RP 158 PDF
RP 158 PDF
RP 158 PDF
OISD – RP -158
First Edition (July, 1997)
Amended edition, August,2000
FOR RESTRICTED
CIRCULATION ONLY
RECOMMENDED PRACTICES ON
Prepared by
OISD publications are prepared for use in the oil and gas
industry under the Ministry of Petroleum and Natural Gas.
These are the property of Ministry of Petroleum and Natural
Gas and shall not be reproduced or copied or loaned or
exhibited to others without written consent from OISD.
Oil Industry in India is more than 100 years old. Over the years, a variety of
practices have been in vogue because of collaboration/ association with different
foreign companies and governments. Standardisation in design, operating and
maintenance practices was hardly in existence at a national level. This lack of
uniformity, coupled with feed back from some serious accidents that occurred in
the recent past in India and abroad, emphasised the need for the industry to
review the existing state-of-the-art in designing, operating and maintaining oil
and gas installations.
With this in view, the Ministry of Petroleum & Natural Gas in 1986 constituted a
Safety Council assisted by the Oil Industry Safety Directorate (OISD), staffed
from within the industry, in formulating and implementing a series of self
regulatory measures aimed at removing obsolescence, standardising and
upgrading the existing standards to ensure safer operations. Accordingly, OISD
constituted a number of functional committees comprising of experts nominated
from the industry to draw up standards and guidelines on various subjects.
This document will be reviewed periodically for improvements based on the new
experiences and better understanding. Suggestions from industry members may
be addressed to:
-----------------------------------------------------------------------------------------------------------------------------------
NAME ORGANISATION
---------------------------------------------------------------------------------------------------------------------------------
LEADER
MEMBERS
MEMBER-COORDINATOR
------------------------------------------------------------------------------------------------------------------------------------
(In addition to the above, several other experts from the industry contributed in the preparation, review
and finalisation of this document.)
RECOMMENDED PRACTICES ON
INDEX
------------------------------------------------------------------------------------------------------------------
S.NO. CONTENT
-----------------------------------------------------------------------------------------------------------------
1.0 INTRODUCTION
2.0 SCOPE
3.0 DEFINITIONS
4.0 PRESSURISED LPG STORAGE
4.1 APPLICABLE CODES & DESIGN PARAMETERS
4.2 LAYOUT
4.3 FOUNDATION & SUPPORTS
4.4 VESSEL ACCESSORIES
4.5 COMMISSIONING AND DECOMMISSIONING
4.6 INSPECTION & TESTING
4.7 PAINTING
4.8 INSULATION
5.0 ANCILLIARIES
5.1 PUMPS
5.2 COMPRESSORS
5.3 PIPING
5.4 VALVES
5.5 THERMAL PRESSURE RELIEF SYSTEM
5.6 FITTINGS
6.0 BULK HANDLING AND TRANSFER
6.1 BULK HANDLING FOR MOVEMENT BY ROAD
6.2 BULK HANDLING FOR MOVEMENT BY RAIL
6.3 BULK HANDLING FOR MOVEMENT BY SEA
7.0 SAMPLING AND DRAINING
7.1 SAMPLING
7.2 DRAINING
8.0 ODORISATION
8.1 SAFETY RELATED PROPERTIES OF
ETHYL MERCEPTAN
8.2 HANDLING OF ETHYL MERCAPTAN
8.3 EQUIPMENT FOR ETHYL MERCAPTAN SERVICE
------------------------------------------------------------------------------------------------------------------
S.NO. CONTENT
-----------------------------------------------------------------------------------------------------------------
8.4 DISPOSAL
9.0 ELECTRICAL AND INSTRUMENTATION
9.1 ELECTRICAL
9.2 INSTRUMENTATION
10.0 SAFETY AND FIRE PROTECTION
10.1 SAFETY
10.2 FIRE PROTECTION
11.0 REFERENCES
---------------------------------------------------------------------------------------------------------------------
ANNEXURES
TABLE
Liquefied Petroleum Gas, otherwise Pressure vessel (both static and mobile)
known as LP Gas or simply LPG, is means any closed metal container or
obtained by refining crude oil in tank of any shape, intended for storage
petroleum refineries and fractionating of LPG which is subjected to internal
natural gas available from oil and gas pressure and having water capacity of
fields. The product conforms to the more than one thousand litres.
requirements of IS : 4576 - 1978.
(a) Bullet
There has been a tremendous growth in
the use of LPG as domestic fuel as well A cylindrical pressure vessel with
as in industries. This rapid growth in hemispherical or dished ends, laid
demand of LPG has led to a substantial horizontally.
increase in the requirement of bulk
storage and handling facilities. Because (b) Horton Sphere
of its flammability and explosive nature,
LPG is a hazardous substance (Refer A spherical pressure vessel, supported
Table-I for safety related properties of vertically.
LPG ). The purpose of this standard is to
recognise the potential hazards of LPG (iii) Water Capacity
and recommend guidelines on safety
procedures and practices to be followed Maximum volume of water a vessel
in its storage and handling. will hold at 15 degree C.
This document covers operation of Filling density means the ratio of weight
equipment and facilities connected with of liquefiable gas allowed in a pressure
storage and handling of LPG at Gas vessel to the weight of water that the
Processing Plants, Refineries and other vessel will hold at 15 degree C.
Bulk Handling installations. It also
includes some basic concepts for design Keeping in view the industry practice of
and construction of such facilities. It does leaving 5% free space in the vessel, the
not include the requirements associated above definition gets modified to:
with bottling and other marketing
functions or transportation of LPG by It is the ratio of the weight of liquefied
trunk pipelines. Also, unless otherwise petroleum gas introduced in the vessel,
indicated, it does not apply to so as to leave a free space of 5% by
refrigerated, underground and mounded volume at the reference temperature, to
storage of LPG. the weight of water the vessel will hold
at 15 degree C. Thus, the filling density
3.0 DEFINITIONS is numerically equal to 0.95 times the
density of LPG at the reference
(i) Bulk Storage temperature.
