Project Basic Assumption For Programme
Project Basic Assumption For Programme
Original Duration
Original
Start Date Completion Remarks
Duration(Days)
09-04-2017 07-06-2019 790 As per contract
While submission for the EOT all the events are considered up to 25th March 2019.
Remaining
Start Date Completion Remarks
Duration(Days)
25-03-2019 21-10-2019 211
As per Approved EOT the Revised date for the Completion is 21st Oct 2019 i.e. 136 days
Remaining Duration
Contract Remaining
Project Finish Date Remarks
Completion Date Duration(Days)
As per Approved
08-06-2019 21-10-2019 136
EOT
Overall Duration
Original
Start Date Completion Remarks
Duration(Days)
09-04-2017 21-10-2019 926
SUMMARY OF PIPELINE
Total Pipe Length Avg
SL No. Zones No of Teams Duration
(m.) Productivity
Productivity/LM
1 Zone‐1 1204.000 70 1 17
2 Zone‐2A 10733.900 66 3 54
Zone‐2B 12909.300 70 3 61
Zone‐2C 10761.250 70 2 77
Zone‐2D 7823.600 63 2 62
Zone‐2E 14076.950 63 4 56