FMDS0281 Act1119
FMDS0281 Act1119
FMDS0281 Act1119
Table of Contents
Page
©2019 Factory Mutual Insurance Company. All rights reserved. No part of this document may be reproduced,
stored in a retrieval system, or transmitted, in whole or in part, in any form or by any means, electronic, mechanical,
photocopying, recording, or otherwise, without written permission of Factory Mutual Insurance Company.
2-81 Fire Protection System Inspection
Page 2 FM Global Property Loss Prevention Data Sheets
List of Tables
Table 1. Control Valves in Automatic and Manual Fire Protection Systems .................................................. 5
Table 2a. ITM Activities Applicable to All Types of Sprinkler Systems ........................................................... 6
Table 2b. Wet Sprinkler Systems .................................................................................................................... 8
Table 2c. Dry, Preaction, Vacuum, Deluge, Fixed-Water Spray, and Refrigerated Area Sprinkler Systems . 10
Table 2c. Dry, Preaction, Vacuum, Deluge, Fixed-Water Spray, and Refrigerated Area
Sprinkler Systems (continued) ..................................................................................................... 12
Table 3. Fire Hydrants, Standpipe Systems, and Monitor Nozzles .............................................................. 13
Table 4. Pressure-Relieving and Suction-Control Valves ............................................................................. 13
Table 5. Backflow Preventers and Single Check Valves .............................................................................. 14
Table 6. Fire Service Mains .......................................................................................................................... 14
Table 7. Fire Pumps ...................................................................................................................................... 15
Table 7. Fire Pumps (continued) ................................................................................................................... 15
Table 8a. Open-Water Sources .................................................................................................................... 19
Table 8b. Water Storage Tanks ................................................................................................................... 20
Table 8b. Water Storage Tanks (continued) ................................................................................................. 21
Table 9a. Gaseous and Dry Chemical Systems ........................................................................................... 22
Table 9a. Gaseous and Dry Chemical Systems (continued) ........................................................................ 23
Table 9b. Water Mist Systems ...................................................................................................................... 24
Table 9b. Water Mist Systems (continued) ................................................................................................... 25
Table 9c. Foam Sytems ................................................................................................................................ 27
Table 9c. Foam Sytems (continued) ............................................................................................................. 28
Table 10a. Prior To, During, and Following the Heating Season ................................................................. 29
Table 10b. Prior To and During Periods of Extreme Cold ............................................................................ 30
Table 11. Waterflow Recommended for Flushing Piping ............................................................................. 37
Table 12. Fire Protection System Inspection Frequency Comparison ......................................................... 50
1.0 SCOPE
This document provides guidance on inspection, testing, and maintenance (ITM) of privately-owned fire
protection systems that automatically or manually discharge fire extinguishing agents (e.g., water, foam, gas,
or dry chemical).
Refer to the applicable FM Global Property Loss Prevention Data Sheet for guidance on fire protection system
design, installation, and acceptance (commission testing).
Refer to the applicable data sheet for guidance on ITM of non-agent discharging fire protection systems,
including stand-alone fire detection systems (Data Sheet 5-48), and containment/drainage (Data Sheet 7-83).
Refer to Data Sheet 10-7, Impairment Management, for precautions to implement when a fire protection
system is out of service.
1.1 Hazards
For a description of the hazards associated with the lack of inspection, testing, and maintenance of fire
protection systems, see the following FM Global Understanding the Hazard (UTH) brochures:
• Lack of Inspection, Testing and Maintenance of Water-Based Fire Protection Systems (P0343)
• Improperly Closed Valves (P0035)
• Dry-Pipe Sprinkler Flushing Investigations (PO241)
• Freeze (P0148)
• Ice Plugs (P0118)
• Ice Plugs in Dry Pendent Sprinklers in Freezers (P0382)
• Fire Pumps (P0252)
• Hot Work (P0032)
• Lack of Emergency Response (P0034)
• Lack of Pre-Incident Planning (P0033)
1.2 Changes
October 2019. Interim revision. Added Appendix C, Fire Protection System Inspection Frequency
Comparison.
2.1 Introduction
Automatic fire protection systems are a reliable and effective means of mitigating fire risk, provided the
systems are properly designed, installed, and maintained. After system installation and acceptance testing,
implementing an ITM program will help ensure the fire system can be depended on to protect your facility.
It is equally important that, when inspection, testing, and maintenance operations are carried out, proper
planning and impairment procedures are followed to minimize the amount of time systems are out of service,
and to have in place a means to readily return the system to service in the event of an emergency during these
procedures. Coordination with the in-house emergency response team, as well as close supervision of any
outside contractors performing these services, are essential to minimize the hazard involved and reduce
the risk to the facility.
Tables 1-10 contain both frequency-based and event-driven ITM activities. Frequency-based activities are
listed with a baseline frequency, and references to any additional technical detail are included in the tables.
Appendix D contains sample forms to serve as checklists and/or to document the results of ITM activities.
These forms may be customized to meet the individual needs of a facility.
(or equivalent) and as outlined Data Sheet 10-7, Fire Protection Impairment Management, to ensure complete
precautionary measures are taken and ignition sources are controlled.
performance, and poor physical condition are instances in which a fire protection system may be considered
out of service. See Data Sheet 10-7 for examples of fire protection systems discovered to be out of service
through ITM.
2.4.1 General
Sections 2.4 through 2.12 contain recommendations for the scope and frequency of fire protection system
ITM activities. Some of these activities may be modified based on positive or negative factors present at the
facility. Clients of FM Global can discuss modifying ITM activities with an FM Global field engineer.
2.4.2 Fire Protection Control Valves in Automatic and Manual Fire Protection Systems
2.4.2.1 Perform control valve inspection and test activities for automatic and manual fire protection systems
in accordance with Table 1.
2.4.2.3 Secure control valves using the following methods. Note that a control valve is considered secured
when the valve operator is prevented from being manipulated more than one turn toward the closed position,
or at all for quarter-turn valves (e.g., ball valves).
A. Secure each control valve separately with a dedicated lock and chain. Secure control valves with a
sturdy, key-operated lock and chain capable of withstanding breakage except by heavy-duty bolt cutters
or similar hand tools. Do not use combination locks. Do not use seals or breakaway locks except when
valves are 1.5 in. (38 mm) nominal diameter or smaller, or control five or fewer sprinklers. Treat valves in
the waterflow alarm sensing lines actuating process and building interlocks as control valves in automatic
fire protection systems.
B. For a wall-mounted post-indicating valve, ensure the valve hand-wheel cannot be removed from the
valve stem when the valve is secured.
C. For a curb-box/road-way valve, secure all operating wrenches with a sturdy lock and chain, and inspect
valve sleeve for cover.
2.4.2.4 Limit the distribution of control valve keys to only individuals responsible for fire protection system
ITM, and local management.
2.4.2.5 Ensure control valves remain accessible in case of an emergency. Additionally, verify the appropriate
signage is in place to identify the control valve and, where necessary, signage is in place to quickly locate
control valves not readily visible.
2.5.1.3.4 Complete piping inspections from floor level unless large sections of piping are obstructed from
view or difficult to see (e.g., within combustible concealed spaces, automated storage retrieval systems or
buildings with tall roofs).
