Gate Rehab PDF
Gate Rehab PDF
Gate Rehab PDF
g
92101465c
Non Record
<
I S Army Corps
I 1Engineers »
irtland District
Value Engineering Study Report
ARIMS 800C
P2 No.: 400906
NWP VE Study No: FY14-01
Workshop Dates: 2-6 Dec 2013
Jf84 ft Date: 30 June 2014
-V215
L66
2014 -----------------------------------------------------------------
C. 1
LIB R A R Y
NOV 1 4 2014
Bureau of Reclamation
Denver, CO
CENWP-VE FY14-01 Value Engineering Study Report
Forward
The US Army Corps of Engineers, Portland District (CENWP), sponsored this Value
lo 201*4
Engineering (VE) Study to assist the CENWP Project Manager and Project Development Team
by providing them with Alternatives and Design Suggestions to identify and/or address the risks,
performance, schedule and costs issues related to the functional needs of the project. The
^ workshop was held in the Portland District office from 2-6 December 2013 (40 hours).
This report is presented in a rolling narrative format to illustrate the sequence of activities that
took place during the VE workshop. The workshop was facilitated in accordance with the SAVE
c>, (Society of American Value Engineers) International VE methodology standards and the U.S.
:> Army Corps of Engineers (USACE) VE Regulation, ER 11-1-321, Change 1, dated 1 January
1-2011, and facilitated by a Certified Value Specialist (CVS).
The VE team was comprised of USACE staff from the Portland District and technical experts
from the Bureau of Reclamation and Tetra Tech, representing the disciplines of: Mechanical
^ Engineering, Electrical Engineering, Civil Engineering, Construction Management, Cost
I Engineering, and Facility Operations.
92101465
June 2014
EXECUTIVE SUMMARY
Value Engineering Study Data
Project: Lookout Point Tainter Gate Rehabilitation
Project Location: L ookout P oint VE Study #: FY 14-01
P2#: 400906 Division/District: N W D /N W P
Product Status: D raft 60% D D R VEO: Jason W eber
Workshop
Workshop Dates: D ecem ber 2 - 6, 2013 40
Duration (hrs.):
Estimated Total
$6,700,000 Study Cost **: $59,000***
Project Cost (PA)*:
* Includes all project costs: PDT Labor & Materials, A/E Services, Studies, Investigations, Construction, etc.
** Includes cost for VEO + VE Team + Contract action. Does not include PDT cost labor.
*** This does not include the VEO.
Reporting Results
Total Number of Alternatives and Design Suggestion/ DEVELO PED 19
Comments ACCEPTED TBD
DEVELOPED 5
Total Number of Alternatives (Quantitative)
ACCEPTED TB D
Total Number of Design Suggestion/Comments DEVELO PED 14
(Qualitative) ACCEPTED TB D
Additional Results
D E V E L O PE D : 4
Number of Alternatives that Add First Costs
ACCEPTED: TB D
$5.5M -
Maximum Credible Potential Added Cost P R O PO SE D :
$5.7M **
( S u m o f e x c l u s iv e A lte r n a tiv e s ; F ir s t C o s t, n o t N e t L ife C y c le )
ACCEPTED : TB D
D E V E L O PE D : 0
Number of Alternatives that Developed Life Cycle Costs
ACCEPTED : TB D
Product Description
The tainter gates at Lookout Point were designed and constructed in the 1950’s. In 2010, the
District performed a comprehensive assessment of the tainter gates in the Willamette Valley and
Rogue Basin projects. Current structural analysis of the Lookout Point gates indicate that the
gates are overstressed when operated, even under normal pool levels. Other gates in the
Willamette Valley designed with the same criteria have shown bent or failed members. In
addition, the mechanical and electrical systems that operate the gates are unreliable and have
shown significant degradation and need to be rehabilitated or replaced.
Due to these findings, a year round gate operating restriction was implemented as an Interim
Risk Reduction Measure (IRRM). The structural analysis indicates the gates may be operated
safely at any time the pool is at or below elevation 915 (upper strut of the gate). As the pool
rises, the spillway gates may be raised in order to track with the pool elevation, keeping the
upper strut above the water surface.
The baseline concept project scope presented to the Team during the VE Study is to rehabilitate
Gates 2 and 3 and include an option to rehabilitate Gate 4 if funding is available. Gates 1 and 5
will be rehabilitated at a later time. The scope of work for each gate is:
• Structural - Strengthen the strut arms and the middle portion of the gate with bracing;
and remove (chemical stripping) the coating and re-coat only the areas disturbed by the
construction (-20% of the cost estimate; $1.3 million).
• Mechanical - Replace all components of the hoist system (-40% of the cost estimate;
$2.7 million).
• Mechanical - Replace the trunnion/pin bushing assemblies (-20% of the cost estimate;
$1.3 million).
• Electrical - Replace all electrical components including the feeder cables and installing a
load-limiting device (-15% of the cost estimate; $1 million).
• Miscellaneous materials, equipment, spares, and skilled craftsmen (-1% of the cost
estimate; $0.1 million).
• Mobilization (-4% of the cost estimate; $0.3 million).
The 30 percent design estimate for this scope of work is $6.7 million, including construction
contingencies in December 2013 dollars.
Portions of this section consist of excerpts from the Draft Design Documentation Report 60%
DDR Lookout Point Tainter Gate Rehabilitation, USACE, January 2014, and Lookout Point
Dam Tainter Gate Rehabilitation Charter, Charter Number 2012-35, USACE.
VE Workshop Highlights
The VE Team met at Lookout Point Dam to learn about the project. Ms. Laurie Ebner,
representing the PDT for USACE, gave a briefing to the Team describing the scope of the
project, risks associated with the project, funding and schedule constraints. The Team then went
out to the dam to see the tainter gates and the associated mechanical and electrical components.
During the study, the Team recognized that there were inconsistencies in the scope of work that
was documented in the Draft 60% DDR and what was presented to the Team during the Value
Study. The Team understands that the PDT is under pressure to quickly develop a design, and
that there are many moving parts working to create a quality design.
The Team focused on improving value to the project by focusing on eliminating the IRRMs,
improving reliability, improving functionality, prolonging life, and minimizing friction. Several
of the alternatives highlight this:
Alternative 2 consists of investigating the potential to re-use and/or refurbish all the components
of the hoist system for all five gates. The impetus for this idea stemmed from two items; seeing
the cost model that showed replacing the entire hoist system was the largest cost (40% of the
costs: $0.9 Million/per gate) and that several components (large parallel gearboxes, small high
speed gearboxes, wire ropes, and motors) have been recently replaced.
