73 34.177 34.450 0.273 Fig 2.3 A
74 34.450 34.744 0.294 Fig 2.5 B
75 34.744 34.756 0.012 Fig 7.8 LVUP
76 34.756 35.284 0.528 Fig 2.5 B
77 35.284 35.296 0.012 Fig 7.8 LVUP
78 35.296 36.210 0.913 Fig 2.5 B
79 36.210 36.235 0.025 Fig 7.8 VUP
80 36.235 36.600 0.365 Fig 2.5 B
81 36.600 36.900 0.300 Fig 2.3 A
82 36.900 37.750 0.850 Fig 2.2 A
83 37.750 38.200 0.450 Fig 2.2 B
84 38.200 39.814 1.613 Fig 2.2 A
85 39.814 39.835 0.021 Fig 7.5 A Minor Bridge
86 39.835 39.980 0.145 Fig 2.2 A
Note:
(i) Any variations in the lengths specified in the above table shall not
constitute a Change of Scope, save and except any variations in the length
Note: Acceleration and deceleration lanes shall be provided as per IRC:92 guidelines.
All intersections and grade separators shall be as per Section 3 of the Manual.
Existing intersections which are deficient shall be improved to the prescribed
standards.
Leads to
Design Carriageway
Sr. Type of Category of
Chainage width of cross
No. Junction Left Right Cross Road
(Km) road
1 0.000 4-Legged Pune Hyderabad NH-65 Four Lane
2 1.583 4-Legged IIT college Mamidipally VR Single Lane
3 4.920 4-Legged Sangareddy Narsapur SH Two Lane
4 6.815 4-Legged Fasalwadi Gowdicharla VR Single Lane
5 7.450 4-Legged Fasalwadi Fields VR Single Lane
6 11.185 4-Legged Village Road Village Road VR Single Lane
7 17.100 4-Legged Sultanpur Korpole VR Single Lane
8 18.350 4-Legged Sarafpally Sarafpally VR Single Lane
9 31.352 4-Legged Dakoor Jogipet VR Single Lane
10 35.290 4-Legged Yerraram Jogipet VR Single Lane
Leads to
Design Carriageway
Sr. Type of Category of
Chainage width of cross
No. Junction Left Right Cross Road
(Km) road
1 3.950 3-Legged Fasalwadi VR Single Lane
2 10.650 3-Legged Village Road VR Single Lane
3 11.370 3-Legged Village Road VR Single Lane
4 11.910 3-Legged Village Road VR Single Lane
5 PAVEMENT DESIGN
5.1 Pavement design shall be carried out in accordance with Section 5 of the
Manual.
Flexible Pavement for Main Carriageway shall be designed for minimum design
traffic of 50 MSA for a minimum design period of 15 years. However, minimum
thickness of Subgrade, Granular Sub-Base, Wet-Mix Macadam, DBM and BC in
flexible pavement shall be 500 mm, 200 mm, 250 mm, 100 mm and 40 mm
respectively.
Flexible Pavement for slip roads and service roads shall be designed for
minimum design traffic of 10 MSA. However, minimum thickness of Subgrade,
Granular Sub-Base, Wet-Mix Macadam, DBM and BC in flexible pavement shall
be 500 mm, 200 mm, 250 mm, 60 mm and 40 mm respectively.
Rigid pavement shall be designed for minimum CVPD of 181221590. However,
minimum thickness of subgrade, GSB, DLC and PQC in rigid pavement shall be
500mm, 150mm, 150mm and 300mm respectively.
5.2 Type of pavement
Flexible pavement is proposed for main carriageway as well as service/slip roads
for the entire project length. Rigid pavement shall be provided for Toll Plaza
location.
5.3 Design requirements:
Shall be as specified in the Manual.
The entire length of the project highway shall be reconstructed from subgrade
level after raising of the road with earth/suitable material.
6 ROADSIDE DRAINAGE
Drainage system including surface and subsurface drains for the Project
Highway shall be provided as per Section 6 of the Manual.