2.5.1.3.5 If damage is discovered during inspections, perform the following:
A. Test a random sample of sprinklers or replace sprinklers in accordance with Data Sheet 2-0.
B. Test a random sample of nozzles or replace nozzles in accordance with Data Sheet 4-2.
C. Protect sprinklers/nozzles, or control the environmental conditions that caused the damage, in
accordance with Data Sheets 2-0 and/or 4-2.
2.5.1.3.6 Increase the inspection frequency (from annually) when sprinklers/nozzles are exposed to harsh
environmental conditions (corrosives, dirt, dust, oil) or prone to impact.
Examples of harsh environmental conditions include process equipment containing elevated temperatures
and high humidity; caustic or acidic vapor, solvent vapor (e.g., dryers/ovens, oil cookers, paint-spray tunnels);
and exhaust ventilation systems conveying particulates or gases/vapor.
Examples of locations where sprinklers/nozzles are prone to impact include in-rack sprinklers within
warehouse racking and sprinklers positioned close to conveyor systems.
2.5.2.2 In systems where hard water is known or suspected, focus inspections at sprinkler-pipe connections
in the following areas:
A. Water-filled piping exposed to high-temperatures, such as in or near heated equipment, or at roof peaks
in warm climates.
B. Older sprinkler systems that have been frequently drained and refilled.
C. Pendent sprinklers located away from air pockets near convective currents (i.e., sprinklers and piping
at the lower portions of a system).
2.5.2.2.1 Inspect a random sample of sprinklers on several branch lines. Remove at least five sprinklers
from different branch lines and inspect the threaded pipe connection and sprinkler internals for deposits.
2.5.2.2.2 Document portions of the system investigated and the findings to ensure future investigations
building on previous inspections including: refrain from re-inspecting sections of the system previously found
free of deposits until the entire system is inspected; and revisit sections of the system where deposits have
been found.
2.5.2.2.3 When deposits are discovered, replace sprinklers containing deposits and widen the scope of the
investigation to include additional sprinklers and piping inspections.
2.5.3 Dry, Preaction, Vacuum, Deluge, Fixed-Water Spray and Refrigerated Area Sprinkler Systems
2.5.3.1 For dry, preaction, vacuum, deluge, fixed-water spray and refrigerated area sprinkler systems, in
addition to the ITM activities listed in Table 2a, conduct the ITM activities listed in Table 2c. Items 1-16 apply
to all dry, preaction, vacuum, deluge, fixed-water spray and refrigerated area sprinkler systems. Item 17
applies to preaction and vacuum systems. Items 18-20 apply to refrigerated area sprinkler systems. Items
21-24 apply to deluge and fixed-water spray systems.
Table 2c. Dry, Preaction, Vacuum, Deluge, Fixed-Water Spray, and Refrigerated Area Sprinkler Systems
ID Recommendation Frequency Details
1 Check system valve air and water Weekly
pressures (including for pilot lines).
2 Verify the quick-opening device for Weekly
in-service conditions, including equalized
air pressure and open control valves.
3 Confirm system valve enclosures are Weekly
maintained above 40°F (5°C).
4 Verify the automatic drain valve is open Monthly
and free to move.
5 Check priming-water level within the Monthly
system valve.
6 Check the condition of the compressed air Monthly
supply (including for pilot lines).
7 Visually check indicating desiccant in Monthly
compressed air dryers for saturation
(including for pilot lines).
8 Physically/visually check the condition of Every 3 years (Annually for - Physically check non-indicating
desiccant in compressed air dryers systems protecting areas desiccant for saturation.
(including for pilot lines). constantly maintained below
freezing) - Visually inspect both indicating
and non-indicating desiccants for
deterioration/breakdown.
9 Test quick-opening devices (QOD) without Annually if FM Approved
tripping the system valve. devices; otherwise quarterly
10 Determine the air leakage rate of the Annually Use leakage rates to:
system (including for pilot lines). - identify systems prone to false trip
during power outages (loss of
compressed air supply).
- determine when action is needed
to reduce air leakage rate or
improve the reliability of
compressed air supply.
11 Test supervisory alarms for low air Annually (Quarterly for Verify supervisory alarms surface on
pressure (including for pilot lines) and low systems protecting areas system control panels, fire alarm
temperature in system valve enclosures. constantly maintained below control panels, and/or at remote
freezing) monitoring stations.
12 Inspect and clean system valve internals Annually
and associated valve trim.
13 Partial-flow trip test system valves. Annually Verify the system valve trip point
(and trip time when possible) are in
agreement with the last full-flow trip
test results.
Table 2c. Dry, Preaction, Vacuum, Deluge, Fixed-Water Spray, and Refrigerated Area Sprinkler Systems (continued)
ID Recommendation Frequency Details
14 Full-flow trip test, videoscope or Every 3 years, or every 10 years for Verify systems can deliver water to
ultrasonic localized guided wave systems with nitrogen hydraulically remote areas within the
evaluation of systems. specified time. The maximum water
delivery time is 60 seconds unless
stated otherwise in an FM Global
data sheet specifically for the
occupancy or hazard being
protected. Use of videoscope or
ultrasonic localized guided wave
evaluation can determine if the
piping is clear of debris and can be
used as an alternative to confirm
delivery of water.
15 Check systems (excluding At 10 years, 20 years, and every 5 See Section 2.5.1.2.
refrigerated area systems and years thereafter
systems originally installed with
nitrogen) containing black steel pipe
for obstructive debris.
16 Check the system for obstructive After the 3rd false trip in 12 months
debris. on open water supply
For preaction and vacuum sprinkler systems, conduct items 1-16 and item 17.
17 Test control panels, fire detectors, Annually See Data Sheets 5-40 and 5-48.
and backup power supplies used to
actuate system valves.
For refrigerated area sprinkler systems, conduct items 1-16 and items 18-20.
18 Verify there is one duplex line in Monthly If ice is forming within the in-service
service supplying compressed air, duplex line, place the second duplex
and check the in-service duplex line line into service, and remove ice
for an ice plug. from the first duplex line.
19 Inspect sprinklers and piping for Quarterly Focus inspections on wall
exterior ice buildup. penetrations where warm moist air
could enter the freezer, including
above personnel and fork-truck
doors, and conveyor openings.
20 Check systems and pilot sprinkler Semiannually and after every Visually inspect pipe internals for ice
lines for ice plugs along with freeze system trip plugs by disassembly and visual
damage to piping and sprinklers. inspection, videoscope or ultrasonic
localized guided wave evaluation.
Inspect each branch line and cross
main to ascertain whether ice has
formed.
Table 2c. Dry, Preaction, Vacuum, Deluge, Fixed-Water Spray, and Refrigerated Area Sprinkler Systems (continued)
ID Recommendation Frequency Details Scope
For deluge and fixed-water spray systems, conduct items 1-16 and items 21-24.
21 Test control panels, fire detectors, Annually See Data Sheets 5-40 and 5-48.
and backup power supplies used to
actuate system valves.
22 Disassemble and inspect system Every 3 years Inspect system strainers for holes
strainers. and corrosion or mechanical
damage.