Alternative 3 consists of recoating the entire tainter gates including the upstream skinplate. The
driver for this idea was based on two items: the Project Manager stating that a goal or objective
of the project is to ensure another 50-year life cycle out of the gates, and that a recent draft report
indicates that there is pitting on the upstream skinplate. The Team understands that the coating -
system will not last 50 years, however, it is advantageous to recoat the entire gate while a
contractor is out at the site and has installed access platforms and containment to perform the
structural portion of the work.
Alternative 4 consists of building stoplogs. The main reason this was developed as an alternative
is that the PDT was very concerned that there are no stoplogs or guides at Lookout Point as has
been the case on previous USACE gate projects. Another reason this was put forth is because
the construction window is from July 15 through November 15 and stoplogs could lengthen the
construction window and give operators more capacity / flexibility during gate construction.
The Team also developed design comments that proposed alternative means to accomplish the
same function, prolonging the life of the tainter gates, addressing operation and maintenance
issues, enabling remote operation of the gates, re-evaluating design assumptions, and addressing
constructability and construction schedule issues. One design comment is to consider revising
the Engineering Manual to allow a lower friction factor to be used on low friction bushings. The
Bureau of Reclamation sometimes uses a design coefficient of friction less than 0.3 for low
friction bushings whose testing indicates a friction coefficient much less than 0.3.
It is the expectation of the VE Team that this report and the ideas contained within, adds value to
the project, and inspires the PDT to come up with additional and/or better ideas to rehabilitate
the tainter gates at Lookout Point.
Half way through the study, the Project Manager told the Team that one of the main purposes of
the project was to ensure another 50-year life cycle for the gates. This reiterated to the Team the
importance of improving reliability of the gates and to prolong the life of the gates.
The Team took some of the functions from the FAST diagram (Figure 1) and brainstormed ideas
to accomplish those functions. The functions used for this exercise were:
FAST DIAGRAM
HOW
------->
(Methods)
Reduce
Flood Damage
Control
Temperature
TABLE OF CONTENTS
EXECUTIVE SUMMARY............................................................................................................. i
Value Engineering Study D ata.................................................................................................... i
Reporting Results......................................................................................................................... i
Additional Results........................................................................................................................ i
Product Description.................................................................................................................... ii
VE Workshop Highlights............................................................................................................ ii
Value Added Alternatives*........................................................................................................ iv
Accepted Design Suggestions/Comments................................................................................. iv
Project Team Roster................................................................................................................... iv
Function Analysis/FAST Diagram............................................................................................. v
INTRODUCTION...........................................................................................................................1
PROJECT DESCRIPTION............................................. 1
Lookout Point Project Description:.............................................................................................1
Lookout Point Tainter Gate Problem Description:..................................................................... 2
Lookout Point Tainter Gate Rehabilitation Baseline Concept:..................................................3
Information Provided to the VE Team:...................................................................................... 5
WORKSHOP RESULTS................................................................................................................ 6
Value Methodology.................................................................................................................... 6
Information Phase.................................... 6
Function Analysis Phase............................................................................................................. 7
Creativity/Brainstorming Phase.................................................................................................. 8
Evaluation Phase......................................................................................................................... 8
Development Phase..................................................................................................................... 8
Presentation Phase...................................................................................................................... 8
IMPLEMENTATION..................................................................................................................... 8
Conclusion...................................................................................................................................... 9
APPENDIX A .............................................................................................................................A-l
Developed Alternatives........................................................................................................... A-l
Alternative 1: Furnish and Install Mechanical Hoist System and Electrical Equipment for
All Gates................................................................................................ A-2
Alternative 2: Investigate Reuse / Refurbishment of Hoist System for all Five Gates. A-3
Alternative 3: Recoating Tainter Gates......................................................................... A-5
Alternative 4: Build Stoplogs........................................................................................ A-7
Alternative 5: National Electric Manufacturers Association (NEMA) B Motor........ A-l 1
APPENDIX B ............................................................................................................................. B-l
Design Suggestions................................................................................................................. B-l
Structural Design Comment 1: Cross Bracing for Strut Arm Support.......................... B-2
Structural Design Comment 2: Improve Drainage on Structural Gates........................ B-3
Structural Design Comment 3: Bolts in lieu of Welding............................................... B-4
Structural Design Comment 4: Address Upstream Skinplate Corrosion Pitting.......... B-5
Structural Design Comment 5: Attach Counterweight to Tainter Gate......................... B-6
Mechanical Design Comment 1: Use Lower Friction Replacement Side Seals...........B-8
Mechanical Design Comment 2: Seal Gate Hoist Gearboxes...................................... B-8
Mechanical Design Comment 3: Provide Means of Containing Grease Leaking from
Hoist Gearboxes...................................................................................... B-9
Mechanical Design Comment 4: Contain Trunnion Bushing Grease......................... B-l 1
Electrical Design Comment 1: Add SCADA Capability............................................ B-l 2
Design Assumptions Design Comment 1: Trunnion Design Friction Factor.............. B -l3
Construction Comment 1: Construct Electrical and Mechanical Components Prior to July
15th........................................................ B-13
Construction Comment 2: Raise Reservoir Level for Power Generation and Recreation
............................................................................................................ B-14
Construction Comment 3: US ACE Design of Construction Platform....................... B-l 5
APPENDIX C ............................................................................................................................. C-l
Information Phase................................................................................................................... C-l
Owner, User, and Stakeholder Issues of Concern.......................................................... C-2
Value Study Objectives.................................................................................................. C-3
Core problems the project is trying to solve................................................................... C-3
Impacts of not doing the project..................................................................................... C-3
Big risks associated with the project............................................................................... C-3
INTRODUCTION
The Value Engineering (VE) Study was sponsored by the USACE Portland District Office and
conducted for the Lookout Point Tainter Gate Rehabilitation Project from December 2 through 6,
2013, at the Portland District office in Portland, Oregon. The Team was comprised of members
of the Portland District Office, Lookout Point Dam, Tetra Tech, and the Bureau of Reclamation.
This report provides a description of the tainter gate problem at Lookout Point, the baseline
concept to solve the problem, and the results of the value study.
PROJECT DESCRIPTION
Lookout Point Project Description:
Lookout Point, located on the Middle Fork Willamette River, is a multi-purpose storage project
that operates to meet the authorized purposes of flood damage reduction, irrigation, power
generation, recreation, navigation, and downstream water quality improvement. The dam is an
earth and gravel-fill structure with a concrete gated spillway. The spillway has five spillbays
controlled by tainter gates. The project has four regulating outlets.
The spillway crest is at elevation 887.5 feet and the elevation of the top of spillway gates (when
closed) is 929 feet. Table 1 lists relevant project elevations and corresponding flows through the
spillway.
Table 1 - Lookout Point elevations and corresponding spillway releases through one spillbay.
1All elevations reference the Lookout Point project datum (approximately NGVD29).