4.0 PRESSURISED LPG STORAGE (i) Each above ground pressure vessel
shall be located in accordance with
LPG is stored in a pressure vessel. Refer the following :
Annexure-A for a LPG storage vessel P&I
diagram and Table 1 for safety related (a) A minimum safety distance shall
properties of LPG. be maintained as per OISD-STD-
118 on "Layouts for Oil and Gas
4.1 APPLICABLE CODES & DESIGN Installations".
PARAMETERS
(b) Vessel shall be in an open space.
(i) Bulk LPG storage facilities shall be Pumps shall be in open space or
installed in accordance with "The under an open shed.
Static & Mobile Pressure Vessels
(Unfired) Rules, 1981" as amended (c) Vessels shall not be installed one
from time to time. above the other.
(ii) Bulk LPG storage vessel shall be (d) Bullets shall be oriented so that
designed, constructed and tested in their longitudinal axes do not point
accordance with Bureau of Indian towards other vessels, vital
Standard Code IS : 2825 or any other process equipments, control
code approved by CCE. rooms, loading stations and
flammable liquid storage tanks.
(iii) The design pressure of vessel for
bulk LPG storage shall not be less (e) LPG storage installations shall be
than the vapour pressure of LPG in located in specially prepared
the vessel at 55 degree C. In case of industrial type fenced compound
propane storage, the design pressure having at least two exit gates.
shall not be less than the vapour However, if such storage is
pressure of propane in the vessel at situated inside a licensed area,
55 degree C. separate fencing is not required.
The number of storage vessels in
(iv) The design temperature of the vessel one group shall not exceed six.
shall be in line with the specifications The aggregate capacity of a
of LPG and statutory requirements. storage group shall be limited to
15,000 cu.m.
(v) The maximum quantity of LPG that
can be stored in a pressure vessel (f) In case, there are more than one
shall be governed by the filling group of storage vessels, the
density of LPG and shall be such that minimum safety distance between
the vessel shall not be more than two installations shall be the same
95% liquid full due to expansion of as the distance between the
the contents with rise in the vessel and the property line in
temperature to 55 degree C. (Refer accordance with OISD-STD-118
Annexure D) on "Layouts for Oil and Gas
Installations".
(g) The top surface of the vessels 4.4 VESSEL ACCESSORIES
installed in a group shall be in the
same plane. (i) All fittings and accessories of the
storage vessel shall be conforming to
(h) Spheres and Bullets shall not be "Static & Mobile Pressure Vessels
grouped together and shall be (Unfired) Rules, 1981".
provided with separate piping
manifold so as to avoid overfilling (ii) Each storage vessel shall be provided
of a vessel due to gravitation from with the following :
the other.
Inspection manhole 1 No.
(ii) Because of the pronounced volatility of Pressure relief valves 2 Nos.
LPG, dykes usually are not necessary. Bottom nozzle for liquid
It is desirable for the grade to be inlet and outlet 1 No.
sloped away from the vessel to a safe Pressure gauge 1 No.
area in such a manner that the spills Liquid level indicator 2 Nos.
from one vessel does not pass Temperature measuring
through the adjoining vessel. device 1 No.
Vapour inlet and outlet nozzle 1 No.
A kerb wall shall be provided on three High level alarm switch 1 No.
sides of the vessel with a pit on the
fourth side. Refer OISD Standard 118 a) One number of Inspection manhole at the
on "Layouts for Oil & Gas Installations" top
for details. The area inside the
storage installation shall be kept free (b) Spheres and bullets shall have a single
from weeds and dry grass. nozzle at the bottom for inlet as well
as for outlet. The nozzle shall be full
4.3 FOUNDATION & SUPPORTS welded pipe, stress relieved along with
the vessel and shall extend minimum
(i) The materials, principles, methods three (3) metres from the shadow of the
and details of design and sphere / bullet. A fire safe remote
construction of foundation and operated (shutdown) valve (ROV) shall
supports should comply with be provided on this bottom nozzle at a
approved codes and specifications. distance of at least three (3) metres from
the shadow of sphere/bullet. The nozzle
(ii) The grade for the vessel shall pipe shall have a slope of 1.5 degrees.
preferably be elevated slightly above
the surrounding terrain to ensure There shall not be any other flanges,
complete drainage from beneath the manhole, instrument tapping on this
bottom of the vessel. nozzle upto the ROV or on sphere/bullet
bottom. In order to avoid stress on the
(iii) Suitable stairs, ladders, walkways nozzle due to relative settling of support
and platforms shall be provided and sphere, supporting the bottom nozzle
allowing easy access for from the vessel support legs should be
operation/maintenance of valves and considered. The top vapour zone of the
equipments. These structural items vessel shall be provided with nozzles for
shall be welded on the pad plates vapour outlet and re-circulation which
made of the same material as the shall also be provided with fire-safe
main equipment. Welding shall be ROVs (Refer OISD Standard 144).
done by qualified welder following
approved welding procedures. In a All the fittings shall be suitable for use at
group of storage vessels, inter- not less than the design pressure of the
connecting walkways with suitable sphere/bullet and for the temperature
guards shall be provided at the top. appropriate to the worst operating
conditions. The remote operated valves
(iv) Supporting structures shall be fire- on the sphere/bullet connected lines shall
proofed so as to support vessel and be fire-safe type. The flange joints of
pipes safely in line with OISD-STD- these valves shall either have spiral
144. wound metallic gasket or ring joints. Plain
asbestos sheet gasket shall not be used.
