Project Basic Assumption For Programme

basic assumption for Prog

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views

Project Basic Assumption For Programme

basic assumption for Prog

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

BASIC ASSUMPTION

As per the Contract Agreement:

Start Date of the Project - 09-04-2017

Completion Date of the Project - 07-06-2019

Original Duration

Original
Start Date Completion Remarks
Duration(Days)
09-04-2017 07-06-2019 790 As per contract

While submission for the EOT all the events are considered up to 25th March 2019.

The Programme has been revised from 25-03-2019.

Remaining
Start Date Completion Remarks
Duration(Days)
25-03-2019 21-10-2019 211

As per Approved EOT the Revised date for the Completion is 21st Oct 2019 i.e. 136 days

Remaining Duration

Contract Remaining
Project Finish Date Remarks
Completion Date Duration(Days)
As per Approved
08-06-2019 21-10-2019 136
EOT

Overall Duration

Original Duration +Remaining Duration

Original
Start Date Completion Remarks
Duration(Days)
09-04-2017 21-10-2019 926
 SUMMARY OF PIPELINE

Total Pipe Length  Avg 
SL No. Zones No of Teams Duration
(m.) Productivity

Productivity/LM 
1 Zone‐1 1204.000 70 1 17

2 Zone‐2A 10733.900 66 3 54

Zone‐2B 12909.300 70 3 61

Zone‐2C 10761.250 70 2 77

Zone‐2D 7823.600 63 2 62

Zone‐2E 14076.950 63 4 56