7 DESIGN OF STRUCTURES
7.1 General
7.1.1 All bridges, culverts and structures shall be designed and constructed in
accordance with Section 7 of the Manual and shall conform to the cross-
sectional features and other details specified therein.
7.1.2 Width of the carriageway of proposed bridges and structures shall be as given
in para 7.3 of this Schedule-B.
7.1.5 The structures shall be designed to carry utility services as per site
requirement.
7.1.6 Cross-section of the new culverts and bridges at deck level for the Project
Highway shall conform to the typical cross-sections given in Section 7 of the
Manual.
7.2 Culverts
7.2.1 Overall width of all culverts shall be equal to the roadway width of the
approaches. All culverts shall also be provided in median gap and also in gap
between main carriageway and service road, in case there is any service road.
Details of Proposed
Structures
Existing Design Size of Vent
Proposed No. of
Sr. Chainage Chainage Provision (m) Remarks
Type Vents
No. (Km) (Km)
B H
1 13.640 10.930 RCC Box Reconstruction 1 2.00 3.00
2 14.245 11.525 RCC Box Reconstruction 1 2.00 2.00
3 14.970 12.250 RCC Box Reconstruction 1 3.00 3.00
4 15.970 13.255 RCC Box Reconstruction 1 2.00 2.00
5 17.750 15.031 RCC Box Reconstruction 1 3.00 3.00
6 18.910 16.190 RCC Box Reconstruction 1 2.00 3.00
7 19.040 16.325 RCC Box Reconstruction 1 2.00 3.00
8 19.275 16.559 RCC Box Reconstruction 1 2.00 2.00
Details of Proposed
Structures
Existing Design Size of Vent
Proposed No. of
Sr. Chainage Chainage Provision (m) Remarks
Type Vents
No. (Km) (Km)
B H
9 19.880 17.165 RCC Box Reconstruction 1 2.00 2.00
10 20.975 18.255 RCC Box Reconstruction 1 2.00 3.00
11 21.180 18.460 RCC Box Reconstruction 1 2.00 2.00
12 21.470 18.750 RCC Box Reconstruction 1 2.00 2.00
13 21.970 19.247 RCC Box Reconstruction 1 2.00 3.00
14 22.730 20.005 RCC Box Reconstruction 2 2.00 2.00
15 22.750 20.025 RCC Box Reconstruction 2 2.00 2.00
16 23.125 20.400 RCC Box Reconstruction 1 2.00 2.00
17 23.450 20.725 RCC Box Reconstruction 1 2.00 2.00
18 26.795 23.890 RCC Box Reconstruction 1 2.00 3.00
19 27.230 24.325 RCC Box Reconstruction 1 3.00 3.00
20 27.410 24.500 RCC Box Reconstruction 2 2.00 2.00
21 27.510 24.603 RCC Box Reconstruction 1 2.00 2.00
22 28.285 25.380 RCC Box Reconstruction 2 2.00 2.00
23 28.710 25.805 RCC Box Reconstruction 1 2.00 2.00
Details of Proposed
Structures
table below:
7.2.6 Floor protection works shall be carried out as specified in the relevant IRC
Codes and Specifications
7.3 Bridges
(i) The existing bridge at the following location shall be re-constructed as new
Structures:
(ii) The following existing narrow bridges shall be retained and widened to 3-lane
National Highway Authority of India 27
Four laning of NH-161 from Kandi (Design Km 0.000) (Km 498.250 of NH-65) to Ramsanpalle (Design Km
39.980/Existing Km 44.757) (Design Length = 39.980 Km) in the State of Telangana under Bharatmala Pariyojna
on EPC Mode
standards so as to utilize them as Main Carriageway on one side as per details given
below. New 3-lane Standards Bridge for Main Carriageway on other side shall also be
constructed as per details given below.