The project has three hydropower units capable of producing 50 MW (each), and a hydraulic
capacity of 2,400 cfs to 2,700 cfs each, depending on pool elevation. Minimum power pool is
819 feet, and minimum conservation pool is 825 feet. The capacity of the four regulating gates
ranges from 4,000 cfs to 6,100 cfs for each outlet, depending on pool elevation. The invert
elevation of the outlets is 724 feet.
This section of the report consists of excerpts from the Draft Lookout Point Spillway Gate
Repair Schedule Issue Paper, USACE, October 2013.
In 2010, the District performed a comprehensive assessment of the tainter gates in the
Willamette Valley and Rogue Basin projects. The comprehensive assessment included a gates
specific potential failure modes analysis (PFMA), structural, mechanical and electrical
assessments, identification of interim reduction measures, and analysis of impacts of the interim
reduction measures. Current structural analysis of the Lookout Point gates indicates that the
gates are overstressed when operated, even under normal pool levels. Other gates in the
Willamette Valley designed with the same criteria have shown bent or failed members. In
addition, the mechanical and electrical systems that operate the gates are unreliable and have
shown significant degradation and need to be rehabilitated or replaced.
Due to these findings, a gate operating restriction was put into effect as an Interim Risk
Reduction Measure (IRRM). The structural analysis indicates that the gates may be operated
safely at any time the pool is at or below elevation 915 (upper strut of the gate). As the pool
rises, the spillway gates may be raised in order to track with the pool elevation, keeping the
upper strut above the water surface. The IRRM gate restrictions are year round.
This section of the report consist of excerpts from the Draft Design Documentation Report 60%
DDR Lookout Point Tainter Gate Rehabilitation, USACE, January 2014, and Lookout Point
Dam Tainter Gate Rehabilitation Charter, Charter Number 2012-35, USACE.
• Structural - Strengthen the strut arms and the middle portion of the gate with bracing
(Figure 1); and remove (chemical stripping) the coating and re-coat only the areas
disturbed by the construction (~20% of the cost estimate; $1.3M).
• Mechanical - Replace all components of the hoist system (Figure 2) (~40% of the cost
estimate; $2.7 million).
• Mechanical —Replace the trunnion/pin bushing assemblies (Figure 1; ~20% of the cost
estimate; $1.3 million).
• Electrical - Replace all electrical components (Figure 3) including the feeder cables and
installing a load-limiting device (~15% of the cost estimate; $1 million).
• Miscellaneous materials, equipment, spares, and skilled craftsmen (~1% of the cost
estimate; $0.1 million).
• Mobilization (~4% of the cost estimate; $0.3 million).
The 30% design estimate for this scope of work is $6.7 million, including construction
contingencies with December 2013 dollars. This estimate was developed by the cost engineer
during the VE Study and the cost model is shown at the end of Appendix C.
Figure 1. Proposed Structural Improvements to Gates 2 and 3 (Gate 4 optional). The yellow
lines in the left figure represent a majority of the proposal bracing for the struts and the middle
portion of the gate. The right figure shows the proposed steel plates added to the strut arms.
Based on USACE’s analysis in the Draft Lookout Point Spillway Gate Repair Schedule Issue
Paper, October 2013, the recommended construction window appears to be from July 15 to
November 15, 2015. If a third gate is repaired, the construction window would most likely be
performed between July 15 and November 15, 2016. The construction season is controlled by
the operating project Rule Curve, which incorporates a low pool elevation during the rainy
season for flood control, and an IRRM restricted full pool elevation for the summer recreation
season. The gate will be on seal during the majority of the construction activity. To complete
the construction on the Lookout Point Tainter Gate, the pool has to be below the spillway crest to
allow for structural repairs, replacement of the pin bushings, seals and exercising of the gate
once wire ropes are re-tensioned. The pool is typically below spillway crest during the flood
season when the project is drafted to capture flood events and reduce downstream flows. This is
a flood control project and if a significant flood event occurs, the pool will rise above the
spillway crest. A majority of this paragraph is an excerpt from the Draft Design Documentation
Report 60% DDR Lookout Point Tainter Gate Rehabilitation, USACE, January 2014.
• Draft Lookout Point Spillway Gate Repair Schedule Issue Paper, USACE, October 2013.
• Portland District Spillway Tainter Gates, Comprehensive Assessment Final Report,
December 2011.
• Draft Site Specific Paint & Corrosion Inspection o f Spillway Gates and Ancillary
Outdoor Equipment Report, USACE, August 2013.
WORKSHOP RESULTS
Value Methodology
The Value Method is a decision making process, originally developed by Larry Miles in the
1940’s, to creatively develop alternatives that satisfy essential functions at the highest value.
The study process follows a job plan that provides a reliable, structured approach to the
conclusion. The purpose of the study is to make good projects better by focusing on improving
value and striving to achieve a high return on investment. It is through the effort of a diverse,
high-performing team that this can be achieved.
This report is the result of a formal Value Study by a team comprised of people with the
diversity, expertise, and independence needed to creatively attack the issues. The team members
brought a depth of experience and understanding of the discipline they represent and an open and
independent inquiry of the issues under study, to solve the problems at hand. The team applied
the Value Method to the issues and supporting information and took a “fresh look” at the
problems to create alternatives that fulfill the client’s needs at the greatest value.
The Value Study Team is a diverse group of professionals from Reclamation, the USACE, and
Tetra Tech. The Design Team members were USACE and Tetra Tech. Further policy and / or
design evaluations will be required prior to acceptance of any alternatives developed during this
study. Alternatives from this study, in and of themselves, do not indicate the technological,
administrative, or policy approval of the agencies represented by the Team. The decision to
accept or reject individual alternatives will be made through a combined effort between the
USACE designers and managers.
The Value Method job plan followed for this study consists of the following phases:
Information Phase
The Team met at Lookout Point Dam to learn about the project. Ms. Laurie Ebner, representing
the PDT for USACE, gave a briefing to the Team describing the scope of the project, risks
associated with the project, funding, and schedule constraints. The Team then went out to the
dam to see the tainter gates and the associated mechanical and electrical components.
• Owners, users, and stakeholders associated or affected by the project and their particular
needs and concerns
• Value Study objectives
• Core problems the project is trying to solve
• Impacts of not doing the project
• Big risks associated with the project
• Constraints on the project
• Design constraints
• Significant concerns about the project
• Assumptions made about the project
The Team also reviewed the cost model (Appendix C) developed by the Design and Estimating
team. The cost model was used to determine:
• the cost drivers to see if there were other ways to design those features
• the minor costs to see if those features are necessary
The FAST diagram developed by the Team is a logic diagram that shows the inter-relationships
of the functions and describes the baseline concept from a function point of view. The FAST
diagram developed a common and deeper understanding of how project objectives are met by the
baseline concept.
