Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Kevin Thompson How Agile Should Your Projects Be

Download as pdf or txt
Download as pdf or txt
You are on page 1of 17

How

 Agile  should  your  Project  be?  


A  Mathematician  Derives  the  Answer  
 
Kevin  Thompson,  Ph.D.,  PMP,  CSP  
Agile  Practice  Lead  
cPrime,  Inc.  
4100  E.  Third  Avenue,  Suite  205  
Foster  City,  CA  94404  
 
Kevin.thompson@cprime.com  
 
Abstract  
Advocates  of  agile  development  claim  that  agile  software  projects  succeed  more  often  than  classic  plan-­‐
driven  projects.  Unfortunately,  attempts  to  validate  this  claim  statistically  are  problematic,  because  
"success"  is  not  defined  consistently  across  studies.  This  paper  addresses  the  question  through  a  
mathematical  analysis  of  these  projects.  We  model  agile  and  plan-­‐driven  software  projects  with  
identical  requirements,  and  show  how  they  are  affected  by  the  same  set  of  unanticipated  problems.  We  
find  that  that  the  agile  project  provides  clear  benefits  for  return-­‐on-­‐investment  and  risk  reduction,  
compared  to  the  plan-­‐driven  project,  when  uncertainty  is  high.  When  uncertainty  is  low,  plan-­‐driven  
projects  are  more  cost-­‐effective.  Finally,  we  provide  criteria  for  choosing  effective  process  types.  
 
Contents  
1   Background...........................................................................................................................................3  
2   Common  Problems  in  Software  Projects..............................................................................................5  
3   Statistics  on  Success  Rates  for  Plan-­‐Driven  and  Agile  Projects.............................................................6  
3.1   Scott  Ambler,  2007 .......................................................................................................................6  
3.2   QSM  Associates,  2008 ..................................................................................................................6  
3.3   Conclusions  from  the  Surveys.......................................................................................................6  
4   Key  Differences  between  Agile  and  Plan-­‐Driven  Strategies .................................................................6  
5   Gedanken  Experiment ..........................................................................................................................7  
5.1   Project  Description .......................................................................................................................7  
5.2   Uncertainty ...................................................................................................................................8  
5.3   The  Plan-­‐Driven  Project ................................................................................................................9  
5.4   The  Agile  Project...........................................................................................................................9  
6   Comparison ........................................................................................................................................10  
6.1   Comparison  of  Planned  Project  Schedules .................................................................................10  
6.2   Comparison  of  Actual  Project  Schedules ....................................................................................10  
6.3   Comparison  of  Project  Results....................................................................................................10  
7   Lessons  Learned  from  the  Gedanken  Experiment..............................................................................10  
7.1   The  Financial  Impact  of  Uncertainty...........................................................................................11  

1  
 
7.2   Risk..............................................................................................................................................11  
7.3   Value  Delivery  and  ROI  versus  Time ...........................................................................................11  
8   Guidance  for  Selecting  Processes .......................................................................................................11  
8.1   Common  Processes.....................................................................................................................12  
8.2   Selection  Criteria ........................................................................................................................12  
8.3   Decision  Matrix  for  Process  Types..............................................................................................13  
9   Conclusion ..........................................................................................................................................15  
10   Appendix:  Task  Durations  for  the  Plan-­‐Driven  and  Agile  Schedules...............................................16  
 

2  
 
 

1 Background  
The  discipline  of  project  management  focuses  on  the  processes,  tools,  and  techniques  used  to  organize  
the  efforts  of  a  group  of  people  to  produce  desired  results.  The  PMBOK®  Guide,  from  the  Project  
Management  Institute  (PMI),  emphasizes  this  point  in  its  definition:  

“Project  Management  is  the  application  of  knowledge,  skills,  tools  and  techniques  
to  project  activities  to  meet  project  requirements.”1  

Up  to  the  present,  the  PMI  perspective  on  managing  projects  has  focused  primarily  on  classic  plan-­‐
driven  strategies.2  Plan-­‐driven  strategies  assume  that  the  work  of  a  project  can  be  planned  in  advance  of  
its  execution,  and  that  execution  can  be  made  to  follow  the  plan  reasonably  well.  Plan-­‐driven  projects  
emphasize  gathering  requirements  (scope),  defining  the  project’s  work  items,  dependencies,  sequence,  
and  estimated  effort  (the  Work  Breakdown  Structure),  and  executing  the  work  to  create  the  desired  
results.    
 
