Productivity of MIVAN SHUTTERING in 3days Cycle
Productivity of MIVAN SHUTTERING in 3days Cycle
Productivity of MIVAN SHUTTERING in 3days Cycle
Labour
Day Description % of Work Time Hours Total
Carp/Fitter Helpers
Day of Cast Wall reinforcement Lifting & Fixing 25% 9 13 6.30 pm 12.30pm 6 132
Wall reinforcement Lifting & Fixing 60% 7 10 8.30 am 12.30 am 15 255
Day 1 Cutting & Bending for next level 35% 2 3 8.30 am 12.30 am 15 75
Wall reinforcement Fixing 15% 7 10 8.30 am 12.30 pm 4 68
Day 2 Slab reinforcement Shifting,Lifting & Fixing 35% 7 10 2.00 pm 12.30 pm 10 170
Cutting & Bending for next level 35% 2 3 8.30 am 12.30 am 15 75
Slab reinforcement Fixing 65% 7 10 8.30 am 8.30 pm 12 204
Day 3 Cutting & Bending for next level 30% 2 3 8.30 am 12.30 am 15 75
1054
Reinforcement Quantity = 5.5 MT.