23 Flush system strainers until clear. After every system trip
24 Remove a random sample of After Every System Trip - Visually confirm waterflow and
nozzles and inspect nozzles, pipe proper spray distribution from
connections, and strainers for nozzles.
obstructive debris. - Compare base of riser and remote
pressure measurements to design
and/or acceptance results.
- If obstructions are suspected,
investigate using one of the
following methods:
a. Disassembly of piping and
visual inspection.
b. Full-trip test and nozzle
inspection.
c. Videoscope inspection in
accordance with 3.1.3.
d. Ultrasonic localized guided
wave evaluation in accordance with
3.1.3.
A. Confirm the pump controller is in automatic mode, and there are no trouble alarms registered on the
controller.
B. Confirm the pump room temperature is maintained above 40°F (4°C).
C. Visually check the fire pump installation before starting the unit to identify:
1. Evidence of loose, rusted, corroded or damaged pump/driver securement bolts
2. Lack of guarding for the pump coupling or other exposed rotating components.
3. Evidence of filings/debris beneath the pump coupling unit indicating coupling deterioration.
4. Evidence of excessive corrosion of piping connected to the pump unit.
If any of the above conditions exist, investigate and resolve the issue before continuing with any testing.
2.9.2.1.2 Test the Electric Fire Pump
A. Test the pump in automatic mode via pressure drop or waterflow alarm, and allow the pump to churn
for a minimum of 10 minutes.
B. At start and throughout the test:
1. Watch for any vibration or water leakage. Terminate churn or flow testing of fire pumps immediately
if there are any indications of excess vibration, unusual loud noise, or excessive leakage from the pump
packing, casing, or engine cooling system. Complete any repairs before resuming any churn/flow
testing.
2. Verify waterflow through the pump seals is adequate (if packed seals are installed).
3. Verify flow from the circulation-relief valve.
4. Verify the pump casing is not overheating.
5. Record suction and discharge pressures.
C. Position properly trained facility personnel at the fire pump controller during any churn or flow testing
to ensure prompt shutdown of the pump system if unusual conditions develop.
2.9.2.1.3 Following the churn-test:
A. Confirm the pump controller is in automatic mode.
B. If pumps are taking suction under lift, inspect the priming tank level and any fill controls.
2. Lack of guarding for the pump coupling or other exposed rotating components.
3. Evidence of filings/debris beneath the pump coupling unit indicating coupling deterioration.
4. Evidence of excess corrosion of piping connected to the pump unit.
If any of the above conditions exist, investigate and resolve the issue before continuing with any testing.
2.9.3.1.2 Test the Diesel Fire Pump
A. Test the pump in automatic mode via pressure drop or waterflow alarm, and allow the pump to churn
for a minimum of 30 minutes.
B. At start and throughout the test:
1. Look for any vibration or water leakage. Terminate churn or flow testing of fire pumps immediately
whenever there are any indications of excess vibration, unusual loud noise, or excessive leakage from
the pump packing, casing, or engine cooling system. Complete any repairs before resuming any
churn/flow testing.
2. Verify waterflow through the pump seals is adequate (if packed seals are installed).
3. If the engine is heat exchanger-cooled, at start and throughout the test verify raw water is flowing
through the engine heat exchanger.
4. If the engine is radiator-cooled, at start and throughout the test verify flow from the circulation-relief
valve.
5. Verify the pump casing is not overheating.
6. If a main-relief valve is installed to protect against diesel engine overspeed, verify water is not
discharging through the valve at churn.
7. If a right-angle gear-drive is installed, verify the gear-drive is not overheating (e.g., if water-cooled,
water is flowing through the heat exchanger).
8. Record suction and discharge pressures.
9. Record engine panel conditions including RPM, oil pressure, and coolant temperature.
C. Position properly trained facility personnel at the fire pump controller during any churn or flow testing
to ensure prompt shutdown of the pump system if unusual conditions develop.
2.9.3.1.3 Following the churn-test:
A. Confirm the pump controller is in automatic mode.
B. If the engine is heat exchanger cooled, inspect and clean the raw water cooling loop strainers as follows:
1. If fed by an open water source, inspect and clean the strainer in the automatic loop after each pump
start test.
2. If fed by a potable/filtered water source, inspect and clean the strainer in the automatic loop at least
semiannually.
3. Inspect and clean the strainer in the manual bypass cooling loop every time it is used.
4. Flushing connections on strainers can be used to clean strainers (weekly or semiannually); however,
remove and visually inspect strainers for damage at least annually.
C. Verify the diesel tank is at least 3/4 full or capable of providing 8 hours of runtime at 100% rated engine
load.
2.10.1.2 Inspect the water level in atmospheric storage tanks weekly if the water source is not equipped
with a supervised water-level alarm. Inspect monthly if the water source is equipped with a supervisory
water-level alarm that has been tested (with satisfactory performance) at least annually. Suction, break, and
gravity tanks are usually considered full when the water level is near the bottom of the overflow pipe inlet.
However, a greater distance below the overflow pipe may be required in FM Global 50-year through 500-year
earthquake zones to provide the necessary freeboard to accommodate water sloshing during a seismic
event.
2.10.1.3 Inspect, test, and maintain tank heating systems per the following:
A. Flush out the water-circulating pipe and heater in the autumn before the heating season starts, and
monthly during the heating season. After the first monthly flushing during the heating season, increase (to
not more than two months) or decrease the flushing time interval depending on the rate of sedimentation.
After flushing, make sure all valves are wide open, the drain valve closed, and the tank filled. If the tank
level is checked by overflowing, do not let ice form on the tank or tower.
B. In the autumn before the heating season starts, test the tank heating system; check the accuracy of
thermometers, pressure gauges, and low-water-temperature alarms, as well as the adjustment of relief
valves, steam regulators, pressure-reducing valves, thermostats, and safety pilots.
C. At the end of the heating season, clean and overhaul heaters, traps, strainers, and other accessories
as necessary. Take apart and renew gaskets of steam, electric, and hot water heaters. Wire brush the
steel or iron heating surfaces of coal, fuel oil, or gas-fired heaters and coat them with oil. Follow the
manufacturer’s instructions regarding lubrication. Have gas- or oil-fired heaters serviced and inspected by
a service organization during the summer.
D. Every five years, or at the interval recommended by the manufacturer, perform major inspection and
maintenance on heaters, steam coils, etc. (e.g., clean pipes, replace badly corroded pipe) per the
manufacturer’s specifications.
2.10.1.4 Perform a thorough visual inspection of water storage tank interiors at an interval not exceeding
five years. More frequent inspection may be necessary under certain conditions (e.g., a tank interior is not
protected by coatings or a liner, paint is exposed to unusually corrosive water or atmospheric conditions, the
5-year inspection indicates deterioration of the tank interior is occurring, or liners or fabric tanks are nearing
the end of their useful life).
Look for signs of debris, pitting, corrosion, spalling, rot, coating failure, liner or fabric tank weakness/failure,
failure or water saturation of insulation, aquatic growth, etc. Inspect interior piping, anti-vortex plates, heater
elements, ladders, etc. Inspect tank floors for evidence of voids beneath or leakage.