In  the  field  of  software  development,  plan-­‐driven  projects  frequently  use  the  Waterfall  model,3  which  
divides  the  schedule  into  explicit  phases,  as  in  Figure  1:  
 
  System  Requirements  
 
 
 
  Software  
  Requirements  
 
  Analysis  
 
 
 
Program  Design  
 
 
 
  Coding  
 
 
  Integration  
 
 
 
Testing  
 
 
 
  Operations  

3  
 
 
Figure  1  Phases  of  a  Waterfall  Process  

 
Plan-­‐driven  strategies  have  been  effective  for  projects  in  many  industries,  but  attempts  to  apply  these  
strategies  to  the  world  of  computer  software  development,  using  the  Waterfall  model,  have  been  less  
successful.  For  example,  the  Standish  Group’s  2009  survey  of  50,000  software  projects  revealed  that  
32%  of  the  projects  succeeded,  44%  of  projects  qualified  as  “challenged”  (late,  over  budget,  lacking  
functionality,  or  having  low  quality),  and  24%  failed.4    
 

 
Figure  2  Standish  Chaos  Report:  2004  –  2009.  Copyright  ©  2010  by  The  Standish  Group  International,  Inc.  

The  difficulty  of  managing  software  projects  has  long  been  noted,  and  many  alternative  strategies  have  
been  proposed.  A  major  contribution  to  this  effort  occurred  in  2001  with  the  publication  of  the  Agile  
Manifesto5,  which  emphasized  collaboration,  results,  and  adaptability  over  process,  documentation,  and  
adherence  to  plans.  While  none  of  these  concepts  was  innately  incompatible  with  plan-­‐driven  
strategies,  taken  together  they  represented  a  significant  shift  in  perspective  regarding  what  matters  
more  in  the  management  of  successful  software  projects,  and  what  matters  less.  
 
A  number  of  agile  project-­‐management  frameworks  have  arisen,  including  Scrum,  XP  (Extreme  
Programming)6,  Commitment-­‐Based  Project  Management  (CBPM)7,  Kanban8,9,  and  others.  In  many  
cases,  these  strategies  predate  the  Agile  Manifesto  (Scrum,  for  example,  debuted  in  1995),  but  have  

4  
 
been  grouped  under  the  umbrella  of  agile  development  because  of  a  common  emphasis  on  the  agile  
principles  listed  in  the  Manifesto.  
 
That  agile  projects  can  succeed  is  not  in  dispute.  Less  clear  are  the  answers  to  these  two  questions:  
 
1. Do  agile  strategies  work  better  than  plan-­‐driven  strategies,  for  software  projects?  
2. If  so,  how  do  we  characterize  projects  for  which  one  strategy  is  more  effective?  
 
This  paper  will  attempt  to  answer  these  questions.  

2 Common  Problems  in  Software  Projects  


Before  trying  to  answer  the  above  questions,  it  is  worth  reviewing  common  problems  in  software  
projects.  The  author’s  personal  experience,  and  numerous  reports,  consistently  shows  the  following  
elements:  
 
1. Creating  detailed  specifications  is  time-­‐consuming,  and  requires  substantial  effort.  
2. Creating  the  project  schedule  is  challenging  because  the  work  breakdown  structure  is  complex,  
and  the  associated  estimates  require  substantial  effort.  
3. Although  work  seems  to  progress  smoothly  at  first,  getting  an  accurate  picture  of  project  status  
is  difficult,  as  it  is  often  not  clear  whether  work  items  are  truly  complete.  
4. Various  unexpected  things  occur  throughout  the  project:  
a. Requirements  are  not  accurate  and  detailed  enough  for  implementation.  Some  have  
been  omitted,  and  some  are  incorrect.  Resolving  the  discrepancies  takes  time.  
b. Design  artifacts  that  appear  at  first  to  be  complete  are  not,  and  require  an  
unpredictable  number  of  revision  cycles  to  finalize.  
c. Development  work  proceeds  more  slowly  than  expected.  Design  issues  have  to  be  re-­‐
visited,  code  reviews  uncover  problems  that  need  to  be  fixed,  and  estimates  are  often  
unreliable  even  in  the  absence  of  these  issues.  
d. The  development  teams  are  distracted  by  the  need  to  fix  critical  production  problems.  
e. Because  the  project  will  take  many  months  to  complete,  customers  who  “missed  the  
boat”  during  the  requirements  phase  submit  change  requests  to  get  their  high-­‐priority  
features  implemented.  The  resulting  scope  changes  increase  project  duration.  
f. Integration  of  new  components  is  more  difficult,  and  takes  longer,  than  expected.  
g. Testing  turns  up  more  defects  than  can  be  fixed  in  the  allotted  time.  
h. Defect  repairs  create  unexpected  regression  errors  that  require  fixing.  
i. The  deployment  process  contains  new  elements  introduced  by  this  project.  Initial  
deployment  efforts  fail,  and  deployment  takes  more  time  than  expected.  
5. The  project  finishes  late,  over  budget,  and  with  higher  defect  rates  or  less  functionality  than  
intended.  
6. Customers  discover  that  the  new  release  doesn’t  provide  what  they  really  wanted.  
 