Flange connections shall be a minimum (ii) Relief Valves shall be spring loaded.
of ANSI-300 lb flange class. All fittings Weight loaded relief valves shall not
shall be minimum 20 mm in length. be permitted.
(c) Bottom water draw off/drain valve (iii) Each safety relief valve (having 100%
relieving capacity) shall be set to start-
Two valves, with suitable distance piece to-discharge at a pressure not in
between them, shall be provided between excess of 110 percent of the design
ROV and the first isolation valve. The first pressure of the vessel and shall have
drain valve from the vessel should be of a total relieving capacity sufficient to
quick shut-off type valve while the second prevent the maximum pressure in the
valve should be throttle type (Globe Valve) vessel of more than 120 percent of the
Note 2
. The material for the drain pipe and design pressure.
related fittings shall be suitable for
cryogenic application. (iv) Each safety relief valve shall be
provided with isolation valve between
(d) Sampling Valve it and the vessel. Each valve shall be
of adequate capacity to allow full
Two valves with suitable distance piece required capacity flow through it.
between them shall be provided between Suitable provision to avoid accidental
ROV and the first isolation valve for closing of the isolation valve is
avoiding icing problem in the upstream recommended.
valve.
(v) Relief valves shall be fitted with
(e) Liquid level gauging device extended vent pipes having outlets at
least 3 meters above the top of the
The storage vessel shall have minimum vessel and atleast 3.5 meters above
two different types of level indicators and the ground level when not connected
one independent high level switch. One to flare system.
level indicator shall be float type and the
other may be differential pressure type in (vi) Relief valves shall be tested for
case of spheres. DP type level transmitter correct operation not less than once in
shall either be sealant filled type or LP a year or as per the statutory
side tubing heat traced. Magnetic float requirements and a record of such
type gauge is recommended for bullets in tests shall be maintained.
place of differential pressure type. High
level alarm shall be set at the level not (vii) For additional information, OISD
more than 85% of the volumetric capacity Standard 106 on "Pressure Relief and
of the vessel. Audio visual indication shall Disposal System" may be referred.
be at local panel and control room.
(i) Inside of bottom crown of sphere should be
(f) Pressure Gauge painted with anti-corrosive paint to protect it
from corrosion.
Minimum of one pressure gauge, duly
calibrated, shall be provided in the vapour 4.5 COMMISSIONING AND
space at the top. DECOMMISSIONING
One temperature gauge shall be provided (a) The following inspections / checks shall be
in the liquid space at the bottom of the carried out :
vessel.
(i) Check that all foreign matters have
(h) Pressure relief valve been removed and the vessel interior
is cleaned before boxing it up.
(i) Minimum of two pressure relieving
valves shall be provided in the vapour (ii) Check that all relief valves have been
space at the vessel top in accordance installed after due testing and
with the design code of the vessel. calibration.
is a hazard in releasing the purge
(iii) Check that all other fittings and water into drains. Immediate flushing
instruments are calibrated. with fresh water minimise this hazard.
Alternatively, the water may be
(iv) Check that valves are installed after released to a safe disposal system.
necessary inspection and removal of
blinds.
(v) Check that all safety facilities such as (b) For displacement purging with no
water sprays, fire protection mixing, the inert gas volume will
equipment etc. have been provided approximately be equal to that of the
and are in working condition. vessel. For dilution purging with
thorough mixing, the volume of inert
(vi) Ensure that pressure testing of the gas required will be about five times
vessel has been carried out as per the vessel volume. To inhibit mixing
appropriate code mentioned in para and thereby excessive consumption of
4.1 and a certificate to that effect purge gas, ensure that the densities of
from the approving authority is the purge gas and the gas to be
obtained. purged are widely different. Thus,
Carbon dioxide (SG: 1.52) is useful for
(b) Leak testing of the vessel and fittings shall removing air (SG: 1.00) and Nitrogen
be carried out with nitrogen, carbon (SG: 0.97) for removing propane (SG:
dioxide or water at a pressure of 7 1.52) or butane (SG:2.01).
kg/sq.cm. When using nitrogen/ carbon-
dioxide for leak testing, leak can be (c) In the case of an inert gas purged
located with soap and water. vessel, precautions should be taken
when entering the vessel for
(c) If nitrogen/carbon-dioxide is used for leak inspection and repair. Personnel
testing, it is sufficient to vent the vessel should be provided with breathing
and proceed with LPG filling operation apparatus or better, the vessel be air
ensuring a pressure of 1.5 kg per purged. The interior of the vessel shall
sq.cm.(g). be checked for breathable atmosphere
and to ensure that the LPG
(d) If water was used for leak testing, then concentration is below 5% of the LEL.
water can be displaced with LPG vapour, ( Refer OISD Standard 112 on Safe
fuel gas or natural gas prior to LPG filling Handling of Air-Hydrocarbon Mixtures
operation. and Pyrophoric Substances).
Preferably, a running air hose may be
(i) As water is displaced by equivalent provided during the initial period.
volume of LPG vapour/fuel gas/natural
gas, a constant watch on the pressure (d) When opening up a LPG storage
and level of water shall be maintained. vessel in which a stock containing
sulphur has been stored, deposits of
(ii) Care shall be taken to drain the pyrophoric iron sulphide may be
residual mixture of water and gas. found. They must be kept wet until
they are removed. If allowed to get
(iii) Similar care shall be taken when filling dried, these deposits may ignite
the vessel with LPG and venting the automatically in presence of air.( Refer
natural gas to a suitable flare/venting OISD Standard 112 on "Safe Handling
system. of Air-Hydrocarbon Mixtures and
Pyrophoric Substances").
