Volume - 4
Volume - 4
VOLUME 4
OUTLINE DESIGN SPECIFICATIONS
VOLUME 4
.> OUTLINE DESIGN SPECIFICATIONS
TABLE OF CONTENTS
SECTION PAGE
SECTION 1 - RAILWAY GEOMETRY, DESIGN LIFE AND LOADS
1.1.2 Codes
ASTM Standards
AASHTO standards
BS standards
Other Publications
1.2.1 General
1.2.2 Minor Deviation in Alignment
1.3.1 General
1.3.3 Clearances
1.4.1 General
1.4.2 Civil Engineering Structures
1 5.1 General
(Not Used)
Seismic Loading
Differential Settlement
(Not used)
-
SECTION'2 GEOTECHNICAL, FOUNDATIONS AND TUNNEL WORKS
Others
Tunnelling
2.7.4 Loads
2.7.6 Flotation
2.7.1 4 Waterproofing
2.8.4 Flotation
2.8.16 ~ e s i g nPrinciples
2.8.17 Flotation
2.8.26 Waterproofing
2.8.30 Flotation
OTHER CONSIDERK~IONSCRITERIA
. .
2.9.8 General
2.10.7 Monitoring
DELETED
4.1 GENERAL
4.2 Deleted
4.3 Deletec!
4.4 UTILITIES
ANNEXURE 1
DMRCINolume-410utlineDesign Spec~ficationIContents
Contract CC-34 (UG-5)
SECTION 1
DMRCNolume-410utlineDesign Specification
Contract CC-34 (UG-5)
SECTION 1
OUTLINE DESIGN CRITERIA
RAILWAY GEOMETRY, DESIGN LIFE AND LOADS
Section 1.1 - GENERAL, CODES AND STANDARDS
1.1.2 CODES
Subject to the requirement of this specification and other control documents all design work
will comply with the appropriate current standards issued by the lndian Railway
Standards(1RS) and Bureau of lndian Standards (BIS), or if such a standard does not exist,
then the appropriate current standard issued by the British Standard Institute (BSI) If
appropriate 'standard from BIS and BSI dose not exist, then subject to approval by the
engineer, an appropriate current standard from a reputable institution may be used. All
standards shall be that including Amendments and Addenda, current at the date of tender.
IRS - Code of practice for plain, reinforced and pre-stressed concrete for general
Bridge construction.
IRS - Code o f practice for the design of substructures and foundation of bridges.
(Part 5) Soundness
(Part 6) Measuring mortar making properties of fine aggregates
1986 Horizontally cast iron double flanged pipes for water, gas
and sewage ,
ASTM Standards
ASTM C-1202 Test methods for Electr~calindication of concrete's ability to resist chloride ion
penetration.
ASTM C-1240 Micro Silica fume In concrete
ASTM D-297 Methods for Rubber Products-Chemical Analysis
ASTM D-395 Compression set of vulcanized rubber
ASTM D-412 Tension testing of vulcanized rubber
ASTM D429 Adhesion of vulcanized rubber to metal
ASTM D-573 Accelerated aging of vulcanized rubber by the oven method
ASTM D-624 Tear resistance of vulcanized rubber
ASTM 0-797 Young's modulus in flexure of elastomer at normal and subnormal
temperature
ASTM D-1075 Effect of water on cohesion of compacted bituminous mixtures
ASTM D- 1143 Test method for piles under static axial comp. test
ASTM D-1149 Accelerated ozone cracking of vulcanized rubber
ASTM D-1556 In-situ density by sand replacement
ASTM D-1559 Test for resistance to plastic flow of bituminous mixtures using Marshall
apparatus
ASTM D-2172 Extraction, quantitative, of bitumen from bituminous paving mixtures
ASTM D-2240 Indentation hardness of rubber and plastic by means of a Durometer
ASTM D-3689 Testing method of testing individual piles under static axial tensile load
ASTM D4945 Test method for high strain dynamic testing of piles
ASTM E-I I spe&cation for wire clot'i; sieve for testing purpose
AASHTO Standards
AASHTO M6-81 Fine aggregate for portland cement concrete
AASHTO M31-82 Deformed and plain billet-steel bars for concrete reinforcement
AASHTO M42-81 Rail-steel deformed and plain bars for concrete reinforcement
AASHTO M54-81 Fabricated steel bar or rod mats for coccrete reinforcement
AASHTO M 57-80 Materials for embankments and sub-grades
AASHTO M 81-75 Cut-back asphalt (rapid-curingtype)
BS Standards
BS: 4395 (Part-2) High strength friction grip bolts and associated nuts and washers for
Structural Engineering Higher Grade
BS: 4447 The performance of pre-stressing anchorages for post-tensioned construction
BS: 4486 Hot rolled and hot rolled & processed high tensile alloy steel bars for pre-
tensioning of concrete
BS: 4550 Methods of testing cement
BS:4592 Industrial type metal flooring, walkways and stair treads.
BS: 4604 (Part-2) the use of high strength friction grip bolts in structural steel work. Higher
grade (parallel shank)
BS: 4870 approval testing of welding procedures
BS: 4871 Approval testing of welders working to approved welding procedures
BS: 4872 Approval testing of welders when welding procedure approval is not required
BS: 5075 Concrete admixtures
BS: 5135 Process of arc welding of carbon and carbon manganese steels
BS: 5212 (Part-2) Cold poured joint sealants for concrete pavements
BS: 5328 Methods for specifying concrete, including ready mixed concrete
BS: 5400 Steel, concrete and composite bridges
BS: 5400 (Part-4) Code of practice for design of concrete bridges
BS: 5400 (Part-6) Specification for materials and workmanship, steel
BS: 5606 Accuracy in building
BS: 5896 High tensile steel wire and stand for the pre-stressing of concrete
BS: 5950 (Part-2) Specification for materials, fabrication and erection: hot rolled sections
BS: 6105 Corrosion-resistant stainless steel fasteners
Bs: 6164 Safety in Tunnelling in the construction industry
BS: 6443 Penetrant flaw detection
BS: 6681 Specification for malleable cast iron
BS: 7079 Preparation of steel substrates before application of paints and related
products
BS: 7542 method of test for curing wmpound for concrete
BS: 81 10 Structural use of concrete
BS: 8301 (Section-5) Code'of practice for building drainage
OTHER PUBLICATIONS
Indian Railway Manual on Design and Construction of well and pile foundations
ClRlA Report 80 A review of instruments for gas and dust monitoring underground
ClRlA Report 81 Tunnel Water proofing
ClRlA Report 44 model code of practice for work ~ncompressed air
Swedish standard 05 59 00
PC1 STD-112-84
CRRl and IOC, New Delhi Bituminous Road Construction Hand Book
MORTH -Specifications
CPWD-Specifications
RAILWAY ALIGNMENTS
1.2.1 General
1.2.1.1 The horizontal and vertical alignments of the railway are given in the Drawings as listed in Tender
Drawings, Volume 6 of Tender Documents.
1.2.1.2 The Corltractor shall design the civil engineering works to these alignments. However, subject to
the provisions of the Contract, changes to the given alignments may be permitted to suit the
specific characteristics of his design at no extra cost to the employers subject to prior approval of
the Engineer.
1.2.1.3 While fixing the design alignment of tunnel, due care of the cant to be provided on curves shall be
taken.