Total
Existing Bridge Typical
Existing ;:Design propo
Type of (Retained/ Total Proposed Cross
Sr. Chainage Chainage sed
Crossing Repair/ Re- width of Bridge section of
No. (Km) (Km) lengt
construction) Manual
h (m)
1x16+
318.2
1 11.235 8.550 Stream Retain & Widen 1x8.4+1x12.5 m Fig: 7.5 A
2
1X16.0 +
2 25.630 22.668 Stream Retain & Widen 40.20 Fig: 7.5 A
1x8.5+1x12.5m
1X16.0 +
3 44.600 39.824 Stream Retain & Widen 21.00 Fig: 7.5 A
1x8.5+1x12.5m
7.3.3 The railings of existing bridges shall be replaced by crash barriers at the
following locations:
Sr. No. Location of Level crossing (km) Number and length of span (m)
Nil
The grade separated structures shall be provided at the locations and of the
type and length specified in paragraphs 2.9 and 3 of this Annex-I.
The existing bridges and structures to be repaired/ strengthened, and the nature
and extent of repairs/strengthening required are given below:
A. Bridges
B. ROB/RUB
8.1 Traffic control devices and road safety works shall be provided in accordance
with Section 9 of the Manual.
9 ROADSIDE FURNITURE
9.1 Roadside furniture shall be provided in accordance with the provisions of the
Section 9 of the Manual.
Excluding overhead signs and other signs at Toll Plaza location which are to be
provided as per Manual of Specifications and Standards as referred in Schedule-
D, the location of these facilities shall be finalized in consultation with
Authority Engineer/Project Director, NHAI as per site requirement. However,
minimum 2 nos. gantry overhead signs for 4-lane width and minimum 28 nos.
cantilever signs for one carriageway excluding Toll Plaza location shall be
provided.
10 COMPULSORY AFFORESTATION
11 HAZARDOUS LOCATION
12 SPECIAL REQUIREMENT
Nil.
13 CHANGE OF SCOPE
The length of Structures and bridges specified herein above shall be treated as
an approximate assessment. The actual lengths as required on the basis of
detailed investigations shall be determined by the Contractor in accordance with
the Specifications and Standards. Any variations in the lengths specified in this
Schedule-B shall not constitute a Change of Scope, save and except any
variations in the length arising out of a Change of Scope expressly undertaken in
accordance with the provisions of Article 13.
Annex-II
SCHEDULE – C
C. PROJECT FACILITIES
Project Facilities
The Contractor shall construct the Project Facilities in accordance with the
provisions of this Agreement. Such Project Facilities shall include:
(ii) One Helipad shall be constructed in the Project Corridor. The location
shall be finalized in consultation with Authority Engineer/Project
Director, NHAI.
(iii) A separate toilet facilities for road users shall be provided near toll
plaza location along with parking facility. One toilet block on each
direction shall be provided as per drawing at Annex-I of Schedule-C.
These toilet facilities shall follow CPWD specifications for sanitary ware
items and fittings such as EWC, Wash Basin, Wash basin- Under counter,
Urinal flat back, PVC Cistern, IWC Orissa Pan, Flush Value –CP, Wash
Basin pillar cock –CP, Bib Cock –CP, Health Faucet, W/c Bib cock, Wash
Basin angle cock.
(b) Road side furniture: The roadside furniture shall be as per Section 9 of the
manual and shall include
i. Traffic Signs: Traffic signs shall include roadside signs, overhead signs, kerb
mounted signs and road marking along the project highway.
ii. Pavement Markings: Shall cover road marking for the entire Project highway
iii. LED Traffic Blinkers: Shall be provided at Intersections for the entire project
highway
vi. Barbed wire fencing: Shall be provided for Entire Project highway.
vii. Hectometer / Kilometer Stones: Shall be provided for Entire Project highway.
(c) Location of Pedestrian facilities: shall include the provision of the Pedestrian
crossing as per manual.
