Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Concrete Pipe Sewerlines by Negative Air Pressure (Vacuum) Test Method (Metric)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Designation: C 1214M – 94 (Reapproved 2000)

METRIC

Standard Test Method for


Concrete Pipe Sewerlines by Negative Air Pressure
(Vacuum) Test Method [Metric]1
This standard is issued under the fixed designation C 1214M; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.

1. Scope TABLE 1 Minimum Test Time

1.1 This test method covers procedures for testing concrete Nominal Nominal
T (Time), T (Time),
Pipe Pipe
pipe sewerlines, when using the negative air pressure (vacuum) Size, mm
min/100 m
Size, mm
min/100 m
test method to demonstrate the integrity of the installed 100 0.9 525 9.7
material and the construction procedures. This test method 150 2.0 600 11.0
covers testing of 100 to 900-mm diameter circular concrete 200 3.5 675 13.0
250 4.7 750 15.0
pipe sewerlines utilizing gasketed joints. 300 6.0 825 17.0
1.2 Methods described in this test method may also be used 375 6.8 900 19.0
as a preliminary test to enable the manufacturer or installer to 450 7.7
demonstrate the condition of sewer pipe prior to delivery or
backfill. Minimum test times presented in Table 1 are for
pipelines. Holding times for testing an individual pipe may C 969 Practice for Infiltration and Exfiltration Acceptance
have to be increased to allow for the accumulation of leakage Testing of Installed Precast Concrete Pipe Sewer Lines2
when the tested pipe are incorporated into a continuous
pipeline. 3. Terminology
1.3 This test method is the metric companion to Test 3.1 Definitions—For definitions of terms relating to con-
Method C 1214. crete pipe, see Terminology C 822.
NOTE 1—The negative air pressure (vacuum) test criteria presented in
this test method are similar to those in general use. The test and criteria
4. Summary of Test Method
have been used widely and successfully in testing smaller diameter pipe. 4.1 The sewerline to be tested is plugged. Air is removed
Larger pipe may be accepted more conveniently by visual inspection and from the plugged line by a vacuum pump or vacuum reservoir.
individual joint testing. The amount of vacuum loss is used to determine the accept-
NOTE 2—It should be understood that no correlation has been found ability of the sewerline.
between loss of vacuum and water leakage.
1.4 This standard does not purport to address all of the 5. Significance and Use
safety concerns, if any, associated with its use. It is the 5.1 This is not a routine test. The values recorded are
responsibility of the user of this standard to establish appro- applicable only to the sewer being tested and at the time of
priate safety and health practices and determine the applica- testing.
bility of regulatory limitations prior to use. See Section 6 for
specific safety precautions. 6. Safety Precautions
6.1 This test may be dangerous if a line is not prepared
2. Referenced Documents properly and proper procedures are not followed.
2.1 ASTM Standards: 6.2 Access manholes or structures must be ventilated and air
C 822 Terminology Relating to Concrete Pipe and Related quality continuously monitored.
Products2 6.3 No one should be allowed in or near the manholes
C 924 Practice for Testing Concrete Pipe Sewer Lines by during testing.
Low-Pressure Air Test Method2
7. Preparation of the Sewerline
1
This test method is under the jurisdiction of ASTM Committee C13 on 7.1 Where practical, clean the line prior to testing, wet the
Concrete Pipe and is the direct responsibility of Subcommittee C13.09 on Methods pipe surface, and eliminate debris.
of Test.
Current edition approved July 15, 1994. Published September 1994. Originally NOTE 3—A wetted exterior pipe surface is desirable and will produce
published as C 1214M–92. Last previous edition C 1214M–92e1. more consistent test results. Air may pass through the walls of dry pipe.
2
Annual Book of ASTM Standards, Vol 04.05. This can be overcome by wetting the pipe. Usually, moisture absorbed

Copyright © ASTM, 100 Barr Harbor Drive, West Conshohocken, PA 19428-2959, United States.

1
C 1214M
TABLE 2 Allowable Air Loss sewerline is lowered by approximately 27.0 kPa of mercury.
Nominal Nominal Close the valve on the vacuum line and shut off the vacuum
Pipe Q, m3/min Pipe Q, m3/min pump. Allow the air pressure to stabilize.
Size, mm Size, mm
8.3 When the pressure has stabilized and is at or below the
100 0.6 525 0.15
150 0.6 600 0.17 starting test vacuum of 23.6 kPa of mercury, commence the test
200 0.6 675 0.18 by allowing the gage pressure to drop to 23.6 kPa of mercury,
250 0.7 750 0.20 at which point the time recording is initiated. Record the drop
300 0.8 825 0.21
375 0.11 900 0.23 in vacuum for the test period.
450 0.14 8.4 If the drop in vacuum is 6.8 kPa of mercury or less
during the test period, accept the line. If the drop in vacuum is
more than 6.8 kPa of mercury during the test period, inspect,
from the backfill is sufficient to cope with this situation. If the problem evaluate, and retest the line to determine the cause of excessive
persists, segmental testing of the line will establish if there is a significant vacuum loss.
leak.
8.5 Use or failure of this vacuum test shall not preclude
7.2 Plug all pipe outlets including laterals. Review safety acceptance by appropriate low-pressure air (see Practice
precautions in Section 6. C 924), water infiltration or exfiltration testing (see Practice
C 969), or other means.
8. Procedure
8.1 Determine the test time for the sewerline to be tested by 9. Vacuum Test Criteria
using Table 1. Table 1 has been established using the criteria
specified in Table 2 and the formulas contained in the Appen- 9.1 An appropriate allowable vacuum loss, Q, in cubic
dixes. The test time is the time required for the vacuum to drop metres per second has been established for each nominal pipe
from 23.6 to 16.9 kPa. size. Based on field experience, the vacuum loss Qs that have
been selected will enable detection of any significant leak.
NOTE 4—To provide satisfactory test results, the vacuum pump should Table 2 lists the Q established for each pipe size.
be capable of evacuating the sewer test section in the required test time,
9.2 When a main line with connected lateral is to be tested
or less, as determined by 8.1. The pump capacity required to accomplish
the evacuation of the line is equal to the rate necessary to reduce the sewer as a unit, the total volume of the main and laterals shall be
to the desired pressure plus the allowable vacuum loss rate: considered and the allowable air loss rate shall be that listed for
the main.
C 5 0.17D 2L/T 1 Q