1.2.2 Minor Deviation in Alignment
Minor deviation horizontal/vertical alignment may be permitted with prior approval of the Engineer
subject to conditions stipulated in Para 3.2 of Employer's requirements - Functional.
1.3.1 General
1.3.1.I The Railway Envelope is defined as the extent of works to be constructed to allow installation and
operation of the railway equipment.
1.3.1.2The Contractor shall be responsible for the design, of a first stage primary concrete in the bored
tunnel. The Track work Contractor will undertake the design of the secondary concrete, track
slabs and track work to conform to the design.
1.3.1.3The design of all railway operating equipment, including signals and signalling cables, the traction
power electrification equipment, telecommunication links, etc. that are required for the railway will
be undertaken by others under contracts with the Employer.
1.3.1.4The requirement for interfacing with Designated Contractors are defined in Volume 3,Employer's
Requirements, Appendix 2D. The Contractor will design, provide and install cable ductslconduits,
hangers and cable trays for the Designated Contractors' equipment. The extent and detail of
such provisions are to be determined by the Contractor through interface co-ordination with the
Designated Contractor.
1.3.1.5Setting out
The Contractor shall provide permanent survey monuments and shall provide full details of co-
ordinates and levels to the Track work Contractor.
1.3.1.6Second pour concrete
The Track work Contractor will carry out the second pour concrete for the track work. In this
regard, the Contractor shall include location and design of starter bars, stirrups and rough surface
in the primary concrete pour to facilitate anchorage of the second pour concrete if so required.
The Contractor shall design drainage pipes, channels and catch basinslsumps to be in the first
pour or structural concrete.
1.3.2 Railway Cross Sections and Structure Gauges
1.3.2.1 The Kinematic Envelope for the rolling stock of the railway, and Structure Gauges for straight and
curved track will be confirmed by the Engineer.
13.2.2 The Tunnel design shall ensure that the proposed size is,adequate to contain the equipment,
required under Clause 1.3.1 above, outside the Structure Gauge.
1.3.3 Clearances
Structures shall not infringe the clearances specified. See also Clause 1.3.2.2above.
1.4.1 General
Clauses 1.4.2 to 1.4.6 below define the design life and serviceability requirements for the various
elements of the structures.
c
The design life of a structure is that period for which it is designed to fulfil its intended function @2
when inspected and maintained in accordance with agreed procedures. The assumption of a
design life for a structure or component does not necessarily mean that the structure will no
c
longer be fit for its purpose at the end of that period. Neither will it necessarily continue to be f-, ,
serviceable for that length of time without adequate and regular inspection and routine
maintenance.All Design Life criteria shall be confirmed.
'-\
1.4.2 Civil Engineering Structures According TO Relevant Codes but not less than :
Micro silica shall conform to ASTM C 1240, latest edition and/or IS 15388:2003. Additionally,
Microsilica from sources of proven credentials of use in major infrastructure projects shall only be
- permitted. Further, such-Microsilica shall be procured only from manufacturers having own
production facilities andlor those who' have bonafide process controls over the production. All
sources for Microsilica shall be approved by Engineer. Nothing extra is payable to the Contractor
in case of addition of Micro silica or any cementitious material in the approved Design Mix to
achieve the specified parameters / proportions of concrete specified in contract or as proposed by
contractor to meet his design parameters.
1.4.3 Deleted
1.4.4 Minimum Concrete Cover
I Soffit
Station Box Base Slab
TOP
Slabs
TOP
I Soffit
I Beams
Side Soffit
I Columns
1.5.1 General
The railway loading applied to structures on the Project shall be as per "Modern rolling stock"
type, with the two following axle configurations as in figure 1.5.1. Dead loads shall be used that
are in accordance with IRS Bridge Rules and IS 456 (for buildings) and IS 875-1 for unit weights
of materials.
Note that the loading due to Rolling Stock may be modified after the proposed rolling stock design
has been finalised. The design vehicle is shown in Figure ,I
.5.1.
For the purpose of computing stresses anti deformations, the following loads and consequential
effects shall be taken into account as applicable.
. .
Dead loads DL
Live loads LL
Dynamic effects Dl
Forces due to curvature or eccentricity of track CF
Temperature effects T
Longitudinal forces LF
Racking forces RF
Forces on parapets
Wind ,pressure effect WL
, Earth Pressure EP
Water Pressure WP
-.
Forces and effect due to earthquake EQ
Erection forces and effects DEL
Buoyancy B
Differential settlement DS
(AASHTO) LRFD guidelines. They shall resist the effect of the worst combination.
FIGURE 1.5.1 "MODERN ROLLING STOCK LOADING FOR THE METRO CORRIDOR
Configuration (alternative - Ij
a = 2250 mm
b = 2500 mm
a = 2605 mm
b = 2290 mm
c = 12310 mm ------------ (2a+2b+c = 22100 mm)
Track: Load due to 60 Kg (LIIC) rails and guard rail and fittings
Track bed: RCC blocks or concrete pour or precast slabs in RCC with inserts and fittings in
case of ballastless track (450 to 600 mm thick).or PSC sleepers over 2501300 mm of ballast
for ballasted track.
Other loads: As per Indian Railway Standards (IRS) and Bureau of Indian Standards (BIS)
Fatigue Loading:
The nominal loading for the design of members in accordance with BS 5400: Part 10 shall
comprise trains with six individual cars each heving four axles, the axle loads and vehicle
lengths will be provided by the Rolling Stock Supplier. The fatigue loading shall be
applied in accordance with the requirements of BS 5400: Part 10 in conjunction with the
projected annual tonnage's of rail traffic per track.
Dynamic Loading:
Coefficient o f Dynamic Impact (CDA): lmpact factor for longitudinal analysis shall be 1.2 while
for transverse analysis the same shall be 1.67.
Dynamic loading shall not be applied to piles, pile caps, centrifugal loads or
brakingltraction loads.
Longitudinal Loads:
Longitudinal loads from braking and traction shall be 18% and 20% of live load per track.
When a structure carries two tracks, both tracks shall be considered to be occupied
simultaneously. Traction forces shall act on one track and braking forces acting on the
other, with both acting in the same direction simultaneously to produce the worst loading
condition.
Longitudinal forces acting on the track shall be considered to be dispersed through the
track before being transmitted to the substructure. This shall be calculated based on IRS
Bridge Rules, IS Codes and relevant BS Codes. . ... -
Provision shall be made for effect of horizontal and longitudinal forces in the rail,
especially in the girders with ballastless deck.
Additional permissible stresses while considering this contingency will be proposed by the
Contractor for review by the Engineer. Forces shall be calculated for continuous welded
rail with a rail structure interaction resulting from temperature differential of rail and
concrete.
Longitudinal forces shall consider the effects on stability and safety arising from a broken
rail in ballastless track.
Centrifugal load
Train Derailment Load:
As per latest Design Code ACI 358.1R-92, for derailment check, derailment load
corresponds to the application of 50% of one coach weight, applied horizontally as a 5m
long uniform impact load. This 'DR" -load corresponds to an ULS load. For SLS
combinations (Group V), a 111.75 coefficient will be applied to the DR load.
