Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Method Statement For Construction of Cofferdam: Beira Lake Bridge Construction By

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 42

Page: Page 1 of 42

Date & Version: 30 April 2019, Rev. A Method Statement Construction of


Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Project: Waterfront Integrated Project, Colombo, Sri Lanka

METHOD STATEMENT FOR


CONSTRUCTION OF COFFERDAM

Beira Lake Bridge Construction


By,
Page: Page 2 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

This version
Reviewed by:
N
a
Achala Kalinga
m
e:
R
ol Deputy Project Manager
e:
Si
gn
at
ur
e:
D
at 30/04/2019
e:

Reviewed for issue by:

Name: K.K. Pushpakumara

Role: HSE Manager

Signature:

Date: 30/04/2019

Authorized by:

Name: Chaminda Nawarathna

Role: Contractor Representative

Signature:

Date: 30/04/2019

The signed original of this page is retained by the issuing team.

Version History

Version Date Status Changes Overview


For
Rev. A 30/04/2019
Implementation
Page: Page 3 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Contents

1. INTRODUCTION .............................................................................................................................................. 4
2. SCOPE OF WORK........................................................................................................................................... 4
3. ASSUMPTIONS ............................................................................................................................................... 4
3.1. Duration ................................................................................................................................................... 4
3.2. Site Access .............................................................................................................................................. 4
4. PRELIMINARY SURVEY DETAILS ................................................................................................................. 7
5. STATUTORY APPROVALS, LICENSES AND CLEARANCES....................................................................... 7
6. FILLING MATERIAL BORROWED FROM OUTSIDE ..................................................................................... 7
7. FILLING OF 1ST STAGE................................................................................................................................... 8
7.1. Placing of Jumbo Bags ............................................................................................................................ 8
7.2. Filling of Final Phase ............................................................................................................................... 9
8. CONSTRUCTION OF TEMPORARY BRIDGE ............................................................................................. 10
8.1. Design Calculation ................................................................................................................................. 11
9. FILLING OF 2ND STAGE ................................................................................................................................ 11
10. REMOVAL & DISMANTLING OF TEMPORARY PLATFORM ................................................................. 13
11. ANNEXES.................................................................................................................................................. 15
Risk Assessment ............................................................................................................................................... 15
Manual Handling Operation Record .................................................................................................................. 23
PPE Risk Assessment ....................................................................................................................................... 24
Noise Risk Assessment Record ........................................................................................................................ 25
Lifting Operation Assessment ........................................................................................................................... 26
CoSHH Assessment – Diesel ............................................................................................................................ 26
CoSHH Assessment – Petrol ............................................................................................................................ 30
MSDS - Diesel ................................................................................................................................................... 33
MSDS – Petrol ................................................................................................................................................... 37
Page: Page 4 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

1. INTRODUCTION
John Keels Holdings has awarded a contract for design and construction of Beira Lake Bridge at Waterfront
project to Access Engineering PLC (AEP). This scope requires construction of a cofferdam at Beira Lake at the
same location of the bridge and this Method Statement only covers the construction of cofferdam.

2. SCOPE OF WORK
Access Engineering PLC pledged to undertake the following works and responsibilities in relation to the
Construction of Beira Lake Bridge of the Waterfront Integrated Resort Development in Colombo.

The construction of cofferdam consists of following tasks.


 Filling of selected part of Beira Lake using the borrowed material.
 Construction of temporary retaining solution with jumbo sand bags.
 Preparation of platform surface with Aggregate Base Course (ABC).
 Fabrication & installation of temporary bridge
 Removal of all filled material and dump in approved land located outside Colombo city limit.

Cofferdams

Temporary
Bridge

3. ASSUMPTIONS
3.1. Duration
 The time frame planned for construction of The Cofferdam is 2 Months.

3.2. Site Access


 When access to site is required to come through the Waterfront Project a minimum of 1 weeks’ notice
shall be given to the Engineer to enable coordination with the Waterfront project Contractor.
 Temporary office shall be maintained by Access Engineering in an agreed and approved area via the
Employer.
Page: Page 5 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Project: Waterfront Integrated Project


