Saudi Oger Ltd. (Project Name) : Plastering
Saudi Oger Ltd. (Project Name) : Plastering
Saudi Oger Ltd. (Project Name) : Plastering
(Project Name)
INSPECTION & TEST PLAN PLASTERING ITP-C-32 Rev. 00
Project No.: Project Title:
Contractor: Contract No: CIVIL
Item No.
Contractor Contractor
Applicable Code or Test Record or (Client) Engr /
Activity Inspection and Test Point Acceptance Criteria Site QA/QC
Standard Document Inspector
Engineer Engrineer
1.0 MATERIAL 1.1 Aggregate: Natural sand of the required gradation. Project specification As per spec. Laboratory records
Visual R R R
1.2 Cement: Portland cement type I. Project specification As per spec. Mill certificate
I/R I/R I/R
2.0 EXECUTION 2.1 Check surface preparation, masonry, concrete. Project specification As per spec. and Code Visual
QR-C-32 I W W
2.2 Check embeded items within wall have been already Project specification As per specification and QR-C-32
installed. approved drawings. I W S
2.3 Electro-Mechanical services have been tested and Project specification As per specification and Electromechanical
approved. approved drawings. RFI's, QR-C-32 I W S
2.4 Check required plaster mix for exterior wall, interior Project specification As per spec. QR-C-32
wall and ceiling. ASTM C-926 I W S
2.5 Application of dash coat, scratch coat, brown coat Project specification As per spec. QR-C-32
and finish coat as per mix design and required ASTM C-926 I S S
thickness.
2.6 Finish coat shall be cured for a minimum of 48 hours. Project specification As per spec. QR-C-32
I S S
2.7 Plaster shall extend 100mm beyond finished ceiling Project specification As per spec. QR-C-32
level for rooms with suspended ceiling. I S S
2.8 Check plaster variation to true finish. Project specification Maximum variation is 3mm QR-C-32
in 3m. I S S
I=Inspect or Perform Work; W=Witness Point; R=Review/ approve Records or Documentation; S=Surveilance or Monitor; H=Hold Point Page 1 of 1