Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

General Structural / Construction Notes and Specifications: Wall Footing Details (Where Applicable)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

REPUBLIC OF THE PHILIPPINES

OFFICE OF THE BUILDING


GENERAL STRUCTURAL / CONSTRUCTION NOTES AND SPECIFICATIONS DOWEL BARS TO MATCH OFFICIAL
HORIZONTAL REINFORCEMENT MUNICIPALITY OF TUBURAN, CEBU

(A) GENERAL REQUIREMENTS 400 400 400 RECOMMENDING APPROVAL :


CHB WALL
100 100
1. ALL STRUCTURAL MATERIALS AND WORK SHALL CONFORM TO THE REQUIREMENTS

200
CHB "t"
OF THE LATEST EDITION OF THE NATIONAL STRUCTURAL CODE OF THE PHILIPPINES HEAD STRUCTURAL SECTION DATE
7. SPLICES SHALL BE SECURELY WIRED TOGETHER AND SHALL LAP AT LEAST 40 TIMES DIAMETER OR 600MM
(NSCP 2001).
WHICHEVER IS GREATER. STAGGER BOTTOM AT LEAST 1.50M FROM SPLICES IN OTHER BOTTOM

100
1 - 16mm Ø VERT. BARS
REINFORCEMENT. STAGGER SPLICES FOR TOP REINFORCEMENT SIMILARLY. CHB VERT. REINF.

200
2. VERIFY ALL DIMENSIONS, ELEVATIONS AND SITE CONDITIONS BEFORE STARTING APPROVED BY :
(SEE SCHED. OF REINF.)
WORK. NOTIFY THE ENGINEER IMMEDIATELY OF ANY DISCREPANCIES. 1 - 16mm Ø VERT. BARS CHB HOR. REINF.

100
8. ALL ANCHOR BOLTS, DOWELS, AND OTHER INSERTS SHALL BE PROPERLY POSITION AND SECURED IN PLACE CHB VERT. REINF. (SEE SCHED. OF REINF.)
PRIOR TO PLACING OF CONCRETE. (SEE SCHED. OF REINF.)
DOWEL BARS TO MATCH
3. NOTES AND DETAILS ON THE DRAWINGS TAKE PRECEDENCE OVER THE GENERAL BUILDING OFFICIAL DATE
NOTES AND TYPICAL DETAILS IN CASE OF CONFLICT. HORIZONTAL
9. ALL CONCRETE SHALL BE KEPT MOIST FOR A MINIMUM OF 7 CONSECUTIVE DAYS IMMEDIATELY AFTER CHB HOR. REINF.
REINFORCEMENT
(SEE SCHED. OF REINF.)
POURING BY THE USE OF CURING COMPOUNDS, OR OTHER APPROVED METHODS.
4. WHERE CONSTRUCTION DETAILS ARE NOT SHOWN OR NOTED FOR ANY PART OF THE WORK, SUCH DETAILS
SHALL BE THE SAME AS FOR SIMILAR WORKS SHOWN ON THE DRAWINGS.
10. STRIPPING OF FORMS AND SHORES:
5. PIPES, DUCTS, SLEEVES, CHASES, ETC. SHALL NOT BE PLACED IN SLABS, BEAMS, OR WALLS UNLESS
FOUNDATION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24 HRS.
SPECIFICALLY SHOWN OR NOTED NOR SHALL ANY STRUCTURAL MEMBER BE CUT FOR PIPES, DUCTS, ETC. CHB "t"
UNLESS SPECIFICALLY SHOWN. OBTAIN PRIOR WRITTEN APPROVAL FROM THE ENGINEER FOR INSTALLATION
SUSPENDED SLAB EXCEPT WHEN
OF ANY ADDITIONAL PIPES, DUCTS,ETC. LOCATE AND PROTECT UNDERGROUND OR CONCEALED CONDUIT, CHB "t"
ADDITIONAL LOADS ARE IMPOSED. . . . . . . . . . . . . . . . . .8 DAYS
PLUMBING OR OTHER UTILITIES WHERE NEW WORK IS BEING PERFORMED. WALL REINFORCING AT
WALL REINFORCING AT INTERSECTION
BEAMS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 DAYS END / DOOR OPENING
6. LOCATE AND PROTECT UNDERGROUND OR CONCEALED CONDUIT, PLUMBING OR OTHER UTILITIES WHERE
NEW WORK IS BEING PERFORMED.
(E) CAMBER REQUIREMENTS
7. TAKE NECESSARY PRECAUTIONS TO MAINTAIN AND INSURE THE INTEGRITY OF THE STRUCTURE DURING
1. UNLESS OTHERWISE NOTED THE PLAN OR SPECIFICATION CAMERA ALL RC BEAMS AT LEAST 10mm FOR
CONSTRUCTION. NEITHER THE OWNER NOR ARCHITECT/ENGINEER WILL ENFORCE SAFETY MEASURES OR 400 LAP SPLICE
EVERY 4000mm OF CLEAR SPAN EXCEPT CANTILEVERS WHICH SHALL BE 50mm FOR EVERY 300mm OF CLEAR
REGULATIONS. IT SHALL BE THE CONTRACTORS RESPONSIBILITY TO PROVIDE ADEQUATE SHORING AND 300
CHB WALL
SPAN.
BRACING OF THE STRUCTURE FOR ALL THE LOADS THAT MAYBE IMPOSED DURING CONSTRUCTION. FURTHER,
THE CONTRACTOR SHALL DESIGN, CONSTRUCT AND MAINTAIN ALL SAFETY DEVICES AND SHALL BE SOLELY VARIES