Ref No: Date: 30/04/2019
Package: Bridge Construction
To be read in conjunction with Risk Assessment No. RA AEBLB/RA/002
To be read in conjunction with Manual Handling Assessment No. MHA AEBLB/MHA/002
To be read in conjunction with PPE Risk Assessment No. PPE AEBLB/PPE/002
To be read in conjunction with Noise Risk Assessment No. NRA AEBLB/NRA/002
AEBLB/CoSHH/002a
To be read in conjunction with CoSHH Assessments No. COSHH
– 002b
Activity: Construction of Cofferdam and Temporary Working Platform
Location: Between Waterfront Building Site and Justice Akbar Road
Times: 0600H to 1800H Duration: - 2 Months
Labour Required:
Site Engineer
Technical Officer
Supervisors
Machine Operators
General Operatives As Required
Labourers
EQUIPMENT
Tools/Plant Required: Personal Protective Equipment:
Various Survey Equipment Safety Helmet
Compulsory
Mobile Crane Including chin strap
Long Reach Excavators Hi Visual Vest Compulsory
Dump Trucks
Barge platform Safety Boots Compulsory
Concrete Truck mixers Gloves Used when required
Skid loaders
Eye Protection Used when required
Compulsory for work over Beira
Life Jacket
Lake
YES - when noise is 83db or
Hearing Protection
over
Safety Harnesses YES - Fall Restraint Only
Project hierarchy for Health and Safety Persons Responsible for First Aid
Tel: 077 532
Deputy Project Manager Mr. Achala
2295
Tel: 076 837
HSE Manager Mr. Pushpakumara
4614 Name: Ayon Senanayaka
Tel: 077 381 Contact No: 077 344 4915
Technical Officer Mr. Liyanage
5823
Tel: 077 344
Supervisor Mr. Ayon
4915
Issue of Safety Training Documentation:
All records relevant to this task i.e. tool box talks attendance record will be held in Access Site office for
review and audit.

Emergency Arrangements:
Access Engineering Qualified First Aider – First Aid Kits Site Office & Stores.
Comply with Access Engineering Fire Safety, Fire Prevention and Evacuation Plans / Procedures
Designated vehicle to be used for emergencies shall be available at all times :- Sudesh : 077 2321239
If necessary, for further investigations / treatments injured person shall be transfer to the nearest hospital
Access & Egress:
Site: Pedestrian and site walkways controlled by Access Engineering.
Access Lighting (safety lighting):
Access lighting (safety lighting) is to be provided and controlled by Access Engineering, all access routes will
be assessed for lighting prior to carrying out works.
Page: Page 6 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Task Lighting:
All task lighting will be supplied and maintained by Access Engineering
Hazardous Materials and Substances:
Concrete, Diesel, Hydraulic fluid, Bentonite, Petrol, Paint, Thinners, Jumbo Bags
Waste Management:
Site: Waste materials will be placed in skips, bins provided by Access.
Access will manage and control the disposal of all waste products/ material accordingly
Materials / Debris / Soil being removed from site shall be transported to an approved landfill site
Special Control Measures:
Adverse weather conditions:
All crane operations shall cease. Works from mobile platforms to cease
Rain fall, Dewatering of site and excavations shall be carried out where and when required
Life Vests will be worn at all times when working over water
All operatives will have undergone Access Engineering and other required inductions necessary to work in
this area.
All Operatives shall receive a daily briefing of works to be carried out that day.
All operatives to receive Tool Box talks Weekly with additional when required.
Complete physical exclusion zones with warning signage displayed will be in place prior to works
commencing and will be maintained by Access Engineering
Only trained (experienced) operatives will move or operate plant.
Work Permit/s required / Assessed:

 BARGE AUTHORISATION 
 LIFTING PLAN

 UTILITIES DRAWING 

Welfare Facilities:
All Welfare facilities i.e. toilets, changing rooms and resting/ eating areas will be provided and controlled by
Access Engineering.
Smoking: Designated areas only.
Typical examples of materials listed below:
Borrowed Soil
Jumbo bags
Steel beams
Steel plates
Various nuts and bolts
Emergency Measures:
 Exclusion Zone:
Access Engineering have assessed that for all operations there will be an exclusion zone constructed
with warning signs displayed around the working Area.
Page: Page 7 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

4. PRELIMINARY SURVEY DETAILS

 Max water level – +1.8m MSL


 Min water level – +1.3m MSL
 Lake Bottom – (-0.3m) MSL
 Average depth – 2.2m
 Average filling height – 2.1m
 Soil filling volume – Approx. 2250m3

5. STATUTORY APPROVALS, LICENSES AND CLEARANCES


Obtaining statutory approvals for traffic management plans, etc. shall be carried out by Access Engineering.

6. FILLING MATERIAL BORROWED FROM OUTSIDE


 Contractor shall deploy at least 2 Nos. of Excavators (20 ton) or any other combination of machinery and
capacity to fulfil the demand of soil at the rate of 250 m 3/day.
 For the purpose of filling of jumbo bags, an imported soil material shall be used such that the jumbo bags
perform efficiently to cut off the water seepage and prevent erosion. Such soil imported shall be used in
a dry state.
 Dump trucks shall be provided by Access Engineering to transport borrow soil at the required rate
mentioned above.
Page: Page 8 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

7. FILLING OF 1ST STAGE

The Access Engineering shall deploy an adequate number of dump trucks (3 cubes) to transport excavated
material to area where filling works to be carried out.
Once the adequate quantity of excavated material is delivered, the D4 capacity Dozer shall be used to push it
gradually in to the lake until the fill is completed 0.5m above the water level so that the newly formed ground shall
be used to unload the rest of material and spread away by Dozer as shown in below. The same step shall be
continued throughout the filling area as indicated.