Perform at least every other inspection (i.e., at ten-year intervals) by draining the tank. Whenever the tank
is to be drained, restrain the empty tank as necessary to resist wind forces (if wind anchorage is not provided).
The inspection between these drained-tank inspections can be made by sending in a diver or remote-
controlled submersible with a camera if the tank can be adequately assessed using these methods. Drain
tanks that have internal heat exchangers to facilitate servicing those items.
Clean the tank interior and repair any deterioration as necessary. For steel tanks, if warranted by the visual
inspection, determine the remaining dry film thickness on tank interior surfaces and/or expand the inspection
to include nondestructive examination (e.g., ultrasonic testing) to evaluate for thinning of the tank walls.
Repaint/recoat the tank interior if needed to prevent corrosion. Replace interior liners and insulation if required.
Table 10a. Prior To, During, and Following the Heating Season
ID Recommendation Frequency Details
1 Disassemble, inspect, and clean accessible Annually - Dismantle and clean heaters, traps, strainers,
water storage tank heating system (following and other accessories accessible from outside
components. season) water storage tanks.
- Clean furnace heat transfer surfaces within fuel-
fired heaters.
- Maintain heating systems in accordance with
manufacturer guidelines.
2 Inspect and test fuel-fired water storage Annually
tank heater burners and fuel-train (following
safeguards. season)
3 Check enclosures containing system Annually
valves, fire pumps, and other wet-piping for (prior to season)
proper insulation; weather sealing around
enclosure penetrations; and in-service and
operable heating systems.
4 Check compressed air supply to dry, Annually
preaction, and deluge systems for (prior to season)
condensate when supply piping runs
outside heated enclosures.
5 Check dry-barrel fire hydrants for trapped After testing and
water. prior to season
6 Check insulation on the water storage tank, Annually
suction line, and refill line. (prior to season)
7 Flush water storage tank circulation heater Annually
and associated piping. (prior to season)
8 Test water storage tank and heating Annually
system temperature indicators, supervisory (prior to season)
alarms, and heater controls.
9 Test accessible water storage tank heating Annually
system components. (prior to season)
10 Disassemble, inspect, and clean heaters, Every 5 years
heat exchangers, and associated piping (during internal
within water storage tanks. tank inspection)
11 Maintain an equipment log of fuel-fired Daily (during the
heating systems for water storage tanks. season)
12 Check water storage tanks for in-service Weekly
heating systems, and verify the tank, (during the
suction line, and fill line are maintained season)
above 40°F (5°C).
13 Check open water sources for in-service Weekly (during
heating systems, if installed, and verify the the season)
suction line is maintained above 40°F
(5°C), the suction inlet extends below the
freeze line, and a vacuum breaker is
maintained within the ice.
14 Check enclosures containing system Weekly (during
valves, fire pump rooms, and/or other wet- the season)
piping for in-service heating systems, and
verify enclosures are maintained above
40°F (5°C).
15 Verify fire pump diesel engine is Weekly (during
maintained above 90°F (32°C). the season)
16 Purge condensate from dry and preaction Monthly (during
system low-point/auxiliary drains. the season)
17 Flush water storage tank circulation Monthly (during
heaters and associated piping. the season)
3.1.1.1 Securement
Securement is intended to limit control valve access. When left unsecured or poorly secured, arsonists can
disable fire protection systems by closing control valves and then setting fires in the now unprotected area.
FM Global loss history indicates would-be arsonists can include the general public, disgruntled employees,
and contractors. Restricting control valve access to individuals responsible for fire protection system ITM
will help ensure fire protection systems remain in-service to defend against arson.
The preferred method for securing control valves is to install a sturdy, dedicated lock and chain on each
valve in a manner that prohibits valve operator access and manipulation without heavy-duty tools.
3.1.1.2 Accessibility
Control valves should remain accessible for inspection and use during emergencies. Interior control valves
may become inaccessible as interior furniture, work-in-process on a production floor, warehouse stock, or
other moveable objects shift during normal operations at a facility or construction projects. To prevent blocking
access, control valves should be clearly marked with signs or stripping, or protected with physical barriers
such as guard-rails.
Exterior control valves are prone to similar accessibility concerns as interior valves in addition to a few hazards
specific to them. In cold climates, snow removal efforts can block or cover valves, while roadway resurfacing
or debris such as dirt and gravel can conceal curb-box/road-way valve covers. To help personnel maintain
access, control valves should be clearly marked and, if warranted, provided with free-standing signs or poles
to help identify valve locations and alert personnel to remove obstructions.
controlled a fire), or unfamiliar with the impairment management program. In either case, the impairment
management program may fail to be implemented or precautions inadequately followed, resulting in an ICV.
The likelihood of a passer-by recognizing an ICV by chance is low, with fire protection control valves often
hidden from sight and the inability of most building occupants to recognize a closed valve or other system
abnormality.
In order to function reliably, supervisory alarms must be installed and adjusted properly, made tamper-
resistant, tested periodically, and supervisory alarm signals not ignored. FM Global’s ICV loss history indicates
supervisory alarm systems do not always meet these guidelines.
Visual inspection verifies that most control valves are full-open as well as secured and accessible.
Physical testing is warranted on control valves where the position indicator is not intrinsic or reliably connected
to the valve gate or disc, or where an external position indicator is not provided. These valves require visual
inspection as well as less frequent physical testing to verify full-open position.
valve is open, shut, locked, or sealed. Provide space on the form for signatures of the valve inspector and
the facility manager responsible for taking action to correct any deficiencies.
• Should be arranged so that removal of the supervisory device from the valve to the extent that its
monitoring capability is adversely affected results in a trouble or supervisory condition being
communicated to the FACP.
• Should provide visual indication at the supervisory device when the device senses an off-normal
valve condition, to facilitate quick identification of the off-normal condition. The visual indication
should not be extinguished but latched on when the valve is restored to its normal condition and only
extinguished and reset after the alarm is acknowledged at the FACP. For applications where each
supervisory device can be identified individually by the FACP with an addressable interface, this
indication is not required.
C. Smart Valve Monitor
• Where security of fire protection control valves or process control valves is paramount, and/or for
large buildings, campuses, and processing sites, the coupling of FM Approved enhanced security
supervisory devices (valve monitors) with FM Approved Wi-Fi devices and associated systems
provides superior supervision of critical valves, as well as significant cost savings (eliminates costly
hard wiring).
Biological growth has been known to cause obstructions in sprinkler piping. Data Sheet 2-1, Corrosion in
Automatic Sprinkler Systems, covers the topic in detail.
E. Sprinkler Calcium Carbonate Deposits
Natural fresh water contains dissolved calcium and magnesium salts in varying concentrations, depending
on source and location of the water. If the concentration of these salts is high, the water is called “hard.” A thin
film composed largely of calcium carbonate, CaCO3, affords some protection against corrosion when hard
water flows through the pipes. However, hardness alone is not the only factor to determine whether a film
forms. Ability of CaCO3 to precipitate on the metal pipe surface also depends on the total acidity or alkalinity,
the concentration of dissolved solids in the water and the pH. In “soft” waters, no such film can form.