The  key  point  is  that  every  aspect  of  the  project  is  subject  to  substantial  uncertainty.  The  cumulative  
effects  of  uncertainty  extend  the  project  duration  well  beyond  the  planned  period,  and  waste  
development  funds  on  the  wrong  features.  

5  
 
3 Statistics  on  Success  Rates  for  Plan-­Driven  and  Agile  Projects  
Our  first  attempt  to  answer  the  questions  posed  in  this  paper  is  to  review  the  published  statistics  on  
success  rates  for  plan-­‐driven  and  agile  projects.  The  2009  Standish  Report  strongly  suggests  that  plan-­‐
driven  software  projects  have  not  been  very  successful,  but  provides  no  information  about  how  agile  
software  projects  compare.  Two  studies  that  address  the  performance  of  agile  versus  plan-­‐driven  
projects  are  described  below.  

3.1 Scott  Ambler,  2007  


Scott  Ambler’s  2007  survey10  in  Dr.  Dobb’s  Journal  provides  information  from  586  respondents.  The  
results  showed  success  rates  of  63%  for  Waterfall  projects,  and  72%  for  agile  projects.  Unfortunately,  
the  study  did  not  attempt  to  define  a  meaning  for  “success,”  so  the  results  reflect  the  respondents’  
(unknown)  definitions.  

3.2 QSM  Associates,  2008  


In  2008,  Rally  Software  commissioned  QSM  Associates  (QSMA)  to  assess  the  performance  of  agile  versus  
plan-­‐driven  projects.11  QSMA  compared  29  agile  development  projects  against  a  database  of  7500  
primarily  Waterfall  projects.  The  study  shows  that  the  agile  projects  were  37%  faster  in  delivering  
software  to  market,  and  16%  more  productive,  while  maintaining  satisfactory  defect  levels.  

3.3 Conclusions  from  the  Surveys  


The  survey  results  are  suggestive,  but  have  some  limitations:  
 
• Sample  sizes  for  agile  projects  are  much  smaller  than  for  Waterfall  projects  
• The  three  studies  (Standish,  Dr.  Dobb’s  Journal,  QSM  Associates)  measure  and  report  on  
different  characteristics  of  the  projects,  rather  than  on  a  uniform  definition  of  success  
 
The  Ambler  and  QSMA  surveys  both  indicate  better  results  for  agile  projects,  but  the  absence  of  
common  metrics  for  success  means  that  the  three  reports  are  not  directly  comparable.    
 
In  fact,  it  may  not  be  possible  to  define  success  consistently  across  plan-­‐driven  and  agile  projects,  given  
the  radically  different  ways  these  projects  operate.  “Planned  scope,  on  time”  makes  sense  for  a  plan-­‐
driven  project,  but  is  not  directly  applicable  to  agile  projects  that  freeze  schedule  and  adjust  scope.  As  a  
result,  comparisons  of  success  rates  for  the  two  styles  of  project  may  not  be  meaningful.  
 
Yet  we  would  still  like  some  guidance  as  to  whether  (and  why)  plan-­‐driven  or  agile  processes  are  more  
effective  for  software  projects,  so  we  will  develop  a  different  approach  below.  

4 Key  Differences  between  Agile  and  Plan-­Driven  Strategies  


One  challenge  to  comparing  the  effectiveness  of  agile  and  plan-­‐driven  strategies  for  software  project  
management  is  the  absence  of  a  unique  definition  for  either.  However,  the  table  below  captures  
common  distinctions  observed  in  many  projects  that  fit  into  these  categories,  with  Agile  Process  
characteristics  drawn  primarily  from  Scrum.  
 
Plan-­‐Driven  Process   Agile  Process  
Predictive   Adaptive  
Fixed  scope   Fixed  schedule  
Adjusts  schedule  to  preserve  scope   Adjustable  scope  to  preserve  schedule  

6  
 
Long  development  cycle  (e.g.,  6  months)   Short  development  cycle  (e.g.,  2—4  weeks)  
Linear   Cyclic  
Organizes  work  into  major  phases   Organizes  work  into  small  deliverables  
Delivers  value  at  project  completion   Delivers  value  incrementally  over  time  
 
The  differences  are  extensive,  and  at  first  glance,  it  isn’t  clear  which  of  the  agile  characteristics  (if  any)  
would  lead  to  improved  performance  for  software  projects.  It  is  also  possible  that  no  one  of  the  
characteristics  dominates,  and  that  a  synergistic  combination  is  responsible  for  benefits.  
 
