Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

05 - 25 KV Traction Power Supply System - RailElectrica

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4
At a glance
Powered by AI
The key takeaways are that 25kV single phase is the most common voltage standard for overhead traction systems and different arrangements have been used to provide power to the Indian Railways network over time including purchasing from utilities and developing their own transmission infrastructure.

The different types of power supply arrangements for Indian Railways discussed are: 1) Purchasing 25kV power from utilities, 2) Owning the 25kV circuit breakers, 3) Taking 132/220kV power and converting within traction substations, 4) Owning the 132kV transmission lines, 5) Using Scott connected transformers.

Sectioning and paralleling posts are provided at neutral sections to extend feed from one zone to another during a power supply failure in one zone. They parallel the OHE of up and down lines and can bridge the neutral section after ensuring no power with bridging interrupters.

7/28/2019 25 kV Traction Power Supply System | RailElectrica

25kV Traction Power Supply System


Mahesh Kumar Jain August 31, 2013

25 kV Single Phase is the most preferred and universally accepted voltage standard for overhead traction system. Looking for any
other voltage system, means every things has got to be developed namely traction power supply system, Over Head Equipment,
vehicle traction system etc. In order to increase OHE voltage. 2×25 kV system is developed so that at vehicle level, the voltage remains
25 kV. Some Railways have preferred for 50 kV system but the same is limited to heavy haul dedicated rail system in which the
locomotive also remains confined in that territory only. There are not many suppliers of this traction system. Dedicated freight Corridor
project in India thought meant for heavy haul, but the locomotive has to work in DFC and IR territory, therefore, 2x25kV power supply
system is chosen.

25 kV Traction power system was designed, developed and demonstrated all over world by SNCF. Indian while
completing electrification of HWH-Bardwan section of Eastern Railway decided to adopt 25 kV system in collaboration with SNCF and
converted 3000V DC just when it was completed into 25 kV instead running it at 3000 V DC. The rolling stock procured from abroad
was diverted for Mumbai Sub-urban system and used after conversion from 3000V DC into 1500 V DC.

132 kV/220 kV 3 phase supply is taken from State Utility and two phase (say U-V)are dropped at Traction Sub-station and for the
purpose of load balancing V-W, VW and W-U phase are dropped at subsequent TSSs. There are mainly five types of power supply
arrangement so far prevailing over Indian Railway network. These developments are historical instead for any technical advantages.

1. Power is purchased and paid at 25 kV from supply utility. Supply utility is responsible for owning, installation,
operation, maintenance of /100/132/220 kV transmission line, grid substation upto 25 kV outgoing terminal. 25 kV feeder circuit
breaker is controlled through SCADA by Traction Power Controller. This arrangement was adopted when IR was not having the
resource and experience of handling HV equipment. Such substations were called GSS.
2. It is similar to 1 above except that 25 kV circuit breakers are owned, installed, operated and maintained by the Railways. In this
arrangement of operation by Railways and maintenance by State Utility has ended.
3. IR observed that there is always delay in which the GSS (Grid Sub-station) were not getting ready and delaying the RE
projects. Scheme was thus adopted to have power supply at 132/220 kV at TSS incoming and thereafter every thing under the
control of IR. These substations were called TSS (Traction Substation).
4. For Tundla-Kanpur section of Allahabad Division, another scheme was adopted in which 132 kV transmission line is also
owned by IR and 3 phase supply is taken at one point and two phase power is tapped at IR owned TSSs. This
system benefited IR to save time on execution of transmission line work, complain from State Utility of power imbalance and
helping IR of improving Load factor. This arrangement has helped IR at a later stage to take power supply directly from NTPC
at better tariff and distribute on its network.
5. In Bhusawal Division of Central Railway, Scott connected transformer used to take care of the issue of power imbalance
generally complaint by State Utility in which 3 phase supply connection is taken and converted in to two phases by Scott
connection transformer. The TSSs are owned by Railways.

Power supply arrangement will take a new shape when evacuation of power supply from IR owned captive power plant at
Nabinagar is synchronized to the grid. This is the subject of discussion at different forums of IR. This will be discussed in a new
chapter later on.

Reliability of Traction Power Supply


Reliability of traction power supply means to design redundancy in such a manner that at no instant there is discontinuity of power
supply to traction vehicle for more than a tripping time plus the time take for isolation and feed extension. This is ensured by having
power supply system to consist Traction Substation, Feeding Post, Sectioning and paralleling Post (SP or also called Neutral Section)
and Sub-sectioning and Paralleling post (SSP) and Elementary section. Redundancies are designed at all stages ensuring availability of
power supply on account of failure of supply from source or any other power supply equipment.

