Method Statement For Road Work
Method Statement For Road Work
Method Statement For Road Work
This version
Reviewed by:
Signature:
Date: 30/04/2019
Signature:
Date: 30/04/2019
Signature:
Page: Page 3 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Date: 30/04/2019
Authorized by:
Signature:
Date: 30/04/2019
Version History
Rev. A 02/03/2017 C
Rev. B 17/04/2017 C
Reference
No. Engineer’s Comment AE’s Reply
Page No.
compaction. (Moisture shall be checked in
random samples).
Note- 1. After ABC levelling and compaction
11 completed, surface undulation shall be Noted 12
checked using straight edge.
Error!
Note-After finishing ABC layer Priming to be
Bookmark
12 done application of MC-30/ CSS-1 Before Included
not
laying asphalt, tack coat CRS-1 to be applied
defined.
Error!
Noted. AE shall submit asphalt mix Bookmark
13 A mix design for asphalt shall be approved.
design separately. not
defined.
Error!
Mention whether the paving is done Yes. Simultaneously pave entire road Bookmark
14
simultaneously with the bridge paving area including bridge area. not
defined.
1. Extraction test shall be done for Bitumen
content in each laying and bitumen content Error!
shall be within range of 4.5-5.0% Bookmark
15 Included
2. Air void shall be within range of 3.0-5.0% not
3. Above limits need be incorporated in to the defined.
method statement.
Error!
Thickness of the lane marking and widths shall AE shall submit drawings with lane
Bookmark
16 be mentioned. Provide a drawing for all the marking details like plan view, thickness
not
lane markings with details. and width of the lines etc.
defined.
Error!
AE shall submit material approval Bookmark
17 Material approval shall be obtained.
separately. not
defined.
Error!
For the immediate reflectivity, glass beads to Bookmark
18 Included
be added. not
defined.
Material approval for thermoplastic and glass
AE shall submit material approval for
19 beads shall be obtained and date of expiry
thermoplastic and glass beads
needs be verified prior to use the same at site.
Error!
Shall get approval for sign boards. Sign boards
Bookmark
20 at entrance might need approval from Noted
not
CMC/RDA
defined.
After levelling, survey dip measurement shall
be taken and if there is significant variation in
21 Agreed 15
dip measurement it should be informed to the
engineer.
22 indicate document number Included 16
This is only acceptable for activities being
23 incomplete after cut-off time of 22.00 and Agreed 16
10.00 hours respectively.
Explanation is insufficient and submit a Traffic
24 Management Plan with all details along with Included. 21
this MS.
Page: Page 6 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Reference
No. Engineer’s Comment AE’s Reply
Page No.
Note that all substances which intend to use
AE shall submit and get approval from
for activities related to this MS should have a
25 the Engineer for all necessary CoSHH 21
CoSHH assessment and it has to be approved
assessments before start the works.
by the Engineer prior submitting this MS.
Rev. B
1 Change to “For Approval” Changed. 2
This statement is not clear. Design and build
contractor shall carry out all the necessary
2 4
works to merge the bridge with existing Justice
Akbar Road.
Please attach ITP highlighting items related to
this MST or make reference of the same (i.e
3 AEBLB-PLN-QA-0001 Section 10.3 - item
No. x.xx
No. x.xx etc...)
4
Page: Page 7 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Contents
COMMENTS REPLY SHEET .................................................................................................................................. 4
1. INTRODUCTION .............................................................................................................................................. 8
2. STANDARDS AND MANUALS ........................................................................................................................ 8
3. SCOPE OF WORK........................................................................................................................................... 8
4. PAVEMENT INVESTIGATION AND TESTING ............................................................................................... 8
5. SITE CLEARING .............................................................................................................................................. 8
6. EARTH WORK ................................................................................................................................................. 9
6.1. Backfilling to Abutment Excavation ........................................................................................................... 9
6.2. Excavation for Road Work (If Any) ............................................................................................................ 9
7. SUBGRADE CONSTRUCTION ....................................................................................................................... 9
8. SUB BASE, ABC AND SHOULDER CONSTRUCTION ................................................................................ 10
8.1. Sub Base ................................................................................................................................................. 10
8.2. Graded Aggregate Base Construction .................................................................................................... 12
8.3. Prime Coat .............................................................................................................................................. 13
8.4. Shoulder Construction ............................................................................................................................ 15
9. OTHER REQUIREMENTS ............................................................................................................................. 15
9.1. Quality Control ........................................................................................................................................ 15
9.1.1. Inspection Procedure ....................................................................................................................... 16
9.1.2. Checklists......................................................................................................................................... 17
9.2. HSE Requirements ................................................................................................................................. 21
9.2.1. Traffic Management at Site .............................................................................................................. 21
9.2.2. CoSHH Assessments ...................................................................................................................... 21
9.2.3. Risk Assessment ............................................................................................................................. 22
9.2.4. Manual Handling Operation Record ................................................................................................ 28
9.2.5. PPE Risk Assessment ..................................................................................................................... 29
9.2.6. Noise Risk Assessment Record ...................................................................................................... 30
Page: Page 8 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
1. INTRODUCTION
This method statement is intended as a guideline for Balmond Studio (The Engineer) Personnel & Access
Engineering PLC Site Staff to ensure a safe and efficient road works activities up to the prime coat of design &
construction of Beira Lake Bridge and associated works at Justice Akbar Mawatha, Colombo – 02. This should
be read in conjunction with the approved drawings relevant to road works, pavement design (AEBLB-RPT-DN-
0006) and other related designs.