On  further  inspection,  though,  one  can  see  that  most  of  the  characteristics  in  the  table  relate  to  the  
time  dimension,  which  suggests  an  avenue  for  exploration.    

5 Gedanken  Experiment  
 
Gedanken  Experiment,  or  “thought  experiment”  in  the  German  language,  was  a  favorite  term  of  Albert  
Einstein’s.  A  Gedanken  Experiment  is  an  experiment  performed  in  the  mind,  instead  of  the  physical  
world,  through  which  we  explore  the  implications  of  our  assumptions  or  theories.  As  the  available  
statistics  have  not  provided  clear  guidance  about  the  relative  merits  of  plan-­‐driven  and  agile  processes  
for  software  projects,  we  will  design  a  Gedanken  Experiment  to  address  these  merits  in  quantitative  
terms.  
 
Section  2  suggests  that  the  greatest  challenge  to  successful  software  projects  is  uncertainty,  which  
impacts  the  project  in  many  ways.  Thus  our  Gedanken  Experiment  will  assess  the  impact  of  uncertainty  
on  two  projects  that  are  designed  to  produce  the  same  deliverables,  using  identical  teams.  One  project  
will  follow  a  plan-­‐driven  process,  while  the  other  will  follow  an  agile  process.    
 
To  make  the  comparison  as  simple  as  possible,  we  will  focus  on  only  one  of  the  distinguishing  
characteristics  of  the  two  processes—the  length  of  the  development  cycle—and  ignore  the  others.  We  
will  then  subject  both  projects  to  the  same  set  of  unexpected  problems,  and  see  how  the  impact  of  
uncertainty  differs  between  them.  

5.1 Project  Description  


The  goal  of  each  project  is  to  create  a  data  warehouse  and  reporting  system,  with  a  set  of  five  reports,  
and  to  deploy  these  capabilities  in  a  new  data  center.  The  information  in  these  reports  is  provided  by  
existing  business  applications.  Customers  will  use  the  new  report  capabilities  to  improve  budgeting,  and  
are  willing  to  pay  for  the  reports  because  the  information  may  produce  significant  cost  savings.  
 
Analysis  of  expected  costs  and  revenues  indicate  that  the  project  should  be  cost-­‐effective  if  we  can  
begin  to  receive  revenues  after  investing  a  maximum  of  one  year’s  funding.  Thus  each  project  has  
funding  for  one  year,  and  extension  is  contingent  on  showing  revenues  by  the  end  of  the  funded  year.  
 
The  system  architecture  contains  the  following  components:  
 
 

7  
 
 
Figure  3  Data  Warehouse  and  Reporting  System  

 
1. An  OLTP  (Online  Transaction-­‐Processing)  database,  which  stores  the  business-­‐application  data  
2. A  replicated  source  database,  which  contains  a  copy  of  a  subset  of  the  OLTP  data  
3. A  Staging  database,  populated  by  ETL  processes  that  pull  data  from  the  replicated  database,  and  
transform  the  data  into  a  table  structure  optimized  for  report  generation  
4. A  Report  database,  which  is  a  copy  of  the  Staging  database,  which  is  used  only  by  the  reporting  
application  
5. A  reporting  application,  which  runs  on  a  dedicated  report  server,  and  which  displays  reports  on  
request,  using  data  from  the  Report  database  
 
The  major  pieces  of  work  to  be  done  are  as  follows:  
 
1. Build  the  production  environment  
2. Configure  production  servers  with  database  and  reporting  software  
3. Create  database  tables  in  the  various  environments,  for  the  various  stages  of  the  data  pipeline  
4. Develop  ETL  (Extract-­‐Transform-­‐Load)  processes  to  transfer  data  between  databases  in  the  
pipeline,  and  ultimately  to  the  reporting  database  
5. Develop  the  reports  
 

5.2 Uncertainty  
The  two  projects  are  subjected  to  the  same  uncertainties,  which  manifest  in  the  following  ways:  
 
• Work  estimates  are  low,  and  all  planned  work  takes  25%  more  time  than  expected.  

8  
 
• Report  #2  depends  on  a  table  in  the  OLTP  source  database  that  has  80  million  records.  The  
special  processing  required  to  deal  with  this  table  adds  3  weeks  to  the  schedule.  
• The  report-­‐software  vendor  releases  a  major  upgrade  ten  months  into  the  project.  This  upgrade  
is  required  to  fix  critical  bugs,  and  adds  3  weeks  to  the  schedule.  
• Several  source  tables  required  for  Report  #3  contain  duplicate  data.  Handling  this  problem  adds  
3  weeks  to  the  schedule.  
• Production  deployment  problems  add  3  weeks  to  the  schedule.  