CHB "t"
2. UNLESS OTHERWISE NOTED ON THE PLANS OR SPECIFICATIONS CAMBER ALLSLABS 8mm PER 3000mm OF
RESPONSIBLE FOR CONFORMING TO ALL SAFETY AND HEALTH STANDARDS, LAWS AND REGULATIONS.
SHORTER SPAN AND 14mm FOR EVERY 2000mm OF SLABS CANTILEVER SPAN.

300

VARIES
CHB VERT. REINF. CHB WALL
8. OBTAIN PRIOR WRITTEN APPROVAL FROM THE ENGINEER IN CASE OF CHANGES TO THE WORKING DRAWINGS.
(F) MASONRY AND CONCRETE BLOCKS (SEE SCHED. OF REINF.)
CHB VERT. REINF.

400 LAP SPLICE


16mm Ø VERTICAL CHB WALL
(B) DESIGN CRITERIA REINFORCEMENT (SEE SCHED. OF REINF.)
1. CONCRETE HOLLOW BLOCKS, UNLESS OTHERWISE SPECIFIED SHALL BE 150MM THICK LOAD BEARING BLOCKS

DOWEL TO MATCH
CHB VERT. BARS

DOWEL TO MATCH
SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF 750 PSI (5.175 MPa) WHILE NON-LOAD BEARING SHALL CHB VERT. REINF.