4.5.2 DECOMMISSIONING
(e) During every hydro-testing, all nuts
The following inspections/checks shall be and bolts of manhole cover of
carried out : sphere/bullet should be replaced.
(i) Piping shall conform to the provisions (ii) Steel screwed fittings and couplings
of ANSI B 31.3. shall conform to ANSI B 16.11. Steel
unions shall have ground metal to
(ii) Furnace butt welded or spiral welded metal seats. Gasket type unions shall
pipes shall not be used. not be used.
(iii) Only seamless pipes are to be (iii) Plugs shall be of steel. Cast iron or
used. brass plugs shall not be used.
(iv) Pipe joints should be welded as far as (iv) All flanges will be connected for
practicable with full penetration weld. bonding for electrical continuity.
Number of flanged or threaded joints
should be kept to a minimum. 6.0 BULK HANDLING AND TRANSFER
(v) Low point drains and high point vents 6.1 BULK HANDLING FOR MOVEMENT
shall be plugged or capped suitably. BY ROAD
(vi) Buried piping should be protected LPG is moved by road in tank trucks.
against physical damage and The tank truck shall be designed,
corrosion with suitable sleeves, constructed and tested in accordance
properly sealed at both the ends, at with the Static and Mobile Pressure
road crossings. Vessels (Unfired) Rules, 1981. A
sketch showing General arrangement
(vii) The design, material and construction of LPG Tank Truck is enclosed as
of hoses shall be suitable for LPG Annexure-B.
(Refer OISD Standard- 135 on
Inspection of Loading/ Unloading 6.1.1 FACILITIES
Hoses for Petroleum Products).
(a) Loading –
5.4 VALVES
Each loading station shall consist
Steel valves conforming to relevant API of the following :
standards shall be used. Cast iron valves
should not be used. (i) A filling line with an isolation valve
and excess flow check valve.
5.5 THERMAL PRESSURE RELIEF
SYSTEM (ii) A vapour return line with an isolation
valve connected back to the storage
Any equipment or section of pipeline in vessel from which the loading pump is
which liquid LPG may be trapped e.g. drawing LPG.
between shut off valves, should be
protected against excessive pressure (iii) Suitable loading arm/flexible hoses
developed by thermal expansion of the (Ref.OISD-STD-135 on Inspection of
contents by providing suitable thermal Loading/ Unloading Hoses for
pressure relief valve(s). If pressure Petroleum Products) shall be provided
relieving devices discharge to atmosphere, at the end of filling and vapour return
the discharge should be arranged in a safe lines for connecting to the tank truck
manner. vessel.
(iii) Weigh bridge of suitable capacity 11. No repairs shall be made on the
truck while it is in the loading area.
A typical sketch of unloading facilities is
shown in Annexure-E. 12. New tank trucks vessels or vessels
received after repair shall be
6.1.2 SAFETY PRECAUTIONS purged before loading as
mentioned under the Item 4.5
1. Transfer of LPG to or from a tank "Commissioning and
truck requires special attention as Decommissioning".
accidental movement of vehicle
may cause rupture in the transfer 13. It is recommended that the
equipments. receiving vessel having a pressure
of less than 1 Kg/sq.cm.g should
2. No source of ignition must be not be filled. Such vessel should be
allowed in the area where product checked for oxygen
transfer operations are carried out. content/explosive mixture and
purged, if necessary.
3. Fire extinguishers shall be placed
near the tank trucks during transfer 14. Venting and purging of LPG during
operations. transfer operation normally should
not be carried out in open
4. The first operation after positioning atmosphere. It should be piped to a
the truck should be to provide suitable flare system. Where such
proper earthing. Earthing shall be facility does not exist, vent pipes
disconnected just before the shall be provided to carry the
release of the truck. vented product to a safe distance
5. Before removing plugs or caps, and released at a height not less
always crack open to allow for than three metres above the
release of trapped LPG and further highest point of any building, shed
to ensure that the valves are or structure within 15m radius.
effectively sealing. Snuffing steam facility may be
provided for the vent line.
6. Hoses should be handled with care
and inspected periodically (Refer 15. Filling/transfer operations should
OISD Standard 135 on Inspection be stopped immediately in the
of Loading / Unloading Hoses for event of -
Petroleum Products).
(i) Uncontrolled leakage
7. While disconnecting hoses/pipes, occurring
connections should be loosened (ii) A fire occurring in the vicinity
(iii) Lightning and thunder storm
(20)Liquid / vapour line valves are in
good condition.
1. Check for following in a tank truck before 3. Stop the truck on a leveled ground and
accepting it for filling: place check blocks at front and rear
wheels.
(1) Two safety valves are provided on the
vessel. 4. Stop the engine and switch off all electrical
equipments.
(2) Fixed tube gauge is provided.
5. All persons should leave the driver's cabin.
(3) Excess flow valve is provided.
6. Make bonding connections of the vehicle
(4) Pressure gauge is provided. at specified point to the fixed grounding
system.
(5) Temperature gauge is provided.
7. Connect loading and vapour lines suitably
(6) Fire screen between cabin and vessel with the loading point. Crack open valves
is provided. on loading & vapour return lines and
inspect hoses & connections for leakage.
(7) 2 Nos. of10 Kgs. DCP Fire Loading should start only when the system
Extinguishers are provided. is leak free.
(12)Approved drawings of vessel are 10. Liquid level may be determined by roto-
available. gauge or fixed liquid level gauge.
Percentage volume to be filled should be
(13)Blind flanges/caps are provided on pre-determined (see Annexure-D and
vessel. Tables-2 & 3).
