OTC19073 Float-Overs Offshore West Africa
OTC19073 Float-Overs Offshore West Africa
OTC19073 Float-Overs Offshore West Africa
This paper was prepared for presentation at the 2007 Offshore Technology Conference held in
• when heavy lift derrick barges are not readily available
Houston, Texas, U.S.A., 30 April–3 May 2007. resulting in prohibitive mobilization cost,
• when an integrated deck would be too heavy for the
This paper was selected for presentation by an OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Offshore Technology Conference and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any
available derrick barge.
position of the Offshore Technology Conference, its officers, or members. Papers presented at
OTC are subject to publication review by Sponsor Society Committees of the Offshore The technology combines ballasting and jacking to improve
Technology Conference. Electronic reproduction, distribution, or storage of any part of this
paper for commercial purposes without the written consent of the Offshore Technology the stability of the heavy transport vessel during the
Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not
more than 300 words; illustrations may not be copied. The abstract must contain conspicuous
transportation phase and uses jacking to provide a quick, and
acknowledgment of where and by whom the paper was presented. Write Librarian, OTC, P.O. therefore safe, transfer of the integrated deck weight onto the
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
pre-installed jacket in order to avoid high dynamic impact
loads.
Abstract
As the topsides are fully completed and tested onshore, this
concept also enables significant cost savings compared to a
Major oil and gas field developments in remote areas on the multi-module lifted topsides in transportation and installation
continental shelf with less benign environmental conditions by minimizing the installation time, offshore hook-up and by
require an efficient method of delivery and installation of the eliminating the need for heavy lift derrick barge.
production topsides. West Africa is one of those areas with its
severe swell conditions and location far away from the major The method also integrates the operations of weighing, load
fabrication yards. out and if necessary, topside supports during the construction
phase.
Technip has developed a special technology, called the
UNIDECK® concept, which enables topsides float-over This technology, for which Technip acts as an installation
installation in these swell conditions, even during the normally contractor, has been implemented in West Africa with the
restricted season for installation from October to April each COB-P1 production platform (9,500 tonne), the Amenam
year. Kpono AMP1 (11,000 tonne) and AMP2 (9,600 tonne)
platforms for TOTAL and the East Area Project GN
This paper gives an overview of the technical aspects involved compression platform (18,000 tonne) for EXXONMOBIL.
in combining the UNIDECK® system with a transport vessel
for the transportation and subsequent installation of two recent In each case, in order to minimize the cost of the operation,
float-over deck installation operations offshore Nigeria. the design of the platform arrangement and the installation
method have been adapted to the particular project in terms of
layout, topside weight, environmental conditions and final
Introduction: The UNIDECK® concept elevation of the deck.
Due to the long swell period conditions in West Africa, Detailed Engineering
conventional float-over by ballasting is too slow and thus, not The activities normally included at the engineering stage
advisable because it causes excessive impacts between the are:
topside and the jacket. Technip has therefore developed a
special technology, called the UNIDECK® concept, which • structural engineering,
enables a very short installation time in these swell conditions • detailed engineering of the operation,
(typically Hs=1.5 m in period of 10 seconds or Hs=1.2 m in
period of 14 seconds), thereby ensuring a safe installation • vessel preparations engineering,
operation and limiting the risk of weather downtime. • specification of the installation equipment,
The method is applicable to three main categories:
• transportation engineering,
• in shallow water where there is not sufficient draft for
• procedures for the installation operation,
derrick barge to enter the site,
• supervision/assistance during the operation.
2 OTC 19073
1. Structural design
Critical to this phase is the interface between the
topside/jacket structural designs and their interaction with the
vessel strength analysis. Therefore, this requires an integrated
study (structural and naval architecture) with a complete
model incorporating the topside/jacket rigidity and the
stiffness of the various components (hawsers, jacking system,
fenders…).
Of major importance is the design of the support on vessel for
all of the operations:
• for the load out; to include for vessel trim and list with
consequential distortion of deck,
• for the transportation; to include for dynamic effects and
vessel-to-deck distortion,
• for the deck elevation/lowering by jacking; to design a
guiding system to cope with the horizontal loads (dynamic
and impact load at time of mating).
The topside support substructure (see Figure 1) concept
developed by Technip is unique and integrates support for the
construction, weighing, load out, sea fastening, transportation
and the offshore installation phases.