I
1.5.6 Temperature Loading
(Not used)
1.5.7.1 Guidelines:
1. For all buried structures an incremental dynamic load should be applied using the methods
outline in Section 1.5.7.2. For the purposes of implementing this method a design seismic
coefficient of 0.1 125 shall be adopted at ground level linearly reducing to 0.056 at 30 m depth as
permitted by Code. These coefficients already include the Importance Factor of 1.5 required.
2. Perform a seismic racking analysis using the procedures outlined in Annexure-I based on an
Operating Design Earthquake (ODE) level event.
3. Consider the worst case loading condition from 1 and 2 to produce an envelope of seismic effects
on the structure. Combine these effects with other appropriate design loads using the load
combinations suggested in Section 1.5.3.
4. As it is not specifically required by the IS 1893 or ODs, a seismic racking analysis for a higher
level (MDE) event need not be undertaken.
5. Owing to the fact that the design level earthquake implied in the Indian Code and ODs is likely to
be exceeded, ductility reinforcement in accordance with the provisions of IS 13920 is considered
necessary to ensure adequate performance during a severe earthquake event.
7. On the basis of the lower level design earthquake implied in the Indian Code and ODs it is
considered that rigid connections at transitions and interfaces are adequate. Such connections
should be designed for the axial loads likely to be developed during seismic ground motions and
should be detailed in a ductile manner.
1.5.7.2 INCREMENTAL DYNAMIC LOADS ON BURIED STRUCTURES
ground ring degrees of flexibility. Based in this work it has been shown that for very flexible walls
where the deflection exceeds approximately.0.5 % of the height of the wall the solution of
dynamic pressures tends towards those suggested by Mononobe and Okabe which were based
on the assumption that a full active wedge develops behind the wall. For buried structures it is
unlikely that such an active wedge will form and it is therefore recommended that solutions based
on rigid retaining walls as developed by Wood are used. The Bulletin of The New Zealand
National Society for Earthquake Engineering (Vol. 13, No. 3) recommends that for buried
structures with depths of fill less than or equal to the depth of the tunnel that the seismic load
increment be calculated based on the pressure distributions shown in Fig 7.1. The dynamic
increment should be added to static earth pressure loads based on at-rest soil pressures in
addition to water pressures and other imposed loads using appropriate load combinations given
in Section 1.5.3.
Fig 7.1- Elastic Dynamic Earth Pressure Increment for Rigid Retaining Walls
The dynamic load increment should be considered in the design of underground structures in
such a way as to increase the earth pressure acting on each side of the structure so that the
forces are in equilibrium. This load combination is therefore only used to establish the local
effects of dynamic earthquake loads and not to determine the racking behavior of the structure. It
is recommended that racking behavior be considered using the free-field deformation approach
discussed in Appendix 1.
Given that IS 1893 permits reduction of the seismic coefficient with depth with the values 30m
depth being half the value at the surface level it is considered appropriate to adopt an average
seismic coefficient, C, , for calculating the dynamic incremental load. This average value should
be based on the value at a level HI3 from the top of the tunnel where H = Depth of tunnel. Thus if
the tunnel is 6m high with 5m if soil cover then the appropriate seismic coefficient used in
calculating the dynamic earth pressure increment is the value corresponding to 5+6/3 = 7m below
the ground level. Interpolating between the value of 0.1 125 at the ground level and 0.056 at 30m
depth results in an average seismic coefficient in this ease, C,= 0.099.
Where cover depths over the tunnels are significantly greater than the height of the tunnel
alternative methods of analysis for obtaining the dynamic earthquake load shall be used
Ground Surface
. .. - ........ .. .- ..- ~ .--. . .- . - . - ---- - ... . - . ... . . ... . -
: .. ..-,,-... ~.
.
' 1..
0.5CoyH
The weight of all permanent and temporary materials together with all other forces and effects
which can operate on any part of structure during erection shall be taken into account. Allowance
shall be made in the design for stresses caused in any member during erection.
Provision shall be made for the effects of shrinkage and creep of the concrete in the structure.
Guidelines in ClRlA (Early Age Thermal Crack Control in Concrete) and BS 8007 may be
followed.
Consideration of the forces resulting from differential settlement shall be made where the nature
of the chosen foundation system and the ground conditions indicate that such a condition may
arise. Where soil analysis is not carried out the following settlement values between adjacent
supports shall be adopted:
a 10 mm Long Term Settlement
-.
Live loads shall generally follow the requirements of National Building Code and IS 875, except
where the loadings given below are more severe.
Platforms and Ticket Hall 5.0k~/m', or a concentrated load of 15kN on a square area of
300mm side, whichever is more onerous (see note 1 & 2
below).
SERVICES BUILDING
Constructioil Load (on tunnel & station box) : 10 kPa on concourse level with no finishes
allowance, with 2 kPa on roof slab and loads from temporary
deck (dead load+ live load)
Traffic live load (on tunnel & station box) : 20 kPa (fill depth greater than 1.3m,otherwise
also check for design vehicle of a 70 tonne tank over an area
of 2.9mX 3.6m
r
--
Equipment
-
1. 33 kV Switch board
(1 No./substation)
A minimum 10 kPa udl has to be applied, unless individual loads exceed this.
-
Note : 1) The design of the station structure shall take into account the dimensions and weights of the
actual equipment to be used.
2) In the design of the station structure due account shall be taken of all loadings resulting from
the method and route to be taken for the installation and subsequent removal and
replacement of the various items of plant and equipment.
VOLUME -4
SECTION 2
SECTION 2
OUTLINE DESIGN CRITERIA
GEOTECHNICAL, FOUNDATIONS AND TUNNEL WORKS
Section 2.1 - GENERAL, STANDARDS AND CODES
2.1 .I.Purpose and Scope
The purpose of this section of these Design Criteria is to establish the minimum
requirements for geotechnical site investigations, studies, analyses, and preparation of
geotechnical reports and the design recommendations for earthworks, foundations,
structures, and substructure design, and the design for bored and cut and cover tunnels for
the Delhi MRTS.
"Geotechnical works" shall mean foundations, earthworks, deep excavations, slopes.
embankments and earth retaining structures.
The Contractor shall be responsible for determining for his design purposes the Geology and
the Geotechnical parameters of the sub-surface strata along the route.
The Employer will make available to the Contractor, for information only, the Geotechnical
Investigation Report prepared by others. The accuracy or reliability of these reports supplied
by the Employer or Engineer in connection with the contract is not warranted. These shall be
supplemented as necessary by additional boreholes as required by the Contractor.
2.1.2 Codes, Standards, and Regulations
The principal'standards listed below shall be complied with. as amended by these Criteria.
The version of the standards, codes, and regulations shall be the latest version and with latest
amendments.
Indian Standards
SP 36 (Part 1) Compendium of lndian Standards on Soil Engineering
(Laboratory Testing)
SP 36 (Part 2) Compendium of Indian Standards on Soil Engineering (Field
Testing)
IS 1080 (986)
I Code of Practice for Design and Construction of Shallow
Foundations on Soils.
IS 1200 (Part I ) Methodology of measuiement of Building and Civil
Engineering Works.
IS 1892 Code of practice for Sub surface investigations for
foundations.
IS 1904 Design and construction of foundations in soils - General
Requirements
IS 2386 Methods of Test for Aggregates for Concrete.
(Part 1 to Part 8) 1963 I
IS 2911 (Part 1) 1979 : Code of Practice for Design and Construction of Pile
Foundations. '
IS 3067 (1988) Code of Practice for General Design Details and Preparatory
Work for Damp-Proofing and Water-Proofing of Buildings.