(17)Excess flow valve and control valve 12. Whether a gauging device is used or a
are available on water drain line. weigh bridge is employed for filling
operation - when the liquid content is
(18)Bonding point is available. approximately within 5% of the safe filling
level, the operator should position himself
(19)Third party inspection/test certificates so that he is in control of the shut off valve
for vessel/fittings are available.
and starts to close the valve as the safe 8. Operations described under Item
filling level approaches. 14 in para 6.1.2 should now be
carried out.
13. When the filling operation is in progress,
the pressure within the tank truck vessel A filling line with excess flow check
should be observed to ensure that it does
not approach the start-to-discharge 6.2 BULK HANDLING FOR MOVEMENT
pressure of the relief valve. Filling rate BY RAIL
may be regulated as required.
LPG is moved in Tank Wagons by the
14. The couplings may then be removed and Railways. These wagons are designed
plugs/caps 4replaced on the tank truck by RDSO and are fitted with various
valves. Re-check tightness with soap devices as shown in Annexure F.
solution.
6.2.1 FACILITIES
1. Operations described under Item 1 Each loading point shall consist of the
through 6 in para 6.1.3(a) should be following:
carried out.
(i) A filling line with excess flow
2. Liquid line and vapour line of the tank check valve and an isolation
truck should be connected to the valve.
respective hoses fixed to the
unloading point. (ii) A vapour line with a check valve
and an isolation valve to be
3. Test the connections for leaks by connected back to the vessel from
slightly opening the valves for which LPG is drawn.
pressurising. When satisfied, valves
on the tank truck and the receiving (iii) Flexible hoses to be connected
vessel should be opened. with the filling and the vapour
return lines.
4. Start the evacuation compressor.
Vapours will be sucked from the (iv) A check valve to the provided at
receiving vessel and will be the end of flexible hose with the
discharged into the vapour space of filling line.
the tank truck vessel creating pressure
differential thereby pushing the liquid A typical sketch of loading facility is
from the tank truck vessel to the shown in Annexure-C.
receiving vessel.
(b) Unloading
5. Care should be exercised to see that
the pressure created within the Unloading of LPG from tank
delivering vessel does not reach or wagons shall be done with the help
exceed the set pressure of the relief of compressor. The compressor is
valve. used to create a differential
pressure between the receiving
6. An authorised person of the company and discharging vessels by
should supervise the transfer withdrawing vapors from the
operation and respond immediately in receiving vessel and forcing it at
the event of an emergency. high pressure into the discharging
vessel thereby establishing a
7. After the liquid has been expelled, the smooth flow. The content of tank
vapour recovery operation may be wagons can be ascertained by
started. Care should be taken not to weighment on weigh bridge before
bring down the pressure of the and after emptying or, alternatively,
delivering vessel below 1.5 the quantity can be determined
Kg/cm.sq.g. based on wagon gauge readings
and differential in storage tank
gauge readings before and after 3. The first operation after positioning
receipt, wherever physical the wagon shall be to provide for
weighment is not possible. proper earthing. Earthing shall be
disconnected just before the release
of the wagon.
6.2.2 SAFETY PRECAUTIONS
4. For connecting and disconnecting
1. Do not allow the locomotive to come hoses, it is advisable to use non-
on the weigh bridge due to its sparking type of tools.
capacity limitation.
5. After the wagons are placed on weigh
Sufficient number of dummy wagons bridge and before the loco is
may be used to avoid loco coming detached, the hand brakes on each
closer to the gantry. and every wagon should be applied.
d) Stop hot jobs, if any, in the 9. Ensure that coir matting/rubber sheet
nearby area. is spread on the platform.
e) Stop all the vehicular traffic in 10. Ensure that electrical continuity of the
the vicinity. system is intact.
f) Start water monitors to form a 11. Ensure that all fittings on the wagons
blanket covering the leak and are checked physically.
the wagon/piping from which
LPG is coming out. 12. Hoses should be hydraulically tested
atleast twice a year (six monthly)
g) Call fire engine with crew to (Refer OISD-STD- 135 on "Inspection
standby till the emergency of Loading / Unloading Hoses for
exists. Petroleum Products").
h) Stop all the maintenance jobs 13. Excess flow check valve will stop the
in the area. flow of LPG in case the flow is in
excess due to accidental rupture of
i) Depressurise the system hoses etc. Close the isolation valve
before attending to the leak. at grade level.
k) Clear the area of all the 15. During unloading operation, after the
people except those who are liquid transfer is over, the wagon
required to meet the pressure shall not be reduced below
emergency situation. 1.5 Kg/sq.cm.(g).
2. Ask loco to move away and 18. Keep a check on the weigh
exhibit caution sign at suitable scale readings. As soon as it
distance away from the shows the required weight of
wagons on both ends. LPG to be filled, close the
LPG isolation valve near the
3. Switch off loco engine, if weigh scale.
parked nearby.
19. Close the wagon filling and
4. Note down wagon numbers vapour return lines valves and
and placement time. also valves on filling and
vapour return lines at the
5. Take loading advice. loading point.
8. Lower the flapper bridge 21. Open the valve on flare line
slowly on the wagon. connection to both feed line
and vapour return line. Thus,
9. Open the lid of the wagon. the hoses are depressurised.
Then, close the flare line
10. Take the tare weight reading connection valves.
and set the pointer of the
scale to zero. Compare this 22. Disconnect the filling and
with the marked tare weight vapour return line hose
on the wagon. connections from the wagon.
Replace and tighten the plugs
11. Connect the filling hose and on filling and vapour return
vapour return line hose to the lines.
wagon. Ensure that the flare
connection valves are closed. 23. Close the top cover of the
wagon and seal it properly.