Unloaded Material

0.5m
Water Level
(MSL)
Newly Formed Fill

Bed Level

7.1. Placing of Jumbo Bags


Once the 1st phase of filling work is completed, the transportation of embankment material which is suitable for
preparation of jumbo bags shall be commenced. This imported material shall be stocked on newly formed ground
in close proximity to the outer boundary of filling area. A 12T excavator shall be used to fill the jumbo bags. While
the preparation of jumbo bags is in progress, a second 20 ton Excavator (Long reach) shall be deployed to place
the filled Jumbo bags in the lake along the boundary as shown in following figure. Care should be taken to keep
Excavator in safe distance from the edge of the fill and as a precaution marker tape will be placed the required
Page: Page 9 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

distance (approximately 1.5 Meters) from the edge this shall ensure the Excavator is always on compacted ground
to withstand the weight of machine. The Placing of Jumbo bags shall be commenced from one corner of the
platform and continued until the outer edge of the Cofferdam is complete.

20 ton Excavator

Water Level

Newly Formed Fill

Max. Allowable Limit

7.2. Filling of Final Phase


Before fill the space between retaining wall and the newly formed fill geotextile will lay on land side of the retaining
wall. This geotextile will ensure that soil will not mix to the water stream.

Geotextile

Water Level

Newly Formed Fill

Filling the space between retaining wall and the slope of the fill shall be carried out in the same way as described
above ensuring machinery movement does not dislocate the jumbo bags which are already in place.
Page: Page 10 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

ABC (200mm)

500 mm
Water Level

3000mm
To be filled with Excavated
material

Lake Bed

Jumbo Bags (1m x 1m x 1m)

8. CONSTRUCTION OF TEMPORARY BRIDGE

Temporary
bridge

Construct the temporary platform is the second step of cofferdam construction. The platform shall be constructed
to approximately 1m above the highest water level generally expected during the major part of the year. The levels
would be established with reference to historical data obtained from relevant authorities, the residence of the area
& other sources available. Finally the top level of working platforms will be decided by considering both high flood
level and the safe and efficient movements of the heavy machinery (E.g.: Dump trucks, Concrete Truck mixers,
etc.)
Page: Page 11 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

The edges of the platforms shall be retained by Jumbo size soil filled bags, sand bags & rubble pitching as
appropriate. Further the exact method of retaining will be chosen taking into consideration the design
requirements, space requirement, expected weather conditions and the depth of water.
The surface of the platforms will be maintained in safe and clean conditions throughout the construction period.
For additional safety requirements traffic on the temporary platform shall be controlled by Access Engineering. In
this case only one vehicle allow to enter the temporary bridge at a time.
This temporary bridge constructed using H irons and MS Plates for allowing water flow.

8.1. Design Calculation


This should be include

9. FILLING OF 2ND STAGE

Long arm
Excavator
Page: Page 12 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

 Jumbo bags are placed near the end of temporary platform by using long arm 20T excavator.
 Geotextile lays on the retaining wall of building side of the waterfront project.
 In this step soil will bring through temporary platform and dump on to the geotextile.
 Only one vehicle is allowed to travel through the temporary platform at a time for safety purpose.
 This procedure shall be continued until completion of the stage 2.

This activity shall commenced after construction of platforms which are necessary for execution of piling and other
activities. There would be two pilling platforms approximately commencing from both lake banks (Building 1 side
and Justice Akbar Mawatha end) and these will extend at least 2.5 m beyond the edge of the outermost component
in the structure concerned.

There is a narrow point in Beira Lake just above the bridge and it is around 12m in width. So a flow area equal to
that narrow point shall be provided through temporary constructed bridge using H irons and MS plates an shown
below.
Page: Page 13 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Jumbo bags filled with soil Deck with steel plates and steel “I” girders

Steel “H” columns driven in to lake bed

10. REMOVAL & DISMANTLING OF TEMPORARY PLATFORM


 Stock piling of dredged material, soil and debris shall be carried out to drain and dewater the material
before transporting.
 Dried material shall be transported to accepted landfills or dump areas designated by authorities
 Maintenance, removal and dismantling work of temporary platform remains limited and confined to the
extent of the temporary platform constructed by the contractor.
 Stock piling of dredged material, soil and debris shall be carried out on a portion of the platform remaining
and the final stock pile shall be deposited on an area designated by the contractor before transporting to
an accepted landfill or dump area.
 Drained water shall be diverted back to the lake in accordance with Sri Lankan Environmental procedures/
recommendations.
Page: Page 14 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Conclusion:
This Method Statement and Risk Assessment is provided to ensure that works to be carried out have been
thoroughly assessed and that every step has been taken for the work to be completed in the safest way
possible.
Attachments:
Add list of any documents attached
Assessor: Name of Assessor Print & Sign Date: 30/04/2019
Approved: Achala Kalinga Date: 30/04/2019
Review:
All reviewing or changes to this document will be made by Access Engineering PLC Site Engineer when
required or if the circumstances change.
Page: Page 15 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