CHB VERT. BARS


---REFER TO STRUCTURAL COMPUTATIONS CHB VERT. REINF. DOWELS (SEE SCHED. OF REINF.)
HAVE A MINIMUM COMPRESSIVE STRENGTH OF 400 PSI (2.76 MPa). DOWEL BARS TO MATCH
(TO MATCH VERT. REINF.)
HORIZONTAL REINFORCEMENT
(C) FOUNDATION CHB VERT. REINF. DOWELS
2. PROVIDE 1-16MMØ VERTICAL BARS AT CORNERS, INTERSECTIONS, END OF WALLS, EACH SIDE OF OPENINGS. (TO MATCH VERT. REINF.)
CHB HOR. REINF.
SUSPENDED SLAB
1. FOOTINGS SHALL BEAR ON SOLID UNDISTURBED EARTH (CONTROLLED, COMPACTED STRUCTURAL FILL OR (SEE SCHED. OF REINF.)
3. LINTEL BEAMS SHALL BEAR AT LEAST 200MM (8") ON EACH SIDE OF MASONRY WALL OPENING.
BOTH) AT LEAST 450MM BELOW LOWEST ADJACENT FINISHED GRADE.
4. WALL REINFORCEMENT SHALL BE AS FOLLOWS: WALL BASE REINFORCEMENT
2. FOOTING IS DESIGNED FOR ASSUMED ALLOWABLE SOIL/FOUNDATION PRESSURE OF 144KPA(3,000 psf). CHB "t"
WALL THICKNESS VERTICAL BARS HORIZONTAL BARS
AT FLAT FLOOR
3. SUB-GRADE PREPARATION INCLUDING DRAINAGE, EXCAVATION,COMPACTION, AND FILLING REQUIREMENTS, TOP OF CHB AT PARAPET/
8 IN. (2OOmm). . . . . . . . . . . . . . 12MMØ @ 400 mm10MMØ @ 600 mm WALL REINFORCING AT CORNER
SHALL CONFORM STRICTLY WITH THE RECOMMENDATIONS GIVEN IN THE SOILS REPORT OR AS DIRECTED BY GRD. FLR. RAILING & PLANT
THE SOILS ENGINEER.
6 IN. (150mm). . . . . . . . . . . . . . . 10MMØ @ 400 mm 10MMØ @ 600 mm BOX
4. THE CONTRACTOR SHALL NOTIFY THE ENGINEER AFTER FOOTING EXCAVATION HAVE BEEN COMPLETED AND
4 IN. (100mm). . . . . . . . . . . . . . . 10MMØ @ 400 mm 10MMØ @ 600 mm
PRIOR TO CONCRETING TO CONFIRM THE DESIGN FOUNDATION CAPACITY.
5. BLOCK WALL REINFORCEMENT BARS SHALL BE LAPPED OF 30 BARS DIAMETERS WHERE SPLICED,
5. ROOF AND AREA DRAINAGE SHALL BE DIRECTED AWAY FROM THE FOUNDATIONS.
HORIZONTAL/VERTICAL DOWELS FROM FOOTING, COLUMNS/WALLS OR SLABS SHALL EXTEND INTO THE
BLOCK WALL A MINIMUM OF 30 BAR DIAMETERS OR A MINIMUM OF 4OOMM WHICHEVER IS LONGER AND
6. EXCAVATIONS SHALL BE PROPERLY BACKFILLED. BACKFILL FOR WALLS SHALL BE PERVIOUS MATERIAL
DOWELS TO MATCH VERTICAL REINFORCEMENTS OF WALL.
ACCEPTABLE TO THE GEOTECHNICAL ENGINEER. DO NOT PLACE BACKFILL BEHIND WALLS BEFORE THEY
HAVE ATTAINED THEIR DESIGN STRENGTH. SHORE AND PROTECT WALLS FROM LATERAL LOADS UNTIL THE
(G) STRUCTURAL STEEL
SUPPORTING MEMBERS ARE IN PLACE AND HAVE DEVELOPED SPECIFIED STRENGTHS.
SEE CONSTRUCTION NOTES
1. ALL STRUCTURAL, STEELS SUCH AS ANGLES, WIDE FLANGE SECTIONS, PIPES STIFFENER PLATES, BASE FOR MASONRY WALL REIN-
(D) REINFORCED CONCRETE
PLATES, ETC. SHALL CONFORM TO ASTM- A-36. FORCEMENT (TYPICAL)
1. CONCRETE SHALL BE MIXED, PROPORTIONED, CONVEYED AND PLACED IN ACCORDANCE WITH THE
2. ALL STRUCTURAL STEEL SHALL BE DETAILED, FABRICATED AND ERECTED BASED ON THE SPECIFICATION FOR
PROVISIONS SET BY THE NSCP 2001. FIN. FLR. LVL.
DESIGN, FABRICATION, AND ERECTION OF STRUCTURAL STEEL GIVEN BY THE NATIONAL STRUCTURAL CODE DOWEL BARS TO MATCH
OF THE PHILIPPINES (NCSP). DOWEL BARS TO MATCH
2. ALL CONCRETE SHALL DEVELOP A MINIMUM COMPRESSIVE STRENGTH AT 28 DAYS WITH CORRESPONDING CHB VERT. BARS DOWEL BARS TO MATCH CHB VERT. BARS
MAXIMUM SLUMP AND MAXIMUM SIZE AGGREGATES AS FOLLOWS: CHB VERT. BARS

VARIES
WHERE SLAB
STRUCTURAL MEMBER 28 DAY STRENGTH MAX. SLUMP MMAX.SIZE AGG. 3. CONNECTION BOLTS (34 ROUND, UNLESS SHOWN OTHERWISE) SHALL CONFORM TO ASTM- A-325. ANCHOR
DEPRESSION OCCURS
A. SLAB ON GRADE 20.7 MPa (3,000 PSI) 100MM(4") 25MM(1") BOLTS (EMBEDDED IN MASONRY OR CONCRETE) SHALL CONFORM TO ASTM- A307 UNLESS NOTED OTHERWISE
ON THE DRAWINGS.

30 BAR DIAMETER
B. FOOTINGS & RETAINING WALLS 20.7 MPa (3,000 PSI) 100MM(4") 19MM(3/4)

30 BAR DIAMETER

30 BAR DIAMETER
N.G.L.
C. COLUMNS/ SHEARWALLS 20.7 MPa (3,000 PSI) 100MM(4") 19MM(3/4) 300

DOWELS
DOWELS
300

DOWELS
D. BEAMS & SLABS 20.7 MPa (3,000 PSI) 100MM(4") 19MM(3/4) 4. ALL STRUCTURAL STEEL SHALL BE CLEAN, RUST FREE AND SHOP COATED WITH THE APPROPRIATE PAINT. (TYP.)
(TYP.)
STRUCTURAL STEEL AND ANCHOR BOLTS SHALL BE MINIMUM ASTM A-36 DOMESTIC, LATEST REVISION.