British Standards Institution
BS 812: 1985/1988 : Testing Aggregates (Parts 117 to 119)
Major structures (viaducts, bridge and crossing structures, bored tunnels, cut-and-cover
tunnels, portal structures, retaining structures, stations, commercial developments,
\
Contract CC-34 (UG-5)
acceptance.
All Consultants-produced laboratory test data shall be prepared using internationally accepted
standards e.g. AGS format, latest version. All data shall be provided in both printed and
electronic file formats. All testing shall be conducted by laboratories holding current
accreditation under International Standards OrganisationIBureau of Indian Standards.
2.2.5 lndexlClassification Testing of Soil Samples
All indexlclassification test procedures for soils shall comply with the requirements of IS
2720lBS 1377. Tests shall include the determination of natural moisture content, specific
gravity, particle size distribution (with and without hydrometer), Atterberg limits, insitu bulk and
dry density, and dry density and moisture content relationships.
2.2.6 Strength Testing of Soil Samples
Strength-test procedures for soils shall include single- and multi-stage, consolidated-drained
and consolidated-undrained triaxial tests; unconsolidated undrained triaxial tests; laboratory
vane shear tests; and pocket shearmeter tests, all according to IS 2720 (Part 11). Unconfined
compressive strength testing for soils shall be according to IS 2720 (Part 10)IASTM D2166,
and consolidated drained direct shear testing shall be according to IS 2720 (Part 13)lASTM
D3080.
2.2.7 Consolidation Testing of Soil Samples
Consolidation. test procedures for soils shall be based on one-dimensional, consolidation
methods according to ARE 2720 (Part 14) or Clause 3 of BS 1377: Part 5, with some minor
modifications as accepted.
2.2.8 Permeability Testing of Soil Samples
Laboratory test procedures of soil permeability shall include constant-head permeability
methods for granular soils, generally according to IS 2720 (Part 17 or 36) or ASTM D2434,
and variable-head permeability methods for cohesive soils, generally according to Soil Testing
for Engineers by T. William Lambe. Permeability of insitu materials shall be measured by
constant-head or variable-head methods, using standpipe piezometers installed during the
ground-investigation programme.
2.2.9 Chemical iesting o f Soil and Groundwater Samples
.. ..
Chemical te'st'"'p@cP;dures' foi" 's6ilP' an&-.?groundwater. shall include, as appropriate:
determinations of resistivity, redox potential, pH, chloride ion content, sulphate ion content,
total sulphate content, total sulphide content, organic content, and carbonate content.
according to IS 2720 or BS 1377 or BS 812, or both, and identification of other potentially
corrosive conditions.
2.2.10 Testing of Rock Specimens
All rock testing shall be according to IS or ISRM suggested methods. Tests shall include the
determination of natural moisture content, porosity, density, adsorption, unconfined
compressive and tensile strength, strength of rock joints, mineralogy, and special tunnel
*
boring machine (TBM) boreability testing.
GENERAL
2.7.1 Method Statement
The Contractor shall prepare and submit to the Engineer for his consent, a detailed design
report including calculations, schedules and drawings for tunnel construction, prior to the
commencement of such works. Additional information shall be supplied upon request of the
The Engineer. The Report shall explain the basis of the design, design assumptions, and
design parameters of all civil and structural works to be undertaken.
The Contractor shall prepare a method statement presenting full details of the design, the
materials, equipment, plant and operations involved in the construction of bored and cut-and-
cover tu~lnelsand submit io i h Engines;
~ as part of the Design Report. The Contractor shall
ensure that ground movements and changes to the piezometric pressure which may affect
adjacent railway tracks, subway, utility services and any adjacent buildings, surface or
underground structures are kept to a minimum.
2.7.2 Types and General Methods of Analyses
The running tunnels shall comprise twin single-track tunnels minimum one tunnel diameter
(external) apart. This Criterion may not apply in areas of poor ground, where greater clear
distances may be necessary.
The top of rail alignment is shown on the Tender plan and profile drawings. Tunnels shall be
either circular or horseshoe shape depending on the method of construction chosen.
The Contractor shall be responsible for the safety and security of excavations at all times
during the execution of the Contract. The Contractor shall present to the Engineer details of
his proposed methods for excavation, and spoil removal. No excavation shall take place until
the Employer Representative's consent has been obtained.
Excavation shall be carried out in a uniform and controlled manner, over-cutting shall be kept
to a minimum. In water-bearing strata the Contractor shall use such methods and take such
steps as are necessary to control flows and maintains the stability of the excavation.
Where the Contract specifies limits to surface settlement and/or protection i n respect of
existing service or structures, the Contractor shall provide calculations demonstrating that the
method of excavation will result in compliance with those requirements. Details of the
monitoring arrangements that are proposed for the recording of movements and the
verification of the degree of any settlement or damage to services'or structures shall be in
accordance with Standard.
Bored tunnels for the Metro Corridor will be in rock and soil and will be excavated mainly
using tunnel boring machines. Initial tunnel support will generally include precast concrete
segments, shotcretelwire mesh, rock bolts, lattice girders, steel sets, or forepoles wherever
necessary.
Geometries and stability of rock wedges affecting ltunnel support requirements, including
completely /highly weathered rock with controlling remnant rock jointing or other structure,
shall be determined analytically, generally using stereographic projection, finite element
method or vector methods. Analyses shall consider planar sliding along individual joints and
block sliding, or fallout, along joint-set combinations. Analyses shall provide for both static
and dynamic loading conditions.
Design Considerations
An ultimate load limit state method such as IS 456 or British Standard 8110 shall be used for
the design of all permanent underground concrete structures.
The method of analysis of the permanent lining shall take into account the proximity to the
face at the time of installation and the potential for additional ground loads as the face
advances.
The design method for the analysis of the bored tunnel linings shall take into account the
interaction between the lining and the ground, the deflection of the lining and the redistribution
of the loading dependent upon the relative flexibility of the lining, the variability and
compressibility of the ground. The method of analysis shall confirm Compressibility of the
ground, durability aspects that shall include impermeability, electrical resistivity of concrete,
ASR resistance and sulphate resistance to the guidelines of the International standards.
Where permanent secondary lining is installed inside a temporary primary lining, the ground
loads used in permanent lining design shall consider all loads as described in Subsection
2.7.4 and any additional ground loads from time-dependent ground strains. If the life of the
temporary lining is less than the design life for the Project then the Contractor shall design the
secondary lining ignoring the contribution of the temporary support for structural purposes.
Due account' shall be taken of the degree of flexibility of the linings to be used in the various
soil conditions and taking account of the size, prox.imity, timing and method of construction of
adjacent excavations. The inherent lining flexibility may have to be reduced in order to
maintain acceptable values for the deflection of the lining.
The soil investigation undertaken by the Employer shall not be relied upon to provide
adequate information concerning the nature of the ground to enable the Contractor to fully
develop comprehensive method statements for tunnelling works and tunnel related activities.
In preparing his designs and method statements the Contractor shall carry out his own
assessment of the adequacy of the available geotechnical information, and shall indicate
where he considers such information to be deficient having regard to the particular works or
activities'to which the design or method statement relates.
