STDB 2 B
STDB 2 B
STDB 2 B
@ CURB RETURNS
6
A 1
A 23. PLACE CONCRETE FOR ANCHOR LUGS AS SOON AS POSSIBLE
ANCHOR LUGS NO.4 @ 18"TRANSVERSE STEEL AFTER COMPLETING EXCAVATION,TO PRESERVE THE INHERENT
NOTE:
OFFSET TO FREEWAY SOIL CHARACTERISTICS. EXCAVATING FOR AND PLACING
LEAVE ISLAND AREA OPEN
CONCRETE FOR ANCHOR SYSTEM MAY BE IN PREFORMED SECTIONS
(SEE PLAN SHEETS) UNLESS OTHERWISE SHOWN
20' CORRESPONDING TO THE WIDTH OF PAVING PLACEMENT.
SAWED JOINTS
IN THE PLANS. BRIDGE
APPROACH SLAB
TYPICAL LAYOUT 24. APPLY A STEEL TROWEL FINISH TO SLEEPER SLABS AND
X (TERMINAL ANCHORAGE AT BRIDGES) AND COAT WITH AN ASPHALT BOND BREAKER.
MA X
4" MA
2" 25. THE DETAILS FOR ANCHORS, LUGS, EXPANSION JOINTS,
1 ‚" D x 22" EPOXY COATED
AND SLEEPER SLABS ARE NOT APPLICABLE UNLESS SHOWN
DOWEL BARS @ 12" SPA.
ELSEWHERE IN THE PLANS.
1" ASPHALT ETHYLENE VINYL ACETATE
CONSTRUCTION JOINT
BOND BREAKER JOINT SEAL PLACED UNDER 26. APPROACH SLAB WILL BE PAID FOR IN ACCORDANCE WITH THE
SEE NOTE A COMPRESSION (EPOXY BONDED ITEM "CONCRETE STRUCTURES."
CONSTRUCTION JOINT (ROUGHEN THE CONSTRUCTION JOINT TO CONCRETE)
BY BROOMING WITH A STIFF BROOM TRANSVERSE TO THE
COAT THIS HALF OF DOWEL BAR WITH 27. WITHIN 5 MINUTES OF SAWING, COMPLETELY REMOVE THE
C
L OF PAVEMENT AND CLEAN THE ROUGHENED SURFACE BITUMINOUS MASTIC TO PREVENT BOND. RESULTING SLURRY FROM THE JOINT BY FLUSHING WITH HIGH
SURFACE OF LAITANCE AND LOOSE MATERIAL PRIOR TO
11" PRESSURE WATER. THEN ALLOW THE JOINT TO DRY FOR A
PLACING CONCRETE PAVEMENT.) 3 •" ROADWAY BRIDGE
MINIMUM OF 48 HOURS BEFORE SANDBLASTING THE JOINT.
„ "
BARS "A"(SPACED AT • PLASTIC DOWEL CAP
END CURB RETURN (4" MIN. LENGTH)
THE SPACING OF THE #4@18" T
(5'R USUAL 28. DO NOT SHEAR CUT DOWEL BARS.
LONITUDINAL STEEL) NO.5 @ 6"
I
*
S
FACE OF CURB
"T"
L
29. SIZE ADDITIONAL SHEAR BARS AS LONGITUDIAL
A
N
D
BARS AND SPACE THEM MIDWAY BETWEEN ALTERNATE
LONGITUDINAL BARS ALONG THE TRANSVERSE CONSTRUCTION
6" JOINT FORMED AT THE LEAVE-OUT.