600 (MIN.)
3. ALL REINFORCING STEEL BARS SHALL CONFORM TO ASTM A615 GRADE 40 FOR 12MMØ AND SMALLER BARS
WHILE BARS 16MMØ AND LARGER SHALL BE GRADE 60. 5. NON- SHRINK GROUT- PRE-MIXED, NON METALLIC, CEMENT-BASED GROUT, MEETING THE REQUIREMENT OF FIN. FLR. LVL. FIN. FLR. LVL.
ASTM C827, ASTM C109 & CRD-C621, WITH A MINIMUM COMPRESSIVE STRENGTH OF 7000psi AT 28 DAYS.

250
250

250
4. ALL FABRICATION, DETAILING AND PLACING SHALL CONFORM TO THE PROVISIONS SET BY THE NSCP 2001 3 - 10mm Ø BOT.
EDITION. 6. PROVIDE MISCELLANEOUS PLATES, ANGLES AND ANCHORS AS SHOWN OR NOTED ON DRAWINGS. BARS

10mm Ø BOT. BARS 6 - 10mmØ BARS (AS 6 - 10mmØ BARS (AS


5. CLEAR DISTANCE SPACING BETWEEN PARALLED BARS IN A LAYER SHALL NOT BE LESS THAN 1.50 TIMES THE 7. ALL CUTTING AND BLOCKING OF STEEL SHALL BE SHOWN ON SHOP DRAWINGS AND PERFORMED IN SHOP. SHOWN)
@ 300 O.C. SHOWN)
NOMINAL DIAMETER OF THE BAR, OR 1.33 TIMES MAXIMUM SIZE AGGREAGATE, NOR LESS THAN 38MM (1 1/2").
8. PROVIDE TEMPORARY BRACING AS REQUIRED FOR A SAFE STRUCTURE UNTIL ALL FINAL CONNECTIONS ARE 10mm Ø BOT. BARS 10mm Ø BOT. BARS 400
400 400 @ 300 O.C.
6. MAINTAIN MINIMUM CONCRETE COVER FOR REINFORCING STEEL AS FOLLOWS: MADE. @ 300 O.C.

FOOTINGS (CAST AGAINST & EXPOSED TO EARTH) . . . . 75MM(3") AT INTERIOR WALLS WITH
AT EDGE / PERIMETER CHB WALL AT INTERIOR CHB WALLS
WHERE CONCRETE IS EXPOSED TO EARTH SLAB ELEVATION DIFFERENCE
BUT POURED AGAINST FORMS. . . . . . . . . . . . . . . . . . . . . . . 50MM (2")
WF - 1 WF - 2 WF - 3
SLAB ON GRADE. . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . 40MM (1 1/2")

COLUMN TIES OR SPIRALS AND BEAM STIRRUPS. . . . . . . 40MM (1 1/2")

SUSPENDED SLABS. . . . . . .. . . . . . . . . . . . . .. . . . . . . .. . . . . 20MM (3/4")


WALL FOOTING DETAILS (WHERE APPLICABLE)

FROM THE OFFICE OF : S E A L PROJECT TITLE : OWNER : SHEET CONTENT: SHEET NO.:
TRIMAR AS SHOWN
ALEX C. MAYOR JR.
CONSTRUCTION CIVIL/STRUCTURAL ENGINEER ENGR. RALPH BACOLOD S1
A PROPOSED COVERED COURT
& TRADING PRC NO.: 100124 PTR NO.: 1660761
MASBATE OIC PROVINCIAL ENGINEER
5
REG. DATE: 07 / 25 /2004 DATE: 01 / 08 / 2019
TALAMBAN, CEBU CITY TIN NO.: 232 - 213 - 366 PLACE: CEBU CITY LOCATION: MASBATE, PHILIPPINES ADDRESS: MASBATE, PHILIPPINES
REPUBLIC OF THE PHILIPPINES

SAW-CUT GROOVE 8mm SAW-CUT GROOVE 8mm WIDE


OFFICE OF THE BUILDING
RET. WALL / CHB WALL WIDE TO BE FILLED WITH 65mm DEEP TO BE FILLED WITH 10mm Ø VERTICAL BARS OFFICIAL
POLYURETHANE SEALANT POLYURETHANE SEALANT SPACED @ 400mm O.C. MUNICIPALITY OF TUBURAN, CEBU
POLYURETHANE SEALANT SLAB ON GRADE
SLAB REINF. SLAB REINF. SLAB REINF.