5.3 The  Plan-­Driven  Project  


The  plan-­‐driven  project  contains  nine  major  phases,  as  shown  in  Figure  4.  
 

 
Figure  4  Microsoft  Project  schedule  for  plan-­‐driven  project  

The  elapsed  time  estimated  for  the  project  is  slightly  less  than  nine  months,  which  leaves  about  three  
months  of  buffer  time  in  the  funded  period.  

5.4 The  Agile  Project  


The  agile  project  does  not  contain  phases  in  the  same  sense  as  the  plan-­‐driven  project.  Instead,  it  is  
structured  to  deliver  functionality  in  increments,  one  report  at  a  time,  as  shown  in  Figure  5.  
 

 
 Figure  5  Microsoft  Project  schedule  for  agile  project  

At  the  conclusion  of  each  major  task,  a  new  report  is  available  for  use  in  the  production  environment.  
This  means  that  each  major  task  contains  testing  and  deployment  overhead,  including  regression  testing  
to  ensure  that  the  creation  of  each  new  report  has  not  broken  any  of  the  previous  reports.  Thus  the  
project  as  a  whole  contains  more  time  allocated  to  these  types  of  work  than  does  the  plan-­‐driven  
project,  which  performs  such  work  once  for  all  reports.  
 

9  
 
We  account  for  the  additional  overhead  of  the  agile  project  by  adding  more  time  for  requirements,  
testing,  and  deployment  work,  relative  to  the  plan-­‐driven  project.  The  time  increment  (at  23%)  is  
somewhat  arbitrary,  and  may  be  an  overestimate,  but  reducing  it  to,  say,  10%  does  not  materially  affect  
the  conclusions.  (See  Table  2  in  the  Appendix  for  details.)  
 
The  estimated  schedule  shows  that  Report  #1  requires  more  time  than  the  others,  because  the  work  
includes  setting  up  the  production  environment.  The  schedule  as  a  whole  requires  approximately  eleven  
months,  which  leaves  one  month  of  buffer  time  in  the  funded  period.  

6 Comparison  
In  this  section,  we  will  compare  the  two  projects,  in  terms  of  their  expected  and  actual  results.  

6.1 Comparison  of  Planned  Project  Schedules  


The  plan-­‐driven  schedule  is  the  clear  winner,  with  completion  estimated  in  two  months  less  time  than  
the  agile  schedule.  Not  only  do  the  plans  show  the  plan-­‐driven  project  completing  earlier,  but  it  has  
more  buffer  time  in  the  funded  year.  

6.2 Comparison  of  Actual  Project  Schedules  


The  addition  of  25%  more  work  time  than  estimated  expands  the  plan-­‐driven  schedule  to  11  months,  
while  the  four  3-­‐week  delays  expands  the  schedule  further  to  14  months.    
 
The  effects  of  uncertainty  on  the  agile  project  also  change  its  delivery  timeline,  as  shown  in  Table  1.    
 
Report   Expected  Time   Actual  Time   Problem  Areas  
to  Delivery   to  Delivery  
(months)   (months)  
1   3   4.5   Deployment  
2   5   7.8   Huge  table  
3   7   11.0   Duplicate  Data  
4   9   14.3   Report-­‐software  upgrade  
5   11   16.8    
Table  1  Effect  of  uncertainty  on  agile  project  schedule  

Three  of  the  reports  are  delivered  within  the  funded  year,  and  the  total  schedule  expands  to  17  months.  

6.3 Comparison  of  Project  Results  


 
The  plan-­‐driven  project  would  be  canceled,  as  it  does  not  complete  or  generate  any  revenues  by  the  end  
of  the  funded  year.  This  means  that  the  entire  investment  in  the  project  would  be  lost.  However,  the  
agile  project  would  deliver  three  working  reports  in  that  same  year,  and  thus  generate  revenues.  This  
means  that  the  project  produces  some  return  on  the  investment,  and  qualifies  as  a  candidate  for  
continuation.  

7 Lessons  Learned  from  the  Gedanken  Experiment  


Several  points  of  interest  may  be  observed  regarding  uncertainty,  risk,  and  return  on  investment  (ROI).  

10  
 
7.1 The  Financial  Impact  of  Uncertainty  
We  see  that  agile  projects  are  no  more  immune  to  delays  from  unexpected  problems  than  are  plan-­‐
driven  projects.  However,  the  way  uncertainty  impacts  the  projects  has  implications  for  ROI.  
 