On the transport vessel, the grillage design allows distribution
of the static and dynamic loads of the topsides to the different
locations of the vessel’s structural hard points. In addition, the
grillage has been designed to optimize the ratio between
topsides weight and vessel strength. Fig. 1: Typical substructure with the cylinder jacks
elevated, GN Compression Platform.
Both the 8 substructures and the grillage (see Figure 2) have
been designed for use on multiple installations and use on a
modular concept for simple adaptation to a particular project.
The sea fastening (see Figure 3) of the topsides has been the lines remain stiff enough to keep a good control of the
designed taking into account the various steps of the vessel’s position and to maintain the second order motions of
operations for a sequential and quick installation or removal the vessel to a low level.
(within 4 hours when a suitable weather window is
The fairleads, sheaves and bollards are designed and sized to
forecasted):
satisfy all possible configurations during entrance, mating and
• partial installation for marine operations at quay just after withdrawal of the vessel.
the load out; additional sea fastening for vessel stand-by at
2.2 Fenders inside the jacket (see Figure 4):
yard under harsh conditions (if any), e.g. typhoons; final
installation prior sail away, Fenders also called jacket leg protectors are provided to
absorb vessel impacts on the jacket. The fenders are fitted with
• partial sea fastening removal when vessel is in stand-by a steel shield to ensure good contact on the vessel own fender
location facing the jacket; final removal prior entrance into (half pipe) and to allow vessel level change during mating.
jacket,
A small gap of about 0.2 to 0.3 m between the vessel hull and
• self releasing (no particular handling required, only the shield is used.
oxycutting) and easy re-installation in case of necessity.
2.1 Mooring system on the vessel: A system of guides and fenders on the stern of the vessel
ensure the guidance and protection during the critical phase of
The mooring consists of a combination of equipment that is
the beginning of vessel entrance into jacket.
sized to suit the vessel motion characteristics, the jacket
rigidity and the environment conditions of the site.
2.3 Transition piece and guide cones:
The mooring lines connected to the jacket use a winch with
wire rope and a nylon tail to adjust the line stiffness. On top of each jacket leg (or pile) is installed a transition
piece. This is composed of a guide cone to facilitate the
The selected line stiffness avoids having resonance with wave
offshore installation and a thick reinforcement.
periods (i.e. the degradation of the vessel motions) and also
The guide cones (see Figure 5) are designed at an angle of 45°
avoids having high dynamic peak loads in the lines. However,
4 OTC 19073
and fitted at their base with a cylindrical part 50 to 100 mm in The mobile piece composed of the funnel and guide pipe,
height to provide the final accurate centering. allows the cone on the jacket to be caught even with some
vessel motion/eccentricity and ensure the stability of the unit
The thick part of transition piece accepts the relatively high
to avoid buckling or collapse.
concentrated impact loads at the steel-to-steel contact without
risk of local deformation.
Finite element analysis is performed to check the local
strength of the transition piece.
To ensure a safe operation even in case of any failure or longitudinally (see Figure 8) onto the Mighty Servant 3.
dysfunction, the system has been developed by incorporating
many redundancies (electrical, hydraulic, control system) and
2 possible degraded control modes (manual and ultimate) have
been foreseen:
• the manual mode, which can be operated from 2 locations:
- the control room allowing slow movements through
the servo valves rack (loss of the P.L.C.s and the
supervisory computers) and fast speed lowering of
the deck without the position synchronization of the
axes in case of complete loss of the control system.
- the H.P.U. control cabinet allowing slow
movements per pair of axis in case of complete loss
of the control room.
• the ultimate mode in case of loss of control system and
power, which can be operated locally near the manifold
blocks allowing lowering of the deck.
• electrical connection of auxiliary power generation to the • vessel configuration: draught, heel angle and overall centre
jacking system and final jacking system testing, of gravity,
• safety access, wire guards and muster points, • all basic data relative to the operation of the hydraulic
system: pressure, flow rates, etc…
• walkways and work platforms, as required,
• jacks extension and loads at each support,
• video camera system.