100
RECOMMENDING APPROVAL :
FLR. LVL. FLR. LVL. 20mm MIN. FLR. LVL. OFFSET VERTICAL BAR
20mm MIN.

SLAB

SLAB
CONC. COVER
CONC. COVER GRAVEL BED 1:6 SLOPE MAXIMUM

"t"

"t"
0.250

DOWEL LENGTH
VARIES
CONCRETE JOINT HEAD STRUCTURAL SECTION DATE

VARIES
0.100

0.100
T / SLAB

JOINT HOOPS

100MM
150mm THK. APPROVED BY :
0.400 SUBGRADE COMPACTED COMPACTED GRAVEL SUBGRADE COMPACTED COMPACTED GRAVEL SUBGRADE COMPACTED EXTERIOR CHB WALL
TO 95% OF MAXIMUM BEDDING (TYP.) TO 95% OF MAXIMUM BEDDING (TYP.) TO 95% OF MAXIMUM

0.200
COMPACTED GRAVEL DRY DENSITY @ OPTIMUM DRY DENSITY @ OPTIMUM DRY DENSITY @ OPTIMUM FOOTING TIE BEAM

NO LAP SPLICE

COL. HOOPS
BEDDING (TYP.) MOISTURE CONTENT (MAX. MOISTURE CONTENT (MAX. MOISTURE CONTENT (MAX. BUILDING OFFICIAL DATE
VAPOR BARRIER DEPTH OF COMPRESSED DEPTH OF COMPRESSED DEPTH OF COMPRESSED

HERE

Lo
WHEN REQUIRED FILL = (200mm PER LAYER) FILL = (200mm PER LAYER) FILL = (200mm PER LAYER)

H/4
Sh
SLAB - ON - GRADE CONSTRUCTION SLAB - ON - GRADE CONTRACTION
SLAB - ON - GRADE EXPANSION TYPICAL WALL TO TIE BEAM
JOINT DETAIL JOINT DETAIL
JOINT DETAIL CHB "t" DETAILS

CLEAR HEIGHT OF COLUMN ("H")


MAIN REINFORCEMENTS TO BE A PIPE SLEEVE MAIN REINFORCEMENTS

SPLICE ONLY WITHIN


CONTINUOUS (TOP & BOT. BARS) REQUIRED
30 BAR Ø (min) 25 MAXIMUM SPACING OF

COLUMN TIES

FOR SPLICE
THIS ZONE

SEE TABLE
30 BAR Ø 0.05030 BAR Ø 30 BAR Ø (min) TIES IN LAP LENGTH
CONCRETE FILLER (SMALLER BETWEEN W OR 100mm)

H /2

LS
t/2
DEPRESSION

"t"
D = FOR BEAM
2t = FOR SLAB

t/2
PIPE

VERIFY
CONCRETE Ø10 X 1.0m LONG @ 300 O.C.
FILLER (PLACED AT MID-DEPTH OF SLAB
D/2

IF THE LOCATION OF THE CONST.


JOINT IS NOT WITHIN THE MIDDLE
SLOPE 1:2 V:H MASTIC SEALANT

St
30 BAR Ø (min) THIRD.

12mm GAP
D/2

D = FOR BEAM EACH SIDE

(MIN.)
2t = FOR SLAB PIPE SLEEVE SUSPENDED SLAB CONSTRUCTION

NO LAP SPLICE
PIPE SLEEVE
COMPRESSIBLE MATERIALS

COL. HOOPS
PROVIDE 2 - Ø25 SHEAR BARS EACH REQUIRED JOINT DETAIL

HERE
CHB WALL

H/4
SIDE IF BEAM CONSTRUCTION JOINT 30 BAR Ø (min) 30 BAR Ø (min)

Lo
IS NOT WITHIN THE MIDDLE THIRD Sh
OF THE SPAN BEAM / SLAB CHANGE SOFFIT SECTION A - A
BEAM CONSTRUCTION DETAIL PIPE SLEEVE THRU WALL T / SLAB

DEPRESSION
D = FOR BEAM
2t = FOR SLAB
JOINT DETAIL

VERIFY
PROPOSED PIPE SLEEVE
2D (NO PIPE SLEEVE LOCATIONS
SCH. 40 G.I. PIPE SLEEVE
SHALL BE ALLOWED W/IN
2 - EXTRA STIR. EA. SIDE
THIS ZONE (TYP.)) 0.200
OF SLEEVE SLOPE 1:2 V:H
2D 2D 30 BAR Ø (min)
D = FOR BEAM
NOTES :
0 2t = FOR SLAB H = CLEAR HEIGHT OF COLUMN.
50 2 EXTRA STIRRUPS
.)