11. ANNEXES
Risk Assessment
Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
Personnel falling from the Injured to
edge of the embankment 1. Barricade to be provided near the lake
person or 2 5 10 Medium 1 2 2 Low
while moving or working 2. Wearing life jacket
drown
near the lake
Electrical
shock, Burns,
Electrical equipment & All electrical equipment to be removed and/or stored
Fire, Cuts /
sockets (Using poorly appropriately at the end of each working day. Cable
Working in land side abrasions,
01 maintained equipment, 4 5 20 High covers to be used. Ensure good housekeeping is 2 5 10 Medium
near the lake muscular
Power leads present a maintained. Safe route to workplace has been agreed.
skeletal and
tripping hazard) Regular check the cable condition.
other physical
injuries
1. Provide safety training before working
Equipment falling to the impact to the
2. Areas must be barricaded
lake due to unsafe person near 2 3 6 Medium 1 2 2 Low
3. Follow approved method statement procedures
operation by
4. Signalman must be present to supervision
Working in uneven floors, 1. Check up the ground or platform conditions if even
rough ground lifting Slips and falls 3 4 12 Medium 2 2 4 Low
slippery or not
overloads
02 Manual Handling 1. Conducting awareness programs for manual
Lifting without proper Injured to
handling
system, Fall without backbone, 3 4 12 Medium 1 3 3 Low
2. Daily conducting toolbox talk
balance Severe injury
3. Proper supervision
Page: Page 16 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
Appropriate measures must be taken to ensure
twisting, sufficient lighting in all situations. Provision of a safe,
stooping or suitable lighting solution must be made, be it by
Poor Visibility 3 5 15 High 2 5 10 Medium
stretching, movement of the machine to a more suitable working
back injury area, or by the supply of additional lighting
equipment.
All new starters and visitors must adhere to on site
Young people - lack of safety rules and regulations and obtain an induction.
twisting,
experience, being unaware Apprentices, other young people, non-Finning
stooping or
of existing or potential 3 5 15 High personnel and visitors are instructed not to touch or 2 5 10 Medium
stretching,
risks and/or use any item of tooling, apparatus or equipment
back injury
lack of maturity unless trained to do so, competent and /or suitably
supervised. PPE suitable for the task must be worn.
damage to the
1. Use experience driver and operators
property /
lack of experience for 2. Follow up approved lifting plan
people who 2 5 10 Medium 1 4 4 Low
operator 3. Evacuate on lookers
are in the
4. Demarcate the working area
vicinity
1. Spray water to control dust generation
Asthma 3 2 6 Medium 1 2 2 Low
Exposure to dust 2. all workers use dust marks
Skin irritation 3 3 9 Medium 1. Use long sleeve cloths 1 2 2 Low
Pricking nails/ irons Minor injuries 1 3 3 Low 1. Wearing proper PPE (Safety shoe etc.) 1 1 1 Low
Site clearing &
03 1. Clear even access to be maintained in working area.
Grabbing
Back pain and 2. Ensure rubbish, debris and materials stored
muscle pain,
Slips, Trips and Falls 2 3 6 Medium correctly. 1 3 3 Low
Minor injury or
first aid case 3. Provide appropriate access/ egress points.
4. Adequate edge protection around the area.
Page: Page 17 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
Impact with moving
Minor Injury 2 4 8 Medium 1. Prepare safe work environment 1 3 3 Low
vehicles
1. Adequate quantity will be carried with jerry cans
1. Splash to
2. Close with proper lid
Fuel Spills eye 2 3 6 Medium 1 3 3 Low
3. Advise not to fill up to maximum level
2. Skin irritant
4. proper supervision
1. Minor
04 Diesel Storage 1. Keep floor clear and free from slippery
Slip and fall injuries 2 2 4 Low 1 3 3 Low
2. Regular supervision & clean all spillage immediately
2. Bruise
1. Deep Burns 1. Install fire Extinguisher
Expose to fire 2. major 2 4 8 Medium 2. Demarcate storage area no naked flame and no 1 4 4 Low
injuries smoking area
Moderate eye
irritant/ Skin 1. Wearing of complete overall
Contact with lubricants Irritant/ 5 2 10 Medium 2. Supervision 2 2 4 Low
respiratory 3. Proper PPE
irritation
Machinery
Deeps cuts or
05 breakdown and Contact with sharp edges 2 4 8 Medium 1. Provide gloves and Boots 1 4 4 Low
wounds
repair
Temporary
1. Taking of frequent breaks
Static Postures discomfort or 3 3 9 Medium 2 3 6 Low
2. Give awareness on ergonomic exercises
pain
Stuck against machinery 1. Employee competent workers
Minor bruises 2 3 6 Medium 1 3 3 Low
parts 2. Supervision
Page: Page 18 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
1, Assign competent operator & signal man
Excavator overturn Fatal 1 5 5 Low 2, Proper instructions & Supervisions 1 3 3 Low
3. Proper maintenance
06 Excavator operation 1. Provide proper PPE
2.keep good housekeeping
Hit by moving object major Injuries 2 5 10 Medium 1 3 3 Low
3. Allow to only operation people
4. Demarcate operation area
1. Provide PPE
Cutting injury minor injury 3 3 9 Medium 2 2 4 Low
2. Awareness program will be conducted
Crushing/