The Contractor shall at his own expense conduct further soil investigations where his designs
or method statements identify that it is necessary or prudent to do so to enable him to identify
all foreseeable circumstances which may affect the execution of the works and to ensure that
there is no likelihood of meeting unexpected conditions of a critical nature.
If the Contractor intends to carry out additional ground investigation from the surface, beyond
the limits of the worksite, he shall make his own arrangements with landowners and occupiers
for the necessary access. He shall not assume that such access will necessarily be granted,
although the Engineer will provide assistance where it appears that this would be beneficial.
If surface access for ground investigation is not available, or if for any other reason there is a
significant likelihood of encountering geological hazards whose location is unknown, the
Contractor shall identify in his method statements the means by which such hazards will be
found as construction proceeds. The Contractor shall also identify how his tunnel design and
construction activities will be modified to recognise the deficiency of ground information prior
to tunnel driving.
During tunnel driving ground investigation data shall be kept under constant review and
reinterpreted as more detailed information becomes available, to maintain up to date
predictions of the ground likely to be encountered. This review shall be fully integrated into
the construction risk control and management systems and should typically include
b) probing ahead of and around the tunnel face, if the ground changes or expected to
change.
concrete.
Linings shall be designed to withstand all environmental loadings and effects without
detriment. In general, tunnel linings shall be designed to fulfil the following requirements and
to resist the following loadings.
Superimposed surface loads from traffic, existing structures over and adjacent to the
tunnel, and any specified future loads.
*
Soillrock, water, and seismic loads.
Railway loads.
(c) Loads from existing or known future adjacent structures above or within the area of
influence, which will remain in place above the tunnels, or any specified future loading.
The applicable foundation load shall be computed based on the height and type of
occupancy or use. For known future buildings, a minimum load based on a dead and
live load of 50 kPa at the foundations shall be used.
-.
(d) Additional support, ground treatment or additional lining thickening shall be provided
unless it can be shown that adequate provision already exists. Non-DMRC structures
shall not be supported directly by the tunnel lining.
(e) Where provision for a specific future structure is not made a minimum surcharge of 50
kPa at the existing or design ground level.
(f) Hydrostatic pressures ignoring pore pressure relief obtained by any seepage into the
tunnel. Ground Water Table assumed to be 4m above the maximum water level
observed i n the past 20 years from Central Water Commission i n the vicinity o f
the site.
(g) Loads and load changes due to known construction activity in the vicinity of the tunnel,
(h) The design of the tunnel linings shall take into account the proximity of the tunnels one
to another, the sequence and timing of construction and the proximity of adjacent
structures and utility services.
2.7.6 Flotation
For flotation check, the water table is assumed to coincide with the Ground level.
Where the bored tunnels are relatively shallow they shall be checked for the possibility of
flotation due to differential water pressure at representative typical locations.
The Contractor shall include in the design of the bored tunnel structures suitable methods for
countering the uplift due to displaced water .
2.7.7 Heave and Settlement
All tunnel designs shall be checked against flotation and heave in accordance with the
methods specified above. Wherever these checks indicate a critical case the Contractor, at
shall carry out a more rigorous analysis. Such analysis shall clearly show the factor of safety
achieved by the design and shall be to the consent of the the Engineer.
2.7.8 Tunnel Lining
The permanent tunnel linings shall be bolted segmental precast concrete, except in case of
cross-passages, enlargement of tunnel and junction of cut &cover and bored tunnel where
cast-in-situ lining shall be used.
Alternative types of lining may be proposed subject to the consen: of the The Engineer
The Contractor shall take into account, inter alia, the following when considering the design of
lining : -
(a) The internal diameter shall take account of the need to accommodate the Structure
Gauge, and the track bed arrangement to be provided by the Trackwork Contractor.
(b) Due allowance for relative movement between tunnels and cut and cover structure as
described in Subsection 2.8.11.
(c) The stiffness of the lining shall be sufficient to limit the maximum allowable deflection to
on radius to 25mm.. The distortional loads adopted shall also take account of the
speed of reloading of the horizontal and vertical groundpressure and in the case of the
shallow tunnels, the ability of the ground above the tunnel to generate sufficient passive
resistance to maintain stability of the lining.
(d) Stresses induced by grouting.
(e) The reinforcement for segmental concrete lining shall be detailed such that no electrical
continuity will exist across the circle joints. To prevent the stray current effects and to
inhibit the corrosion, Microsilica shall be added in to concrete (minimum 5% by the
weight of cement). Such concrete shall be tested in accordance with ASTM C 1202 and
DIN 1048. RCPT value shall not exceed 1000 coulombs and water permeability shall
not be more than 10 mm. However, reinforcement for in situ concrete lining or other
structures shall be bonded to mitigate stray currents. Similarly SGI lining segments
shall be bonded to mitigate stray current effects. The bonding will be part of the
(a) a segment shall be considered as a short column subjected to axial load with a load
factor of 1.4 applied to all loads. The design of the segments shall be adequate for all
temporary loads during stacking, lifting, erection and impact.
(b) the width of segments shall suit the method of construction and shall nct be so large
that part shoving of the shield becomes a geneiai necessiiy.
(c) the width of segments shall be consistent with the capacity of the circle bolting
arrangements to withstand the shear forces induced in linings built with staggered
joints.
(d) the lengths of segments shall be chosen with regard to bending stresses during
. handling and erection and the long term stresses due to deflection and thrust. In the
design for handling and erection a safety factor of 5.0 shall be applied to the self weight
of the segment combined with zero axial load.
(e) opening of longitudinal joints
(f) the design of linings shall include suitable taper rings in order to negotiate the
alignment curvature and to correct for line and level during construction with the
minimum use of circumferential joint packers consistent with attaining the required
degree of water tightness of the tunnels; see Subsection 2.7.18 below.
Drilling for fixing at pre-determined points on the lining may be permitted.
Grout holes shall be provided in segment as per design excluding the key, and shall be of a
nominal 50 rnrn diameter.
2.7.12 Conventional Tunnel Lining
Arch girders, base plates, ties and connections shall be formed from steel conforming to
Standards. Arch girders shall be rolled to suit the dimensional requirements of the approved
design.
The Contractor shall provide dimensional details of the arches, calculations regarding
imposed loads and design and such other information.
Spiles, Dowels and Rock bolts
Spiles shall be steel rods or tubes of diameter not less than 25 rnrn of steel.
Rock dowels shall be untensioned steel bars threaded at one end and provided with a face
plate, shim plates and a conical seated washer and nut, or split or deformed steel tubes, or
glass fibre reinforced resin rods.
Rock bolts shall be tensioned bar manufactured out of one of the followings : solid steel bar,
slit or deformed steel tube, glass fibre reinforced resin rods.
Alternative materials shall be subject to the consent of the Engineer incharge.
Sprayed concrete
Materials for sprayed concrete shall comply with Concrete Materials 'section of the
Construction Specification.
Cavity grouting
General purpose cement grout with suitable admixture shall be mixed in accordance with the
proposed design mix and purpose of use. Grout shall be used within one hour of mixing.
2.7.13 Tunnel Boring Machine (TBM) and Shields
The Contractor shall be fully responsible for the selection, design and supply of tunnelling
machines, shields and backup equipment. The TBM shall also meet all the requirements as
specified in Employer Requirements and Outline Construction Specification.
