15-Jan-18 National 1 005a Blinding for Main Building 170 22-Jan-18 12-Feb-18
Tests Interval
S.No RFI NO POUR Grade Location Description of work Casting Tests Test Report
CARD NO Date Date Ref
7 Days 28 days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Main 7 Days CR-1801/8610 21.5 20.0 18.5 20.5 18.5 19.5 20.0 19.5 20.0 20.0 18.0 20.0
1 005a CPR/001 20/20 OPC + GGBS Blinding 1/15/2017 1/22/2017 2/12/2017
Building 28 days
20/10 Protection Main 7 Days
2 10 CPR/002 screed Building Protection screed 2/3/2018 2/10/2018 3/3/2018