When  uncertainty  is  low,  ROI  is  a  calculation:  A  project  will  take  X  months  to  complete,  cost  $Y,  and  
yield  $Z  of  revenue  over  the  following  twelve  months.  
 
When  uncertainty  is  high,  ROI  is  a  gamble:  
 
• The  project  might  not  finish  
o It  may  be  late,  and  not  complete  before  the  company  goes  out  of  business  
• Funding  might  disappear  
o Business  priorities  can  change.  The  company  may  get  out  of  the  tire  business,  and  start  
selling  rear-­‐view  mirrors.  
• Customer  interests  can  change  
o Last  year’s  best-­‐selling  Pet  Rock  is  this  year’s  gravel  
 
In  high-­‐uncertainty  environments,  risk  is  more  about  losing  the  entire  investment  than  it  is  in  having  less  
ROI  than  expected.  

7.2 Risk    
Risk  scales  with  scope  and  project  duration.  Thus  the  plan-­‐driven  project’s  all-­‐or-­‐nothing  approach  to  
delivery  risks  the  complete  loss  of  investment,  while  the  agile  project’s  focus  on  delivering  incremental  
value  as  early  as  possible  reduces  risk  by  maximizing  the  probability  of  getting  some  ROI.    

7.3 Value  Delivery  and  ROI  versus  Time  


The  agile  project’s  incremental  delivery  of  value  not  only  reduces  risk,  but  provides  superior  ROI  
compared  to  the  plan-­‐driven  project.  
 
It  is  generally  understood  that  receiving  $100  per  month  for  ten  months  is  better  than  receiving  $1000  
after  ten  months.  This  is  because  
 
1. Having  cash  now  is  more  useful  than  not  having  it  
2. The  ability  to  supply  money  might  stop  after  five  months,  and  receiving  some  is  better  than  
receiving  none  
3. The  time  value  of  money  favors  increments  over  time  (i.e.,  we  might  invest  each  increment  and  
earn  more  interest  than  we’d  get  from  the  single  large  payment).  
 
The  same  logic  applies  to  agile  projects  that  deliver  functionality  in  useful  increments  over  time,  rather  
than  deferring  delivery  of  all  functionality  to  the  end  of  a  large  project.  

8 Guidance  for  Selecting  Processes  


All  else  being  equal,  the  incremental  value  delivery  of  agile  projects  reduces  risk  and  improves  ROI  in  
high-­‐uncertainty  contexts,  relative  to  monolithic,  plan-­‐driven  projects.  Both  types  of  project  will  be  
impacted  by  uncertainty,  but  agile  projects  are  more  robust,  in  the  sense  that  they  can  deliver  value  
even  when  affected  by  a  degree  of  uncertainty  that  can  cause  plan-­‐driven  projects  to  fail.  
 

11  
 
In  practice,  “all  else”  is  seldom  equal,  and  the  incremental  deliveries  of  agile  projects  may  add  significant  
overhead  relative  to  a  plan-­‐driven  project.  The  overhead  is  worth  paying  for  high-­‐uncertainty  projects,  
because  the  agile  project  delivers  value  more  reliably.  However,  if  uncertainty  is  low,  plan-­‐driven  
projects  provide  greater  predictability  and  efficiency,  and  thus  lower  cost.  
 
This  line  of  thinking  suggests  that  we  select  processes  that  best  fit  the  characteristics  of  projects,  and  
the  following  sections  provide  guidance  for  how  to  do  so.  

8.1 Common  Processes  


We  first  consider  four  processes  that  either  define  or  are  common  representatives  of  their  categories.  
One  of  these  (the  plan-­‐driven  process)  is  classic,  while  the  others  are  commonly  considered  to  be  agile  
processes.  
 
Plan  Driven  
This  classic  category  is  described  in  Section  1,  and  includes  Waterfall  and  SDLC  processes.  
 
Scrum  
This  agile  process  plans  and  implements  work  in  short  iterations,  called  Sprints.  Each  Sprint  produces  a  
set  of  completed  and  tested  deliverables.  Scrum  is  popular  for  software  development  and  IT-­‐project  
management.  
 
CBPM  
Commitment-­‐Based  Project  Management  is  an  agile  process  whose  characteristics  are  driven  by  the  
hardware-­‐design  world  in  which  it  was  born.  CBPM  assumes  that  work  is  continuous,  because  it  cannot  
readily  be  divided  into  short  iterations.  Like  Scrum,  it  presumes  that  work  contains  enough  uncertainty  
to  render  detailed  plans  obsolete  in  short  order.  Thus  CBPM  incorporates  frequent  re-­‐planning  exercises  
every  few  weeks,  in  order  to  provide  short-­‐term  plans  of  useful  reliability.  
 
