Two (2) Storey Residential House Project Owner Brgy. Matobato, Calbayog City 205. 847 M
Two (2) Storey Residential House Project Owner Brgy. Matobato, Calbayog City 205. 847 M
PROGRAM OF WORK
PROJECT DESCRIPTION:
Construction of Two (2) Storey Residential Building Located at Brgy. Matobato, Calbayog City
( and to include all items as stated below )
ESTIMATED COST OF PROPOSED WORK
I EARTHWORKS m3
II REINFORCING STEEL BARS kg
III CARPENTRY WORKS m2
IV STRUCTURAL CONCRETE m3
V MASONRY WORKS m2
VI TRUSS AND ROOFING units
VII PLUMBING WORKS m2
VIII CEILING WORKS set
IX DOORS AND WINDOWS set
X ELECTRICAL WORKS ls
X1 PAINTING WORKS m2
XII TILE WORKS m2
XIII FINISHES AND ACCESSORIES set
DURATION ACTIVITY
ITEMS OF WORK
(DAYS) PRECEDES FOLLOWS
I. EARTHWORKS
A. Clearing, Grabbing & Layout
B. Excavation
C. Earthfill
V. MASONRY WORKS
R. Chb Walling
S. Mortaring and Plastering
T. Plain Cement Finish
X. ELECTRICAL WORKS
BB. Installation of Wirings
CC. Installation of Outlets
ESTIMATED QUANTITIES
I. EARTHWORKS COMPUTATION
A. Clearing
And Grabbing Area = 205. 847 m²
Total Vol. = 20 x 2 m³ = 40 m³
Wall Footing:
Total Length = 84.67 m
Total Vol. = 84.67 x 0.5 x 0.4 = 16.93 m³
Back Fill:
Footing = 1 x 1 x 0.2 x 20 = 4.0 m³
Column = 0.3 x 0.3 x (2-0.2) x 20 = 3.24 m³
Wall Footing = 84.67 x 0.4 x 0.15 = 5.08 m³
Masonry Wall = 84.67 x 0.2 x 0.35 = 5.93 m³
Total Back Fill = 18.25 m³
ESTIMATED QUANTITIES
II. REINFORCING 10mm 12mm 16mm Tie
COMPUTATION
STEEL BARS RSB RSB RSB Wire ***
(pcs) (pcs) (pcs) (kg)
D. Footing
E. Wall Footing
Reinforcement
•Wall Footing:
Longitudinal Bar( using 12 mm Ø x 6 m commercial length )
Total Length = 94 m (with 10% splicing and wastage allowance)
Req'd = 3 pcs.
Equivalent Weight:
10 mm Ø Bar = 19 pcs x 3.70 kg/pc. = 70.3 kg
12 mm Ø Bar = 47 pcs x 5.33 kg/pc. = 250.51 kg
16 mm Ø Bar = 74 pcs x 11.84 kg/pc. = 876.16 kg
Total Weight = 1116.97 kg
ESTIMATED QUANTITIES
II. REINFORCING COMPUTATION 10mm 12mm 16mm Tie
STEEL BARS RSB RSB RSB Wire *** ***
(pcs) (pcs) (pcs) (kg)
F. Column
Reinforcemen•Vertical bars: Column 1
(Foundation toReinforcing Bar: ( using 16 mm Ø x 10 m commercial length )
Ground Floor) Cut Length = 3.96 m
Req'd = 2 pcs. per column
Length of Excess = 10 - 2(3.96m) = 2.08 m
(excess per 10m C.L.)
# of bars/column = 2 ÷ 2 = 1 pcs.
Total # of bars = 20 x 1 = 20 pcs. ……… ……… ……… 20
Total # of bars = 20 pcs. of 2.08 m
(excess)
Cut Length = 8.0 m
Req'd = 4 pcs. per column
Length of Excess = 10 - 8m = 2.0m
No. of Bars = 20 x 4 = 80 pcs. ……… ……… ……… 80
Total # of bars = 80 pcs. of 2.0 m
(excess)
F. Column
Reinforcemen•Vertical bars: Column 1
(Ground Floor Reinforcing Bar: (using 16mmØ of excess bars from found.-1st flr.)
