Progress Analysis 2014 03 24
Progress Analysis 2014 03 24
Progress Analysis 2014 03 24
Cluster p ( Phase 1 )
Excavation Foundation Blinding Footing Slab on Grade Stub Wall Backfilling Ground Slab G. Floor Tunnel (F.F. Slab) F. Floor Tunnel (Roof Slab) Parapets & Staircase Parapet & Upstands Staircase Blockwork Int. Plaster Wall & Floor Tiles Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Joinery Works Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Wardrobe Shutters Kitchen Cabinet Carcass Kitchen Work Top Kitchen Cabinet Shutters Vanity Carcass Vanity Metal Frame Vanity Work Top Vanity Shutters 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
Increase in this w
Planned
Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension Gypsum Board False Ceiling Tiles Handrails Balcony Handrails Staircase Handrails Internal Painting Works Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Paint External Cladding Works External Painting Undercoat External Painting Final Coat Roofing & Water Proofing Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles External Works GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Boundary Wall Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works MEP 1st Fix Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork
8 14 14 14
14 14 4
14
14 14 14 14 14 14 14
Condu. for Drainage & Water Supply High Level Drainage MEP 2nd Fix Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's MEP Final Fix Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Handing Over Testing & Commissioning. Disinfection. Snagging & Cleaning.
14 14 14 14 14 14 14
11
14
0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14
14 14
0 0 0
14 14
14 14 14 14 14
0 0 0 0 0 0
14 14 14 14 14
14 14 14 2
0 0 0 0 0
14 14 14 14
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 14 14 14 13
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 0 0 0 0 14 0 0 0 0 0 0 0 0 14 14 14 14 10
0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 8 0 0 0 7 6 0 0 0 8 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2
14 7 8
14 6
14
14 14 14 14 14 14 14
10 14 1 4 4 4 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 6 0 0 4 0 0 8 0 0 0 0 0 0 0 0 0 0
2 0 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 14 14 8 14 14 10
Increase in the last week (12 Dec , 2013) Actual Increase in Planned Increase in Actual Planned
Increase in p
14
0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 5 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14
14 14
0 0 0
14 14
14 14 14 14 14
0 0 0 0 0 0
14 14 14 14 14
14 14 14 1
0 0 0 0 0
14 14 14 14
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 3 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 14 14 11 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 14 0 0 0 0 0 0 0 0 14 14 14 14 8
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 8 0 0 7 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4
14
14
14 14 14 14 14 14 14
8 14 0 4 4 3 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 8 1 6 9 0 0 3 0 0 0 0 0 0 0 0 0 0
4 0 0 0 2 1 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 14 14 13 8 1
Increase in previous week (5 Dec , 2013) Actual Increase in Planned Increase in Actual
14
0 0
0 0 0 0 0 0 0 0 0 0 0 6 2 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 14
0 0 0
14 14 14 14 14
0 0 0 0 0 0
14 14 9 0
0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 6 7 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 0 0 0 14 14 14 14 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 14 0 2 3 1 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 7 7 1 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 2 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Planned
Actual
14
14
14 14
14 14
14 14 14 14 14
14 14 14 14 14
14 14 14 14
8 12 5 0
14 14 8 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0
14
0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 0 0 0 14 14 14 14 4
14
14 14 14 14 14 14 14
14 14 14 6 1
4 14 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0
Increase in this w
Planned
Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension Gypsum Board False Ceiling Tiles Handrails Balcony Handrails Staircase Handrails Internal Painting Works Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Paint External Cladding Works External Painting Undercoat External Painting Final Coat Roofing & Water Proofing Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles External Works GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Boundary Wall Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works MEP 1st Fix Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork
73
20 13 73 54 47 40 24
Condu. for Drainage & Water Supply High Level Drainage MEP 2nd Fix Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's MEP Final Fix Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Handing Over Testing & Commissioning. Disinfection. Snagging & Cleaning.
