Field Visit Report-132 KV TL Khar-August 05, 2019.
Field Visit Report-132 KV TL Khar-August 05, 2019.
Field Visit Report-132 KV TL Khar-August 05, 2019.
This report is made possible by the support of the American People though the
United States Agency for International Development. The contents are the sole
responsibility of Halcrow Pakistan (Pvt) Ltd and do not necessarily reflect the
views of USAID or the United States Government.
Independent Quality Assurance for USAID Stabilization Program Activities in FATA and KP
Field Visit Report
Document history
Independent Quality Assurance for USAID’s Stabilization Program Activities in FATA and KP
Field Visit Report: 132kV Transmission Line Timergara to Khar, Tribal District Bajaur
This document has been issued and amended as follows:
Project Title
IQA for USAID’s Stabilization Program Activities in FATA and KP
Visit Location(s)
132 kV Transmission Line, Timergara to Khar Grid Station
Visit Reference
110
S.
Name Designation & Responsibility Contact Information (Email / Mobile No.)
No.
2. SITE ACTIVITIES
2.1 Day 1: August 05, 2019
9:40 am - 03:20 pm
HPK field team visited the site of 132kV Transmission Line to monitor the ongoing
stringing activity at towers locations #102,103,104,105, and to inspect the
completed stringing at tower # 106,107,108,109,110,111,112,113,114,115
24 - - - - - -
Location# 104 (ZM-30+3M), (29˚-7’-05’’ LT), GPS Coordinates (34˚- 44.635’ N, 071˚- 33.047’ E)
Earth
Foundation Tower Back Span Welding and
Resistance Number, Phase
Tower Concrete Erection as per painting of
Measured & Danger Sign
Status Progress Progress Profile (m) Nuts Bolts
(Ohms)
100% 06.63 Ω 100% 245 - -
80KN Hardware for LYNX
Dampers Accessories
Material Insulator & Shield Wire
Installed Nos. SS-L SF-9 SB-L SB-9 MS-L RS-L
48 06 Set - 06 - - -
Location # 106 (ZM-60), (59˚-00’ RT), GPS Coordinates (34˚- 44.364’ N, 071˚- 33.098’ E)
Earth
Foundation Tower Back Span Welding and
Resistance Number, Phase
Tower Concrete Erection as per painting of
Measured & Danger Sign
Status Progress Progress Profile (m) Nuts Bolts
(Ohms)
100% 03.70 Ω 100% 286 - -
80KN Hardware for LYNX
Dampers Accessories
Material Insulator & Shield Wire
Installed Nos. ST-L TF-9 SB-L SB-9 MS-L RS-L
24 03 Set - 03 01 - -
24 03 Set - 06 02 - -
24 03 Set - 06 02 - -
40 05 Set 01 Set 05 02 - -
24 02 Set 01 Set 04 02 - -
24 03 Set 01 Set 06 02 - -
24 03 Set 01 Set 06 02 - -
24 03 Set 01 Set 06 02 - -
REMARKS:
Tower Location No. 102,103,104,105,106,107,108,109,110,111,112,113,114,115:
i. Installation of disc Insulators on tower location # 102,103,104,105 & 106 were
completed and installation / fitting of accessories were in progress.
ii. Stringing of ACSR Lynx Conductor in between tower locations
#107,108,109,110,111,112,113,114 & 115 was completed.
iii. Tightening of bolts and nuts of newly erected towers was in progress.
iv. Tower name, Phase & Danger sign plates as well as anti-climbing devices are
yet to be fixed on the structure.
(See Fig. 01 to 04)
Fig. 01. View of In progress stringing of ACSR Lynx conductor at Tower Location # 102
(ZM-60) (August 05, 2019)
Fig. 02. Stringing of ACSR Lynx conductor at Tower Location # 107 was completed
(ZM-30) (August 05, 2019)
completed
(June 21, 2019)
Fig. 03. Stringing of ACSR Lynx conductor at Tower Location # 110 was completed
(ZM-60) (August 05, 2019)
Fig. 04. Stringing of ACSR Lynx conductor at Tower Location # 113 was completed
(ZM-01) (August 05, 2019)
Fig. 05. The contractor’s staff working at Tower Location # 102 without using PPE
(ZM-60) (August 05, 2019)
Fig. 08. ACSR Lynx conductor left neglected at Tower Location #111
(ZM-30) (August 05, 2019)
Fig. 09. Inadequate ground clearance of ACSR Lynx conductor between tower location #112
& 113 (August 05, 2019)