The list of functions and the FAST diagram are shown in Appendix D. After this phase of the
study, the project manager told the Team that one of the main purposes of the project was to
ensure another 50-year life cycle for the gates. This reiterated to the Team the importanqe of
improving reliability of the gates and to prolong the life of the gates. i ~ : *
Creativity/Brainstorming Phase
During this phase of the study, the Team was encouraged to offer any and all ideas, including
“wild” ideas, to solve the identified problems and perform the intended functions. Criticism was
prohibited during this phase so that all Team members would be comfortable offering thoughts
and ideas. It has been demonstrated that one person’s extreme idea can often be the spark for
someone else's ‘brilliant’ idea. Ideas were not evaluated during this phase of the study.
The Team took some of the functions from the FAST diagram and brainstormed ideas to
accomplish those functions. The functions used for this exercise were:
The Team also listed miscellaneous ideas to improve the project and address constructability
issues. The Team came up with 58 ideas, which are listed in the Disposition of Ideas table in
Appendix E.
Evaluation Phase
The ideas were evaluated, analyzed, and prioritized, and the best ideas were developed to a level
suitable for comparison, decision making, and adoption. The Team members were instructed to
vote on the ideas (developed during the Creativity / Brainstorming Phase) that the Team should
consider and discuss. The Team members were not restricted to a certain number of votes. A
record of the number of votes for each idea is included in the Disposition of Ideas table in
Appendix E.
Development Phase
The Team determined that five of the ideas should be developed as alternatives (Appendix A),
and fourteen ideas should be developed as Design Suggestions (Appendix B). The rest of the
ideas are listed in the Disposition of Ideas Table in Appendix E.
Presentation Phase
The Team developed and presented a PowerPoint presentation summarizing the results of the
study. The list of attendees and a copy of the PowerPoint presentation is in Appendix F.
IMPLEMENTATION
This report presents a summary of the activities performed during the VE Study and the results
of the VE Study that consists of five alternatives and fourteen design comments. The Product
Development Team and Portland District VE Officer will review the report and develop an
implementation plan that includes a disposition (accept, reject, partial acceptance, etc.) of the
alternatives, the rationale for the dispositions, and a plan of action to incorporate the accepted
alternatives into the design process. A Final VE Study Report will be prepared when the
implementation results are finalized.
CONCLUSION
The VE Team recognized that there were inconsistencies in the scope of work that was
documented and what was presented to the Team during the Value Study. The Team
understands that the PDT is under pressure to quickly develop a design and that there are many
moving parts working to create a quality design.
The VE Team developed five alternatives and fourteen design comments for the PDT to
consider. The five alternatives strived to add value to the project by:
It is the hope of the VE Team that this report and the ideas contained in this report, adds value to
the project, and inspires the PDT to come up with additional and/or better ideas to rehabilitate
the tainter gates at Lookout Point.
A P P E N D IX A
Developed Alternatives
The Team developed five Alternatives with Performance Metrics as shown in Table 2.
P e r fo r m a n c e M e tric A lt 1 : ■¡QQEj A lt 3: A lt 4: A lt 5:
R e p la c e R e- S to p lo g s B M o to r
A ll M & E S tu d y C o a tin g
At a minimum, a preliminary investigation should be performed that lists all the components of
the hoist system, the cost to replace those components, and the likelihood that they may be re
used or re-furbished.
The Team understands that this contract has to be awarded in FY14 and rehabilitation of the
gates occurs in FY15 (Gates 2 and 3) and FY16 (Gate 4). If this investigation cannot be
completed in time to award the contract in FY14, and it is believed there could be significant
savings, then the PDT may want to consider postponing the project a year. If there are
significant savings as a result of an investigation, this ensures that Gate 4 can be rehabilitated in
this contract and gives USACE flexibility to consider one or more of the following:
• replace the mechanical hoist systems for all five gates (Alternative 1).
• recoat the entire gate, including the skin plates (Alternative 3).
• purchase stoplogs (Alternative 4).
Ways to Implement:
Perform a thorough examination of the hoist system and document the findings. Incorporate into
the plans and specifications, which hoist components are to be reused and what work is required
to refurbish and upgrade hoists.
Potential Risks:
• May not be sufficient information available from the original manufacturer to determine
if current EM’s and ER’s are met.
• Refurbished hoists may have shorter life span than new hoist systems.
• There may be hazardous materials in the coatings that need to be mitigated.
Costs
Baseline Concept $6,700,000
Alternative 2 Concept $6,700,000
Savings $ 0*
Implementation Costs $ 200,000
Net Additions $ 200,000
* Savings could be extensive since 40% ($0.9M/gate) of the project cost is for full replacement of the hoist
system.
3A: Recoat entire tainter gate including upstream skinplate with a conventional coating system.
3B: Recoat entire tainter gate including upstream skinplate with metalized zinc, 14-16 mils
thick, instead of a conventional coating system.
Critical Items to Consider:
3A and 3B: The existing coatings are hazardous and must be properly contained when removed.
3B:
• Application is possible in colder weather.
• Easily repairable.
• Color does not fade or chalk.
• Shorter curing time.
• One coat process.
Disadvantages (compared to the baseline concept):
3A and 3B:
• Higher costs (materials and application).
• Longer construction duration.
3B:
• Specialized coatings contractor and equipment needed to apply metalizing.
• More stringent inspection is required.
• Abrasive-blasted surfaces must be coated that day.
• Surfaces must be very clean.
• One color - light grey.
Potential Risks:
May negatively impact construction schedule or require an additional construction season.
3A Costs
B a se lin e C o n c e p t $2,250,000 / gate
A lte rn a tiv e 3 A C o n c e p t $2,485,000 / gate
A d d itio n s $ 235,000/g a te
3B Costs
B a se lin e C o n c e p t $2,250,000 / gate
A lte rn a tiv e 3 B C o n c e p t $2,570,000 / gate
A d d itio n s $ 32 0 ,0 0 0/g a te
If designed and procured, the stoplog system could be employed to provide added flexibility in
scheduling the rehabilitation of the Tainter Gates at LOP. Once procured, the stoplog system
would be available for future O&M and capital works projects at LOP Dam.
Further consideration could be given to size the stoplogs so that they could be used at other
locations in the area other than LOP.
This alternative is proposed because members of the PDT stated that the lack of stoplogs was a
big concern.
The Team assumes that a typical stoplog would be constructed with approximately the same
weight (amount of steel) and be placed in easily accessible support slots mounted on the face of
the piers. The typical unit stoplog weight is approximately 13,000 lbs. and the lifting beam is
approximately 2,000 lbs. The combined lifting beam and stoplog weight appears to be within the
LOP crane lifting limit.