In automatic sprinkler systems, the calcium carbonate scale formation tends to occur on the more noble
metal in the electrochemical series, copper, just as corrosion will affect the less noble metal, iron.
Consequently, scale formation naturally forms on sprinklers often plugging the orifice. The piping may be
relatively clear. This type of sprinkler obstruction cannot be detected or corrected by normal flushing
procedures. It can only be found by removal and inspection of sprinklers in suspected areas.
Most public water utilities in very hard water areas soften their water to reduce consumer complaints of scale
buildup in water heaters. Thus, the most likely locations for deposits in sprinkler systems are where sprinklers
are not connected to public water, but supplied without treatment, directly from wells or surface water in very
hard water areas.
Applying guidelines for determining whether the system is free from obstructing material is often a judgment
based on the actual physical evidence obtained. Base the analysis on whether there appears to be sufficient
material of sufficient size that could obstruct the flow of water through smaller branch lines and sprinklers.
In selecting specific systems or branch lines for investigating, consider the following:
• Lines found obstructed during a fire or during maintenance work.
• Systems adjacent to points of recent repair to yard mains, particularly if hydrant flow shows material in
the main.
Include test flows through 2-1/2 in. (64 mm) fire hose directly from cross mains and flows through 1-1/2 in.
(38 mm) hose from representative branch lines. Two or three branch lines per system is considered a
representative number of branch lines when investigating for scale accumulation. If significant scale is found,
investigate additional branch lines. When investigating for foreign material (other than scale), the number
of branch lines needed for representative sampling is dependent on the source and characteristic of the
foreign material.
If the facility has a fire pump, ensure that it is in operation for all flows. Use burlap bags or equivalent to
collect dislodged material as is done in the investigation of yard mains. Continue each flow until the water
clears. Allow a minimum of 2 to 3 minutes at full flow for sprinkler mains.
1. Dry Pipe Systems
Flood dry-pipe systems one or two days before obstruction investigations to soften pipe scale and deposits.
Having selected the test points of a dry-pipe system, close the main control valve and release air from the
system. Check the piping visually with a flashlight while it is being dismantled. Attach hose valves and 1-1/2
in. (38 mm) hose to ends of lines to be tested, shut these valves and have air pressure restored on the system
and the control valve reopened. Open the hose valve on the end branch line allowing the system to trip in
simulation of normal action. Clear any obstructions from the branch line before proceeding with further tests.
After flowing the small end line, shut its hose valve and test the feed or cross main by discharging water
through a 2-1/2 in. (64 mm) fire hose, collecting any foreign material in a burlap bag.
After the test, internally clean and reset the dry-pipe valve. Lock its control valve open and conduct a drain
test.
2. Wet Pipe Systems
Testing wet systems is similar to testing dry systems except the system must be drained after closing the
control valve to permit the installation of hose valves for the test. Slowly reopen the control valve and make
a small hose flow as prescribed for the branch line, followed by the 2-1/2 in. (64 mm) hose flow for the cross
main.
In any case, if lines become plugged during the tests, piping must be dismantled and cleaned, the extent
of plugging noted and a clear flow obtained from the branch line before proceeding further.
Make similar tests on representative systems to indicate the general condition of the wet systems throughout
the facility, keeping a detailed record of what is done.
3. Videoscope Inspection
An advantage to this technique is that it allows an investigation during cold weather, and if the results are
not satisfactory, can indicate a direct need for full flushing without having to go through a flushing investigation
during cold weather. Use of videoscopic techniques can result in time savings when used in an appropriate
fashion.
The skill of the operator of the video scope equipment is definitely a factor in the final conclusions drawn.
Experience in the traditional flushing investigation method is essential in selection of test points and in
determining the number of representative points. When comparisons are made between the video image and
the debris collected from the burlap bag, a mapping is created. After several systems are evaluated, this
mapping becomes more evident. Without the prior knowledge of the traditional investigation method, it would
be difficult to draw any comparison.
There may be cases that arise where a conclusion cannot be made based on video scope examination alone.
The video scope method is most useful when the condition of the pipe is definitely bad or definitely good.
In those cases, where the conclusion can not be reached, conduct a traditional flushing investigation.
Flush connections from yard piping to sprinkler risers. These are typically 6 in. (150 mm) mains. Although
flow through a short open-ended 2 in. (50 mm) drain may create sufficient velocity in a 6 in. (150 mm) main
to move small obstructing material, the restricted waterway of the globe valve usually found on a sprinkler
drain may not allow stones and other large objects to pass. If presence of large size material is suspected,
a larger outlet will be needed to pass such material and to create the 750 gpm (2839 L/min) flow necessary
to move it. Fire service connections on sprinkler risers can be used as flushing outlets by removing or inverting
the check valve. Yard mains also can be flushed through a temporary fitting installed on the riser connection
before the sprinkler system is installed.
B. Sprinkler Piping
Two methods are commonly used for flushing sprinkler piping: 1) the hydraulic method; and 2) the Hydro-
pneumatic method.
The hydraulic method consists of flowing water progressively from the yard mains, sprinkler risers, feed mains,
cross mains and finally the branch lines in the same direction in which it would flow during a fire.
The Hydro-pneumatic method uses special equipment and compressed air to blow a charge of about 30
gal (114 L) of water from the ends of branch lines back into feed mains and down the riser, washing the foreign
material out of an opening at the base of the riser.
The choice of method depends on conditions at the individual facility. If examination indicates the presence
of loose sand, mud or moderate amounts of pipe scale, the piping can generally be satisfactorily flushed
by the hydraulic method. Where the material is more difficult to remove, and available water pressures are
too low for effective scouring action, the Hydro-pneumatic method is generally more satisfactory.
In some cases, where obstructive material is solidly packed or adheres tightly to the walls of the piping, the
pipe will have to be dismantled and cleaned by rodding or other means.
Flood dry-pipe systems with water one or two days before a flushing to soften pipe scale and deposits.
Successful flushing by either the hydraulic or Hydro-pneumatic method is dependent on establishing sufficient
velocity of flow in the pipes to remove silt, scale and other obstructive material. With the Hydro-pneumatic
method, this is accomplished by the air pressure behind the charge of water. With the hydraulic method,
ensure waterflow rates are at least the rates of flow indicated in Table 11.
When flushing a branch line through the end pipe, sufficient water must be discharged to scour the largest
pipe in the branch line. Lower rates of flow may reduce the efficiency of the flushing operation. To establish
the recommended flow, remove small end piping and connect the hose to a larger section, if necessary.
Where pipe scale indicates internal or external corrosion, clean and measure the pipe wall thickness to
determine if the walls of the pipe have weakened. Hydrostatically test the system as outlined in Data Sheet
2-0, Installation Guidelines for Automatic Sprinklers.
Remove several sample pendent sprinklers per system and inspect until it can be concluded that all sprinklers
are free of obstruction material.
Painting the ends of branch lines and cross mains is a convenient method for keeping a record of those
pipes that have been flushed.
1. Hydraulic Method
After the yard mains have been thoroughly cleared, flush risers, feed mains, cross mains and finally the branch
lines. In multi-story buildings, flush systems by starting at the lowest story and working up. Branch line
flushing in any story may follow immediately the flushing of feed and cross mains in that story, allowing one
story to be completed at a time. Following this sequence will prevent drawing obstructing material into the
interior piping.