12. Ensure that the header is Remove earthing connections.
charged with LPG and the
bulk loading pump is running. 24. Prepare the gate pass.
13. Open the tanker filling line 25. Release the hand brake of the
valve and vapour return line wagon.
valve.
26. Release all the wagons on the
14. Open the LPG isolation valve, loading points in the lot.
located near the weigh scale.
(b) Unloading Operations
15. Check the system for leaks.
1. Ascertain that the liquid discharge
16. Open the valve on the vapour valve and the vapour valve within
return line. Now slowly open the tank wagon cover are in the
the valve on the filling line. closed position.
Increase the valve opening
2. Open the port covers in the side of 10. Recheck the lines and
the domeshell, if exist. Unscrew connections to make sure that
the plugs in the outlets of the they are connected correctly.
vapour valve and the liquid valves
using a box wrench. This must be 11. After the liquid and vapour lines
done slowly. have been secured and tested,
both liquid education valves
3. If there is any sound of escaping should be opened slowly and
vapour or if there seems to be completely. Then, open all other
pressure behind the plugs, the valves in the liquid line working
pressure must be allowed to from the tank wagon to the
relieve itself past the threads storage tank.
before the plugs are entirely
disengaged. 12. Open the storage tank filling valve
slowly, be careful not to open this
4. If the vapour discharge continues valve too far if the tank wagon
or if there is evidence of a liquid pressure is in excess of the
discharge, the valves should be storage tank pressure or the tank
retightened. wagon excess flow check valves
may get closed.
5. With the plugs removed, screw
pipe nipples into the outlets of the 13. If the tank wagon pressure is
valves after first having applied a higher than that in the storage
modest quantity of sealant to the tank, do not open the valves in
male threads, keeping the sealant vapour line or operate the
away from the end of the thread. compressor. When the rate of
Tighten nipples with a pipe liquid flow drops to an
wrench. unsatisfactory level with the
storage tank filling valve wide
6. Connect the two liquid transfer open, open the vapour valves
unloading swing arms or hoses to between the tank wagon and the
the nipples attached to the liquid storage tank.
discharge valves. Connect the
vapour or equalizing swing arm or 14. At this point, make sure that the
hose to the nipple attached to the control valves at the compressor
vapour valve. In most of the are in a position which allow the
cases, these connections will be compressor to draw vapours from
made by means of either a ground the storage tank and force it into
joint union or a hose coupling. the tank wagon, then start the
compressor.
7. In the event, a ground joint union
is used, no gasket will be required. 15. When the tank wagon is held at a
If a hose coupling is employed, pressure of 2.0 to 2.5 Kg/sq.cm.
ensure that the appropriate gasket above the storage tank pressure,
is in place. Make sure that they the tank wagon should be emptied
are secured tightly by appropriate into the storage vessel.
means.
16. A flow of gas instead of liquid
8. After the vapour and liquid hoses through the sight-flow glass in the
have been connected and before unloading line indicates that the
any valve is opened, the valves on wagon is empty of liquid. Recheck
the tank wagon are crack opened this by opening the sample valve
in order to apply pressure to the in the tank wagon dome.
hoses as a test for leaks.
17. When the tank wagon is emptied
9. If any leak appears, the valve of all liquid, stop the compressor
should be immediately closed and and close the liquid valves
corrective measures applied. beginning at the storage tank and
progressing to the tank wagon.
18. If the facilities are so arranged that it is removed from the siding
vapours may be removed from the promptly.
tank wagon, the pipeline at the
compressor should be arranged 28. Gauge the storage tanks, within
so that the compressor will draw the plant, which have received the
vapour from the tank wagon and LPG to determine that the liquid
force it into the storage tank. The level is appropriate.
sequence of piping line-up during
unloading liquid LPG and vapour 29. In the event of LPG received on
LPG is shown in Annexure - E. weight basis, the tank wagon may
require weighing following the
19. In this operation, the vapour completion of the unloading
should be discharged below the operation.
surface of the liquid in the storage
tank to hasten the liquefaction 6.2.4 DEGASSING OF SICK/LEAKY TANK
and, in turn, help prevent WAGONS
excessive pressure in the storage
tank. (a) Recommended Procedure
26. Any defect observed in the tank - Finally the vessel should be flushed
wagon should be noted on the with air to displace the nitrogen.
appropriate forms and routed in Barrel should be tested finally with
accordance with acceptable explosive meter to ensure that
procedure. hydrocarbon concentration is below
10% of LEL.
27. Notify the railways in writing about
release of wagon and ensure that (b) Alternate Procedure
code for existing ships carrying liquefied
Alternately, wagons may be gases in bulk covers ships built before
degassed by steaming or filling with the application date of the new ship
water. However, it should be code. Put together these codes are
ensured that wagon is made water known as the IMO gas codes. The
free after degassing. international code for the construction
and equipment of ships carrying
6.3 BULK HANDLING FOR MOVEMENT liquefied gases in bulk, with the short
BY SEA title of the International Gas Carrier
(IGC) code, applies to ships contracted
Transportation of LPG in bulk by tankers on or after July 1, 1986. With its revised
may be carried out under fully- and clarified wording, this IGC code
pressurised, semi-pressurised (semi- includes all the updated requirements of
refrigerated) or fully refrigerated at the previous gas codes for new ships.
atmospheric pressure conditions. The ISG code has been incorporated
into the 1974 Safety of Life at Sea
Pressurised Ships (SOLAS) Convention and in 1986
became mandatory for all Flags whose
The cargo is carried in a number of governments are signatories to the
cylindrical pressure vessels (or cargo SOLAS Convention.
tanks) capable of withstanding the
maximum pressure likely to be met in Some of the factors to be taken into
service (usually 17 bars). consideration, which effect the design
and construction of ships carrying gas,
Semi-Refrigerated Ships are :
The pressure of the cargo is very much (a) Types of cargo to be carried
reduced by lowering its temperature to
about 0 deg.C by the process of (b) Condition of the carriage (i.e. fully
refrigeration and tanks containing the pressurised, semi-refrigerated or fully
cargo need not be so strong as those of refrigerated)
pressurised ships. The tanks are
thermally insulated. (c) Type of trade, which in turn,
determines the degree of cargo
Fully Refrigerated Ships handling flexibility required by the
tanker.