(e) Truck lay byes: shall be provided at following locations as per manual:
25.225(RHS)
2 Before Sultanpur Km 16.450 Both
3 At Chowtakur Km 21.525 Both
(g) Rest Areas: Rest Area shall be provided at the following location as per Manual:
Sr. No. Existing Chainage Design Side
(Km) Chainage
(Km)
1 43.280 38.500 RHS
(h) Advanced Traffic Management System: The Contractor shall design, install,
operate and maintain Highway Traffic Management System (HTMS)/Advance Traffic
Management System (ATMS) as part of the project facilities as per Manual.
Annex-I
(Schedule-C)
SCHEDULE - D
(See Clause 2.1)
D. SPECIFICATIONS AND STANDARDS
1 Construction
The Contractor shall comply with the Specifications and Standards set forth
in Annex-I of this Schedule-D for construction of the Project Highway.
2 Design Standards
Manual of Specifications & Standards for four laning of Highways through PPP
IRC:SP:84-2014, referred to herein as the manual.
Annex – I:
(Schedule-D)
All Materials, works and construction operations shall conform to the Manual of
Specifications and Standards for Four laning of Highways (IRC:SP:84-2014),
referred to as the Manual, and MORTH Specifications for Road and Bridge Works.
Where the specification for a work is not given, Good Industry Practice shall be
adopted to the satisfaction of the Authority’s Engineer.
2.2 Not withstanding anything to the contrary contained in Paragraph 1 above, the
following Specifications and Standards shall apply to the Project Highway, and for
purposes of this Agreement, the aforesaid Specifications and Standards shall be
deemed to be amended to the extent set forth below:
(iii) Width of new 3 Bridge Cl. 7.3 Fig. 7.5 Fig. 7.5 A
beside existing Two (iv) (d) New two Lane Bridge New two Lane Bridge with
Lane Bridge with with one side foot one side foot path : 12.50 m
Footpath plus new 2 path : 12.30 m (8.5 m (7.0 m Carriageway + 1.5 m
Lane Bridge with Carriageway + 2x1.0 Paved Shoulder + 2x1.0 m
Annex-II
(Schedule-D)
Fig 2.5A: Typical Cross Section for approaches to 6 lane LVUP with Slip Roads on existing road
(Open country Plain / Rolling Terrain)
Fig 2.5B: Typical Cross Section for approaches to 6 lane LVUP,VUP and Bridges in bypass location
(Open country Plain / Rolling Terrain)
Fig 2.6B: Typical Cross Section for approaches to 6 lane LVUP with Slip Roads on both sides
(Builtup section Plain / Rolling Terrain)
FIG 7.5 A: Typical Cross Section of New 3 Lane Bridge beside Existing 2 Lane Bridge plus New 2 Lane Bridge on either side
1.2 Proportion of the contract price for different stages of construction of the Project
Highway shall be as specified below.
Weightage
in
percentage Percentage
Item Stage for payment
to the weightage
Contract
Price
1 2 3 4
A - Widening and Strengthening of existing Road
1. Earthwork up to top of the Sub-grade 7.152%
2. Sub-base course 5.925%
3. Non-Bituminous base course 5.830%
4. Bituminous Base Course 10.422%
5. Wearing Course 0.678%
6. Widening and Repair of Culverts 0.000%
C. 2 - Reconstruction / New
Service Slip Road (Rigid Pavement)
1. Earthwork up to top of the Sub-grade 0.00%
2. Sub-base course 0.00%
3. Dry lean Concrete Course (DLC) 0.00%
Weightage
in
percentage Percentage
Item Stage for payment
to the weightage
Contract
Price
1 2 3 4
4. Pavement Quality Concrete Course (PQC) 0.00%
0.00%
D. Re-construction and New culverts on existing road,
realignments, bypasses.
