Bus Station Construction Method of Statement
Bus Station Construction Method of Statement
Bus Station Construction Method of Statement
PROJECT MULTAN
Page 1 of 7
CONSTRUCTION OF GREENFIELD PEPSICO
PROJECT MULTAN
CONTENTS
1. OBJECTIVE
2. SCOPE OF WORK
2.1 Work PERMIT REQUIRED
2.2 REFERENCES
2.3 ABBREVIATIONS/DEFINITIONS
2.4 RESPONSIBILITIES
3. EQUIPMENT’S
4. MANPOWER STATUS
5. METHDOLOGY
6. QUALITY ASSURANCE AND QUALITY CONTROL PROCEDURE
7. HEALTH AND SAFETY
8. RELATED DOCUMENTS
Page 2 of 7
CONSTRUCTION OF GREENFIELD PEPSICO
PROJECT MULTAN
1. OBJECTIVE
The purpose of the method statement is to describe the method of testing HVAC Duct
system for air leak (by light test) that will be performed in the scope of PepsiCo at PepsiCo
Green Field project Multan. This statements made shall be followed by Supervisors and
Foremen without omissions.
2. SCOPE OF WORK
The Method Statement defines the methodology of carrying out air leak test by light in
HVAC Duct system related to supply, fresh air and Exhaust duct system lines.
2.1 REFERENCES
Following documents are considered as reference documents:
Page 3 of 7
CONSTRUCTION OF GREENFIELD PEPSICO
PROJECT MULTAN
2.2 ABBREVIATIONS/DEFINITIONS
PM PROJECT MANAGER
CM CONSTRUCTION MANAGER
SE SITE ENGINEER
I/C IN CHARGE
HSE HEALTH, SAFETY & ENVIRONMENT
IMTE INSPECTION, MEASURING & TEST EQUIPMENT
MS Method Statement
QA&QC Quality Assurance and Quality Control
QIP Quality Inspection Plan
2.3 RESPONSIBILITIES
PM will be responsible for the initialization of the work, as well as to manage the
resources to perform their respective activities of Ducting Light testing in
compliance with the quality, schedule and safety requirements of the project.
Site Engineer will ensure that the Ducting light testing activities are conducted
according to this method statement, latest project drawings & client specification.
QA&QC Engineer/inspector will assure that all the relevant work is carried out in
conformance with project specification, QAP and QIP.
HSE team will assure the implementation of HSE plan.
3. EQUIPEMENT’S
The following equipment’s shall be deployed to site as per required numbers.
Test assembly
Light source
Electrical power
4. MANPOWER STATUS
Project Manager
Site Engineer
QA/QC Engineer / Inspector
Related Manpower
HSE Personnel/Representative
Page 4 of 7
CONSTRUCTION OF GREENFIELD PEPSICO
PROJECT MULTAN
5. Methodology:
To verify whether duct is free of the air leak - smoke test, light test or leakage test as per
code ASHRAE can be used.
By SMACNA
“HVAC Duct Construction Standards” Ducts are low pressure can be used
Light test to verify connection of the elements duct, prior start insulation. The points of
leakage if found any shall be sealed with approved sealing material.
Request for Inspection (RFI) shall be submitted to QA/QC section prior to commencing
the installation work. The supervisor in coordination with the QA/QC inspector shall
inspect all the necessary requirements prior to carrying out light test, thus ensuring the
readiness of the work.
Check all Applicable Documents & Specifications available & are approved.
Inspection of Tools and Equipment.
Check all arrangements done for carrying out light test.
Page 5 of 7
CONSTRUCTION OF GREENFIELD PEPSICO
PROJECT MULTAN
Work Permit must be obtained before piping duct light testing and work to be
supervised by a competent person assigned by site authority.
Workers will use Personal Protective Equipment (hard hat, gloves, goggle etc.)
When working at height, safety harness with double lanyard shall be fixed with
approved safety lines, and man lift/scaffolding shall be used.
Only two persons may be attached to a life line is going to be used at any time.
All man lifts/trucks/cranes to be inspected and approved for use on site.
Team coordination shall be implemented by the work supervisor.
Valid certification of all lifting equipment will be verified prior to operation.
All personnel involved in Hvac installation shall be competent enough and well
conversant with the work to be carried out.
The working area should be cleared of items that may cause injury during work..
The area will be assured free of unauthorized workers / persons and tools. Before
testing activity.
8. RELATED DOCUMENTS
Permit to Work
Job Safety Analysis
Request for inspection
Client specifications
Latest revision of Drawings
Page 6 of 7