22 31 10 2 3 3 3
78
0 0
0 0 0 0 0 0 0 0 6 4 0 2 6 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
78
78 78
0 3 0
78 75
78 78 78 38 14
6 6 4 4 4 0
67 60 50 43 36
8 24 2
6 6 6 6 0 6 6 5 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
21 21 21 11
4 4
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 0 0 1 0 0 0 0 0 0 0 0 6 0 0 0 0 0 0 6 0 6 0 6 4 4 4 6
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 4 0
78
67
14 7 67 50 43 36 18
78 78 38 14
10
6 6 0 6 2 3 3 3 0 0 0 0 0 0 0 0 0 0 0 0 0
0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 25 4
Increase in the last week (12 Dec , 2013) Actual Increase in Planned Increase in Actual Planned
Increase in
78
0 0
0 0 0 0 0 0 0 0 6 4 0 2 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
78
78 78
0 5 0
78 70
78 78 78 32 10
6 6 5 5 5 0
61 54 45 38 31
6 18
6 6 6 6 0 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
15 15 15 5
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 11 0 0 0 0 0 0 6 0 6 0 6 5 5 5 6
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31 0 0 0 0 0 0 0 0 0 0 0 0 6 4 0
78
56
8 1 61 45 38 31 12
78 78 32 10
6 6 0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 19
Increase in previous week (5 Dec , 2013) Actual Increase in Planned Increase in Actual
78
0 0
0 0 0 0 0 0 0 0 8 6 0 4 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
78 78
0 5 0
78 78 78 26 6
5 5 6 5 5 0
4 8
5 5 5 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 0 1 0 5 6 5 5 5
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 0 0 0 0 0 0 0 0 0 0 0 0 8 6 0
47
78 78 26 6
5 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Planned
Actual
78
78
78 65
78 78
56 49 39 33 26
78 78 78 18
10 10 10 2
56
40
56 39 33 26 7
78 78 18
5 14
Increase in this w
Planned
Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension Gypsum Board False Ceiling Tiles Handrails Balcony Handrails Staircase Handrails Internal Painting Works Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Paint External Cladding Works External Painting Undercoat External Painting Final Coat Roofing & Water Proofing Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles External Works GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Boundary Wall Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works MEP 1st Fix Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Condu. for Drainage & Water Supply High Level Drainage MEP 2nd Fix Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's MEP Final Fix Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Handing Over Testing & Commissioning. Disinfection. Snagging & Cleaning.
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
68
8 0
0 0 0 12 0 12 10 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18
68 66
6 3 0
13 0
58 46 46 0 0
0 0 0 0 0 0
0 0 0 0 0
0 0 0 0
0 0 0 0 0
0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 58 46 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 10 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Increase in the last week (12 Dec , 2013) Actual Increase in Planned Increase in Actual Planned
Increase i
68
4 0
0 0 0 10 0 12 12 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14
68 54
6 0 0
7 0
46 36 36 0 0
0 0 0 0 0 0
0 0 0 0 0
0 0 0 0
0 0 0 0 0
0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 46 36 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 12 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Increase in previous week (5 Dec , 2013) Actual Increase in Planned Increase In Actual
68
5 0
0 0 0 10 0 10 10 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
68 44
5 0 0
34 24 24 0 0
0 0 0 0 0 0
0 0 0 0
0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 34 24 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10 10 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Planned
Actual
68
2 0
68 34
0 0 0 0 0
24 14 14 0 0
0 0 0 0
0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 24 14 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Planned No of Villas Cluster Q & M 19-Dec 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 2 0 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Status Completed Not Started Completed Completed Not Started Completed Completed Completed Completed Completed Not Started Completed Completed Completed In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Completed Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Completed Completed Completed Completed In Progress In Progress Completed Not Started In Progress In Progress In Progress In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started 5-Dec h h h h h h h h h h h s s s s h h h s s s h h h h h h h h h h h h h h h h h h h h h h h h h h h h s h h h h h h s h s h s s h h s s s h h h s h h h h h h h h h h h h h h s s h h s s s s s h h s h h h h h h h h h h