Kanban  
Kanban  is  an  agile  process  that  does  no  planning.  Instead,  it  is  a  pull-­‐oriented  process  that  focuses  on  
reacting  effectively  to  unpredictable  requests,  by  re-­‐prioritizing  them  on  a  daily  basis,  and  setting  work-­‐
in-­‐process  limits  to  minimize  the  cost  of  uncompleted  work.  
 

8.2 Selection  Criteria  


We  next  consider  the  following  four  criteria:  
 
Planning  Criticality:  The  two  values  are  Needed,  if  planning  is  needed,  and  Not  Needed,  if  it  is  not.  
 
Requirements  Reliability:  The  two  values  are  Low  and  High.  Low  means  that  requirements  are  not  well  
understood,  may  contain  significant  errors,  and  may  be  unstable  (i.e.,  change  substantially  over  the  
duration  of  the  project  schedule).  High  means  that  requirements  are  accurate,  complete,  and  stable  
over  time.  
 
Estimation  Reliability:  The  two  values  are  Low  and  High.  Low  means  that  estimates  are  not  reliable  
(factor-­‐of-­‐two  errors  are  common,  and  larger  errors  are  not  uncommon).  High  means  that  estimates  are  
reliable  (say,  usually  within  20%  of  actuals).  
 

12  
 
Cyclic  Granularity:  The  two  values  are  Yes  and  No.  Yes  means  that  a  specific  set  of  requirements  can  be  
completed  and  validated  in  short  (2—4  week)  development  cycles.  No  means  that  the  work  cannot  be  
divided  into  regular  cycles.  

8.3 Decision  Matrix  for  Process  Types  


The  table  shows  which  type  of  process  is  best  suited  for  a  project,  based  on  the  project  characteristics.1  
 
Planning   Requirements   Estimation   Cyclic   Process  
Criticality   Reliability   Reliability   Granularity  
Not  Needed   Any   Any   Any   Kanban  
Needed   Low   Low   No   CBPM  
Needed   Low   High   No   CBPM  
Needed   Low   Low   Yes   Scrum  
Needed   Low   High   Yes   Scrum  
Needed   High   Low   No   CBPM  
Needed   High   High   No   Plan-­‐driven  
Needed   High   Low   Yes   Scrum  
Needed   High   High   Yes   Plan-­‐driven  
Figure  6  Decision  Matrix  for  Process  Types  

Perhaps  surprisingly,  the  greatest  divide  is  not  between  plan-­‐driven  and  agile  processes,  but  between  
the  agile  Kanban  process  and  everything  else.  The  reason  for  this  divide  is  that  Kanban  dispenses  with  
planning  entirely,  while  the  others  assume  planning  is  necessary,  but  differ  on  how  it  is  conducted.  
 
Plan-­‐driven  processes  work  well  when  both  requirements  and  estimation  are  reliable,  which  is  
commonly  the  case  for  repetitive  work.  When  requirements,  estimation,  or  both  are  unreliable,  Scrum  
and  CBPM  are  most  appropriate,  the  choice  driven  by  whether  the  work  can  be  divided  into  iterations.  
 
The  following  flowchart  illustrates  a  common  decision  process  for  selecting  process  types.  
 

                                                                                                                         
1
 Any  means  that  the  line  is  valid  for  any  possible  value  of  the  parameter.  

13  
 
 
Figure  7  Flowchart  for  Process  Selection  

 
 

14  
 
 
Finally,  the  Adaptive  Spectrum  diagram  below  provides  a  convenient  summary  of  the  relationship  
between  process  types  and  appropriate  projects,  based  on  the  total  uncertainty  (scope  +  effort  
estimates)  inherent  in  the  work  of  the  project.  
 
Adaptive  Spectrum  
 

 
Predictive  Planning   Adaptive  Planning   Reactive  Planning  
Plan-­‐Driven   Scrum   Kanban  
Waterfall   XP    
SDLC   CBPM    
 
Figure  8  The  Adaptive  Spectrum  of  process  types  

9 Conclusion  
A  mathematical  analysis  of  the  effects  of  uncertainty  on  agile  and  plan-­‐driven  projects  shows  that  an  
agile  process  is  more  likely  to  deliver  value  when  uncertainty  is  high,  than  is  a  plan-­‐driven  process.  
However,  since  the  short  iterations  of  an  agile  process  impose  more  overhead,  relative  to  a  plan-­‐driven  
process,  the  latter  is  likely  to  cost  less  and  complete  more  quickly  for  projects  where  uncertainty  is  low.  
The  concluding  recommendation  is  to  understand  each  project’s  characteristics,  including  its  level  of  
uncertainty,  and  choose  a  process  that  is  well-­‐suited  to  its  characteristics.  