FACE OF W = SMALLER DIMENSION OF COLUMN CROSS SECTION.


YP

EACH SIDE OF SLEEVE


(T

TOP BARS SUPPORT Sh = HOOP AND SUPPLEMENTARY CROSSTIE SPACING NOT TO EXCEED W/4, 6db OF VERTICALS OR 150mm
TOP BARS
AND NEED NOT BE TAKEN LESS THAN 100mm
Ø16 EXTRA BARS BEAM / SLAB CHANGE SOFFIT

40
St = COLUMN TIE SPACING, NOT TO EXCEED 16db OF VERTICALS, 48db OF TIES, OR 150mm, WHICHEVER IS LESSER.
E.F. (DIAGONALS)
10MMØ TOP BARS
DETAIL Lo = LARGEST COLUMN DIMENSION, BUT NOT LESS THAN 16 OF CLEAR HEIGHT OR 0.50M
D

PIPE SLEEVE 0.050

D/5
@ 0.15M O.C. JOINT HOOPS = NO. OF HOOPS VARIES DEPENDING ON BEAM DEPTH
Ø 16 CROSS ANCHORS COL. HOOPS = SEE COLUMN SCHEDULE FOR SETS AND SPACING

40
WELDED TO SLEEVE COL. TIES = SEE COLUMN SCHEDULE FOR SETS AND SPACING
Ø 16 EXTRA BARS E.F.
(TYPICAL) BOTTOM BARS
BOT BARS SECTION A -A TYPICAL MOMENT FRAME

0.125

0.100
STIR. AS SCHED. NOTES :
FACE OF 4d (MIN.)
SUPPORT
PIPE SLEEVE MAXIMUM 1. SEEK STRUCT'L ENGINEER'S COLUMN DETAIL
0.30L L/2 0.30L DIAMETER APPROVAL FOR PIPE SLEEVES
LIMIT LOCATION OF PIPE SLEEVE IS : (LEAST GOVERNS) W/ DIAMETERS BIGGER THAN
THE MAXIMUM STIPULATED. 10Ø LONGITUDINAL BARS @
L 10MMØ BOTTOM BARS
0.30M O.C.
A) 15 OF BEAM DEPTH @ 0.25M O.C.
LEGEND : 2. PIPE SLEEVES SHALL BE LOCATED
1. D = DEPTH OF BEAM / GIRDER WITHIN TENSION ZONES OF BEAM.
B) 100mm 0.600
2. d = PIPE SLEEVE DIAMETER
3. NO PIPE SLEEVES SHALL BE
ALLOWED AT TWICE THE
PIPE SLEEVE THRU BEAM DETAIL BEAM DEPTH (2D) FROM
THE SUPPORT. TYPICAL CANTILEVER
0.400 W = 1.20m. (max) 0.400 0.400 W = 1.20m. (max) 0.400 SLAB SECTION

SEE WALL
SCHEDULE

550

WALLS LESS THAN


4-Ø16 VERT. BARS

200mm THK.
2 - 12mm Ø TOP & 2 - 12mm Ø TOP &
BOTTOM BARS (LINTEL BOTTOM BARS (LINTEL
550
BEAM CONNECT BEAM CONNECT
(TYP.)
COLUMN TO COLUMN) COLUMN TO COLUMN)
AT INTERSECTION
WINDOW
WALLS LESS THAN
OPENING
200mm THK.

2 - 12mm Ø VERTICAL
BARS (STIFFENER
DOOR COLUMN TERMINATE AT
H

OPENING LINTEL BEAM)


(TYP.)
550

(TYP.)
CHB CHB

550
WALL 2 - 12mm Ø VERTICAL WALL
BARS (STIFFENER
COLUMN TERMINATE AT
LINTEL BEAM)
550
(TYP.)
4-Ø16 VERT. BARS

AT CORNER
RC WALL CONNECTION AT
INTERSECTION
TYPICAL DOOR OPENING TYPICAL WINDOW OPENING
WITH LINTEL BEAM WITH LINTEL BEAM