0 0 0 5 0 5 5 6 5 5 0 5 5 5 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 0 1 0 5 6 5 5 5 5 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Planned No of Villas Cluster N & O 19-Dec 0 0 0 0 0 0 0 0 6 4 0 2 6 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 4 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Status Completed Not Started Completed Completed Not Started Completed Completed Completed In Progress In Progress Not Started In Progress In Progress In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Completed Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Completed Completed In Progress In Progress Not Started Not Started In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started 5-Dec h h h s h s s s s s h s s s s h s s s s h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h s h h s h h h h h h h h s h h h h h h s h s h s s s s s s s h s s s s s h h h h h h h h h h h h h
5 0 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Activites
Excavation Foundation Blinding Footing Slab on Grade Stub Wall Backfilling Ground Slab G. Floor Tunnel (F.F. Slab) F. Floor Tunnel (Roof Slab) Parapets & Staircase Parapet & Upstands Staircase Blockwork Int. Plaster Wall & Floor Tiles Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Joinery Works Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Wardrobe Shutters Kitchen Cabinet Carcass Kitchen Work Top Kitchen Cabinet Shutters Vanity Carcass Vanity Metal Frame Vanity Work Top Vanity Shutters Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension Gypsum Board False Ceiling Tiles Handrails Balcony Handrails Staircase Handrails Internal Painting Works Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Paint External Cladding Works External Painting Undercoat External Painting Final Coat Roofing & Water Proofing Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles External Works GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Boundary Wall Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works MEP 1st Fix Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork Condu. for Drainage & Water Supply High Level Drainage MEP 2nd Fix Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's MEP Final Fix Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Handing Over Testing & Commissioning. Disinfection. Snagging & Cleaning.
5-Dec
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6 7 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 7 1 0 0 0 0 0 0 0 0 0 0 0 0 0
12-Dec 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7 8 0 0 7 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 8 1 6 9 0 0 3 0 0 0 0 0 0 0 0 0 0
12-Dec 0 0 0 0 0 0 0 0 0 0 0 0 0 5 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 11 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 4 0 0 0 2 1 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12-Dec 0 0 0 5 0 6 6 5 5 5 0 6 6 6 6 0 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 11 0 0 0 0 0 0 6 0 6 0 6 5 5 5 6 6 6 0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12-Dec 0 0 0 0 0 0 0 0 6 4 0 2 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 31 0 0 0 0 0 0 0 0 0 0 0 0 6 4 0 0 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12-Dec 4 0 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12-Dec 0 0 0 10 0 12 12 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19-Dec 0 0 0 12 0 12 10 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Status Completed Not Started Completed In Progress Not Started In Progress In Progress In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started In Progress In Progress Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started
s h s s h s s s h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h h s s h h h h h h h h h h h h h h h h h h h h h h h h
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER P - 14 VILLAS PROGRESS TREND ANALYSIS Activites
Excavation Blinding Footing Stub Wall Backfilling Ground Slab G. Floor Tunnel (F.F. Slab) F. Floor Tunnel (Roof Slab) Parapet & Upstands Staircase Blockwork Int. Plaster Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Wardrobe Shutters Kitchen Cabinet Carcass Kitchen Work Top Kitchen Cabinet Shutters Vanity Carcass Vanity Metal Frame Vanity Work Top Vanity Shutters Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light Sun Pipe Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Suspension Gypsum Board False Ceiling Tiles Balcony Handrails Staircase Handrails Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Cladding Works External Painting Undercoat External Painting Final Coat Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles
Trend Bars
Status
3 6 8 2
2 2 4 10 1 14 1 1 12 14 14 14 14 14 14 10 10 4 14 2 4 1 1 12 10 13 13 14 4 4 4 14 14 14 3 8
No Progress Slow in progress No Progress No Progress No Progress No Progress No Progress No Progress No progress this week
No Progress No Progress this week Slow in progress No Progress this week No Progress this week No Progress Slow in progress No Progress No Progress No Progress
7 2 1 1 12 13 13
No progress this week Slow in progress No Progress this week No Progress this week Slow in progress
14
No Progress
3 6 6 8
4 6
Page 47 of 60
Cluster P (14)
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER P - 14 VILLAS PROGRESS TREND ANALYSIS Activites
GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork Condu. for Drainage & Water Supply High Level Drainage Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Testing & Commissioning. Disinfection. Snagging & Cleaning.