• environmental conditions (wave, wind and current by
reading of a rider buoy) and the weather forecast for the
The Black Marlin vessel left the South Korean yard less than coming hours (12 to 36 hours depending on the operation
15 days after the load out operations of the GN topside. stage),
• video camera to visualize the legs during the mating
3. Transportation operation,
The topsides, supported on the substructures, are transported • display of tensions in the mooring lines,
from the fabrication yard to the installation site on the heavy
transport vessel. The transport is quick and safe with a high • vessel motions by gyrocompass.
degree of flexibility in weather routing. An average speed of
12 – 13 knots was achieved for the entire trip from South This information was assessed for the decision-making at each
Korea/Middle East to Nigeria via Cape of Good Hope, step of the installation operation.
including a port call for boarding of the installation key
personnel.
8 OTC 19073
The offshore installation started by manoeuvring and mooring By using winches on the deck, the vessel was moved into the
the Black Marlin vessel outside the jacket using a combination jacket that was protected by 8 soft rubber arch fenders located
of 4 anchoring lines connected to anchors pre-tested at 80 tons at each pile.
(see Figure 11). Once the stern of the vessel reached the 2nd row of the jacket,
the 2 ‘bow longitudinal mooring lines’ attached to the first
row of piles were connected to the vessel and the deck was
elevated 1,750 mm.
When the vessel stern reached the last row of the jacket, the 2
‘stern longitudinal crossed mooring lines’ were uncrossed
using winches on the vessel deck. At the final position, the
vessel was moored inside the jacket by the 4 longitudinal lines
and 4 transversal lines were added to the external piles. This
ensured accurate positioning of the deck legs over the jacket
legs.
These 8 mooring lines were designed to keep the vessel’s
natural period away from the wave periods and short enough
to avoid slow drift effects. This was obtained by adding a
stretcher (stiffness 100 tons/m) in each of the mooring lines.
The maximum allowed loads in these lines were 90 tons.
Fig. 11: Vessel moored outside the jacket The total displacement of the vessel being about 100,000
tonne, the amount of energy due to the vessel motions was
Then, the 2 ‘stern longitudinal crossed mooring lines’ were
substantial but the compliant UNIDECK® system allowed
connected from the stern of the vessel to the furthest piles of
control and such energy to be handled without any large
the jacket, to allow an accurate control of the vessel’s stern impact forces.
while entering into the 1st row of the jacket (see Figure 12).
The concept is based on jacks resisting the vessel’s • associated with a self propelled vessel, it allows a shorter
longitudinal motions with a constant load. transportation time to the installation site compared to
tug-barge combination due to higher transit speed and less
The efficiency of the anti-surge system has been recently
weather sensitivity, and reduces the accelerations due to
proven during the AMP2 (Amenam Kpono Phase 2 Project)
lower motion response than barge transportation,
platform installation in West Africa, where it was used for the
first time. • the method considerably reduces the integration, pre-
During this operation, only 50% of the anti-surge system was commissioning and offshore commissioning work by full
used and the surge movements were reduced by a factor of onshore completion and commissioning of the deck
three (see Figure 15). compared to a multi-module lifted topsides,
• it reduces the cost of the installation compare to a heavy
lift derrick barge installation.
Acknowledgement
The authors would like to thank our Clients EXXONMOBIL
and TOTAL and the management of TECHNIP and
DOCKWISE for granting the permission to publish this paper.
The authors also express their special appreciation to their
colleagues for the support and advice they have provided.
References
1. J.H. Sigrist and J.C. Naudin, Technip:
” Experience in Float-over Integrated Deck-
Design and Installation”, paper OTC 8121,
presented at the Offshore Technology
Conference, held in Houston Texas, 6-9 May
1996.
2. J.H. Sigrist, P.A. Thomas and J.C. Naudin,
Fig. 15: Vessel motions Technip: ” Experience in Float-over Integrated
Deck-Flexibility of the concept”, paper OTC
8616, presented at the Offshore Technology
Conclusion Conference, held in Houston Texas, 1998
The UNIDECK® method is well proven technology and
presents a large number of advantages that reduce the
integration and commissioning schedule and cost of a Topside
Platform Development Project.
These advantages can be summarised as follows:
• it allows topsides installation in shallow water where
there is not sufficient draft for derrick barge to enter the
site,
• this method enables topside installation when an
integrated deck would be too heavy for existing derrick
barge,
• the substructures of the Unideck® concept, based on a
modular arrangement, include supports for the topsides
construction, load out and sea fastening for the
transportation,
• the jacking operation is fully reversible,
• a jacking system with a high level of redundancy is used
to perform the various operations including weighing,
load out and offshore installation,