To flush risers, feed mains and cross mains, attach 2-1/2 in. (64 mm) hose gate valves to the extreme ends
of these lines. Such valves usually can be procured from the manifold of fire pumps or hose standpipes.
As an alternative, an adapter with 2-1/2 in. (64 mm) hose thread and standard pipe thread can be used with
a regular gate valve. Attach a length of fire hose without a nozzle to the flushing connection. To prevent
kinking of the hose and to obtain maximum flow, install an elbow between the end of the sprinkler pipe and
the hose gate valve. Attach the valve and hose so that no excessive strain will be placed on the threaded
pipe and fittings. Support hose lines properly.
Where feed and cross mains and risers contain pipe 4, 5 and 6 in. (100, 125 and 150 mm) in diameter, it
may be necessary to use a Siamese with two hose connections to obtain sufficient flow to scour this larger
pipe.
Flush branch lines after feed and cross mains have been thoroughly cleared. Equip the ends of several branch
lines with gate valves, and flush individual lines of the group consecutively. This will eliminate the need for
shutting off and draining the sprinkler system to change a single hose line. Use a minimum 1-1/2 in. (38 mm)
hose diameter and keep it as short as practical. Branch lines may be flushed in any order that will expedite
the work.
2. Hydro-Pneumatic Method
The apparatus used for hydro-pneumatic flushing consists of a hydro-pneumatic machine, a source of water,
a source of compressed air, a 1 in. (25 mm) rubber hose, for connecting to branch lines and a 2-1/2 in. (64
mm) hose for connecting to cross mains.
The hydro-pneumatic machine consists of a 30 gal (114 L) water tank mounted over a 25 ft3 (700 L)
compressed air tank. The compressed air tank is connected to the top of the water tank through a 2 in. (50
mm) lubricated plug cock. The bottom of the water tank is connected through a hose to a suitable water
supply. The compressed air tank is connected through a suitable air hose to either the facility air system or
a separate air compressor.
To flush the sprinkler piping, the water tank is filled with water, the pressure raised to 100 psi (690 kPa, 6.9
bar) in the compressed air tank, and the plug cock between tanks opened to put air pressure on the water.
The water tank is connected by a hose to the sprinkler pipe to be flushed. Then the lubricated plug cock
on the discharge outlet at the bottom of the water tank in snapped open, permitting the water to be “blown”
through the hose and sprinkler pipe by the compressed air. The water tank and air tank must be recharged
after each blow.
Outlets for discharging water and obstructing material from the sprinkler system must be arranged. With
the clappers of dry-pipe valves and alarm check valves on their seats and cover plates removed, sheet metal
fittings can be used for connection to 2-1/2 in. (64 mm) hose lines or for discharge into a drum. (Maximum
capacity per blow is about 30 gal [114 l]). If the 2 in. (50 mm) riser drain is to be used, remove the drain
valve and make a direct hose connection. For wet-pipe systems with no alarm check valves, the riser must
be taken apart just below the drain opening and a plate inserted to prevent foreign material from dropping
to the base of the riser. Where dismantling of a section of the riser for this purpose is impractical, do not use
the hydro-pneumatic method.
Before starting a flushing job, each sprinkler system to be cleaned must be studied and a schematic plan
prepared showing the order of the blows.
To determine the piping is clear after it has been flushed. Investigate representative branch lines and cross
mains using both visual examination and sample flushing.
C. Branch Lines
With the yard mains already flushed or known to be clear, flush the sprinkler branch lines next. The order
of cleaning individual branch lines must be carefully laid out if an effective job is to be done. In general, flush
the branch lines starting with the branch closest to the riser and work toward the dead-end of the cross main.
The order of flushing the branch lines is shown by the circled numerals. In this example, the southeast
quadrant is flushed first, then the southwest, next the northeast, and last, the northwest.
Air hose, 1 in. (25 mm) in diameter, is used to connect the machine with the end of the branch line being
flushed. The hose should be as short as practical. When the blow is made, allow the air pressure to drop to
85 psi (586 kPa) (5.9 bar) before the valve is closed. The resulting short slug of water will have less friction
loss and a higher velocity and hence do a more effective cleaning job than if the full 30 gal (114 L) of water
is used. One blow is made for each branch line.
D. Large Piping
When flushing cross mains, completely fill the water tank and raise the pressure in the air receiver to 100
psi (690 kPa, 6.9 bar). Connect the machine to the end of the cross main to be flushed with not more than
50 ft (15.2 m) of 2-1/2 in. (64 mm) hose. After opening the valve, allow air pressure in the machine to drop
to zero. Two to six blows are necessary at each location, depending on the size and length of the main.
3.1.4 Overheating
Overheating means subjecting sprinklers to temperatures in excess of the recognized safe maximum
temperature in the absence of fire. It may result from hot processes, artificial heat, or lack of ventilation. If
the temperature approaches the rated operating temperature even for a short period, it may cause sprinklers
to open. If a solder-type sprinkler is exposed for a long time to a high temperature, although below its rated
temperature, the soldered joint may gradually give way, with partial separation of the soldered members.
This weakness will, in time, cause the sprinkler to operate.
Changes in occupancy that may affect room temperatures, such as increased drier temperatures, installation
of new heat-producing equipment, overhead heating coils or unit heaters, frequently cause premature
opening of sprinklers through overheating. When such changes are made, install sprinklers of higher ratings,
if needed.
Nominally rated 360°F (182°C) solder-type sprinklers may fail to open after prolonged exposures to
temperatures of approximately 300°F (149°C). The maximum allowable ambient temperature to which 360°F
(182°C) sprinklers may be exposed is 300°F (149°C). The suspected cause of failure is the migration of tin
from the high tin content solder alloy into the brass of the sprinkler link. Also, some of the brass’s copper
migrates into the solder. The result is a new, higher melting point alloy at the junction of the solder and brass.
Sprinkler manufacturers have altered the design of the link in an attempt to reduce solder migration. It has
not yet been determined whether this is an effective solution. Testing is recommended every three years to
verify the condition of 360°F (182°C) sprinklers that are exposed to high temperatures.
Bulb-type sprinklers and those using a chemical compound having a sharp melting point do not have the
“cold-flow” properties of solder and are not subject to danger of operation from long exposure to temperatures
below that of normal operation. In a very few instances, bulbs of sprinklers manufactured prior to 1931 have
developed minute cracks as a result of being repeatedly subjected to temperatures close to the operating
point. This allows liquid to escape, making the sprinkler inoperative. Replace the sprinkler if a bulb-type
sprinkler is observed with no liquid or less than the normal level of liquid in the bulb.
3.1.5 Corrosion
Corrosive atmospheres may build up deposits that prevent sprinklers from opening by attacking the solder
so it is chemically changed or becomes hard and infusible.
Typical corrosive atmospheres are produced by chlorine, phosphine, sulfur dioxide, zinc chloride, ammonia,
and hydrochloric, sulfuric and acetic acids. Corrosion of unprotected sprinklers can usually be detected by
effects varying from an inconspicuous discoloration of the frame and gray powder on the solder, caused by
acetic acid fumes, to the brilliant green caused by chlorine fumes.