Trend Bars
Status
6 1 13
7 1 14 13
12
No Progress
No progress this week No progress this week No progress this week No progress this week
8 2 4 13 1 1 1 1 1 1 5 8 1 13 11 13 2
No Progress Slow in progress Slow in progress No Progress No Progress this week Slow in progress No Progress this week No Progress No Progress this week No Progress No Progress No Progress
Page 48 of 60
Cluster P (14)
Activites
Excavation Foundation Blinding Footing Slab on Grade Stub Wall Backfilling Ground Slab G. Floor Tunnel (F.F. Slab) F. Floor Tunnel (Roof Slab) Parapets & Staircase Parapet & Upstands Staircase Blockwork Int. Plaster Wall & Floor Tiles Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Joinery Works Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Wardrobe Shutters Kitchen Cabinet Carcass Kitchen Work Top Kitchen Cabinet Shutters Vanity Carcass Vanity Metal Frame Vanity Work Top Vanity Shutters Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER Q - 40 VILLAS Cumulative No of Actual No of Villas Cluster Q Planned Villas Cluster Q PROGRESS TREND ANALYSIS
Planned
40
Trend Bars
Status
Actual
40
As per Baseline
7
26-Dec-13
2-Jan-14
40 40
40 40
7 7
40 40 40 40 40
40 40 40 40 40
7 7 7 7 7 2 8 10 8
40 40 40 40
40 40 26 6
7 7 7 7
14 16 4 7
16
6 2
2 1
5 3
40 40 36 33 26 19 21
7 7 7 7 7 7 7
14 7 16 9 9
7 7 7 7 7 7
7 7 7 7 7 7 7
Slow In Progress
7 7 21 7 7 2 7
Slow In Progress No Progress
Page 49 of 60
Cluster Q (40)
Activites
Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension Gypsum Board False Ceiling Tiles Handrails Balcony Handrails Staircase Handrails Internal Painting Works Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Paint External Cladding Works External Painting Undercoat External Painting Final Coat Roofing & Water Proofing Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles External Works GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Boundary Wall Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works MEP 1st Fix Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER Q - 40 VILLAS Cumulative No of Actual No of Villas Cluster Q Planned Villas Cluster Q PROGRESS TREND ANALYSIS
Planned
2
Trend Bars
Status
Actual
As per Baseline
7
26-Dec-13
2-Jan-14
14 14 7
7 7 7
14 7
7 7 7
No Progress No Progress
8 8
7 7
No Progress No Progress
21
7 7
No Progress No Progress
37
slow in progress
30 32 18
7 7 7
30 23 16 9
7 7 7 7
10 40 13 40
7 7 7 7
7 7
Slow In Progress
40 16 40
7 7 7
40 40 40 40 40
40 40 40 40 17
7 7 7 7 7 2 8 4 10 8 2 11
No Progress this week
Page 50 of 60
Cluster Q (40)
Activites
Condu. for Drainage & Water Supply High Level Drainage MEP 2nd Fix Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's MEP Final Fix Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Handing Over Testing & Commissioning. Disinfection. Snagging & Cleaning.