FROM THE OFFICE OF : S E A L PROJECT TITLE : OWNER : SHEET CONTENT: SHEET NO.:
TRIMAR AS SHOWN
ALEX C. MAYOR JR.
CONSTRUCTION CIVIL/STRUCTURAL ENGINEER ENGR. RALPH BACOLOD S2
A PROPOSED COVERED COURT
& TRADING PRC NO.: 100124 PTR NO.: 1660761
MASBATE OIC PROVINCIAL ENGINEER
5
REG. DATE: 07 / 25 /2004 DATE: 01 / 08 / 2019
TALAMBAN, CEBU CITY TIN NO.: 232 - 213 - 366 PLACE: CEBU CITY LOCATION: MASBATE, PHILIPPINES ADDRESS: MASBATE, PHILIPPINES
0.30 L1 0.30 L1 0.30 L2 A B
20.00
COLUMN TIES/HOOPS
(SEE SCHEDULE)

N.G.L

0.200
A FTB1
7
C1 C1

F1 F1

50mm THK. GRAVEL BEDDING A


D

FTB2

FTB2
6.00
T1

T2
0.075

0.075
50mm THK. GRAVEL BEDDING 50mm THK. GRAVEL BEDDING

SECTION
L1 L2

BARS ALONG SHORT SPAN 6


C1 C1
BARS ALONG LONG SPAN
F1 F1

SCHEDULE OF STRUCTURAL PIPE BEAMS

FTB2

FTB2
6.00
W1

W2
INSIDE OUTSIDE
SECTION DIAMETER DIAMETER
5
C1 C1

F1 F1

PLAN
DIMENSION (mm)

FTB2

FTB2
6.00
L1 L2
DESIGNATION SCH. No. REMARKS
OUTSIDE DIAMETER INSIDE DIAMETER

3"Ø 40 88.9 73.7 TRUSS MEMBER


FOOTING 1 FOOTING 2 2"Ø 40 60.3 52.5 TRUSS MEMBER

TYPICAL TIE BEAM TO FOOTING DETAILS

36.00
4
SCALE 1 : 100 M C1 C1

F1 F1

FTB2

FTB2
6.00
SCHEDULE OF FOOTING
FOOTING DIMENSION FOOTING REINFORCEMENT
FOOTING DEPTH
ALONG SHORT ALONG LONG REMARKS
SCHEDULE OF BASE PLATES & ANCHOR BOLTS
NUMBERS (m)
L (m) W (m) T (m) SPAN SPAN BASE PLATE DIMENSION (mm) ANCHOR BOLTS
COLUMNS
1.60 1.60 0.30 1.10 7-Ø16 7-Ø16
WIDTH, B LENGTH, L THICKNESS, t DIAMETER (mm) LENGTH (mm) NO. OF PCS 3
F1 ISOLATED C1 C1
C1 400 500 16 20 1000 6
F1 F1
C3 400 400 16 20 1000 6

C4 450 450 16 20 1000 6

FTB2

FTB2
6.00
NOTES: fy = 248 MPa (A36 Steel)

SCHEDULE OF COLUMN SCHEDULE OF FOOTING TIE BEAM


0.500
DIMENSION BAR REBAR LONGITUDINAL BARS STIRRUPS WEB
MARK
B H DIA. LOCATION LEFT MIDSPAN RIGHT TYPE MEMBERS
0.400

FOOTING 2
TO TOP 6 6 6 C1 C1
ROOF FTB1 250 400 Ø16 B
12-20MMØ BOTTOM 3 3 3 F1 F1

TOP 4 4 4
CONF. REINF. 3SETS-11PCS 10MMØ @ 100MM Ø16 B
FTB2 250 400
COLUMN TIES 3SETS-10MMØ @ 150MM BOTTOM 3 3 3

FTB2

FTB2
6.00
JOINT REINF. 3SETS-10MMØ @ 100MM

DESIGNATION C1 MATERIAL SPECIFICATION:


f'c - 3,000 psi (20.7 MPa)
fy - 40,000 psi (275 MPa) for 16mmØ and smaller
- 60,000 psi (414 MPa) for 20mmØ and larger
MATERIAL SPECIFICATIONS
Concrete: fc' = 3,000 psi
Steel: fy = 40 ksi for 16mmØ and smaller STIRRUPS TYPE: FTB1
fy = 60 ksi for 20mmØ and larger B - 10 mmØ BAR SPA. @ 1-0.05 m, 12-0.10, REST @ 0.15 m TO MID SPAN 1
C1 C1