Culverts (Length < 6 m) 10.527%
Weightage
in
percentage Percentage
Item Stage for payment
to the weightage
Contract
Price
1 2 3 4
(b) In case of Underpasses :- Rigid pavement
including drainage facility complete in all respects as
specified
3. Approaches: On completion of approaches
including Retaining walls / Reinforced Earth walls, stone
pitching, protection works complete in all respects and fit
for use. 81.575%
Weightage
in
percentage Percentage
Item Stage for payment
to the weightage
Contract
Price
1 2 3 4
6. Wing walls / Return walls 0.00%
7. Approaches (Including Retaining walls /
Reinforced Earth wall, Stone Pitching and protection
works) 0.00%
Weightage
in
percentage Percentage
Item Stage for payment
to the weightage
Contract
Price
1 2 3 4
i. Toll Plaza 19.186%
ii. Road side Drains 5.903%
iii. Road signs, markings, Km stones, safety devices
etc.-- 26.901%
iv. Project facilities (TLB, BLB, Rest Areas etc.) 0.000%
a) Bus bays 5.328%
b) Truck Lay Byes 0.882%
c) Rest Areas 8.762%
d) Helipad 1.095%
e) KM Stones, boundary stones 0.073%
f) Lighting & LED blinker 5.053%
v. Road side plantation 1.724%
vi. Rain water Harvesting 1.150%
vii. Prtection work (crash barrier, railing, fencing,wire
mesh & kerb in structures) 17.355%
viii. Repair of protection works other than approaches to
the bridges, elevated sections / flyovers / grade separators
and ROB / RUBs 0.000%
ix. Site clearance & Dismantling 1.334%
ix. Advance Traffic management system (ATMS) 5.254%
x. Safety and Traffic management during construction 0.000%
Percentage
Stage of Payment Payment Procedure
-weightage
pavement) completion of a stage in full length or 5(five) km.
length, whichever is less..
@. For example, if the total length of bituminous work to be done is 100 km, the cost per km
of bituminous work shall be determined as follows:
Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)
L = Total length in Km
Similarly, the rates per km for other stages shall be worked out accordingly.
Note: The length affected due to law and order problems or litigation during
execution due to which the Contractor is unable to execute the work, may be
deducted from the total project length for payment purposes. The total length
calculated here is only for payment purposes and will not affect and referred in
other clauses of the Contract Agreement.
Procedure for estimating the value of Minor Bridges and Underpasses/Overpasses shall be
as stated in table 1.3.2:
Table 1.3.2
Stage of Payment Weightage Payment Procedure
1 2 3
A.1-Widening and repair of
minor bridges (length > 6m
and < 60m)
Minor Bridges 0.187% Cost of each minor bridge shall be determined on
pro rata basis with respect to the total linear
length of the minor bridges. Payment shall be
made on the completion of widening & repair
works of a minor bridge.
A.2- New minor bridges
(i) Foundation + Sub- 4.425% (i) Foundation +Sub-Structure: Cost of each
Structure: On completion of minor bridge shall be determined on pro rata
the foundation work including basis with respect to the total linear length (m) of
foundations for wing and the minor bridges. Payment against foundation +
return walls, abutments, piers sub-structure shall be made on pro-rata basis on
upto the abutment/pier cap. completion of a stage i.e. not less than 25% of
the scope of foundation +sub-structure of each
bridge subject to completion of atleast two
foundations along with sub-structure upto
abutment/pier cap level of each bridge.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(ii) Super-structure: On 2.183%
completion of the super-
structure in all respects (ii) Super-structure: Payment shall be made on
including wearing coat, pro-rata basis on completion of a stage i.e.
bearings, expansion joints, completion of super-structure of atleast one span
hand rails, crash barriers, road in all respects as specified in the column of
signs & markings, tests on “Stage of Payment” in this sub-clause.
completion etc. complete in all
respect.
(iii) Approaches: On 0.249% (iii) Approaches: Payment shall be made on
completion of approaches pro-rata basis on completion of a stage i.e.
including Retaining walls, completion of approaches in all respect as
stone pitching, protection specified in the column of “Stage of Payment” in
works complete in all respect this sub-clause.
and fit for use.