where: 10. Precision and Bias


C = vacuum pump capacity, m3/s, 10.1 No justifiable statement can be made either on preci-
T = required test time, or less, sion or bias of this procedure since the test result merely states
D = pipe internal diameter, m, whether there is conformance to the criteria for success
L = length of test section, m, and specified. Due to the sealing effects of ground water and
Q = allowable vacuum loss rate, m3/s. internal flow on sewerline, the test conditions and results are
8.2 Evacuate air until the internal air pressure of the not reproducible.

APPENDIXES

(Nonmandatory Information)

X1. EQUATIONS USED IN PRACTICE C 1214M

X1.1 The required test time per 100 m for a single diameter converted to an equivalent length of required test time as
pipe using Table 2: follows:
TT 5 ~5.3 3 10 28! ~D 2L/Q! (X1.1) Le 5 (~d21/D 2! (X1.3)
TT 5 ~L 1 L e! ~T/100! (X1.4)
X1.2 The required test time for a single diameter pipe using
Table 1: X1.4 The symbols used in the equations in this test method
are defined as follows:
TT 5 ~L! ~T/100! (X1.2)
where:
X1.3 For testing a sewer system involving different diam- T = minimum test time per 100 m of pipe vacuum to drop
eter pipe, the allowable vacuum loss rate shall be that for the from 23.6 to 16.8 kPa of mercury, min,
TT = minimum test time for total system, min,
main sewer. The volume of each size of lateral pipe is

2
C 1214M

D = designated inside diameter of test section or main l = total length of each diameter lateral, m, and
sewer, mm, Q = allowable air loss rate, m3/min.
d = designated inside diameter of lateral, mm,
L = length of test section or main sewer, m,
Le = total volume of all laterals connected to the main
sewer expressed as an equivalent length of the main
sewer, m,

X2. APPLICATION OF PRACTICE C 1214M

X2.1 The following examples have been prepared to X2.3.2 Solution:


demonstrate the techniques of applying this test method. X2.3.2.1 Use Eq X1.3 to convert the total volume of
150-mm laterals to an equivalent length of main sewer:
X2.2 Example 1—A sewer system consists of 180 m of
450-mm diameter concrete pipe between manholes A and B; 10 Le 5 ( ~d21/D2!
m of 300-mm diameter pipe between manholes B and C. Le 5 ~150 2 3 275!/~4502!
X2.2.1 Find—The appropriate test times to demonstrate the Le 5 30.6 m
integrity of the installed lines.
X2.2.2 Solution: X2.3.2.2 For the connected system, use Eq X1.4 and from
X2.2.2.1 For the main sewer between manholes A and B, Table 1, T = 7.7 min/100 m for 450-mm pipe:
use Eq X1.2 and from Table 1, T = 7.7 min/100 m for 450-mm TT 5 ~L 1 Le! ~T/100!
pipe. TT 5 ~180 1 30.6! ~7.7/100!
TT 5 ~L! ~T/100! TT 5 16 min
TT 5 ~180! ~7.7/100!
TT 5 14 min X2.4 If a line fails the vacuum test, the following course of
action should be considered:
X2.2.2.2 Similarly, for the main sewer between manholes B
and C: X2.4.1 Segmentally test the line and compare the time-
TT 5 ~10! ~6/100! vacuum loss values in each segment.
TT 5 0.6 min X2.4.2 If the values in each segment are comparable, the
vacuum loss problem may be distributed throughout the line,
X2.3 Example 2—The 180 m of 450-mm diameter concrete and further analysis should be made.
pipe between manholes A and B in Example 1 has connected X2.4.3 If the values in each segment are significantly
150-mm laterals with a total length of 275 m. different, each segment may be evaluated and further analysis
X2.3.1 Find—The appropriate test time to demonstrate the be made to determine the location of any significant vacuum
integrity of the installed lines. loss.

The American Society for Testing and Materials takes no position respecting the validity of any patent rights asserted in connection
with any item mentioned in this standard. Users of this standard are expressly advised that determination of the validity of any such
patent rights, and the risk of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM Headquarters. Your comments will receive careful consideration at a meeting of the responsible
technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should make your
views known to the ASTM Committee on Standards, at the address shown below.

This standard is copyrighted by ASTM, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.
Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above address or at
610-832-9585 (phone), 610-832-9555 (fax), or service@astm.org (e-mail); or through the ASTM website (www.astm.org).

You might also like