The cargo is carried at atmospheric
pressure and the cargo tanks are "box- (d) Terminal facilities available when
shaped" as opposed to cylindrical/ loading or discharging the vessel.
spherical in case of pressurised/semi-
refrigerated tankers for better utilisation (e) Cargo containment systems (IMO
of ship's space. code identifies five different types).
Pressure ships usually range from very (f) Materials of construction (Fully
small capacity upto 2000 cum. capacity. refrigerated LPG cargoes must have
The capacity of semi-refrigerated ships tanks capable of withstanding
usually ranges from 1000 to 15000 temperatures down to (-)55 degree
cu.m. Fully-refrigerated tankers could be C. Alloy steels such as fully killed fine
made very much larger and for any grain carbon manganese steel,
given size, much lighter. sometimes alloyed with 0.5% Nickel
are used.)
6.3.1 CARGO CARRIER DESIGN & (g) Tank insulation (for refrigerated
CONSTRUCTION cargo)
Vapourisers
(c) Overfill alarm. When actuated, this
Cargo heaters will shuttle main loading valve and
sound an alarm.
The deep well pump supplies liquid to
the booster pump to send the product However, the design of the tankers with
ashore. In pressurised ship, liquid is regard to provision of facilities,
withdrawn by pressurising the tank equipments, accessories and safety
through vapour compression from other features must be in accordance with the
tanks. All semi and fully-refrigerated IMO requirements.
tankers are provided with cargo heaters The electrical equipments of all gas
to enable the vessels to discharge into tankers are subject to the requirements
pressure storage ashore and a booster of the Flag Administration, the
pump if the discharge pressure is Classification Society and of IMO. The
significantly above 9 bars. Each cargo certified safe electrical equipment found
tank is provided with the following on gas tankers are :
equipments:
(i)Intrinsically safe
a) Two cargo pumps, one each on
either side of the longitudinal bulk (iii) Flameproof
head.
(iv) Pressurised or purged
b) Liquid discharge line from the tank
dome, connected to the main liquid (v) Increased safety
line.
6.3.3 TRANSFER PIPEWORK
c) All emergency pump trunk way.]
The following facilities on transfer piping
d) A liquid loading line connected to the between Terminal and Shore tanks
main liquid line. should be provided:
e) Two liquid level indicating devices (a) ROVs at both the ends of transfer
one on each side. These usually line.(Additional ROV at critical
consist of a float attached to a self locations in the pipe line route.)
winding tape which moves up and
down, either on guide wires or inside
(b) Relief valves on liquid line to surge (c) Nitrogen cylinders with attendant
vessel with an audible alarm system facilities for hose purging/testing
connected to high safe venting and alternate supply to ROVs and
system other instruments.
(c) Physical protection against impact to (d) The following agents may be
vent/drain pipes incorporated in terminal fire
control system :
(d) Protection of pipeline against
corrosion, particularly when the (i) Water
pipeline passes under public road (ii) Foam
way, which is likely to be water- (iii) Dry chemical powder
logged
6.3.6 UNLOADING OPERATIONS
(e) Pipe work passing public road way
be designed to acceptable public It is essential that the ship and terminal
highway authority standard in terms operators are familiar with the basic
of roadway axle weights characteristics of each other's facilities,
are aware of the precise division of
6.3.4 TERMINAL FACILITIES responsibilities and are able to
communicate effectively during the time
Transfer of LPG from ship to terminal they are together involved in the joint
and vice versa is accomplished using operation of cargo handling.
hoses or loading arms. If terminal
authorities supply the cargo transfer 6.3.7 COMMUNICATION
hoses, it is recommended that NFPA
section 59 regulation 4.5 be followed Reliable and effective communications,
and complied with. However, if the irrespective of whether they are directly
hoses are ship hoses, these should between the tanker and the terminal or
conform to section 5 of IMO (IGC). indirectly via third party, are pre-
requisites of safe and efficient cargo
Provision of vapour return facility operations before the tanker comes
depends on economics, transfer rates, alongside and during the period of cargo
distance of jetty from storage tanks, operations and until the tanker departs.
product pressures and temperatures etc. Terminal communication should be
compatible with tanker's system.
In case of pressurised gas transfer, it is
observed that the pumping rate falls off
gradually due to back pressure of the 6.3.8 PRE-CARGO TRANSFER
shore tank. A suitable vapour recovery DISCUSSIONS
system or reliqifaction of the gas from
the receiving tank is well considered. Before any cargo transfer operation is
commenced, it is imperative that the
6.3.5 ANCILIARY EQUIPMENTS intended procedures are thoroughly
discussed and a meeting held between
(a) These include pipe work, valves, the responsible personnel from the
relief valves, rotating equipment tanker and the terminal. The purpose of
(pumps, compressors), the meeting is primarily to make both
exchangers, instrumentation, gas sides fully conversant with the
detection systems etc. characteristics of the tanker and shore
cargo handling systems, the envisaged
(b) Transfer line inerting facilities such operational and safety procedures and
as inert gas generation combined requirements and the parameters to be
with water base foam generator adhered to during the transfer.
and pipeline pig system or water
storage with corrosion inhibitor The content of the meeting will depend
chemical dosing transfer and on a wide variety of circumstances but
supply facilities. the following broad outlines form the
basis of such meetings :
(a) The names and roles of terminal
and ship personnel who will be (i) Trim correction - to make allowance
responsible for cargo transfer for the liquid level indicating
operations may be noted. devices not centrally located.