External appearance is not always a sure guide, and badly corroded sprinklers may appear only slightly
discolored. Corrosion, once started, is usually progressive and in time renders the sprinkler completely
inoperative. A very thin hard corrosion on a sprinkler that has been in service 15 to 20 years is generally more
harmful than a loose bulky deposit on a more recently installed sprinkler, even though the older sprinkler
may appear to be in better condition.
All sprinklers are likely to become inoperative when hard deposits form around the valve-retaining members
and pack tightly between the arms of the yoke.
2. Accelerators and exhausters. Inspect the quick-opening device condition if provided. Inspect quick-
opening devices to make certain that (a) supply valves are open; (b) air pressure and system pressure
are equalized; and (c) excess water is drained off.
3. Riser temperature. Check the temperature in the dry-pipe valve room during winter months. Maintain
temperature at or above 40°F (5°C). Heat tape and steam tracing are not satisfactory substitutes for
a heated room or enclosure.
B. Monthly Inspections and Tests
1. Automatic drain. Make sure the automatic drain from the dry-pipe valve intermediate chamber is
free to move. With some valves, this requires lifting the rod that extends through the drain-valve
opening, or insertion of a rod or pencil through the valve opening if the drain valve is not so equipped.
Where the velocity-type of automatic drain valve is used, make sure by means of the push rod or by
feeling through the discharge end of the valve with a finger that the clapper or ball is off its seat.
2. Priming water. Priming water must be retained over the air clapper to prevent air leakage and
premature tripping of the valve. To test for priming water level, use the valve provided for that purpose.
However, all dry-pipe valves are not trimmed in the same manner, and it may be necessary to use
the priming water supply connection. Draw off excess water, which could prevent the dry-pipe valve
from tripping.
3. Air leakage. Make sure no air leakage has been caused by operation of test valves. Such leakage
can be detected by applying water or preferably soap solution to the valve stem at the packing nut.
Check for leakage at valves in the air supply line; loss of air here also can cause premature tripping.
Stop the leakage at valves by tightening the stuffing boxes.
4. Accelerators and exhausters. Check the operation of exhausters and accelerators (quick opening
devices) when the design permits testing without tripping the dry-pipe valves. Post and follow test
procedures based on the manufacturer’s recommendations. A sudden drop in air pressure will actuate
these devices and trip the dry-pipe valves. When it is necessary to reduce system air pressure, shut
off or deactivate the quick opening device. After completing work, be certain the equipment is left in
operating condition.
5. Low point drains. Just prior to and during freezing weather, test all low points by opening the drain
valve to see that pipes are entirely free of water or ice. Depending on the amount of condensate in
the piping, more frequent inspecting and draining may be necessary.
C. Quarterly Inspections and Tests
1. Alarms. Test alarms by admitting water through the test connections to the pressure switches and/or
water motors. Test hydraulic alarms only when pipes and water motors are not subject to freezing.
In prolonged cold spells see that moving parts are free and the pipes drained and clear of frost.
D. Annual Inspections and Tests
1. Trip Test
Annual trip testing of dry-pipe valves is recommended to ensure reliable operation. Record trip test
records and compare with previous test results. Record details of the trip test such as static water
pressure, system air pressure, and trip point air pressure and valve trip time after test valve air release.
Testing is the best means of determining whether adjustments, repairs, or replacement of parts are
needed. Valves that have not been operated for several years may fail or be very slow in action. Delayed
tripping of a dry-pipe valve in event of fire could be disastrous.
Make annual trip tests during the season when there is no danger of freezing. Also, if possible, make
trip tests when facility operations are shut down in the area controlled. If more than one valve can
be worked on at a time, select alternate systems to avoid impairments to large areas where protection
cannot be restored quickly. Before control valves are closed, follow the fire protection impairment
precautions outlined in Section 3.1.1.
Before the tests, see that controlling valves are open, and make the usual flow test from the 2 in. (50
mm) drain. If there is evidence of foreign material in the yard mains, flush them clean before the starting
other tests.
Examine automatic drip valves at the dry-pipe valve to make sure they are open, not obstructed with
scale or dirt, and operative so far as can be determined. Ball drips may be taken apart for this
inspection. Where there is central-station sprinkler supervisory service or flow alarms connected to the
public fire service, make arrangements to avoid calling out fire apparatus or messengers.
Release the air through the system test valve at the end of the sprinkler system in order to simulate the
operation of one sprinkler. Install a system test valve if one is not provided.
To prevent water from entering the sprinkler system, throttle the control valve to a position where flow
from a 2 in. (50 mm) drain would maintain about 5 psi (30 kPa, 0.3 bar) under the dry-pipe valve.
Immediately after the dry-pipe valve trips, close the control valve and open the drain valve. By keeping
as much water as possible out of the piping, drainage is made easier, especially if there are many
low points or pendent sprinklers.
Tripping dry-pipe valves with throttled water supplies will not completely operate some models that
require a high rate of flow to complete the movements of the parts. In that case, a higher flow rate may
be needed to ascertain that all parts are free to move and the valve trips properly.
After the test, thoroughly drain the system including low point drains and remove the cover plate from
the valve. Examine the position of the parts, and determine whether or not operation has been normal.
Thoroughly wash the inside of the body, and wipe the clappers dry with a clean cloth. Remove all dirt
and scale, giving special attention to the small valves or ports to drains and alarm devices. Examine
particularly for dirt under the clapper hinges; a large amount of dirt may indicate the system is
obstructed.
If rubber rings or seats are deformed or otherwise in poor condition, replace them with new parts
supplied by the valve manufacturer. Keep spare rubber on hand for quick replacement to avoid an
extended impairment.
2. Pitch of Pipes
Dry systems may freeze-up as a of water collecting in improperly pitched pipes. Carefully check the
pitch of all piping in dry-pipe systems each autumn, using a spirit level to detect dips and small pockets
in the lines. Sagging floors and roofs may seriously interfere with drainage even if the pipes were
properly pitched when installed. Replace broken, missing, or loose hangers, and otherwise restore the
system to ensure good drainage. Install valved drains at all low points that cannot be eliminated.
3.1.7 Hydrants
To ensure that a hydrant will work correctly when it is needed, a periodic testing and maintenance program
should be followed. AWWA Manual M17, Installation, Field Testing, and Maintenance of Fire Hydrants,
outlines various points to check, lubrication repairs and record keeping procedures to carry out a meaningful
inspection. Hydrants should be inspected yearly, and in locations of freezing climates, two inspections per
year may be appropriate.