Tunnelling machines shall be robust with adequate safety margins for the anticipated duty,
designed and manufactured to comply with all safety standards.
The Contractor shall submit to the Engineer incharge for his consent, a programme for the
provision, factory inspection, testing, transport, erection and commissioning of each TBM or
shield. The Engineer's consent does not, however, absolve the contractor of his responsibility
to use appropriate equipment and complete the work as scheduled.
New or reconditioned machines shall be assembled at the manufacturer's works on
completion of fabrication or modification and tested to demonstrate that all components
operate correctly before the Employer or his authorised representative. Test running will also
be required at site following assembly, prior to commencement of tunnel driving.
The Contractor shall ensure that all key personnel who are responsible for the driving,
maintenance and control of the machine have received the necessary training in the duties
that they are required to perform. Such training shall include emergency procedures.
r
The Contractor shall provide and maintain a complete list of the names of persons and their
duties, responsible for the operation of the machine, who have completed the appropriate
The cross passage lining shall be in-situ concrete lining designed generally in accordance
with the requirements of the above Clauses with the following exception that the maximum
allowable deflection on radius shall be 15 mm.
The junctions with the running tunnels shall be steel framed and encased with in situ,
concrete. The junctions shall be designed to support fully the running tunnel linings at the
openings together with the ground and groundwater loads on the junction itself, and maintain
the specified water tightness of the tunnels.
Where openings are to be formed in running tunnels having segmental concrete or SGI linings
temporary .internal supports to the running tunnel lining shall be provided. These supports
shall adequately restrain the lining such that on completion of the cross passage and removal
of the temporary supports the total deflection of the lining does not exceed as described
above.
2.7.19 Sumps i n Running Tunnels
Sumps shall be located at every low point within each running tunnel.
Wherever practicable the vertical alignment shall be chosen such that the locations of sumps
avoid critical sections where their construction could have an adverse effect on adjacent
structures.
The size of each sump shall take account of the anticipated rate of-flow into the sump, the
priority rating, the number and types of pumps to be installed and the reserve capacity
required above alarm level.
The reserve capacity of a groundwater seepage sump shall be calculated on the basis of the
area of tunnel lining applicable to the sump in accordance with the following formula.
VR = A*v*~*F.o.s.*Io"
Where,
VR = Volume of reserve, m3
A = Tunnel lining area, m2
v = Maximum leakage rate, llm2/day
t = Maximum response time, (day)
F.0.S = Factor of Safety
.-..For.runningAunnel low point sumps the response time 't" shall be 24 hours and the factor of
safety shall be 1.5.
The sump design shall include outlets for the longitudinal drain pipe and discharge mains.
pumps of suitable capacity and power connection. Sumps shall be fitted with steel covers and
provided with step irons or access ladder as approved. Permanent discharge mains shall be
installed as well as embedment of conduits for permanent electric power cables to the pumps.
The Contractor shall investigate the overall capital cost and running costs and feasibility of
either installing the discharge mains to the station or a direct pumping main through a
borehole to the surface and submit his recommendation for consent. The layout shall be such
as to facilitate easy removal & replacement of pumps.,
The linings of the sumps shall be designed for the appropriate ground and groundwater loads.
The design and construction of the junctions with the running tunnel linings shall be in
accordance w~ththe general requirements of these Outline Design Specifications.
2.7.20 Ground Treatment and Temporary Support
For all bored-tunnel sections, a plan shall be prepared, based on all of the available data, of
the anticipated need for and methods of providing the following.
Ground treatment at break-in Ibreak-out locations
Ground treatment in advance of the tunnel excavation.
Temporary support during tunnel excavation.
This information and the assumptions on which it is based shall be shown on the design
drawings. The effect of tunnelling activ~tieson structures located above the line of the tunnel
shall be determined and any remedial action necessary to minimise the settlement of these
structures shall be implemented prior to tunnel excavation.
A detailed materials and workmanship specification shall be provided for the use, if any, of
shotcrete, or rock bolts, or both as part of any finallpermanent liner or support system for
tunnels.
2.7.21 Tunnel Emergency Evacuation Walkway
The Contractor shall be responsible for the design, provision and installation of a tunnel
emergency evacuation walkway throughout bored and cut and cover tunnels. The location of
the walkway shall be determined to provide a generally continuous walkway to permit
emergency evacuation at any point in the tunnel. For a tunnel linking a side platform station to
a central platform station the tunnel walkway can only provide continuity at one end. At the
other end a fixed stairway shall be provided to track level to enable maintenance staff to cross
the track to the platform end steps.
The walkway shall provide a durable non-slip surface set to a fall away from the track at the
same level to the platform. The walkway shall be minimum 750 mm wide and provide a
750mm wide X 2000mm high walkway space clear of fixed equipment. The detail of walkway
is specified in tender drawings (Volume 6).
The Contractor shall liaise with the Designated Contractor to determine the setting out
dimension from track centre line.
The design shall perm~tmaintenance access to tunnel services mounted below the walkway
and allow for ducts andloipipes to'pass~fiombelow to above walkway level without impinging
on the 750mm clear width.
The walkway shall be designed for a uniformly distributed load of not less than 5.0kNlm2 and
shall be securely fixed to resist the effects of passing trains and movement of passengers and
emergency services personnel. The design life shall not be less than 50 years.
Metal components such as bearers or handrails shall be provided with stray current corrosion
protection as required. Particular attent~onshall be paid to step voltage from the Rolling Stock
to earth for the protection of passengers.
(vii) any particular difficulties that special plant might meet with in respect of access,
clearances and working space;
(viii) the noise levels produced;
(ix) control over heave, swell, piping and instability of the base of construction;
(x) the methods by which the completed structure shall be secured against flotation;
(xi) the method of waterproofing the completed structure:
(xii) Slope instability.
The following methods of construction shall be used in soft ground either individually or in
combination depending upon the particular requirements of the location, size and type of
structure.
Diaphragm Walling
Particular attention shall be paid to the stability of the reinforcement cage during placing,
methods for forming and locating box-outs, waterproofing of the vertical panel joints,
support of the walls during excavation and integrity and watertightness.
Secant PilinglSheet piling1Soldier piling
Particular attention shall be paid to the formation of piles to ensure their integrity and
watertightness, and to the support of the completed walls during excavation.
The method of construction to be followed shall be approved by the Engineer. Diaphragm
walling will be preferred for the station
2.8.3 Diaphragm Walling
General
The Contractor shall prepare and submit to the The Engineer for his consent a detailed design
including calculations schedules and drawings for each proposed diaphragm wall installation,
prior to the commencement of such works. Design should take into account the following;
Earth Pressure
Hydrostatic Pressure (Sround Water Table assumed t o be 4m above the maximum
water level observed i n the past 20 years from Central Water Commission i n the
vicinity o f the site.)
Decking Load
Surcharge.Load (A surcharge load of 24 kNlm2 shall be applied at ground level and
IRC loading at GL for Roof Slab)
Supporting Arrangements
Any other incidental load
Minimum grade o f concrete shall be M35.
Method Statement
The Contractor shall prepare a method statement giving the full details of materials, plant and
operations involved in the construction of diaphragm walls. This shall be incorporated into the
design submission for consent and shall include details of:
the formation of the joints between panels and installation of waterstops;
the method of producing the durable concrete with admixtures.