1. Good Supervision
Hit by moving object cutting 2 3 6 Medium 1 3 3 Low
2. Arrange safe work environment
Injuries
07 Sign Board Fixing 1. Supervision
vascular /
Manual Handling 4 2 8 Medium 2. Competence person use for the tasks 2 2 4 Low
nerve damage
3. Giving awareness
1. Frequently change the postures
Neck/ body
Awkward posture 4 2 8 Medium 2. Giving awareness 2 2 4 Low
pains
3. Take regular intervals
1. Conducting regular workplace inspections that
include housekeeping.
2. Regular cleaning program both during, before and
Poor housekeeping Minor / Major after shifts.
08 Housekeeping 2 3 6 Medium 1 3 3 Low
practices Injuries 3. Workplace procedures for cleaning up spills and
other emergency.
4. Keeping work areas well maintained, clean, well lit,
uncluttered and free of waste.
Page: Page 19 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
1. Worker skill & ability checked. Motivated and
Un-skilled or inexperienced provide necessary trainings.
3 3 9 Medium 2 3 6 Medium
employees on work 2. Proper rest provided.
3. Briefing & supervision ensured.
1. Tasks are not allocated to staff with known health
issues and to further injury.
Frequent or prolonged 2. Make them less able to lift and carry.
3 4 12 Medium 1 4 4 Low
physical effort. 3. Adequate rest breaks taken.
4. Handling activities are distributed throughout a
team – job sharing and rotation.
If possible loads are broken down into smaller, more
Loads - Heavy bulky or manageable weights and sizes where possible.
(difficulty to move)
unwieldy. Difficult to grasp, 3 4 12 Medium Weights marked on loads where possible and if 1 4 4 Low
unstable, unpredictable unsure of weight, staff instructed to ask for assistance
with contents liable to shift. and test weight. PPE provided where appropriate –
gloves, safety boots.
Contact with overhead and hidden cables.
- Use of hand tools or battery operated tools
wherever possible.
Minor Injury or
Risk of electrocution. 3 5 15 High - All portable equipment must be PAT tested every 2 5 10 Medium
Serious Injury
09 Work in a site year.
- Regular inspections of equipment before and after
use.
Lack of personal protective Minor Injury or
2 5 10 Medium PPE may be required; the Personal Protective 1 5 5 Low
equipment (PPE). Serious Injury Equipment checklist should be completed.
Page: Page 20 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
Good housekeeping in place to ensure nothing is
stored in such a way that it will fall from height.
- Materials, tools or debris must not be thrown.
Minor Injury or - Areas where there is a risk of a falling object needs
Being hit by Falling objects 3 5 15 High 2 5 10 Medium
Serious Injury to be clearly indicated and unauthorized people need
to be kept from it.
- PPE may be required; the Personal Protective
Equipment checklist should be completed.
Ensure machine is positioned well away from site
Falling into excavations, hazards before work commences. If unavoidable,
Major/Fatal 3 5 15 High suitable protection measures must be in place, ie 2 5 10 Medium
water
barriers. PPE requirements must be assessed prior to
work commencing eg. Need for Life jackets, etc.
HSE Manager must have an up to date first aid
qualification & first aid equipment within easy reach.
Emergency Procedures /
Major/Fatal 3 5 15 High Supervisors must have a charged mobile phone and 2 5 10 Medium
Considerations
the medical & emergency contact details of all
present to be carried as standard.
Isolate machine electrics. Caution on start-up and
disconnection/ reconnection of batteries. Site may
require hot work permit.
Fire & other emergencies /
Fire risk from welding Major/ Fatal 3 5 15 Suitable tested Firefighting equipment should be on 2 5 10 Medium
High
repairs or hot work the site before work commences. Supervisor should
be observe the work. Oxy Acetylene equipment
should be in date and tested. Operators should be
trained. Screens, shields or dampening down of work
Page: Page 21 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Original Risk
Sr. Revised Risk Rating
Activity Hazard Involved Risk Rating Mitigation Action Remarks
No.
P I V R P I V R
area may be required. Cutting and welding sparks
should be contained where possible and protection
measures implemented to ensure the safety of other
people and property in close proximity. Flammable
substances should be removed from working area
before work commences.
Burn risk should be minimized by the use of correct
PPE.
Clearly defined designated access route to and from
Fire
work area. Ensure all debris is removed from
evacuation
walkways and disposed of safely. Daily inspection to
Access / egress (Blocked hindered/
be carried out by AE and sub-contractor
exit routes, Unauthorized unsafe 3 5 15 High 2 5 10 Medium
representative. Clear signage for visitors to main
access) access/
entrance / other services. Restricted access to
egress,
construction areas all staff advised during team
assault
briefing.
Page: Page 22 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Assessor: - K.K.Pushpakumara (Designation) HSE Manager Date: 30/04/2019