It is assumed that the Tainter Gate spillway bays throughout the Willamette Valley range in
width from 35 feet to about 50 feet. An assessment should be made of the spillway bays that do
not presently have stoplog guides or stoplog capability to assess the potential for greater use of
the proposed stoplogs.
This is not included in the project scope of work, but it provides protection in the event there is a
flood and/or it allows the reservoir to store additional water during the 15 July to 15 November
construction window.
Ways to Implement:
Installation work may require divers for portions of the guides that may be below the water
surface. The anchorage system will require minimal dive time.
Advantages:
• Provides additional flood protection for tainter gate rehabilitation (especially when the gates
are off the trunnion pins) during construction window.
• Adds flexibility to construction window.
• Re-use stoplogs for other LOP maintenance projects.
• May be able to design such that the stoplogs can be used at other facilities.
• Ease of installation.
• Minimal lift load.
• Available for use on this construction contract.
Disadvantages:
• Height of protection is fixed based on number of stoplogs procured (assumed five units each
approximately 3-feet high, total height approximately 15 feet).
• Additional cost to the project that is currently not in the agreed upon scope of work.
Potential Risks:
• Unknown availability of rental cranes in area for placement.
DETAIL 1
STEEL BEAM
VERTIOLE
IT E M U N IT S Q U A N T IT Y U N IT C O S T TO TAL
2 - H P 14x7 3 @ 4 8 ' lb 1 0 ,0 0 0 $ 6 .7 8 $ 6 7 ,8 0 0
Sill angle 4 x 4 x 1 /2 @ 1 2 .8 lb 1,0 0 0 $7 $ 6 ,7 8 0
12" std pipe 1/2 round @ 4 9 .6 lb 1,2 0 0 $ 6 .7 8 $ 8 ,1 3 6
G uide angles 2 .5 x 2 .5 x 0 .2 5 lb 100 $ 6 .7 8 $678
5 stoplogs @ 1 3 ,0 0 0 lb e a lb 6 5 ,0 0 0 $ 6 .7 8 $ 4 4 0 ,7 0 0
Lifting Beam @ 2 0 0 0 lb lb 2 ,0 0 0 $ 6 .7 8 $ 1 3 ,5 6 0
75 anchors, nut, w asher, epoxy ea 75 $ 1 3 1 .0 0 $ 9 ,8 2 5
C oncrete and Grout cy 3 $ 5 0 0 .0 0 $ 1 ,5 0 0
Dive team installation da 1 $ 1 0 ,0 0 0 .0 0 $ 1 0 ,0 0 0
Shipping 100w 773 $ 6 .8 0 $ 5 ,2 5 6
G uide and Sill system install da 5 $ 6 ,7 5 0 .0 0 $ 3 3 ,7 5 0
Blast and Paint sf 6 ,5 0 0 $ 8 .0 0 $ 5 2 ,0 0 0
P E R Bay T o ta l A d d itio n s $ 6 4 9 ,9 8 5
C o n tin g e n c y 2 5 .0 0 % $ 1 6 2 ,4 9 6
M a rk -u p s 2 0 .0 0 % $ 1 2 9 ,9 9 7
T o ta l C o s t D e c re a s e /ln c re a s e $ 9 4 2 ,4 7 8
P er Bay Cost Differential R ounded: $ 9 5 0 ,0 0 0
This Team proposes using a NEMA design B motor controlled with a variable frequency drive
(VFD). The original Lookout Point drawings show a NEMA design D motor. These motors
were later replaced with NEMA design B motors that have performed very well. The NEMA
design B motor has much less locked rotor torque than the design D motor and the VFD is, by
design, a load-limiting device. As such, the load on the structure can be restricted and eliminate
the need for a separate load-limiting device.
Critical Items to Consider:
The motor has to be adequately sized so that the gate can be opened in the more demanding load
case of single sided lifting. If this is not accomplished, the motor may fail to open the gate.
Ways to Implement:
Incorporate in the design a NEMA B motor and VFD.
Advantages (compared to the baseline concept):
• The NEMA design D motor is difficult to obtain and is not available from any normal
motor manufacturer as “standard.” The NEMA design B motor is a standard motor and is
readily available from most, if not all, manufacturers.
• The VFD provides many advantages, including reduced mechanical stresses on the
components due to the “soft start” and “soft stop” capability. In addition, the VFD
provides current limiting which equates to limited torque (load).
Disadvantages (compared to the baseline concept):
• NEMA design B motors have a lower start up torque than a design D motor. The VFD
would need to be programmed to overcome inertia loads.
Potential Risks:
None identified.
Costs
Baseline Concept $6,700,000
Alternative 5 Concept $6,700,000
Savings $ 0*
*The Team presented that there would be a $180,000 savings by switching from D motors to B motors. The Team
found out during the presentation that Design B motors were installed on Fall Creek, which was the primary basis
for the Lookout Point 30% design cost estimate. Therefore, there is no reportable savings because a B motor is
included in the cost estimate.
A P P E N D IX B
Design Suggestions
Special consideration would also be needed to connect the larger cross bracing members to the
strut arms.
This design has been analyzed using STAAD V8i structural software. The cross brace system
cuts down the un-braced length of the strong axis of the critical members, but does not increase
the flexural strength of the sections near the trunnion. Therefore, the interaction ratio for the
strut arms near the trunnion will be insufficient according to Engineering Manual 1110-2-2702.
Advantages:
• Minimize on-site welding within the spillway.
Disadvantages:
• Increase in material cost.
• Possible increase in structure weight affecting the mechanical systems.
• Increase in design work.
• Does not increase flexural strength.
• Will need to add steel in addition to cross bracing to get required strength.
Potential Risks:
May not provide an adequate interaction ratio for the strut arms.
Cost Impacts:
Increase in cost because of the additional steel.
Potential Risks:
None Identified.
Cost Impacts:
This is an increase to the scope of work and will add minimal costs.
Disadvantages:
• The bolted steel plates may allow small openings where moisture could penetrate and
initiate corrosion.
Potential Risks:
• The tradeoffs between this suggestion and the baseline may be difficult to quantify.
Cost Impacts:
• The Team is unsure of the cost impacts.
Advantages:
• Extend life of upstream skin plate by repairing corrosion damage.
Disadvantages:
• Requires access to entire upstream face of gate, which would not be required in baseline
scope of work.
Potential Risks:
• Excavation of cracks in welds could lead to significant scope growth, which could exceed
budget for repairs.
Cost Impacts:
This is an increase in scope and therefore will add cost to the baseline concept.
Disadvantages:
A large engineering effort will be required to design the counterweights and determine how to
attach it to the existing structure.
