Spec Compliance Sheet
Spec Compliance Sheet
Spec Compliance Sheet
Title: Main Works LUSAIL STADIUM: MATERIAL SUBMITTAL FOR Document no.: SC-C01-CAG-HBC-MAS-SE-00063 Rev. 2
Specs Compliance
Specifications Proposed
Item (Yes/No)
PART 2 – SYSTEMS AND MATERIALS
2.1 SYSTEM DESCRIPTIONS
A RAF-101
1 Fully accessible raised access flooring system Yes
2 Core: High density particle board Yes
3 Top and bottom surface: Galvanized steel laminated to core and flush Yes
with sides
4 Structural grade: Extra heavy duty in accordance with MOB PF2 Yes
PSU/SPU or equivalent standard.
5 Support System: Yes
a. The support system shall be provided strictly in accordance with
that recommended in writing by the manufacturer of the floor panels.
b. The fixing zones indicated on the Design Drawings shall be
adhered to.
c. The works shall be supported directly onto the primary structure.
d. All steel shall be hot dip galvanised in accordance with BS EN
12825 or equivalent standard
6 Panel: Yes
a. Panel Thickness: 39mm
b. Weight: 52kg/m2
c. Panel size: 600x600mm
d. The joints between flooring panels shall be constant with fixing
details as indicated on the Shop Drawings
e. Cut-outs in panels shall be carried out at the point of
manufacturer and not on Site. All exposed ends, cuts, etc shall be
suitably finished and sealed.
f. Panels shall be protected against corrosion after fabrication and
Page 1 of 2
prior application of finishes. All exposed faces of metal, including
ends, shall be treated to avoid corrosion.
g. No panels shall have sharp edges.
h. The core of the panel shall be protected by the metal
encapsulation, steel backing.
i. All exposed faces of metal, including ends, shall be treated to
avoid corrosion.
7 Sub-floor: Concrete with concrete sealer or as indicated on the Yes
Drawings.
a. Refer to Section 033550 Concrete Finishing
8 Pedestals shall be provided to support the finished floor height above Yes
the sub-floor as indicated on the Drawings.
9 Accessories: Yes
-Cut-out panels shall incorporate electrical outlets/air supply outlets
and all services outlets as indicated on the Services Engineer’s
drawings.
-Temporary cover plates shall be included as necessary.
-Floor air supply outlets shall be in accordance with the Service
Engineer’s Drawings
-Installation and final setting out of service outlets: All installation
procedure shall be strictly in accordance with the manufacturer’s
recommendations to the satisfaction of the Service Engineer and the
Engineer.
Page 2 of 2