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER Q - 40 VILLAS Cumulative No of Actual No of Villas Cluster Q Planned Villas Cluster Q PROGRESS TREND ANALYSIS
Planned
40 40
Trend Bars
Status
Actual
16 25
As per Baseline
7 7
26-Dec-13
4 2
2-Jan-14
40 33 34 34 34 2 4
7 7 7 7 7 7 2 2
27 9 8
7 7 7 7 7
7 7
7 7 7
Page 51 of 60
Cluster Q (40)
Activites
Excavation Foundation Blinding Footing Slab on Grade Stub Wall Backfilling Ground Slab G. Floor Tunnel (F.F. Slab) F. Floor Tunnel (Roof Slab) Parapets & Staircase Parapet & Upstands Staircase Blockwork Int. Plaster Wall & Floor Tiles Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Joinery Works Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Wardrobe Shutters Kitchen Cabinet Carcass Kitchen Work Top Kitchen Cabinet Shutters Vanity Carcass Vanity Metal Frame Vanity Work Top Vanity Shutters Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER M - 38 VILLAS Cumulative No of Actual No of Villas Cluster M Planned PROGRESS TREND ANALYSIS Villas Cluster M
Planned
38
Trend Bars
Status
Actual
38
As per Baseline
7
26-Dec-13
2-Jan-14
38 38
38 38
7 7
Complete Complete
38 38 38 36 28
38 38 38 34 14
7 7 7 7 7 8 6 8 2 4 6 8 6
18 18 18 8
6 24
7 7 6 16
6 2
No progress
1 1
7 7 7 7 7 7 7
Not Started Not Started Not Started Not Started Not Started Not Started Not Started
7 7 7 7 7 7 7 7 7 7 7 7 7
Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started
7 7 7 7 7
Not Started Not Started Not Started Not Started Not Started
Page 52 of 60
Cluster M (38)
Activites
Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension Gypsum Board False Ceiling Tiles Handrails Balcony Handrails Staircase Handrails Internal Painting Works Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Paint External Cladding Works External Painting Undercoat External Painting Final Coat Roofing & Water Proofing Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles External Works GRC Works Under Ground Water Tank Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures Sweet Soil Boundary Wall Precast Boundary Wall (Other Sides) Boundary Wall Railing Manhole Works MEP 1st Fix Condu. for Drainage Piping in SubStr Condu. in Structure (Grade Slab) Condu. in Structure (GF Tunnels) Condu. in Structure (FF Tunnels) Condu. & Fix Sw.Boxes in Blockwork
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER M - 38 VILLAS Cumulative No of Actual No of Villas Cluster M Planned PROGRESS TREND ANALYSIS Villas Cluster M
Planned Actual As per Baseline
7
Trend Bars
Status
26-Dec-13
2-Jan-14
7 7 7
7 7 7
7 7
7 7
7 7 7
7 7 7 7
7 38 38 7 7 7 7 7 7
Not Started Complete Not Started Not Started Not Started Not Started Not Started
11
7 7
38 38 36 28 15
38 38 34 14
7 7 7 7 7 8 6 8 2 4 6 8 6
Slow In Progress Slow In Progress No progress
Page 53 of 60
Cluster M (38)
Activites
Condu. for Drainage & Water Supply High Level Drainage MEP 2nd Fix Inst.of FCU's Wiring Works Inst.of AC Duct Refrigrant Pipes Inst.of Water Heaters Inst.of CU's MEP Final Fix Inst.of Exhaust Fan Inst.of AC Grills & Diffusers Inst.of Water Pumps Electrical Accessories Inst.of Light Fittings Switchgear Circuit Breakers Inst. of Sanitary Fittings & Wares Handing Over Testing & Commissioning. Disinfection. Snagging & Cleaning.