I
r
The Contractor shall check the cut and cover tunnels for the possibility of flotation due to k-
differential water pressure and shall design the structure such that adequate factors of safety
against flotation are provided as set out below. @z
During service stage analysis ground water level shall be assumed to be coincident f
with the Ground Level.
A load factor of 0.90 shall be applied to the self weight of the structure, including the first
stage only of the track concrete.
A load factor of 1.0 shall be applied to the weight of backfill material over the structure.
The overall factor of safety against flotation shall not be less than 1.05 and 1.10 for any
construction stage and after the completion of the Permanent Works respectively.
Suitable measures to counteract flotation forces for the Permanent Works shall be
incorporated in the Contractor's design. The me*ure(s) chosen shall suit the particular
conditions and the method of construction and may include: Integration of Dlwall with
structure;
Clauses 2.2.3,4.1 of Part I and 3.2.4 of Part 2 of BS 8110 shall be modified such that for
members exposed to earth and ground water, the calculated maximum crack width shall not
exceed 0.2 mm irrespective of whether any additional protections, such as waterproofing
membrane, are provided to the members at the exposed face of the structure. Provisions
shall be made to ensure that calculated width of cracks due to early thermal cracking is not
more than 0.2 mm. '
Walls and slabs of underground structures are USU~IIY thick. Therefore adequate
consideration shall be given to the risk of early thermal cracking and shrinkage effects. Micro
silica or any other suitable cementitious material confirming to relevant BIS codes shall
be used by the weight of cement in such manner that shall replace the cement quantity for
same grade of concrete to reduce the risk of early thermal cracks. This concrete shall serve
as a measure to reduce the thickness of walls & slab to minimise the risk of thermal cracks.
The designer shall ensure that any requirements considered appropriate such as cement
chemistry and curing methods are properly addressed.
2.8.8 Corner Details
Particular attention shall be paid to the corner joints of large structural members. External
walllslab junctions shall be provided with crack control steel and transverse ties. Radius of
bend of main tension bars shall be increased to cater for the high bearing stresses within the
bend.
2.8.9 Construction Joints
The design and detailing shall be such that the number of constructionjoints will be as few as
practicable and shall minimise leakage.
2.8.10 Slab to Wall Connections
For top down construction in particular, attention shall be paid to the practicalities of the
design and detailing of the slab to wall connections and the means by which the integrity of
the construction joints at these connections will be assured.
2.8.11 Connections between Bored Tunnels ICut and Cover Structures
Where bored tunnels are connected to cut and cover structures, the connection shall be
designed so that completion of the joint is carried out by the contractor for the cut and cover
structure. Design of the joint shall consider the possibility of differential movement, either
during backfilling or subsequently. Unless it can be shown that differential movement of the
bored tunnel and cut and cover structures will be sufficiently small not to cause overstressing
with a rigid joint, the joint shall be designed to permit an appropriate degree of rotational
movement. Particular attention shall be paid to the waterproofing detail, to ensure that the
watertightness of the joint is not inferior to the standard joint between precast tunnel
segments.
2.8.1 2 Base stability
The Contractor shall include in design adequate precautions against base heave in the clayey
silts during construction. The stability of the bottom of the excavation shall be checked in
accordance with an acceptable method of analysis. A surcharge of 20 k ~ l shall m ~ be allowed
for, applied at ground level to the ground surrounding the excavation.
The alluvial deposits comprising "Delhi Silt" are predominantly silt with Alwar sand horizons
and a variable proportion of clay. Silts are readily mobile under the action of water and are
thus susceptible to piping. The Contractor shall allow in his design adequate precautions
against piping and base failure where the alluvial deposits are to be exposed.
The Contractor shall show in his calculations the contribution made to the base stability of the
excavation by his proposed method of construction an4 shall state the factor(s) of safety used
in the design. The factor(s) of safety shall relate to the method of construction and to the
particular location of the Works and shall be subject to the consent of the The Engineer.
The Contractor shall check the stability of the completed structure against failure due to base
heave under the structure.
2.8.1 3 Waterproofing
Please refer Volume - 5 Outline Construction Specification, Section - 10.
2.8.14 Heave and Settlement
Heave and settlement between adjacent line structures shall be evaluated and due allowance
incorporated into the size of the structures and detailing of joints to ensure that the structure
gauge is not infringed within the design life.
The differential movements, including relative rotation, between structures calculated to take
place after track laying has been carried out shall not exceed the requirements of the track
design.
(v) Ground water loading, backfill and other imposed loadings such as surcharge and
highway loadings.
For the purpose of assessing ground pressures the underground station shall be regarded as
a rigid box structure subject to earth pressure at rest.
Temporary Ground Support shall be designed in accordance with the requirements of Section
2.9.
2.8.16 Design Principles
The method of construction for the cut and cover stations shall take into account the following:
(iii) The degree of settlement which would be expected. In this context the proximity of
the works to existing structures must be considered.
(v) Any particular difficulties that special plant might meet with in respect of access,
clearances and working space.
(vi) Control over heave and instability of the base of the excavation.
(vii) The methods by which the completed structure shall be secured against flotation.
12
Most structures in "poor" condition 5
Water-supply structures 5
Heritage structureslbridge structures 5
Above limits are maximum permissible, however this may have to restricted further if required
to avoid damage to the adjacent structure or causing discomfort to the occupants.
Along the proposed alignment, other limitations may be imposed at existing adjacent
structures, such as hospitals, school buildings, telephone-exchange structures, special water-
supply structures and Heritage structures.
Methods of reducing vibration, such as limiting explosive charge per delay or operating pile-
driving equipment at lower energy levels, may be required. The use of expansive agents or
mechanical excavation methods shall be required in place of blasting at certain critical
locations. In addition working hours for such equipments causing vibrations may have to
restricted, keeping the convenience and comfort of the occupants in mind.
INSTRUMENTATION AND MONITORING
2.9.8 GENERAL
The Contractor shall submit a complete comprehensive instrumentation scheme including
Real Time Monitoring with the Preliminary Design to achieve the following:-
1. Safety during and after the construction by providing early warning of any excessive and
undue ground movement of adjoining premiseslstructures/utilities.
I
2. To provide settlement, deflection and deformation data for the verification of initial design
of the permanent structures and the temporary works supporting excavations.
.. .
8. To suggest
... , <...
<.
preventive and remedial measures to be adopted to ensure that the various
-parameteriareke-ptwithin acceptable limits.
9. To suggest the frequency of the monitoring.
10. To suggest the method of data recording and report generation system for the use of the
contractor and The Engineer.
TYPES OF INSTRUMETATIONS
Instruments of robust nature shall be used which are capable of giving reliable data to within
the manufacture's tolerances over long periods measurement.
The Contractor shall establish suitable temporary bench marks for the purposes of monitoring
vertical movements. Such bench marks shall be outside the zone of influence of construction,
and shall be agreed with the Engineer .
Precise levelling points are to be provided on monuments at ground level to extend
-
commencement to enable a base line to be established. Monitoring will continue until such
time when it is mutually agreed that movement due to the works or ground treatment has
stopped or slowed sufficiently to be deemed negligible.
REVIEW LEVELS
a) Prior to the start of construction the designer shall assign predetermined review levels to
every instrument installed or to be installed at the site. There shall be three types of
review level: trigger, design and allowable.
b) The design level is defined as the highest or lowest (as appropriate) reading anticipated
based on the design. These are not to be exceeded during the works.
c) The trigger level is a reading at a predetermined level prior to the design level (for
example, 70% of the expected maximum stru! load, settlement or lateral deflection).
