For NAGOYA
Bridge specifications
Project : Furukawa Viaduct,The New Meishin Expressway
Structure : (9~13)spans continuous box girder
Total length : 1,475.0m
Span length : 36.0m (average)
Effective width : 15.0m (average)
Horizontal
alignment : Rmin=700m
Segment configurations
Cast-in-place concrete
4700
Plan Plan
4640 7000 4485 4640 7000 4485
2320
145 ~1032 3590 560 5000 565 3590 145 ~1032 2320 1490 3590 560 5000 560 3590 1335
Cross-section Cross-section
transversal tendon
transversal tendon
1S21.8
1S28.6
1 2 3
19φ15.2 n = 12
Full-scale span test
Segment fabrication
Stock yard in the precast concrete factory
Erection Outline
Cast-in-place Concrete Slab
Erection Girder
Precast Panels
Core Segments
Pier Segment
Span-by-span erection
Setting of PC panels
Construction of cast-in-place concrete slab