CONSTRUCTION OF 160 VILLAS - DSOA CLUSTER M - 38 VILLAS Cumulative No of Actual No of Villas Cluster M Planned PROGRESS TREND ANALYSIS Villas Cluster M
Planned
13 22
Trend Bars
Status
Actual
As per Baseline
7 7
26-Dec-13
2-Jan-14
7 7 7 7 7 7
7 7 7 7 7 7 7
7 7 7
Page 54 of 60
Cluster M (38)
Trend Bars
Status
Actual
28
Complete
27 18
28 28
7 7 2
Complete Complete
9 3
28 28 28
7 7 7
4 2 2 4 4
7 7
7 7 7 7 7 7 7
Not Started Not Started Not Started Not Started Not Started Not Started Not Started
7 7 7 7 7 7 7 7 7 7 7 7 7
Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started Not Started
7 7 7 7 7 7
Not Started Not Started Not Started Not Started Not Started Not Started
7 7 7
7 7
7 7
7 7 7
7 7 7
7 9 28 7 7 7 7 7 7 6 2 14 6
Not Started
Not Started Not Started Not Started Not Started Not Started
Activites
Excavation Foundation Blinding Footing Slab on Grade Stub Wall Backfilling Ground Slab G. Floor Tunnel (F.F. Slab) F. Floor Tunnel (Roof Slab) Parapets & Staircase Parapet & Upstands Staircase Blockwork Int. Plaster Wall & Floor Tiles Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Joinery Works Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Wardrobe Shutters Kitchen Cabinet Carcass Kitchen Work Top Kitchen Cabinet Shutters Vanity Carcass Vanity Metal Frame Vanity Work Top Vanity Shutters Miscellaneous Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Shower Enclosure Sky Light Sun Pipe UPVC Doors & Windows. Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Works False Ceiling Suspension
Trend Bars
Status
20 10
40 40
7 7
4 3
40 40 40 2
7 7 7
6 12 12 4 4 2
7 7
7 7 7 7 7 7 7
7 7 7 7 7 7 7 7 7 7 7 7 7
7 7 7 7 7 7
7 7 7
7 7
7 7 7
7 7 7
7 4 40 7 7 7 7 7 7 8 8 24
7 7 7
CONSTRUCTION OF 160 VILLAS - DSOA Total Project (160 villas) PROGRESS TREND ANALYSIS
Cumulative No of Villas Planned
F. Floor Tunnel (Roof Slab) Parapet & Upstands Staircase Blockwork Int. Plaster Kitchen Wall Tiles Bathroom Wall Tiles Wet Area Waterproofing Bathroom Floor Tiles Int. Flooring Marble/Granite Steps External Floor Tiles Int. Door Frame Int. Door shutter & Ironmongery External Door Frame External Door shutter & Ironmongery Wardrobe Carcass Kitchen Cabinet Carcass Kitchen Work Top Vanity Carcass Vanity Metal Frame Vanity Work Top Kitchen Exhaust Hood Mirrors Fixing Cat Ladder Sky Light Sun Pipe Aluminium Doors Aluminium Window Frames Glass for windows False Ceiling Suspension Gypsum Board Balcony Handrails Staircase Handrails Int. Paint Under Coat & First Coat / Spray Plaster Int. Paint Final Coat External Plaster External Cladding Works External Painting Undercoat External Painting Final Coat Light Weight Concrete Waterproofing Memberane Protection Board Aggregate Filling & Roof Paving Tiles GRC Works Heel Kerb Shaded Structure : Pergola Interlock Tiles Pump & Gas Enclosures 118 102 102 102 93 92 92 92 92 89 81 83 76 69 78 71 71 67 60 62 62 57 60 52 83 64 64 76 76 69 76 69 70 70 83 14 92 92 92 80 92 85 78 71 72 75 52 70 56
Activites
Trend Bars
Status
Actual
156 126 146 107 65 56 54 54 50 52 24 25 20 14 14 14 14 14 14 36 14 14 14 14 24 14 14 14 14 14 39 22 24 24 54 20 78 54 35 30 66 62 60 54 36 20 14 20 24
3-Mar-14
10 8 12 10 6 5 3 8
10-Mar-14
14 8 8 7 6 12 6 7 5 7
17-Mar-14
8 8 6 10 6 8 16 11 12 15
24-Mar-14
12 10 8 10 6 4 6 8 9 8 8
Slow In Progress Slow In Progress Slow In Progress
5 5
4 3 2
1 6
12 14 14 14 14 22
No progress No progress
12 10 13 14 4 14 14 14 4 5 1 13 13 4 14 7 7 6 9 18 2 2 5 6 6 4 6 4 2 12 11 10 8 4 5 4 8 9 10 6 2 2 7 4 4 4 6 2 13 1 6 13 Page 60 of 60 10 15 6 7 4 4 2 4 5 2 8 10 2 6 9 18 8 6 5 6 6 12 6 4 6 4
No progress No progress Slow In Progress No progress No progress No progress No progress No progress Slow In Progress Slow In Progress