A greater force would be exerted on the trunnion pin and bushing. This would increase the
frictional force and the demand on the mechanical hoist system. This could possibly negate any
reduction in force achieved by installing the counterweight.
Potential Risks:
Structural analysis of this may prove that the negatives outweigh the positives.
Cost Impacts:
The Team is unsure of the cost impacts.
Advantages:
• Reduced side seal friction reduces the lift load, which increases the safety factor on the
hoist capacity.
• Reduces wear on seals for gates with frequent operation.
• Potentially allows use of less costly hoist components.
Disadvantages:
• PTFE clad seals may not seal as well.
• More costly.
Potential Risks:
None identified.
Cost Impacts:
This will add minimal costs to the baseline concept.
Disadvantages:
• Increasing internal dead space over oil in gearbox may require custom design, which will
increase cost and may require additional lead-time.
Potential Risks:
None identified.
Cost Impacts:
This is an increase to the scope of work and will add minimal costs.
Advantages:
• Grease would not enter the river thus reducing the number of spills that have to be
reported to the various concerned agencies. .
• Oil / water separators are available that do not require electric power.
Disadvantages:
• Increases costs and maintenance.
Potential Risks:
None noted.
Cost Impacts:
This is an increase to the scope of work and will add minimal costs.
MECHANICAL MOIST
EQUIPMENT
MACHINERY
PLATFORM
DRAIN
OIL WATER
SEPARATOR
Mechanical seals would be installed after installation of new composite bushing. The bushing
length would be reduced to allow room for the seals. Epoxy could be used to hold the seals in
place. Relief port would be installed in a tapped port on the pier end of the trunnion pin to
accept spring loaded grease relief fitting. The opposite end of the pin would have the grease fill
port. The grease line/tubing would be extended to reach the new fill port location. Grease would
fill passage in pin to passages in bushing and then out relief at end of pin. Maintenance
personnel would see grease exiting relief port and have access to collect this small amount of
grease.
A potential risk or downside to this proposal is reduced ability to flush old grease from the
bushing. This proposal should be considered in conjunction with replacing existing bronze
bushings with self-lubricating composite bushings since the necessity to periodically flush old
grease out of bearing should be reduced.
Advantages:
• Eliminate excessive grease dripping into waterway.
• Clear indication to maintenance personnel that bushing has adequate grease.
• Relatively easy to install.
• Minimal modification to current baseline trunnion pins.
• Reduced long-term O&M costs for grease clean-up.
Disadvantages:
• Slight reduction in length of new bushing to leave space for seals reduces capacity.
• New mechanical seals likely custom design and manufacture due to large size.
Potential Risks:
• More difficult to flush all grease from bushing if this becomes necessary.
Cost Impacts:
This will add costs to the baseline concept.
This proposal is to add to the baseline concept those features necessary for full SCADA
operation with the exception of the communication card, which permits the connection with the
outside world. This is an opportune time for including these features. The electrical contractor
would perform the installation.
Advantages:
Easily incorporate SCADA capability in the future at a minimal cost.
Disadvantages:
Additional components during this phase or work.
Potential Risks:
None identified.
Cost Impacts:
This is an increase to the scope of work and will add minimal costs.
Advantages:
Use of a lower friction factor for instances where low friction composite materials are used in the
trunnion pin assemblies would result in more efficient designs allowing funding to be available
for other required modifications.
Disadvantages:
There are no perceived disadvantages to re-evaluation of the friction factor.
Potential Risks:
The history of the use of composite materials in trunnion bushings is limited.
Cost Impacts:
Specific cost impacts are not quantified for this recommendation. Implementation of a lower
friction factor for instances where low friction composite materials are used in the trunnion pin
assemblies would result in positive project cost impacts.
Advantages:
By doing the mechanical and electrical work ahead of the remaining construction, this reduces
(eliminates) coordination efforts between different crafts.
The mechanical and electrical work would be complete and available during the balance of the
work as required.
Disadvantages
The long lead items must be considered and the mechanical and electrical contracts must be
awarded well in advance of the scheduled construction season.
Scheduling will be critical to maintain availability of gate operation at all times. All gate outages
for this effort will need to be coordinated with operations.
Potential Risks:
Operations may require a gate that is not available.
Cost Impacts:
There are no additional costs involved with this effort.
The Team recommends that the reservoir be maintained at a higher elevation than minimum pool
to reduce the impacts to power generation and recreation. Another way of addressing this would
be to allow higher reservoir levels during certain parts of the day when peaking power is desired
and lowering the reservoir during the non-peaking events.
Critical Items to Consider:
The Design Team would need to understand the risk of relatively sudden raises in reservoir
elevation during the Jul 15 to Nov 15 timeframe and what amount of warning time is afforded in
these reservoir rises.
Advantages:
With a higher reservoir, the power revenue impacts can be reduced and more recreational
benefits realized.
Disadvantages:
The only disadvantage is the increased risk of flooding the spillway.
Potential Risks:
The risk of a river event being encountered that causes an unexpected and uncontrolled rise in
reservoir level must be addressed. If the reservoir operation during this time of year (Jul 15 to
Nov 15) were less erratic and more predictable, then this risk would be more acceptable.
Cost Impacts:
The cost impacts of a higher reservoir level would be increased power revenue.
The proposal is necessary to minimize time needed to tear down and rebuild the platform, as well
as eliminate uncertainty associated with contractor design in regards to unforeseen cost and
unsatisfactory design.
Critical Items to Consider:
The platform will need to be easily removed and placed in a manner that complies with safety
requirements. The structure will also have to withstand forces from movement/placement using
a crane system. Will need to be possible for structure to sit for extended period and then be used
at a later time.
Advantages:
• Eliminates need for USACE to approve a contractor’s design.
• Cut construction labor costs.
• Minimize construction window.
• Make construction easier.
• Platform will be used for multiple gates.
Disadvantages:
• Increase design effort in a compressed design schedule.
• Design may not meet the specific needs of the contractor.
• USACE assumes majority of risk associated with dictating what contractor must do.
Potential Risks:
If design does not meet needs of contractor safety, then the ability to perform work will be
greatly diminished and may increase cost.