F1 FOUNDATION PLAN F1
SCALE 1 : 100 M

FROM THE OFFICE OF : S E A L PROJECT TITLE : OWNER : SHEET CONTENT: SHEET NO.:
TRIMAR AS SHOWN
ALEX C. MAYOR JR.
CONSTRUCTION CIVIL/STRUCTURAL ENGINEER ENGR. RALPH BACOLOD S3
A PROPOSED COVERED COURT
& TRADING PRC NO.: 100124 PTR NO.: 1660761
MASBATE OIC PROVINCIAL ENGINEER
5
REG. DATE: 07 / 25 /2004 DATE: 01 / 08 / 2019
TALAMBAN, CEBU CITY TIN NO.: 232 - 213 - 366 PLACE: CEBU CITY LOCATION: MASBATE, PHILIPPINES ADDRESS: MASBATE, PHILIPPINES
REPUBLIC OF THE PHILIPPINES
OFFICE OF THE BUILDING
OFFICIAL
MUNICIPALITY OF TUBURAN, CEBU

RECOMMENDING APPROVAL :

HEAD STRUCTURAL SECTION DATE

APPROVED BY :
SCHEDULE OF TRUSSES
PIPE 2"Ø SCH.40 BUILDING OFFICIAL DATE
STRUCTURAL PIPE
DESIGNATION SECTION

BOTTOM CHORD 3"Ø B. I. PIPE SCH40


500x400x16mm THK
3"Ø B. I. PIPE SCH40

0.75
20mm Ø x 1000mm BASE PLATE TOP CHORD
ANCHOR BOLTS
(6 PCS PER COLUMN) 2"Ø B. I. PIPE SCH40
25mm THK NON SHRINK
WEB MEMBERS
LEVELING GROUT
C - PURLINS PIPE 2"Ø SCH.40
REINFORCED 2"Ø B. I. PIPE SCH40 @ 0.80m O.C. STRUCTURAL PIPE
CONCRETE COLUMN
16mmØ PLAIN ROUND BAR WITH
CROSS-BRACING
TURNBUCLE
TYPICAL TRUSS TO RC COLUMN TYPICAL
SAGRODS 10mmØ PLAIN ROUND BAR
CONNECTION DETAILS STRUT DETAILS
SCALE 1:20 M SCALE 1:20 M
4.500
5.500

1.000

1.000 1.000 0.950 0.950 0.950 7 @ 0.95M = 6.65M 10 @ 0.95M = 9.50M 1.000

21.000

TRUSS DETAIL
SCALE 1:100 M

FROM THE OFFICE OF : S E A L PROJECT TITLE : OWNER : SHEET CONTENT: SHEET NO.:
TRIMAR AS SHOWN
ALEX C. MAYOR JR.
CONSTRUCTION CIVIL/STRUCTURAL ENGINEER ENGR. RALPH BACOLOD S4
A PROPOSED COVERED COURT
& TRADING PRC NO.: 100124 PTR NO.: 1660761
MASBATE OIC PROVINCIAL ENGINEER
5
REG. DATE: 07 / 25 /2004 DATE: 01 / 08 / 2019
TALAMBAN, CEBU CITY TIN NO.: 232 - 213 - 366 PLACE: CEBU CITY LOCATION: MASBATE, PHILIPPINES ADDRESS: MASBATE, PHILIPPINES
A B REPUBLIC OF THE PHILIPPINES

1.50 20.00 1.50 OFFICE OF THE BUILDING


OFFICIAL
MUNICIPALITY OF TUBURAN, CEBU

1.00
RECOMMENDING APPROVAL :
TRUSS
7
HEAD STRUCTURAL SECTION DATE

APPROVED BY :

6.00
BUILDING OFFICIAL DATE

TRUSS
6

6.00
TRUSS
5

6.00

STRUT

STRUT
36.00
TRUSS
4

ROOF FRAMING PLAN


SCALE 1 : 100 M

6.00

TRUSS
3
6.00

TRUSS
2
6.00

TRUSS
1
1.00

FROM THE OFFICE OF : S E A L PROJECT TITLE : OWNER : SHEET CONTENT: SHEET NO.:
TRIMAR AS SHOWN
ALEX C. MAYOR JR.
CONSTRUCTION CIVIL/STRUCTURAL ENGINEER ENGR. RALPH BACOLOD S5
A PROPOSED COVERED COURT
& TRADING PRC NO.: 100124 PTR NO.: 1660761
MASBATE OIC PROVINCIAL ENGINEER
5
REG. DATE: 07 / 25 /2004 DATE: 01 / 08 / 2019
TALAMBAN, CEBU CITY TIN NO.: 232 - 213 - 366 PLACE: CEBU CITY LOCATION: MASBATE, PHILIPPINES ADDRESS: MASBATE, PHILIPPINES

You might also like