Approved: - Achala Kalinga (Designation) Deputy Project Manager Date: 30/04/2019


Page: Page 23 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Manual Handling Operation Record

` Mark as appropriate
ONE ACTIVITY MUST BE HIGHLIGHTED

YES YES

NO

All operatives involved in this task have undertaken Manual Handling Training. All
PPE required for this task will be provided and used.

Assessed by: K.K. Pushpakumara Signature- Date: 28/08/2016


____________________
Page: Page 24 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

PPE Risk Assessment


Assessment Number : AEBLB/PPE/002 Company: Access Engineering
Date: 30/04/2019
PLC
Activity: Construction of Cofferdam Location: Waterfront Integrated Resort perimeter line
PPE Risk Assessment
Compulsory ++
Nature of Risk(s) Typical PPE Considerations
A Falls of Materials + YES
B Striking Against ++ YES
C Flying Particles + YES
D Molten Liquid N/A N/A
E Cuts and abrasions  YES
F Hazardous Fumes/Dust + YES
G Working at Height  YES
H Moving Vehicles/Plant + YES
I Noise  YES
J Working over/adjacent to water  YES
K Working in Cold Weather  NO
L
M
PPE Requirements

Head Eye Hearing Foot Hand/Arm Body Resp. Fall Life Jacket High
Restraint (buoyancy Visibility
aid) Vest
         
MANDATORY WHEN WHEN MANDATORY WHEN WHEN WORKING AT WORKING MANDATORY
REQUIRED REQUIRED REQUIRED REQUIRED HEIGHT OVER WATER

Other Control Measures Implemented:


Site Safety Inspections, Revision of PPE requirement to be monitored and assessed and if required amended

PPE Inspection/ Maintenance Arrangements:


All PPE is to be visually inspected on a daily basis prior to commencing works.
Fall restraints to be inspected in line with manufactures recommendation and inspection registers update.
Training/Instruction Required in Safe Use of PPE
Verbal Instruction YES Written Instruction No
Tool Box Talk YES ON METHOD Specialist Training No
STATEMENT
Issued by: Achala Kalinga Approved K.K. Pushpakumara
by:
Designation: Deputy Project Manager Designation: HSE Manager
Date: 30/04/2019 Date: 30/04/2019
PPE Risk Assessment Record Ref: AEBLB/PPE/002
Page: Page 25 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Noise Risk Assessment Record

Noise Risk Assessment Record Assessment Ref: – AEBLB/NRA/002


Project: Waterfront Company: Access Location: Between Justice Akbar Mw.
Integrated Resort Engineering & Waterfront building site
PLC
Operation: Construction of Noise Source: Surrounding No‘s Up to 3 No Operatives
Cofferdam works Exposed:
Noise Measurement

85 90
200
- +
ST ANDARD PEA K A C TIO N L EVEL FR E Q U E N C Y B A N D
N O IS E M E T E R A B O V E 85 d B (A ) A B O V E 90 d B (A ) A B OV E 200 pa A N A L YS IS R E Q 'D
2M TEST
YE S NO Y ES NO Y ES NO YES NO Y ES NO YES NO


Type of Noise
    

COMBINED
CONTINUOUS IM PACT TRANSIENT SINGLE SOURCE
SOURCES
YES NO YES NO YES NO YES NO YES NO

    
Control Measures

ACOUSTIC LIMIT
SUBSTITUTION ENCLOSURE MAINTENANCE DISTANCING MODIFICATION SCREENING EXPOSURE TIME

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

      
Hearing Protection

CORRECT TRAINING
EARMUFFS EARPLUGS ATTENUATION LEVELS REQUIRED
YES NO YES NO YES NO YES NO

   
Assessment Conclusions: Noise levels and risk controlled – Works can commence
Remedial Action Required? Risks & Controls Communicated to persons at
risk?
Yes, Record Attached No, Not Yes, Record No, Not Applicable
Applicable  Attached 
Assessed by: K. K. Designation: HSE Date: 30/04/2019
Pushpakumara Manager
Page: Page 26 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Lifting Operation Assessment


Lifting plans with required details shall be submitted separately through Aconex prior commencing of any lifting
operation.

CoSHH Assessment – Diesel

HAZARDOUS SUBSTANCES
YOU NEEDS TO KNOW THIS!
WHAT IS IT?

Diesel
Ultra Low Sulphur Diesel
Refined petroleum middle distillate consisting of hydrocarbons having ~12- 16 carbon
atoms

HOW IT IS HAZARDOUS:

Symbol:
S
R values:
Health Hazards values:
Combustible Class: S2
liquid. S 16
may cause cancers R 12
Severely (03) S 23
R 38
Irritating to skin. Flammable S 24
R 45
Irritating to liquid and Hazardous to S 29
R 46
eyes. vapour . environment S 36/37
R 51/53
R 65 S 45
R 67 S 61
S 62
Flammable

WHAT IS IT USED FOR

Diesel used as fuel for burners, gas turbines and light and heavy engines.