3. SCOPE OF WORK
This method statement describes the procedure of pavement construction upto graded aggregate base coarse
priming which is included roadway embankment construction, sub grade & sub base construction works related
to the Beira Lake Bridge Construction Project.
Work sequence as follows,
Pavement Investigation And Testing
Roadway excavation
Subgrade construction(Embankment filling)
Sub base construction
Aggregate base coarse(graded aggregate base)
Graded aggregate base priming(Prime coat)
5. SITE CLEARING
Mobilization of resources as per the site requirement and the available site space per effective handling
of resources.
Page: Page 9 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Clear site is required in order to facilitate the setting out, level marking and for other demarcation work of
the pavement construction area as a preliminary activity.
To proceed with the bridge approach road construction, existing structures shall be demolished by the
Employer.
Other disturbance in the bridge approach road area like trees, office containers, workers rest room, etc.
shall be removed/ relocated by AE.
Cleaning of the either side of the road will be done by using Backhoe loader and Labors.
Barricade the location to be cleaned & Grubbed with warning tape, traffic cones, sign board etc.
6. EARTH WORK
The Road length will be divided as right hand side & left hand side from the Centre line of the Road (Select the
sides by looking from road side to building side). If required as per the site condition, the work will be executed in
those two sections (RHS and LHS) separately. However each and every activity shall be nominated during the
execution work by using RHS or LHS identity.
7. SUBGRADE CONSTRUCTION
The approval of subgrade material shall be obtained by the Engineer and tested to ascertain whether they confirm
to Embankment soil Type 1 or Type 2.
Setting out
After the site has been cleared the limits of the sub grade shall be set out as per the limits showing in the approved
drawings and each time make sure to established level peg, control point or any other demarcation at least 2m
beyond(2m offset point) the required point otherwise it will be disturbed due to execution works. Further those
Page: Page 10 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
setting out or level marking shall be undergone a frequent rechecking process to make sure the accuracy by site
surveyor.
The pegs or stakes showing limits of the subgrade shall be fixed at a pre-identified distance outside the actual
limits of the fill.
Moisture content of material shall be checked by and adding water if required.(Lab testing is not required,
just to make visual inspection and as per the behavior during manual handling and hand touching shall
be enough to define moisture content)
Compact the layer until achieve 98% degree of compaction from the MDD by using 8-10 ton smooth
wheel roller as determined by BS1377 Test 13 or AASHTO-180
Degree of compaction is not achieved to the required level by density test, same layer shall be scarified
upto previous layer and add water then compact it again. Field density shall be conducted again for that
layer and check the required compaction.
Requirement fulfil
Materials use for filling Compaction of Sub Grade
Watering, Compaction
& Level Checking
Not OK Ok
Page: Page 12 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Test Frequencies
Degree of Compaction
per each layer
Field Moisture Content
Watering, Compaction
& Level Checking
Finishing Operation
The Shoulder shall be finished to levels, grades, slopes and cross sections shown on the drawings. The top
surface shall be finished to the specified slope to ensure that the water from the road, drains over the shoulder
freely
9. OTHER REQUIREMENTS
9.1. Quality Control
To be read in conjunction with Quality Plan for Beira Lake Bridge construction project (AEBLB-PLN-QA-001)
Hold points and witness points shall be notified to the QA/QC Engineer according to the ITP (attached to the
Quality Management Plan - AEBLB-PLN-QA-0001). QA/QC Engineer shall inspect the site work as scheduled.
Permission of the Engineer will be obtained before proceeding beyond Hold Point.
Availability of for approved alignment drawings for bridge approach area shall be satisfied before the
commencement pavement construction. In addition to the above following documents and approvals shall be
available with contractor in order to assure the proper quality.