(b) The terminal representatives shall (ii) Shrinkage factor - for correction of
check that pre-arrival instructions to volume at 15 deg.C.
the ship on cargo, cargo disposition
and cargo conditioning have been (iii) Low sounding trim corrections to
carried out. They also shall check allow for the wedge shaped
that all necessary tanker volume.
equipments inspection and tests
have been performed. Volume at Corrected
15 Deg.C = Volume X VRF
(c) Similarly, the tanker's officers shall Quantity at Volume at
satisfy themselves that the relevant 15 Deg. C = 15 Deg. C X Density
terminal equipment and inspection at 15 Deg. C
checks have been carried out
satisfactorily. (VRF is ascertained by ASTM-IP Table
- 54).
(d) Terminal representatives and
customs and/or independent 7.0 SAMPLING AND DRAINING
surveyors, where necessary, will be
informed of the cargo tank data e.g. 7.1 SAMPLING
temperature, pressure, whether
free of cargo, liquid heel or arrival (a) Standard for Sampling and
dip, composition of tank vapour Testing of LPG
and quantity of cargo on board.
Sampling of LPG for different
6.3.9 SHIP/SHORE SAFETY CHECKLIST analytical tests shall be carried out
in accordance with the guidelines
Checklist for Ship/Shore safety is given given in IS 1448.
in Annexure -G.
(b) Safety During Sampling
6.3.10 DISCONNECTION OF HOSE/
UNLOADING ARM In handling LPG samples, the
following safety precautions shall
On completion of unloading operation be followed :
the tanker discharge pipeline need to be
purged to push liquid LPG to the (i) Special sampling bombs shall
receiving tank. Purging may be done by be used for LPG sampling.
LPG vapour, inert gas or water as per The coefficient of thermal
the design of the system. However, expansion of LPG is
before disconnecting hoses or unloading sufficiently high to develop
arm, it is to be ensured that there is no very high pressure on heating.
liquid LPG left between the tanker main Arrangement of rupture disc or
valve and shore isolation valve. Product any other suitable safety relief
from this length of pipeline is to be safely device may be incorporated in
vented. the sampling bomb.
(v) Sampling normally involves (iii) Ice formation may also lead to
venting product into the regular freeze up by plugging the
atmosphere. Therefore, orifice and stopping flow of gas.
absence of source of ignition Additives like methanol or propylene
must always be confirmed glucol may be added to LPG to
before and during sampling of prevent water deposition and/or
LPG. hydrate formation.
(v) Rigid connection should be welded (iii) Motor terminal boxes should be
or flanged joint type. sealed with cold setting plastic
compound.
(vi) Fluoroplastics and asbestos are
satisfactory material for gasketing. (iv) Although LPG storage vessels do
not require lightening protection,
(vii) For pressure gauges, stainless steel ground rods shall be provided for
diaphragm type is recommended vessels supported on non-
with stainless steel socket and tip. conductive foundations. Similar
ground rods shall be provided for
8.4 DISPOSAL loading/unloading gantries.
(v) High pressure switch - alarm and 3. The Static and Mobile Pressure
shutdown Vessels (Unfired) Rules – 1981.
10. IS:800 – 1962 – Code of Practice 17. Guide for Inspection of Refinery
for use of Structural Steel in Equipment – Chapter VI, Pressure
rd
General Building Construction. Vessels – 3 Edition 1976, API
Publication.
11. IS:875 – 1964 – Code of Practice
for Structural Safety of Buildings : 18. NFPA 58 – Storage and Handling
Loading Standards. of Liquefied Petroleum Gases
1979.
12. IS:2911 – Code of Practice for
Design and Construction of Pile 19. OISD – STD – 105 on Work
Foundation. Permit System.
13. ASME Boiler and Pressure Vessel 20. OISD – STD- 106 on Pressure
Code Sect. VIII Division 1 Relief and Disposal System.
American Society of Mech.
Engineers., New York (1977). 21. OISD- STD – 112 on Safe
Handling of Air – Hydro – Carbon
14. IS:1448 – Method of Test of Mixtures and Pyrophoric
Petroleum and its Products. Substances.
LPG has relatively high coefficient of expansion. If sufficient vapour space is not left in the
vessel, pressure inside the vessel would shoot up rapidly once the vessel becomes liquid full. Hence
care is exercised in limiting the filling of storage vessel to the filling density of LPG. The filling density
is defined so as to leave a guaranteed free space of five percent at the reference temperature of 55
degree C. As per Static and Mobile Pressure Vessels (unfired) Rules - 1981, the design pressure of a
vessel shall not be less than the vapour pressure of the gas in the vessel at 55 degree C.
The following information are required to work out the safe filling capacity of a storage vessel.
b) Safe maximum quantity of LPG at 15 degree C that can be filled by volume percent of water
capacity
FD x 100
= ----------------------------------------
Density of LPG at 15 degree C
c) Safe maximum quantity of LPG at t degree C that can be filled by volume percent of water capacity
FD x 100
= -------------------------------------------
Density of LPG at t degree C
FD x 100
= --- ----------------------------------------
Density of LPG as 15 degree C x VRF
SHIP:_________________________________________DATE:______________
PORT &BERTH:_________________________________TIME:______________
We have checked with each other the items on the above check list and have satisfied ourselves that
the entries we have made are correct to the best of our knowledge.