Second Floor) Cut Length = 1.96 m
Req'd = 2 pcs. per column
(Foundation to
Second Floor) ( Using No. 16 Tie Wire )
C-1 = 20 x 18 = 360 ties
ESTIMATED QUANTITIES
II. REINFORCING COMPUTATION 10mm 12mm 16mm Tie II. REINFORCING
STEEL BARS RSB RSB RSB Wire *** STEEL BARS
(pcs) (pcs) (pcs) (kg)
H. Slab on
Ground
Floor Area = 103.47 m²
Temperature Bars: ( using 12 mm Ø x 6 m commercial length )
Equivalent Weight:
12 mm Ø Bar = 205 pcs x 5.33 kg/pc. = 1092.65 kg (Second Floor to
Roof)
( Using No. 16 Tie Wire at 0.30 cm long )
H. Slab
(2nd Floor)
Floor Area = 91.724 m²
Temperature Bars: ( using 12 mm Ø x 6 m commercial length )
No. of Rebars = 91.724 m² x 2.360 pcs/m² = 216.47 pcs. , say.. 217 (Foundation t
Second Floor)
Equivalent Weigth:
12 mm Ø Bar = 217 pcs x 5.33 kg/pc. = 1153.78 kg
No
( Using No. 16 Tie Wire at 0.30 cm long )
No. of kg = 91.724 m² x 0.174 kg/m² = 15.96 kg , say.. ......... .................. 20
TWO - STOREY RESIDENTIAL HOUSE Page: 5/16 Project : TWO - STOREY
BRGY. MATOBATO, CALB. CITY Location : BRGY. MATO
ESTIMATED QUANTITIES
Equivalent Weight:
10 mm Ø Bar = 38 pcs x 3.70 kg/pc. = 140.6 kg
16 mm Ø Bar = 100 pcs x 11.84 kg/pc. = 1184 kg Req'd Plywood
Total Weigth = 1324.6 kg
Wood Frame
•Stirrups, B-1: ( using 10 mm Ø x 10.5 m commercial length )
Cut Length = 0.879 m C.W. Nails ( 8d )
Req'd = 449 pcs. C.W. Nails ( 2d )
C.W. Nails ( 2d )
TWO - STOREY RESIDENTIAL HOUSE Page: 7/16 Project : TWO - STOREY RESID
BRGY. MATOBATO, CALB. CITY Location : BRGY. MATOBATO, C
ESTIMATED QUANTITIES
= 272.29 m² ÷ 2.88 m²/pc = 94.55 pcs. , say.. ......... ......... ......... .................. 95 Gravel Req'd.=
= 40 pc x 25.06 bd.ft./pc = 1002 bd.ft. ......... ......... 1002 H. Concrete Slab Vol. =
Slab
C.W. Nails ( 8d ) = 272.29 m² x 0.08 kg/m² = 21.78 kg. Using Class C Concrete Mix
C.W. Nails ( 2d ) = 40 pcs. x 0.055 kg/pc = 2.2 kg. Cement =
23.98 kg. , say.. ......... ......... 24 Sand =
Gravel =
Gravel Fill =
= 76.0 m
K. Beams andBeams: ( with 5% wa
For vertical support using 2" x 3" lumber: Slab Vol. =
76.0 x 6.00 = 456.0 bd.ft. ( concrete Slab: ( with 10% w
For horizontal support using 2" x 2" lumber: Vol. =
76.0 x 4.70 = 357.2 bd.ft.
Total = 813.2 bd.ft. ......... ......... 813.2
Using Class A Concrete Mix
Common Wire Nails ( 4" ) = 76.0 x 0.73 = 55.5 kg , say.. ......... ......... 56 Cement =
Sand =
Gravel =
ESTIMATED QUANTITIES
ESTIMATED QUANTITIES
San IV. DOORS AND
COMPUTATION 10mm Tie 0.3x 0.2x
CHB Cem. d
RSB Wire (bags) 0.3 0.2 WINDOWS
(pcs) (m³ tiles
(pcs) (kg) tiles
)
BY DIRECT COUNTING :
(77.3 x 3) + (62.91 x 3) = 420.63 m²
(12 x 2) + (24.84 x 1) = 48.84 m² S. Doors Doors:
Net Area = 371.79 m² D-1, Wooden
D-2, Wooden
( Using 13.0 pcs of CHB per m² to give allowance for wastage ) D-3, Wooden
371.79 m² x 13 pcs/m² = 4833.27 pcs. , say..4834 D-4, Wooden
D-5, Wooden Pa
D-6, Glass
( using 10 mm Ø x 6 m commercial length ) D-7, Steel
371.79 m² x 2.13 m/m² = 791.92 m D-8, Steel
371.79 m² x 2.15 m/m² = 799.35 m D-9, PV
Total = 1591.27 m
196.85 m² x 11.11pcs/m² x 1.05 = 2296.35 pcs. , say.................... ........ ........ ....... 2297
( with 5% allowance for breakage )
ESTIMATED QUANTITIES
Equivalent Volume:
ESTIMATED QUANTITIES
ESTIMATED QUANTITIES
( 0.81m x 3.60m Ga. 26 Corr. G.I. Roofing Sheet ) W. Plumbing Work BY DIRECT COUNTING:
Materials and
( 16.55 m x 5.09 m ) Accessories
16.55 ÷ 0.70 = 24 rows Water Closet
5.09 ÷ 3.35 = 2 pcs per row Lavatory
( 13.85 m x 4.51 m ) Kitchen Sink
13.85 ÷ 0.70 = 20 rows Bath Tub
4.51 ÷ 3.35 = 1.5 pc per row Water meter
( 4.6 m x 2.9 m ) Gate valve
4.6 ÷ 0.70 = 7 rows Faucet
2.9 ÷ 3.35 = 1 pc per row Shower Head
( 10.65 m x 1.7 m )
1.7 ÷ 0.70 = 3 rows
10.65 ÷ 3.35 = 3.5 pcs. per row Sanitary pipes and fittings:
(24 x 2)+(20 x 1.5)+(7 x 1) = 85 pcs. , say.. 85 Pipes, 100mm dia x 3.0
Pipes, 75mm dia x 3.00
ESTIMATED QUANTITIES
No. of CHB =
= 4 sets
= 1 sets
= 2 sets * Cement Mortar
= 1 set Cement =
= 1 set Sand =
= 5 sets
= 8 sets
= 3 sets * Structural Concrete:
No. of Bars =
No. of Bars =
Equivalent Weigth:
10 mm Bar =
12 mm Bar =
* Tie Wire: ( Using No. 16
For CHB Wall:
No. of kg =
For Concrete Reinforcement:
No. of kg =
TWO - STOREY RESIDENTIAL HOUSE Page: 14/16 Project : TWO - STOREY RESIDEN
BRGY. MATOBATO, CALB. CITY Location : BRGY. MATOBATO, CAL
ESTIMATED QUANTITIES
Equivalent Weigth:
44 pcs x 3.70 kg/pc. = 162.80 kg
50 pcs x 5.33 kg/pc. = 266.50 kg
429.30 kg
( Using No. 16 Tie Wire at 0.30 cm long )
ESTIMATED QUANTITIES
(115 m² ÷ 2.88 m²/pc) x 1.10 = 43.92 pcs. , say.. 44 * Primer Paint: ( With Cove
( with 10% allowance for wastage)
Coverage =
44 + 43 + 7 = 94 pcs.
2" x 2" Lumber = 94 pcs x 5.33 bd.ft./pc = 501.02 bd.ft ......... 501.02
ESTIMATED QUANTITIES
COMPUTATION
842 m²
30 m² ÷ 4 L = 7.50 m²/L
40 m² ÷ 4 L = 10.0 m²/L
ITEMS Quantity & Unit Engineer Foreman Carpenter Mason Steelman Laborer Output / Day
I. EXCAVATION
A. Clearing, Grabbing, and Layout sq.m. sq.m.
B. Excavation cu.m. cu.m.
C. Earth Fill cu.m. cu.m.
N. Roof Beams
N1. Cutting & Bending of Bars kg. kg.
N2. Installation of Scaffoldings bd.ft. bd.ft.
N3. Installation of Bars kg. kg.
N4. Installation of Forms sq.m. sq.m.
O. Concreting of Roof Beams cu.m. cu.m.
Duration (days)
2/2
Project : TWO - STOREY RESIDENTIAL HOUSE
Location : BRGY. SAN POLICARPO CALB. CITY
Subjects : S - CURVE
S - CURVE
₱ 2,000,000.00
₱ 1,800,000.00
Amount
₱ 1,600,000.00
₱ 1,400,000.00
₱ 1,200,000.00
₱ 1,000,000.00
₱ 800,000.00
₱ 600,000.00
### 2 3 4 5 6 7 8 9 10 11 12 13 14 15
###### ### ₱ 17,924.00 ### ### ₱ 42,512.00 ₱ 50,708.00 ###
### ₱ 87,118.00 ₱ 106,978.00 ₱ 126,838.00 ₱ 146,698.00 ###
₱ 400,000.00
₱ 200,000.00
₱ 0.00
Days
Project : TWO - STOREY RESIDENTIAL HOUSE Page: 1/5
Location : BRGY. SAN POLICARPO CALB. CITY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
DAYS
N O. O F M A N P O W E R
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
DAYS
MANPOWER SCHEDULE (CARPENTER)
Project : TWO - STOREY RESIDENTIAL HOUSE Page: 2/5
Location : BRGY. SAN POLICARPO CALB. CITY
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
DAYS
N O. O F M A N P O W E R
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
DAYS
MANPOWER SCHEDULE (MASON)
Project : TWO - STOREY RESIDENTIAL HOUSE Page: 3/5
Location : BRGY. SAN POLICARPO CALB. CITY
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
DAYS
Project : TWO - STOREY RESIDENTIAL HOUSE Page: 4/5
Location : BRGY. SAN POLICARPO CALB. CITY
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
DAYS
Project : TWO - STOREY RESIDENTIAL HOUSE Page: 5/5
Location : BRGY. SAN POLICARPO CALB. CITY
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81
DAYS