(iv) Guide Bunds and River 0.00% (iv) Guide Bunds and River Training Works:
Training Works: On Payment shall be made on pro-rata basis on
completion of Guide Bunds completion of a stage i.e. completion of Guide
and river Training Works Bunds and River training Works in all respects as
complete in all respects specified.
B.1-Widening and repair of
underpasses / overpasses
Underpasses / overpasses 0.00% Cost of each underpass/overpass shall be
determined on pro rata basis with respect to the
total linear length of the
underpasses/overpasses. Payment shall be
made on the completion of widening & repair
works of a underpass/overpass.
Procedure for estimating the value of Major Bridge work, ROB/RUB and Structures shall be
as stated in table 1.3.3:
Table 1.3.3
Stage of Payment Weightage Payment Procedure
1 2 3
A.1- Widening and repairs of
Major Bridges
(i) Foundation 0.00% (i) Foundation: Cost of each Major Bridge shall
be determined on pro rata basis with respect to
the total linear length (m) of the Major Bridge.
Payment against foundation shall be made on
pro-rata basis on completion of a stage i.e. not
less than 25% of the scope of foundation of the
major Bridge subject to completion of atleast two
foundations of the major Bridge.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(ii) Sub-structure 0.360% (ii) Sub-Structure:. Payment against Sub-
structure shall be made on pro-rata basis on
completion of a stage i.e. not less than 25% of
the scope of sub-structure of the major bridge
subject to completion of atleast two sub-
structures of abutments/piers upto abutment/pier
cap level of the major bridge.
(iii) Super-structure (including 0.126% (iii) Super-structure: Payment shall be made
bearings) on pro-rata basis on completion of a stage i.e.
completion of super-structure including bearings
of atleast one span in all respects as specified.
(iv) Wearing Coat including 0.474% (iv) Wearing Coat: Payment shall be made on
expansion joints completion of wearing coat including expansion
joints complete in all respects as specified.
(v) Miscellaneous Items like 0.033% (v) Miscellaneous: Payments shall be made on
hand rails, crash barriers, road completion of all miscellaneous works like hand
markings, etc. rails, crash barriers, road markings etc. complete
in all respects as specified.
(vi) Wing walls/return walls 0.00% (vi) Wing walls/return walls: Payments shall be
made on completion of all wing walls/return walls
complete in all respects as specified.
(vii) Guide Bunds, River 0.00% (vii) Guide Bunds, River Training works:
Training works etc. Payments shall be made on completion of all
guide bunds/river training works etc. complete in
all respects as specified.
(viii) Approaches (including 2.250% (viii) Approaches: Payments shall be made on
Retaining walls, stone pitching completion of both approaches including stone
and protection works) pitching, protection works, etc. complete in all
respects as specified.
A.2- New Major Bridges
Procedure for estimating the value of other works done shall be as stated in table 1.3.4:
Table 1.3.4
Stage of Payment Weightage Payment Procedure
Unit of measurement is each completed toll
plaza. Payment of each toll plaza shall be made
on pro rata basis with respect to the total of all
(i) Toll plaza 19.186% toll plazas.
Unit of measurement is linear length in km.
Payment shall be made on pro rata basis on
completion of a stage in a length of not less than
(ii) Road side drains 5.903% 10 % (ten per cent) of the total length.
Unit of measurement is linear length in km.
(iii) Road signs, markings, km Payment shall be made on pro rata basis on
stones, safety devices and completion of a stage in a length of not less than
other road furniture etc. 26.901% 10 % (ten per cent) of the total length.
(iv) Project Facilities
a) Bus bays 5.328%
b) Truck lay-byes 0.882%
c) Rest areas 8.762% Payment shall be made on pro rata basis for
completed facilities.
d) Helipad 1.095%
e) KM Stones, boundary
stones 0.073%
f) Lighting & LED blinker 5.053%
(v) Roadside plantation Unit of measurement is linear length. Payment
shall be made on pro rata basis on completion of
a stage in a length of not less than 10% (ten per
1.724% cent) of the total length.