6" LIME TREATED 6" (TYP) 2'-0"
NO.5x2'-9"@12"C-C
3'-0"
SUBGRADE
TIE BARS POLYETHYLENE
SLEEPER SLAB NO.5x(SLAB WIDTH-4")
FOAM(6 LB. 30. IF THE CONCRETE DESIGN REQUIRES GREATER THAN 5.5 SACKS
@10" SPACING
DENSITY) OF CEMENTITIOUS MATERIAL PER CUBIC YARD, WRITTEN
3'-0" NORMAL FACE OF ABUTMENT APPROVAL BY THE AREA ENGINEER WILL BE REQUIRED. ENSURE
TO JOINT BACKWALL CONCRETE PAVEMENT MIXES PLACED FROM APRIL 1 TO OCTOBER
2'-0" 31 CONTAIN A MINIMUM OF 25 PERCENT BY WEIGHT OF CLASS
6-NO.4 X (SLAB WIDTH-4") EXPANSION JOINT JUNCTION WITH BRIDGE "F" FLY ASH.
6"
MAX
7"
T
EXIST JRCP PROP JRCP
NO.4 BARS
SAWED JOINT SEALED WITH CLASS 4,
EXISTING BASE @ 12" BASE AND 10"10"
5, OR 7 JOINT SEALING MATERIAL
TREATED
SUBGRADE 1 „"x22" EPOXY COATED DOWEL BAR @ 12"C-C
SECTION B-B ** T/2 +1 •"
COAT THIS HALF WITH BITUMINOUS MASTIC
MIN
8"
(FOR PROPOSED PAVEMENT DEPTHS OF 7" MAX)
T
TIE BARS
BASE AND
REPLACE ANY BENT LONGITUDNIAL REINFORCING. IF THERE IS NOT SUFFICIENT TREATED
DRILL HOLE TO PROVIDE PLASTIC DOWEL CAP TO FIT
EXPOSED REINFORCING TO PROVIDE A MINIMUM OF A 33 TIMES BAR DIAMETER LAP, DOWEL (2" MIN LENGTH) SUBGRADE
SNUG FIT. PLACE USING
ƒ " EXPANSION JOINT
REMOVE THE EXISTING PAVEMENT AND SUFFICIENTLY EXPOSE THE EXISTING REINFORCING MEET EXISTING SUBGRADE
EPOXY GROUT.
TO PROVIDE A 33 TIMES BAR DIAMETER LAP. REPLACE ANY SHEAR BARS THAT ARE
* SEE NOTE A DISTURBED, BY DRILLING AND GROUTING AS REQUIRED BY NOTE #29. PERFORM THIS SECTION B-B
@ CURB RETURNS
SEE NOTE A
CORRECTIVE ACTION AT NO EXPENSE TO THE DEPARTMENT. (FOR PROPOSED PAVEMENT DEPTHS OF 8" MIN)
BEGIN TIE BARS
NOTE A:
* SEE SHEET 1 OF 2 FOR …"
ƒ"
STEEL PLACEMENT FOR THE
*IN AREAS OF CURB RETURNS RESPECTIVE LANE WIDTHS.
CLASS 4, 5, OR 7 JOINT
‚ "
CLASS 4, 5, OR 7 JOINT
‚ "
OR OTHER IRREGULAR AREAS, EDGE OF CONC. SEALING MATERIAL
SEALING MATERIAL
PLACE A REINFORCEMENT
ARRANGEMENT WHICH WILL BE BLOCK OUT
1 ƒ "
END CURB RETURN LONGITUDINAL
PLACEMENT LENGTH VARIES
MIN
APPROXIMATELY EQUAL BY STEEL
(25' R USUAL 1 ‚"
**
Texas Department of Transportation
… "
WEIGHT TO THE MAIN SLAB OR
‚ "
FACE OF CURB) TIE BARS @ 20"
AS DIRECTED. Houston District
T/4
FIBER BOARD
TYPICAL 6" MIN
12" MAX
"
JOINTS WHERE DIRECTED. 1" D POLYETHYLENE
ˆ" MINIMUM WIDTH FOAM BACKER ROD DETAILS
OPTIONAL SAW CUT
EXPANSION JOINT DESIGN
1'-6" SAWED JOINT EXPANSION JOINTS (FOR PAVEMENT THICKNESS 10 INCHES OR LESS)