APPENDIX C
Information Phase
United S tates A rm y C orps o f Engineers R estore full flood control to Lookout Point Lake
Elim inate the Interim Risk Reduction M ea su res
M inim ize flood d am a g e
Ensure a reliable and functional facility
A w ard contract in F Y 1 4
Costs less than the su b -ag re em en t with B PA
Design, construct, o perate and m aintain a safe
project
O ptim ize capital and O & M costs
Ensure no injury and loss of life
National M arine and Fisheries Service Good w a te r quality upstream and dow nstream of
Lookout Point D am for fish habitat
O regon D ep a rtm en t of Fish and W ildlife G ood w a te r quality upstream and dow nstream of
Lookout Point D am for fish habitat
United S tates Fish and W ildlife Good w a te r quality upstream and dow nstream of
Lookout Point D am for fish habitat
• Construction window
• Time to design and award the project
• Costs must be less than the sub-agreement with BPA
D esign constraints
• Meet E’s (Engineering Manuals), ERs (Engineering Regulations), Codes, Schedule, and
Operational requirements
• Project Schedule must incorporate long lead items
CENWP-VE FY14-01
COST MODEL
Optional -Skilled Craftsman Optional - Miscellaneous
Labor, $20,000, 0% materials, equipment,
Mobilization/Demobilization
Optional - Electrical Controls , $290,000, 4%
for Gate 4, $290,000, 4%
.Electrical Feeders for Gates
Optional - Mechanical for. 3 & 2, $130,000, 2%
Gate 4 - Trunnion
Pin/Bushing, $440,000, 7% Electrical Controls for Gates
3 & 2, $580,000, 9%
APPENDIX D
Function Analysis
P ro je c t R e g u la te R iv e r
Reduce F lo o d D a m a g e
U p g ra d e E q u ip m e n t
E lim in a te IR R M ’s (B a s ic )
Im p ro v e R e lia b ility (B a s ic )
R e s to re F u n ctio n
S to re W a te r
R e le a s e W a te r
Im p ro v e S a fe ty
Spend M oney
O p tim iz e C o s ts
G e n e r a te Pow er
C o n tro l W a t e r T e m p e ra tu re
R e s is t H y d ro s ta tic F o rc e s
R e s is t F o rc e s (B a s ic )
R e s is t S e is m ic F o rc e s
R e s is t G ra v ita tio n a l F o rc e s
R e s is t T o rs io n F o rc e s
R educe S tre s s
In c re a s e S tiffn e s s
M e c h a n ic a l - B e a rin g s / H u b M in im iz e Friction (B a s ic )
R educe O&M
P ro lo n g Life
R o ta te G a te
S u p p o rt G a te
M e c h a n ic a l - H o ists Lift L o ad
Suspend L o ad
S to re Rope
Lower Load
Apply Torque
Control Position
Limits Torque
Improve Safety
Improve Reliability
Indicate Position
Simplify Operation
CENWP-VE FY14-01
FAST Diagram
HOW
------>
(Methods)
Reduce
Flood Damage
Control
Temperature
A P P E N D IX E
Creativity/Brainstorming/Evaluation
3. E n c lo s e th e m e c h a n ic a l / T e a m d e te rm in e d th a t a s tru c tu re o v e r a n d 5
e le c tric a l e q u ip m e n t a ro u n d th e e le c tric a l a n d m e c h a n ic a l w o u ld
re q u ire to o m u c h m a in te n a n c e a n d w o u ld
in tro d u c e w in d lo a d in g to th e d eck.
4. P la ce s te e l on th e w e b in s te a d T e a m d e te rm in e d th is w o u ld n o t w o rk , a s it 0
o f th e fla n g e w o u ld n o t a d d re s s th e to rs io n a l fa ilu re m ode.
5. P u t in a la rg e r b e a m in s te a d o f T e a m d e te rm in e d th a t th is m o s t lik e ly w o u ld be 0
ste e l w e ld in g p la te s m o re e x p e n s iv e th a n th e b a s e lin e c o n c e p t a nd
d id n o t a d d va lu e .
6. U se tu b e s te e l to b ra c e th e s tru t T e a m d e te rm in e d th a t th is m o s t lik e ly w o u ld be 0
a rm s in s te a d o f th e p la te s m o re e x p e n s iv e th a n th e b a s e lin e c o n c e p t a nd
did n o t a d d va lu e .
7. U se c ro s s b ra c e s to b ra c e th e D e v e lo p e d a s S tru c tu ra l D e s ig n C o m m e n t 1. 1
s tru t a rm s in s te a d o f ste e l p la te s
8. Im p ro v e d ra in a g e on th e D e v e lo p e d a s S tru c tu ra l D e s ig n C o m m e n t 2. 6
s tru c tu ra l g a te s
9. T h in n e r p la te s s a n d w ic h in g th e In c o rp o ra te d in S tru c tu ra l D e s ig n C o m m e n t 3. 0
fla n g e o f th e s tru t a rm s
10. B o lt th in n e r p la te s s a n d w ic h in g D e v e lo p e d a s S tru c tu ra l D e s ig n C o m m e n t 3. 1
th e fla n g e o f th e s tru t a rm s
13. P u t m e ta l s p ik e s on g a te to R e fe r to th e P D T to c o n s id e r. 2
c o n tro l th e b ird s
15. S e a l th e g e a r b o x e s D e v e lo p e d a s M e c h a n ic a l D e s ig n C o m m e n t 2. 6
F u n c tio n - Im p r o v e F u n c t io n a lity o f th e G a te ( S t r u c t u r a l)
Idea D is p o s itio n # o f V o te s
(m a x is 7)
3. R e v is e th e g a te s to h a ve a D e v e lo p e d a s S tru c tu ra l D e sig n C o m m e n t 5. 1
c o u n te rw e ig h t
6. R e m o v e th e ta in te r g a te s a n d T e a m d e te rm in e d th a t O b e rm e y e r g a te s o f th is 1
p u t in O b e rm e y e r g a te s s iz e h a ve n o t bee n u se d a n d th e m a te ria l o f
O b e rm e y e r g a te s w o u ld p re s e n t a d d itio n a l
p ro b le m s .
7. U se a ir b la d d e rs fo r th e g a te s T e a m d e te rm in e d th a t th is is n o t an e ffe c tiv e 0
so lu tio n .
8. C o u n te r b a la n c e th e ta in te r T e a m d e te rm in e d th is w o u ld be d iffic u lt to 0
g a te s w ith w a te r d e s ig n a n d n o t as e ffe c tiv e as Id ea 3 th a t
in c o rp o ra te s a c o u n te rw e ig h t.
3. O n ly re p la c e th e tru n n io n s p in s T e a m d e te rm in e d th is d id n o t a d d re s s th e 0
a nd b e a rin g s s tru c tu ra l p ro b le m s w ith th e g ate s.
4. In c re a s e s tru c tu ra l s te e l on th e T e a m d e te rm in e d th a t th e re w e re b e tte r 2
s tru t a rm s a n d in c re a s e th e m e th o d s fo r e lim in a tin g th e n e e d o f a lo a d -
c a p a c ity o f th e h o is ts a nd lim itin g d e v ic e th a t a re in c o rp o ra te d into
m o to rs a n d e lim in a te th e load A lte rn a tiv e 5.
lim itin g d e v ic e
6. U se a d e s ig n B m o to r in s te a d o f D e v e lo p e d a s A lte rn a tiv e 3. 6
a d e s ig n D
7. R e p la c e th e h o is t s y s te m w ith T e a m d e te rm in e d th e h y d ra u lic h o is ts w o u ld 1
h y d ra u lic a c tu a to rs be v e ry large, in te rfe re w ith th e w a te r flo w a nd
p re s e n t p o te n tia l le a k s o f oil to th e river.