Remedial measures become effective when trigger values are exceeded.
d) The allowable level is defined as the reading at which the Contractor is considered to be
failing to comply with the maximum or minimum (as appropriate) levels consistent with the
requirements of the contract.
e) The values for the review levels' shall be proposed by the Contractor for the acceptance of
the Employers' Representative, and shall form part of the design.
f) During construction, the contractor may propose changes to the values selected as
review levels. Changes to the review levels will have to be justified on the basis of
observed performance, and shall be submitted for the acceptance of the Employers'
Representative.
g) If the reading on any instrument reaches the trigger level, the Contractor shall report to
the Employers' Representative with his review of the data obtained from that instrument.
If, as a result of the review, it is considered that the design level is likely to be exceeded,
the Contractor shall reassess the design and undertake such protection measures as are
necessary. If it is considered that the allowable level could be reached or exceeded, then
the contractor shall propose and implement remedial measures to ensure that the
allowable level is not exceeded.
h) If the reading on any instrument reaches the design level, the Contractor shall report to
the Employers' Representative with the review or the data obtained from the instrument.
The Contractor shall reassess the design and undertake such protection measures as are
necessary. If it is considered that the allowable level could be reached or exceeded, then
the contractor shall propose and implement remedial measures to ensure that the
allowable level is not exceeded.
i) If the reading on any instrument reaches, exceeds, or can be expected to reach, based
on existing trends, the allowable level, the Employers' Representative shall be informed
immediately. The Contractor shall immediately make the related part of the works safe,
and then cease work in that part of the work until remedial measures have been
submitted, accepted by the Employers' Representative and implemented.
FREQUENCY OF MONITORING
a) Sufficient time shall be allowed between installation of instruments and commencement of
relevant site activities to enable a reliable set of base readings to be established. These
time. scales are to be agreed with the Employers' Representative.
b) All instruments shall be connected to data logging equipment where possible so that
measurements can be taken on a continuous 24 hours basis. Data shall be accessible via
computers in the Employers' Representative site offices. An alarm system shall be
incorporated into the computer network, with the alarm being activated if gauge readings
exceed either the agreed trigger or allowable values. In addition to that, the excavation
works for the Stations & Shafts shall be monitored by applying On Site Visualization
(OSV) monitoring.
c) Reports of monitoring results shall be submitted to the Engineer within 24 hours. A
detailed graphical presentation of historical values of monitoring shall be submitted on a
weekly basis in a format required by the Engineer. All resultslinformation shall be
submitted on virus free 3.5 inch computer d i s k e f t e s l ~ ~The
. information on the diskettes
must be retrievable using Microsoft Excel software running on 1BM PC or compatible
systems. Where a greater frequency of monitoring is required than o n a 24 hour cycle, the
Contractor shall submit the reading taken directly at the site to the Engineer on the same
day.
d) All instruments shall, be suitably protected against accidental damage, vandalism and
adverse climatic conditions. Any damaged instrument shall be replaced immediately, with
a set of set of base readings being taken as soon after installation as possible.
The observations so recorded from the various instruments should be kept in such a
fashion, which can function as an evidence if required in any legal disputes and should
help the owner responsible for construction for framing their replies and other related
legal paper
The Contractor shall permit access to the site for personnel from academiclresearch
institutions duly approved by the employer so that they can collect relevant data for
making studies on performance of various: underground construction elements. The
Contractor shall make all such instrum$ntation data freely available to these
academidresearch institutions for academid<esearch purposes only.
2.9.9 Seepage Barriers
The contractor shall provide seepage walls or barriers to all external underground walls that
lie within public areas, staffrooms and plantrooms, except for pumprooms, ECS and Tunnel
Veniilation rooms, shafts and plenums. In the public area, the seepage barrier may be
provided by either a finished wall with air gap behind or by architectural finishes mounted on
framing attached to the external wall. In non-public areas a block or brickwork wall shall be
provided. In all cases the Contractor shall design the seepage gap with a seepage drainage
channel such that discolouration or water damage to the seepage walls cannot occur. Access
panels to inspect and maintain the drains shall be provided.
At platform level in the stations, the visual aspect of the platform walls must be aesthetically
pleasing and exposed diaphragm walls must be provided with a surface which will give a
uniform finish without distinct changes in colour or alignment. All external trackside
diaphragm walls must be either rendered or shotcreted or provided with another finish which
is acceptable to the Engineer.
The Contractor shall be responsible for the control of all ground movements and for any
resulting damage to buildings, bridges, tracks and roads. The Contractor's attention is drawn
to the General Conditions of Contract and Employer's Requirements relating to repair of
damage should any arise as a result of the Contractor's construction activities.
The Contractor shall take due regard of the presence of utilities over and adjacent to the
Works. The Contractor shall carefully and regularly monitor the ground adjacent to open cut
excavations and along tunnel drives to determine the rate and magnitude of any settlements.
Settlement shall be limited such that any individual structure or buildings shall not suffer
damage greater than "Slight" as defined in the Damage Classification Table 2.10.1.
Settlement to Important Structures, Bridges, and Heritage Buildings shall be limited to
"Negligible" as defined in the Damage Classification Table 2.1 0.1.
The general approach to settlement control and building protection shall involve the
procedures described below.
2.10.2 Minimising Ground Movements
Station boxes shall be constructed in such a way as to minimise ground movements through
immediate installation of support to the ground and to minimise the inflow of water. Care
should be exercised to ensure that over excavation does not take place.
Construction from the surface shall be undertaken with due regard to the settlement
associated with the particular method chosen. In particular, the following methods will not be
permitted:
1. Use of ground anchors beneath adjacent buildings.
2. Non-recoverable timber ground support
Ground water lowering by pumping is not prohibited by either the current Delhi Government
Laws or Regulations. However, the Contractor shall take adequate precaution in using this
method which shall only be used inside the station box or cut & cover tunnel after the walls
have been installed. Necessary approval will be required from Delhi Water Board who will
offer guidance on disposal of water.
2.1 0.3 Prediction o f Ground Movements
The Contractor shall obtain consent from the Engineer for his proposed methods of
supporting and predicting settlements adjacent to structures. Proven methods based on
practical experience shall be used.
The Contractor shall provide predictive assessments of the anticipated ground movements
when making submittal for consent of his proposed method of construction of particular
sections of tunnel.
I
Monitoring of ground settlement shall be carried out during construction by the Contractor, to
check that the ground is behaving as predicted. The Contractor shall submit for the Engineer's
consent a monitoring system and procedures to immediately detect movements as specified
in Appendix 15, Real Time Monitoring of Employer's Requirement, Volume-3.
The extent of monitoring of structures shall be carried out on a case-by-case day to day or
more frequent basis depending upon the assessment of risk of damage. Special attention
shall be paid to the historical buildings located along the alignment. Monitoring shall begin
prior to commencement of the Works to enable base-line values to be determined accurately,
and shall continue until all settlements due to the underground works, as shown by the
monitoring, has effectively stopped for a period of three months.
The Contractor shall make monitoring results available for inspection by the The Engineer at
the construction site offices.
On
.- services disrupted. . .