LTCC
LTCC
LTCC
3. VALEDICTION Construction Co. entered into a P80M fixed price contract for the construction of
a private road for FAREWELL SPEECH, Inc. The performance obligation on the contract is
satisfied over time. VALEDICTION measures its progress on the contract using the “cost-to-
cost” method. The estimated total contract cost is P40M. The following were the actual costs
incurred by VALEDICTION during the first year of the construction:
What is the percentage of completion of the contract as of the end of the first year?
a. 42% b. 45% c. 50% d. 46%
4. On Oct. 1, 20x1, ABC Co. enters into a construction contract with a customer. The performance
obligation in the contract will be satisfied over time. ABC Co. uses the “cost-to-cost” method in
measuring its progress. The estimated total contract cost is ₱10M. In 20x1, ABC Co. incurred a
total cost of ₱6M, which includes ₱2M advance payment to a subcontractor (the subcontracted
work is not yet started) and ₱200,000 cost of materials not yet installed. ABC Co. does not regard
the cost of the unused materials as significant in relation to the expected total contract costs.
Moreover, ABC Co. retains control over the unused materials because it can use them in a
Page |2
contract with another customer. The contract price is ₱20M. How much is the revenue
recognized in 20x1?
a. 7,600,000
b. 12,000,000
c. 8,200,000
d. 11,600,000
5. On January 1, 20x1, ABC Co. enters into a contract with a customer for the construction of a
building. The contract price is ₱1,000,000. The following are the transactions during 20x1:
At contract inception, the customer makes an advance payment of ₱100,000 as facilitation
fee.
ABC Co. incurs total contract costs of ₱300,000 during the period.
The estimated costs to complete as of year-end amounts to ₱500,000.
ABC Co. collects the billing, net of 10% retention by the customer to be used to rectify any
unsatisfactory work determined at the completion of the contract.
How much is the gross profit earned from the contract in 20x1?
a. 75,000
b. 82,000
c. 375,000
d. 482,000
Use the following information for the next three cases (three questions per case):
In 20x1, ABC Co. enters into a construction contract with a customer. The contract price is
₱10,000,000. Information on the contract follows:
20x1 20x2 20x3
Costs incurred to date 2,400,000 4,500,000 6,000,000
Estimated costs to complete 3,600,000 1,500,000 -
Case #1:
At contract inception, ABC Co. assesses its performance obligations in the contract and concludes
that it has a single performance obligation that is satisfied over time. ABC Co. determines that the
measure of progress that best depicts its performance on the contract is “cost-to-cost” method.
Case #2:
At contract inception, ABC Co. assesses its performance obligations in the contract and concludes
that it has a single performance obligation that is satisfied over time. However, ABC Co. determines
that the outcome of the performance obligation cannot be reasonably measured but expects to
recover the contract costs incurred.
Case #3:
At contract inception, ABC Co. assesses its performance obligations in the contract and concludes
that it has a single performance obligation.
In its determination of the satisfaction of the performance obligation, ABC Co. identifies that, during
the construction period, ABC Co. retains control over the asset created in the contract. This
precludes the customer from simultaneously receiving and consuming the benefits provided by
ABC Co.’s performance as ABC Co. performs. Moreover, the asset created in the contract has an
alternative use to ABC Co. because, in case the contract is cancelled, ABC Co. retains ownership over
any asset created and can direct that asset for another use without significant modification or cost.
Accordingly, ABC Co. concludes that the performance obligation is satisfied at a point in time.
Page |4
ABC Co. determines the point in time when the performance obligation is satisfied using the
principles in PFRS 15 and concludes that the performance obligation is satisfied only when the
construction is completed and the control over the promised good is transferred to the customer.
15. ABC Co. started work on two separate projects during 20x1. Information on these projects is
shown below:
Estimated costs to
Project Contract price Costs incurred complete Progress billings
A 9,000,000 4,000,000 2,000,000 5,000,000
B 8,000,000 5,000,000 - 8,000,000
How much is the total balance of the “construction in progress” accounts as of December 31, 20x1
under percentage of completion method?
a. 4,000,000
b. 6,000,000
c. 14,000,000
d. 0
“Come to Me, all you who labor and are heavy laden, and I will give you rest.” (Matthew
11:28)
- END -
SOLUTIONS:
1. B
2. D
3. Solution:
Page |5
The percentage of completion as of the end of the first year is computed as follows:
Total costs incurred to date
Percentage of completion =
Estimated total contract costs
Percentage of completion = 18,000,000 ÷ 40,000,000
Percentage of completion = 45%
4. Solution:
Percentage of completion = (6M – 2M – 200K) ÷ 10M
Percentage of completion =(3.8M ÷ 10M) =38%
38% x 20M = 7.6M
5. A Solution:
Total contract price 1,000,000
(a) Costs incurred to date 300,000
Estimated costs to complete 500,000
(b) Estimated total contract costs 800,000
Expected gross profit from contract 200,000
Multiply by: Percentage of completion (a) ÷ (b) 37.50%
Gross profit earned to date 75,000
Less: Gross profit earned in previous years -
Gross profit for the year 75,000
Solutions:
20x1 20x2 20x3
Total contract price 10,000,000 10,000,000 10,000,000
Costs incurred to date (a) 2,400,000 4,500,000 6,000,000
Estimated costs to complete 3,600,000 1,500,000 -
Estimated total contract costs (b) 6,000,000 6,000,000 6,000,000
Expected profit (loss) 4,000,000 4,000,000 4,000,000
Multiply by: % of completion (a) ÷ (b) 40% 75% 100%
Profit (loss) to date 1,600,000 3,000,000 4,000,000
Profit recognized in prior years - (1,600,000) (3,000,000)
Profit (loss) for the year 1,600,000 1,400,000 1,000,000
Page |6
Solutions:
20x1 20x2 20x2
Contract revenue to date (a) 2,400,000 4,500,000 10,000,000
Contract revenue in prior yrs. - (2,400,000) (4,500,000)
Contract revenue for the year 2,400,000 2,100,000 5,500,000
Cost of construction (b) (2,400,000) (2,100,000) (1,500,000)
Profit (loss) for the year - - 4,000,000
The “contract revenue to date” in 20x1 and 20x2 are equal to the costs incurred to date. However, the contract
(a)
revenue to date in 20x3 is the transaction price of ₱10,000,000 because the contract is 100% complete.
The revenues recognized in 20x1 and 20x2 are equal to the recoverable costs incurred during those years. In
20x3, when the construction is completed, the revenue recognized is the transaction price adjusted for the revenues
recognized in the previous years.
(b) “Costof construction” is equal to the costs incurred during the period. In 20x2 and 20x3, the costs of construction are computed as
“costs incurred to date” minus “costs incurred in prior years: 20x2: (4.5M – 2.4M = 2.1M) and 20x3: (6M – 4.5M = 1.5M).
Solutions:
No revenue is recognized during the construction period because the performance obligation is satisfied at a point
(a)
in time. The whole of the transaction price is recognized as revenue only in 20x3 when the construction is completed
and the control over the promised good is transferred to the customer.
Page |7
The costs incurred each year during the construction period are deferred and recognized in full only in 20x3 when
(b)
15. B Solution:
The balances in construction in progress accounts as of December 31, 20x1 under percentage of
completion are determined as follows:
CIP – A CIP – B
Costs incurred 4,000,000 5,000,000
Profit 2,000,000 3,000,000 8,000,000 *
6,000,000 -
*Since project B is 100% complete, it is assumed that the completed project was turned over to the
customer.