HOW IS IT USED

Exposure by inhalation or skin contact should be minimized by the following;


• Avoid inhaling, use well-ventilated conditions. If this is not the case, seek advice from
your supervisor.
• Chemical type goggles or a face shield is recommended to prevent eye contact.
• Avoid contact with skin and clothing.
• Always keep container sealed when not in use.
• Always have a spill kit available before re-filling takes place.
• Where the possibility of splashing is possible, eye protection is to be worn.
• Common sense always to prevail when using substances.
• If ever in doubt, always stop and ask.
• Mobile fuel tanks must be 'bunded'.
Page: Page 27 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

IN CASE OF FIRE

• Use dry powder, foam, or CO2 or water fog to cool any overheating containers.
• Depending of the fire and quantity of the substances, caution is strongly advised in
attempting to extinguish fire. If risk of personal injury do not attempt to put fire and follow
site systems to go to assembly point.
• Note: Water jet must not be used.
IN AN EMERGENCY

• Inform Management immediately if you have any reaction to this substance.


• First Aid - Skin
Following contact with the product, wash thoroughly with soap and water. Remove
heavily contaminated clothing. Wash contaminated clothing before re-use. Do not use
solvents to remove. If irritating persists, obtain medical advice.
• First Aid - Eyes
Immediately flush eye thoroughly with plenty of water for a minimum of 15 minutes.
Hold eyelids apart while flushing eyes and lids. Obtain medical attention.
• First Aid - Ingestion
Ensure that breathing passages are not obstructed. Do not induce vomiting. Wash out
mouth with clean water and obtain medical attention immediately.
• First Aid - Inhalation
Remove from exposure to fresh air. Obtain medical attention. Excessive exposure may
cause patient to stop breathing. Obtain and administer immediate medical attention. Be
aware not to transfer burns from the lips (cross contamination) to the rescue giving First
Aid.

STORAGE
• Store in closed containers in a well-ventilated area away from sources of heat, ignition
and strong oxidizing agents. Keep out of direct sunlight. Stable under normal conditions.
Protect containers against static electricity, lightning and physical damage. Use
grounding cables.
• Spills - Contain and absorb using suitable absorbent. This substances is expected to
be partially or slowly biodegradable.
• Disposal - Transfer into approved containers/packaging and dispose into hazardous
waste containers on site.
ADDITIONAL INFORMATION

• Waste Classification
LoW: 13 07 01⃰ Entry type: AH
• Accidental release
Exclude sources of ignition and ventilate the area. Exclude non-essential personnel.
Collect spillages with absorbent granules and dispose in hazardous waste containers,
for large spills use breathing apparatus.
• Material of gloves
Wear suitable imperious gloves (butyl / nitrile type).
• Sensitization
Substance is believed to not be a skin sensitizer, however possibility of allergic
sensitization should be considered. Hypersensitive persons may develop assumptions
and should refrain from working with this product.
• Possible irreversible effects following prolonged and repeated skin exposure. May
enter lungs and cause damage if swallowed. May caused irritation to eyes and
respiratory tract. Hydrogen sulphide may be released when heated. Exposure to vapor /
mist may cause dizziness and drowsiness.

Ceylon Petroleum Corporation


Manufacturer /
509, Danister de Silva Mawatha
Supplier
Colombo 09
Page: Page 28 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

ECOLOGICAL / ENVIRONMENTAL / TOXICOLOGICAL INFORMATION


 Do not allow the product to reach ground water. Water bodies or sewage systems.
 Harmful effects on man and environment are unknown and are not to be expected when application
is in accordance with the instructions and the advice within the Material Safety Data Sheet.
 Has the potential to bioaccumulation, however metabolism or physical properties may reduce the bio
concentration or limit bioavailability.
Authorized by HSE Manager,
I confirmed that I have considered and understand the chemical to be used and the associated hazards. I am
satisfied that all of the hazards have been identified and that the control measures to be followed will reduce
the risks to as low a level as reasonably practicable.

Print Name: K.K. Pushpakumara Designation: HSE Manager


Date: 30/04/2019 Signature:
Declaration by Engineer,

I confirm that I have read this CoSHH Assessment and that I understand the hazards and risks involved and
will follow all of the safety procedures stated.

Print Name: Achala Kalinga Designation: Deputy Project Manager


Date: 30/04/2019 Signature:
Page: Page 29 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Declaration by Employee,
I have read and understood the safety information in regards to the hazardous substance to which this sheet
relates.
Name Signature Date
Page: Page 30 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

CoSHH Assessment – Petrol

HAZARDOUS SUBSTANCES
YOU NEEDS TO KNOW THIS!
WHAT IS IT?