15  
 
 

10 Appendix:  Task  Durations  for  the  Plan-­Driven  and  Agile  Schedules  


 
Categories  and  Tasks   Duration  (Days)  
Plan-­‐ Agile  
Driven  
Write  specs  for  report  capabilities  
Interview  representative  users   5   10  
Write  specifications   3   5  
Get  feedback  from  users     2   5  
    Revise  specifications   2   5  
Analyze  source  schema  
Identify  relevant  tables  from  OLTP  system   15   15  
    Document  table  relationships   10   10  
Design  ETL  process  
    Develop  schema  for  report  DB   10   10  
    Design  ETL  logic  to  populate  report  DB   20   20  
Implement  ETL  process  
Replicate  subset  of  OLTP  DB  to  local  copy   5   5  
Implement  ETL  for  local  copy  to  staging   20   20  
Implement  ETL  for  staging  to  warehouse   20   20  
    Replicate  warehouse  to  report  DB   3   5  
Develop  BI  metadata  layer  
Design  metadata  layer   5   5  
    Implement  metadata  layer   3   5  
Create  reports  
Write  Report  #1   3   3  
Write  Report  #2   3   3  
Write  Report  #3   3   3  
Write  Report  #4   3   3  
    Write  Report  #5   3   3  
Test  reports  
Test  Report  #1   3   3  
Test  Report  #2   3   3  
Test  Report  #3   3   3  
Test  Report  #4   3   3  
    Test  Report  #5   3   3  
Fix  bugs  in  Reports  

16  
 
Fix  all  bugs   3   5  
Retest   3   5  
Fix  any  new  bugs   2   5  
Retest   2   5  
Fix  remaining  bugs   1   2.5  
    Verify  quality  is  acceptable   1   2.5  
Deploy  for  users  
Set  up  servers   5   5  
Install  software   5   5  
Create  databases   5   5  
Build  ETL  process   5   7  
Perform  "smoke  test"   2   6  
Fix  problems   3   7  
    Go  live   1   5  
Total  Duration   191   235  
Table  2  Task  Durations  for  the  Plan-­‐Driven  and  Agile  schedules  

 
Trademarks  
PMBOK®  is  a  registered  trademark  of  the  Project  Management  Institute.  
 
                                                                                                                         
1
 A  Guide  to  the  Project  Management  Body  of  Knowledge:  PMBOK®  Guide,  Third  Edition.  Project  Management  
Institute,  Inc.  2004.    
2
 The  PMBOK  does  not  use  the  term  “plan-­‐driven,”  but  the  latter  has  become  a  common  term  for  any  process  that  
assumes  predictability  over  time  scales  longer  than  a  few  weeks.  
3
 “Managing  the  Development  of  Large  Software  Systems,”  by  Winston  W.  Royce.  Proceedings  of  the  IEEE  
WESCON,  August,  1970.  Royce  did  not  coin  the  term  “Waterfall,”  or  recommend  the  process  to  which  this  term  
was  later  applied,  but  did  document  the  process.  
4
 CHAOS  Summary  2009,  The  Standish  Group  International.  
(http://www.standishgroup.com/newsroom/chaos_2009.php).  2009  
5
 Manifesto  for  Agile  Software  Development.  www.agilemanifesto.org,  2001.  
6 nd
 Extreme  Programming  Explained:  Embrace  Change  (2  Edition),  by  Kent  Beck  and  Cynthia  Andres.  Addison-­‐
Wesley  Professional.  2004.  
7
 No  Surprises  Project  Management:  A  Proven  Early  Warning  System  for  Staying  on  Track,  by  Timm  Esque.  
Ensemble  Management  Consulting.  December  1,  1999.  See  also  the  white  paper  by  Jose  Solera  at  
http://www.pmlead.com/.    
8
 Kanban,  by  David  J.  Anderson.  Blue  Hole  Press.  2010.  
9
 Kanban  and  Scrum—Making  the  Most  of  Both,  by  Hendrik  Kniberg  and  Mattias  Skarin.  C4Media.  2010.    
10
 Defining  Success,  by  Scott  W.  Ambler.  Dr.  Dobb’s  Journal.  (http://www.drdobbs.com/architecture-­‐and-­‐
design/202800777).  Oct  31,  2007.  
11
 The  Agile  Impact  Report:  Proven  Performance  Metrics  from  the  Agile  Enterprise.  Rally  Software  Development  
Corp.  2008.  

17  
 

You might also like