Substation
Special features for ensuring continuity of supply are summarized as follows:

1. 132/220 kV supply is taken through double circuit 3 phase transmission line or drawing two phases from the nearby grid
substation. If the grid substation is nearby, it is better to avail three phases. Advantage is to facilitate its usage for general
supply. When general supply load is high, then the same can also be arranged by installing 132/33kV transformer at TSS.
Railway Board has issued instruction to this effect to improve reliability of power supply for general purpose and avoidance of

https://www.railelectrica.com/traction-distribution/25kv-power-supply-system/ 1/4
7/28/2019 25 kV Traction Power Supply System | RailElectrica
use of Diesel Generator set for emergency loads. Some other important points in this regard which can be helpful in decision
making are
It is observed that failure of 132kV feeder is rare therefore it is better to avoid expenditure for running duplicate feeder.
This has been done in some cases
When there are two feeders, some of the Railways preferred for paralleling of two feeders to reduce transmission
losses. This can be of use of the metering is at supply point. However there are instructions of Regulatory commission
that the metering shall be provided at user point.
There are some utility which asks for high load factor, say 35% DVC, which is difficult to achieve. The load factor of
Railway feeder is generally 25% and therefore Railways had to pay heavy penalty. By having general supply feeder
also at TSS, load factor can be improved and penalty payment can be converted into purpose full gain.
2. Two sets of 132kV busbars are provided. One is called main busbar and the other maintenance or transfer busbar. They are
coupled through bus coupler circuit breaker.
3. Isolators on both sides of circuit breakers and provision of transfer busbar and bus coupler enable maintenance of circuit
breakers and busbars.
4. Two numbers of Traction Transformer initially of 10/12.5 MVA and presently 30/32.5 MVA of 132-220/25 kV single phase are
provided at each Traction Substation. For cost cutting, there was a phase during which only one transformer was provided at
alternate TSSs. One number transformer is a hot standbye. One leg of the transformer is solidly earthed and connected to rail
which acts as a return conductor. In order to avoid unbalance, Scott connected transformer were also used in BSL division of
Central Railway.
5. An auxiliary transformer of 25kV/230V of 5/10/25 kVA rating is provided to meet the auxiliary load of lighting, control, fannage
etc. at the substation. During initial state single phase connection was also given for oil filtration plant which was discontinued
later on and mobile oil filtration plants working on DG sets were preferred.
6. In order to improve power factor, series condenser with reactor is introduced on the return conductor at the secondary side of
the transformer. Dynamic compensation is also provided at few of the Sub-station to take care of over compensation. There are
some state utilities who levy penalty for over compensation but in many it has been over ruled by Regulatory Commission. The
cost of Dynamic compensation is high and its own power consumption is so high through out the day that it exceeds the
benefit.
7. Lightening arresters are provided at each control posts to protect every sub-section agaisnt voltages surges. Earth connection
to lightening arrestor should have copper equipvalent area of 50 sq.mm.

Layout diagram of a typical traction substation is shown in Fig below.

Location of Traction Sub-station or Feeding Post


Following points are considered while selecting the site for TSS

1. Norms for locating the TSS based capaicty of transformer and voltage regulation is 50-80 Km for 25 kV without booster
transformer, 40-50 Km with booster transformer and 80-100 Km for 2×25 kV AT system.
2. Voltage is maintained between 27.5 kV (Max.)
3. TSS shall be approachable by all weather road and preferably near a full fledged Railway station for better connectivity by
Road as well rail.
4. Location should be free from water flooding and water logging.
5. To avoid land acquisition

https://www.railelectrica.com/traction-distribution/25kv-power-supply-system/ 2/4
7/28/2019 25 kV Traction Power Supply System | RailElectrica
6. There is a need to convert FP with neutral section. Such planning can be decided in advance.

Feeding and Sectioning Arrangements


Power generation and transmission is at three phase whereas electric traction requires power supply at single phase. It is not possible
to avail only single phase therefore, each of the three phase system is dropped at subsequent substation and segregated at 25 kV side
OHE by a neutral section. The substations along the rail route are located about 50-60 Km and one neutral section in between. Details
of the neutral section will be discussed in separate chapter. Loco pilot is required to switch off the locomotive circuit breaker while
approaching the neutral section for which warning board is provided at 500 and 250 M before the opening and closing command for
circuit breaker. Switching Off and On of circuit breaker is required to avoid bridging of live and dead wire and at entrance and dead wire
with live wire at the exit. A typical layout of OHE feeding system is given in the figure below:

Sectioning and Paralleling Post


Sectioning and Paralleling post is provided at neutral section to extend feed of one zone into another zone during power supply failure
of any zone. SP post consists of two paralleling interrupters to parallel OHE of UP and DN line, one on each side of neutral section. Two
bridging interrupters are provided to bridge the neutral section after ensuring no power supply by no volt relay. Bridging interrupter is
normally kept open except when an emergency feed is extended. During feed extension it is also necessary to warn the driver by a
caution order to drop the pantograph while negotiating the insulated over lap.
OHE and feeding arrangement in between feeding post and neutral section is termed as Section.

https://www.railelectrica.com/traction-distribution/25kv-power-supply-system/ 3/4
7/28/2019 25 kV Traction Power Supply System | RailElectrica

Sub-sectioning and paralleling Post (SSP)


Each section is subdivided into two or three subsection by the provision of SSP every 10-15 Km. This facilitates isolation of faulty
sections. Each SSP is provided with two numbers of interrupter of 600 A capacity and one interrupter. Interrupter is operated on load
and is used for feed extension or isolation during failure.

Elementary Section
Each subsection of 10-15 Km is further subdivided into elementary section. Two adjacent elementary sections are separated by
insulated overlap bridged by manually operated isolator. Isolators are generally located near a Railway stations where station staff is
trained to operate the isolator. Traction Power Controller issues direction therough a control order along with exchange of private
number to operate a particular isolator.

Video of current collection

https://www.railelectrica.com/traction-distribution/25kv-power-supply-system/ 4/4

You might also like