Petrol
GASOLINE RON
Refined petroleum middle distillate consisting of hydrocarbons having ~4 - 11 carbon
atoms

HOW IT IS HAZARDOUS:
Symbol:
Class:
R
(03) Health Hazards values: S
Combustible Extremely values:
liquid. flammable,
may cause R45
Irritant, Carcinogenic- S2
cancers R46
Harmful, category 2. S29
R63
Dangerous for Mutagenic- S45
R65
the Category 2. Hazardous to S53
R12
environment Toxic to . environment S61
R67
Reproduction R38 S62
- category 3. R51/53
Flammable

WHAT IS IT USED FOR

Petrol used as fuel for motor car engines.

HOW IS IT USED

Keep away from heat/ sparks/ open flames/ hot surfaces. – No smoking.
Avoid breathing dust/ fume/ gas/ mist/ vapors/ spray.
Wear protective gloves/ protective clothing/ eye protection/ face protection.

IN CASE OF FIRE

Dry powder, Carbon Dioxide and foam use a smothering technique for extinguishing fire.
A forced stream of water could scatter flames of burning Petrol. Flammable vapours will
be emitted from heated liquid.
Use a water spray (cautiously) to cool fire - exposed containers to prevent violent
rupture. Water runoff to sewer may carry combustible petrol and create a fire or
explosion hazard.
Fire fighters should use self-contained breathing apparatus and protective clothing.
IN AN EMERGENCY
Page: Page 31 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Inform Management immediately if you have any reaction to this substance.


Eye Contact: Flush thoroughly with running water for 15 min. including under
eyelids.
Skin Contact: Remove contaminated clothing, wash affected area with soap and
water.
Inhalation: Remove to fresh air. If necessary apply artificial respiration.
Ingestion: Contact physician: Aspiration hazard: do not induce vomiting. If
spontaneous vomiting occurs. Hold the victim’s head lower than hips to help prevent
pulmonary aspiration.
Seek medical assistance for further treatment, observation and support after first aid.
STORAGE
• Storage - Store in closed containers in a well-ventilated area away from sources of
heat, ignition and strong oxidizing agents. Protect containers from physical damage.
Out door or detached storage preferred for large amounts. Use of non-sparking tools
and explosion proof electrical services are necessary. Ground and bond containers to
prevent static sparks. No smoking in areas of use.
Avoid prolonged or repeated skin contact and breathing of vapours or mists.
Follow good hygienic practice in the use of this material. Do not put oily rags into
pockets. Wash hands and exposed skin frequently during work day.
• Disposal - May be disposed of through controlled incineration or absorbed
material can be buried in an approved landfill. Follow CEA and local legal
regulations.
ADDITIONAL INFORMATION
• Spills - Notify safety personnel of large leaks or spills. Remove sources of heat or
ignition. Provide optimum explosion- proof ventilation. Clean up personnel need
protection against liquid contacts and vapour or mist inhalation. Contain spill and
collect liquid. Do not flush to sewer or surface water. Use absorbent material (sand)
to pick up small spills and residues promptly to reduce fire or vapour hazard. Use
non- sparking tools.

• PPE - Wear protective rubber gloves to prevent repeated or prolonged contact &
safety glasses if splashing of liquid may occur. Additional protective clothing may
be required depending on working conditions. Launder work clothes at least weekly
and when contaminated before re-use.
• Sensitization - Not expected to be a skin sensitizer.
Ceylon Petroleum Corporation
Manufacturer /
Supplier
509, Danister de Silva Mawatha
Colombo 09
ECOLOGICAL / ENVIRONMENTAL / TOXICOLOGICAL INFORMATION
 Do not allow the product to reach ground water. Water bodies or sewage systems.
 Toxic to aquatic organisms, may cause long term adverse effects in the aquatic environment
 Harmful effects on man and environment are unknown and are not to be expected when application
is in accordance with the instructions and the advice within the Material Safety Data Sheet.
 Contains components with the potential to bio accumulate.
Authorized by HSE Manager,
I confirmed that I have considered and understand the chemical to be used and the associated hazards. I am
satisfied that all of the hazards have been identified and that the control measures to be followed will reduce
the risks to as low a level as reasonably practicable.

Print Name: K.K. Pushpakumara Designation: HSE Manager


Date: 30/04/2019 Signature:
Page: Page 32 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

Declaration by Engineer,

I confirm that I have read this CoSHH Assessment and that I understand the hazards and risks involved and
will follow all of the safety procedures stated.

Print Name: Achala Kalinga Designation: Deputy Project Manager


Date: 30/04/2019 Signature:

Declaration by Employee,
I have read and understood the safety information in regards to the hazardous substance to which this sheet
relates.
Name Signature Date
Page: Page 33 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

MSDS - Diesel
Page: Page 34 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 35 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 36 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 37 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

MSDS – Petrol
Page: Page 38 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 39 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 40 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 41 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC
Page: Page 42 of 42
Date & Version: 30 April 2019, Rev. A Method Statement Construction of
Cofferdam (Temporary Working AE-MST-CN-0002
Reference: Platform)
Author: Access Engineering PLC

You might also like