8. A ir b ag flo a t on th e g a te T e a m d e te rm in e d th is w a s an im p ra c tic a l 0
s o lu tio n .
9. W o rm g e a r d riv e n h o is ts T e a m d e te rm in e d th a t in -k in d re p la c e m e n t o f 0
th e e x is tin g g e a rs w a s a p re fe rre d s o lu tio n .
13. B io d e g ra d a b le oil T e a m d e te rm in e d th a t b io d e g ra d a b le o il m u s t 2
be re p o rte d a s a s p ill; th e re fo re , th e re is no
a d v a n ta g e o v e r th e b a s e lin e c o n c e p t.
14. D e v e lo p a w a y to c o n ta in th e D e v e lo p e d a s M e c h a n ic a l D e sig n C o m m e n t 4. 6
g re a s e in th e tru n n io n s
15. R e p la c e b e a rin g s / b u s h in g in T e a m d e te rm in e d th a t re fu rb is h m e n t o f th e N o t v o te d
th e m e c h a n ic a l d riv e tra in w ith e x is tin g d riv e tra in w a s a p re fe rre d s o lu tio n on; a d d e d
s e lf-lu b ric a tin g o n e s (s e e A lte rn a tiv e 2). to th e list
a fte r v o tin g
1. N e w c o m p o s ite b u s h in g T e a m d e te rm in e d th a t th is is in c o rp o ra te d in 4
th e b a s e lin e c o n c e p t.
4. R e -u s e th e pin, c le a n o u t th e T e a m d e te rm in e d th a t re p la c e m e n t w ith a 3
g re a s e /b u s h in g a n d re -g re a s e c o m p o s ite b u s h in g s y s te m w o u ld be a b e tte r
fric tio n re d u c in g s y s te m a n d re d u c e s o r
e lim in a te s g re a s e s p ills.
C onstruction Item s
4. In v e s tig a te th e w a lk e r v a lv e T e a m d e te rm in e d th is w a s b e y o n d th e s c o p e 4
is s u e s a t th e R O ’s o f th e V E S tud y.
Id e a D is p o s itio n # o f V o te s
( m a x is 7 )
M is c e lla n e o u s Ite m s
1. E lim in a te th e g a te s T e a m d e te rm in e d th a t th e g a te s a re re q u ire d 0
to re g u la te flo w s .
3. M a k e m in o r re p a irs to th e T e a m d e te rm in e d th is n o t n e e d e d a t th is point. 0
s p illw a y b rid g e
A P P E N D IX F
Presentation
PowerPoint Presentation
Lookout Point Tainter Gate
Rehabilitation VE Study Out-Brief
VE Team
Dave Stewart. Jamie Macartney, Nick Hanson. Kent
Schlundt. Joe Russell, James Schroeder. Anil Naidu,
Kristy Fortuny. Jeff Morris
6 December 2013
US Army C o rp i of E n g in eers
BUILDING STRONG,
December 2 - 6, 2013
Mechanical
-Bearing/Hub Minimize Friction
-Hoists Improve Functionality
Key Problems
Big Risks
■ Inadequate resources to address multiple
simultaneous problems in the basin
■ Compressed design schedule
■ Unforeseen conditions that can increase the
scope of work
■ Inexperienced contractor performing the work
* Floods during construction
■ Damage gate during construction
PORTLAND DISTRICT 1?
m
BUILDING STRONG,
PO R T L A N D D IS T R IC T B U ILDING STR O N G
■ 58 Ideas Generated
■ 5 Alternatives
■ 14 Design Suggestions
________
PORTLAND DISTRICT
_______________________
17
m
BUILDING STRONG,
PORTLAND DISTRICT 1«
m
BUILDING STRONG,
A lte r n a tiv e 1
- M e c h a n ic a l/E le c tr ic a l fo r AH G a te s $ 3 .3 M illio n In c re a s e
A lte r n a tiv e 2
- R e - U s e /R e fu r b is h H o is t S y s te m S 2 0 0 .0 0 0 In c re a s e ( fo r s tu d y : c o u ld
y ie ld h ig h c o n tra c t c o s t s a v in g s )
A lte r n a tiv e 3
- R e - C o a t E n tir e G a te S 2 3 5 .0 0 0 p e r g a te In c re a s e (v in y l)
S 3 2 0 ,0 0 0 p e r g a te In c re a s e (m e ta liz e d )
A lte r n a tiv e 4
- P r o c u r e m e n t o t S to p lo g s S 1 M illio n In c re a s e
A lte r n a tiv e 5
- D e s ig n B E le c tric M o to rs S 1 8 0 .0 0 0 D e c re a s e
m i
_____ _____
P ro je c t Im p r o v e m e n ts X X X X X
A d d e d S u s t a in a b ility X
S c h e d u le Im p r o v e m e n ts X X X
Q u a lit y I m p ro v e m e n ts X X X
F u n c t io n a l X X X X X
Im p r o v e m e n ts
A d v a n c e d C o n s tr u c tio n X X X
Ite m
P la n V a lid a tio n X X X X
H -JL-JI
Questions?
Thank You!
APPENDIX G
Value Engineering Team Roster
Team Member Name Company Role
J a m e s S c h ro e d e r U SACE T e a m M e m b e r / M e c h a n ic a l
E n g in e e r
K risty F o rtu n y U SACE P a rt-T im e T e a m M e m b e r /
T e c h n ic a l T e a m L e a d e r
Jo e R u sse ll, A V S T e a m M e m b e r / C o n s tru c tio n /
U SACE
C o s t E s tim a to r
A n il N a id u U SACE T e a m M e m b e r / O p e ra tio n s
D a v e S te w a rt T e tra T e c h T e a m M e m b e r / E le c tric a l
E n g in e e r
N ic k H a n so n T e a m M e m b e r / E n g in e e r-In -
USACE
T ra in in g
J a m ie M a c a rtn e y , P E T e a m M e m b e r / C o n stru c tio n ,
B u re a u o f R e c la m a tio n
C o n tra c tin g , C iv il E n g in e e r
K e n t S c h lu n d t, P E T e a m M e m b e r / M e c h a n ic a l
B u re a u o f R e c la m a tio n
E n g in e e r
J e f f M o rris, P E , C V S B u re a u o f R e c la m a tio n T e a m F a c ilita to r / C iv il E n g in e e r