Incr - XXX
Incr - XXX
Incr - XXX
PROJECT: Jazan Refinery and Terminal Project, PKG.14 NCR No. NCR-S-CON-
Date 29-July-2018
Client : Saudi Aramco
Page 1 of 3
Inspection Lot. No. : NA
Nonconforming Item PVC Cable ties used instead of Nylon coated SS tie.
▪ Description of Non-Conformance :
During routine site surveillance at Berth 1, it has been observed that PVC cable ties has been used in dressing cables inside
perforated cable tray from Junction Box # T01-AJB-1201 to Instrument #T12-AL/XA-1184. This does not comply to Saudi Aramco
standards as per SAES-J-902 Para 5.7.
Attachments:
1. Attachment #1: Photo
2. Attachment #2: Drawings
3. Attachment #3. SAES-J-902 Para 5.7.
Y.B.WON 9-July-2019
Reviewed by:
Zahid Hussain 29-July-2019
Approved by:
Name(Contractor- SQCM) Date
Name(Contractor-QC-Supervisor) Date
▪Proposed disposition (Attachment: □ Yes, □ No) Use as is □ Repair □ Rework □ Reject □ Others □
1.Root Cause:
2.Correction :
▪Disposition Result
Verified by:
Name(Contractor/ ) Date
Attachments Remarks
F13-02 -01(Rev. 3) (29-Aug.-2014)