Material approval for Type I, II earth
Page: Page 16 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Site Engineer is the person who directly engage with the site execution work and he should have clear awareness
regarding the above mentioned items and the validity and applicability of their including.
After levelling, survey dip measurement shall be taken and if there is significant variation in dip measurement it
should be informed to the engineer.
Abstracted ITP from Quality plan shall be added.
9.1.1.Inspection Procedure
Requirements relevant to this matter have been mentioned in the quality system procedure for inspection and
testing (AEBLB-PLN-QA-0002). Further details regarding to this matter are included in quality system procedure
for field inspection and test.
In some cases, it is difficult or impossible to decide about the completion time of some activity due to the available
site condition or constraints at that time, but there are some possibility to complete or not. In this kind of situation
that particular activity may not be included in the ahead IR list that is provided in previous day. Under that
consideration the revised IR list will be provided in next day morning before 10.00hrs. This is only acceptable for
activities being incomplete after cut-off time of 22.00 and 10.00 hours respectively.
Page: Page 17 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
9.1.2. Checklists
Page: Page 18 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Page: Page 19 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Page: Page 20 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
Page: Page 21 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
9.2.2.CoSHH Assessments
To be read in conjunction with Diesel (AEBLB-HAZ-HS-0001), Petrol (AEBLB-HAZ-HS-0002), Engine oil
(AEBLBHAZ-HS-0003), and Hydraulic oil (AEBLB-HAZ-HS-0004) CoSHH assessments.
Page: Page 22 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
9.2.3.Risk Assessment
Risk Assessment criteria
Value Estimation
1 Injuries or illnesses requiring no treatment or first-aid only
2 Injuries or illnesses requiring medical treatment beyond first-aid
Severity
3 Temporary impairment, causing lost-time or job restriction
4 Permanent/prolonged impairment
5 Fatality
Value Estimation
1 Foreseeable, very low probability , might be seen once during working life
2 May have occurred in past, expects to see several incidents during working life
Probability
3 Occurred in past, expected one per year, would not be surprised by incident
Approved: (Name) Achala Kalinga (Designation) Deputy Project Manager Date: 30/04/2019
Page: Page 28 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC
YES YES
NO
All operatives involved in this task have undertaken Manual Handling Training. All
PPE required for this task will be provided and used.
Compulsory +++
Nature of Risk(s) Typical PPE Considerations
A Falls of Materials + YES
B Striking Against ++ YES
C Flying Particles + YES
D Molten Liquid N/A N/A
E Cuts and abrasions YES
F Hazardous Fumes/ Dust + YES
G Working at Height YES
H Moving Vehicles/ Plant + YES
I Noise YES
J Working over/ adjacent to water YES
K Working in Cold Weather NO
PPE Requirements
Head Eye Hearing Foot Hand/ Body Resp. Fall Life High
Arm Restraint Jacket Visibility
(buoyancy Vest
aid)
Working
When When When When Working
Mandatory Mandatory Over Mandatory
Required Required Required Required At Height
Water
Other Control Measures Implemented:
Site Safety Inspections, Revision of PPE requirement to be monitored and assessed and if required amended
85 90
200
- +
STANDARD PEAK AC TIO N L EVEL FR E Q U E NC Y BA N D
N O IS E M E T E R A B O V E 85 dB (A ) A B O V E 90 dB (A ) AB OV E 200 pa A N A L YS IS RE Q 'D
2M TEST
YE S NO Y ES NO YES NO Y ES NO Y ES NO YES NO
Type of Noise
COMBINED
CONTINUOUS IM PACT TRANSIENT SINGLE SOURCE
SOURCES
YES NO YES NO YES NO YES NO YES NO
Control Measures
ACOUSTIC LIMIT
SUBSTITUTION ENCLOSURE MAINTENANCE DISTANCING MODIFICATION SCREENING EXPOSURE TIME
Hearing Protection
CORRECT TRAINING
EARMUFFS EARPLUGS ATTENUATION LEVELS REQUIRED
YES NO YES NO YES NO YES NO
Assessment Conclusions: Noise levels and risk controlled – Works can commence
Remedial Action Required? Risks & Controls Communicated to persons at
risk?
Yes, Record
Attached
No, Not
Applicable Yes, Record
Attached No, Not
Applicable
Assessed by: J. C. Designation: HSE Officer Date: 30/04/2019
Dissanayaka
Page: Page 31 of 31
Method Statement For
Date & Version: 30 April 2019, Rev. C AEBLB-MST-CN-0006
Honeycomb Rectific
Author: Access Engineering PLC