Inspection Test Record (Itr) - A Jacket Pre-Loadout ST08-A Inspection / Test

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

INSPECTION TEST RECORD (ITR) - A

JACKET PRE-LOADOUT ST08-A


INSPECTION / TEST OK N/A P/L No.
a. Grout Connection Station
i. Located at Leg B3-for all Skirt Sleeve (B1-4, C1-4, B1-1a & C1-1a)
b. Color Coding
i. Primary Line-Green
ii. Secondary Line-Yellow
iii. Tertiary Line-Red
3 • Inspect the 2” quick connect hose connector that is being used at the grout station
(Specified by the CONTRACTOR and installed by the FABRICATOR).
• Check the tertiary line at the pile sleeve along with the 2” Male R.O.V hose connector and
determine that the position is at the outer region of the York Plate on the pile sleeve. ROV
holding handles installed for ROV to hold during handling the
valves.
• FABRICATOR to check tertiary pipe supports and is clear from any structural
obstruction.
GROUTING PACKER & PILE GRIPPER INFLATION SYSTEM
• Inspect the Pile Gripper inflation port that is provided with the secondary inflation line
system and to determine if it is ROV accessible to the surface inflation hose.
• Inspect the Grout Packer inflation port that is provided with the secondary inflation line
system and to determine if it is ROV accessible to the surface inflation
hose.
• Ensure that low heat application at the welds in the packer area is used in
4 accordance with the manufacturers fitting instructions.
• Check the position of the ROV secondary hot-tap inflation port and ensure that it is
installed facing outward of the jacket that will allow the facilitation of the ROV operations.

• FABRICATOR is to fully test and commission the Grout Packer Inflation System, Pile Gripper
System together with air lines, grout lines and flooding lines and flooding
lines at the yard and to be witnessed by the CONTRACTOR.
• The Quick Connect Panel (QCP) for the grout packer & pile gripper inflation should
be accessible by the walkway on jacket sea deck to jacket leg B3.
BOAT LANDING
• Check boatlanding pre-installed rigging make-up, arrangement, ID and tie-down (if
any)
5
• Check any potential interference when installing boatlanding to jacket.
• Boat landing trail fit shall be performed by FABRICATOR and witnessed by
CONTRACTOR.
6 BOAT LANDING-POST LOADOUT
• Witness MPI padeyes and shackles after lifting (if required)
• Check for damages during loadout.
• Check and inspect lifting riggings after lifting.
7 JACKET POST LOADOUT
• Check all sea fastenings.