C. Maintenance
• Lubrication
• Range of motion
• Mechanical stops are tight
4.0 REFERENCES
4.1 FM Global
Data Sheet 1-23, Fire Barriers and Protection of Openings
Data Sheet 2-0, Installation Guidelines for Automatic Sprinklers
Data Sheet 2-1, Corrosion in Automatic Sprinkler Systems
Data Sheet 3-7, Fire Protection Pumps
Data Sheet 3-10, Installation/Maintenance of Private Fire Service Mains and Their Appurtenances
Data Sheet 5-20, Electrical Testing
Data Sheet 5-40, Fire Alarm Systems
Data Sheet 5-48, Automatic Fire Detection
Data Sheet 7-83, Drainage Systems for Ignitable liquids
Data Sheet 9-18, Prevention of Freeze-Ups
Data Sheet 10-0, The Human Factor of Property Conservation
Data Sheet 10-3, Hot Work Management
Data Sheet 10-4, Contractor Management
Data Sheet 10-7, Fire Protection Impairment Management
Pocket Guide to Inspecting, Testing and Maintaining Fire Protection Equipment (P0418)
Managing Fire Protection System Impairments (P9006)
Hot Work Permit System Wall Hanger Kit (P9311K)
Fire Protection Control Valves (P9603)
Fire Pump Testing and Maintenance Checklist (P8217)
Freeze-up Checklist (P9521)
Understanding the Hazard: Lack of Inspection, Testing and Maintenance of Water-Based Fire Protection
Systems (P0343)
Understanding the Hazard: Improperly Closed Valves (P0035)
Understanding the Hazard: Dry-Pipe Sprinkler Flushing Investigations (PO241)
Understanding the Hazard: Freeze (P0148)
Understanding the Hazard: Ice Plugs (P0118)
Understanding the Hazard: Ice Plugs in Dry Pendent Sprinklers in Freezers (P0382)
Understanding the Hazard: Fire Pumps (P0252)
Understanding the Hazard: Hot Work (P0032)
Understanding the Hazard: Lack of Emergency Response (P0034)
Understanding the Hazard: Lack of Pre-Incident Planning (P0033)
4.2 Other
Compressed Gas Association (CGA). CGA C-6, Standards for Visual Inspection of Steel Compressed Gas
Cylinders.
Deluge valve: A control valve that automatically releases water to a piping system that supplies open nozzles.
DIOM: Design, installation, operation, and maintenance.
Dry-pipe valve: A control valve that, on loss of system air pressure, automatically releases water into a piping
system that supplies closed nozzles.
Dry pendant sprinkler: A dry extension to a sprinkler’s waterway that has an inlet seal that operates with
the sprinkler fusible element in order to keep water a specified distance from a sprinkler that may be located
in a freezing environment.
Enhanced security control valve: A valve fitted with or incorporating an FM Approved “Enhanced Security
Supervisory Device,” which has a greater level of tamper resistance and operational reliability than “Standard
Security Supervisory Devices” per the new FM Approval Standard 3135.
Fire department connection: A connection to the fire protection system through which the fire service can
pump supplemental water into the system.
Fire service: A term for firefighters in any area of the world. Includes fire departments, fire brigades, fire
and emergency services, and fire/rescue.
Fire hydrant: A valved connection on a water main for the purpose of supplying water to fire hose or other
fire protection equipment.
FM Approved: Products and services that have satisfied the criteria for FM Approval. Refer to the Approval
Guide, an online resource of FM Approvals, for a complete listing of products and services that are FM
Approved.
Foam concentrate: A liquid stored in a containment vessel that, when metered into a flowing water stream
at a specific concentration, will generate a foam-water solution for firefighting purposes.
Flushing: The practice of flowing water or pneumatically blowing through a fire protection piping system
for the purpose of removing obstructions.
Hose connection: A valve and connection method for fire hose.
Impairment: The planned or unplanned shutdown of a fire protection system.
Inspection: A visual examination that determines if a condition, device, equipment, or system is suitable
for service.
Main drain (2-inch drain): The primary drain for a sprinkler system located on the system riser.
Maintenance: Work conducted to ensure continued satisfactory operation of a device or system.
Manual: An operation that requires human intervention.
Obstruction: Foreign material in a fire protection system that restricts or prevents flow.
Open water supply: Fire protection water source that is open to an outdoor environment (e.g., reservoirs,
ponds, lakes, rivers).
Pre-action valve: A control valve that, upon some combination of detection of a fire and loss of system air
pressure, automatically releases water into a piping system that supplies closed nozzles.
Pressure reducing valve: A valve that will reduce the downstream fire protection water pressure under both
flowing and non-flowing conditions.
Scale: Thin surface deposits that develop on the interior of fire protection water pipe due to corrosion.
Smart valve monitor: An FM Approved “Enhanced Security Supervisory Device” fitted with an FM Approved
wireless/Wi-Fi secure/encrypted device and associated system, that provides near real-time surveillance
of control valves to any location/interface required.
Supervision: An automatic means of monitoring a system or a device status and indicating abnormal
conditions.
Test: To physically operate a device or system for the purpose of verifying operational condition.
6. Added annual obstruction investigation requirement for dry and pre-action systems that trip frequently
that take suction from open reservoirs.
7. Provided more specific guidance for special hazard protection systems (Table 8).
8. Removed guidance on non-OEM plating of sprinklers.
9. Added internal pipe corrosion guidance.
10. Clarified inspection frequency for hydrant control valves.
11. Clarified the water delivery time requirement of 60 seconds for dry system testing.
12. Added Zebra mussel obstruction information.
January 2006. Minor editorial changes were made for this edition of the data sheet.
September 2005. Minor editorial changes were made for this edition of the data sheet.
January 2003. Minor editorial changes were made for this edition of the data sheet.
January 2001. An FM Global comment has been added after Section 2.10, Condition of Sprinklers, outlining
requirements for sprinkler testing contained in NFPA 25, ‘‘Inspection, Testing and Maintenance of Water-
based Fire Protection Systems’’, and the FM Global position in that regard.
September 2000. This revision of the document has been reorganized to provide a consistent format.
July 1986. The following changes were made in:
1. The section entitled ‘‘Precautions Against Freezing’’ has been revised to include recommendations to
establish an active cold weather readiness program. Additional cold weather precautions based on loss report
recommendations have also been included.
2. The section on sprinkler system obstructions has been revised.
a) A recommendation has been included that all proposed preaction and dry systems should be installed
using galvanized piping. Loss studies have shown that dry-pipe systems are involved in the majority of
obstructed sprinkler system fire losses. Pipe scale was found to be the most frequent obstructing material.
b) The recommendation to flush dry system no more than 10 years after installation has been revised
to 15 years, 25 years and every five years thereafter. Loss studies have better defined those systems most
likely to be obstructed and to result in a large loss. The importance of flushing has been emphasized
by listing conditions that ‘‘do’’ rather than ‘‘may’’ indicate the need for flushing.
c) Discussion with regard to Asiatic Clams has been added. Thus far the majority of problems associated
with this clam have involved clogging of condensers, heat exchangers, pump impellers and other
associated water systems for power utilities and industry. However, there has also been an instance
reported to FM Global Research where two dry-pipe sprinkler valves failed to trip during testing due to
‘‘several buckets of clam shells’’ found on the wet side of the system. At several other locations, sprinkler
piping has been found plugged with shells and clam growth found inside protection mains. To date, no
effective method of controlling clam infestations has been established. The problem is still under
investigation. It is suspected that chlorination is the most practical method. Should chlorination be used,
it is suggested that clams within the fire protection system be exposed to a minimum residual chlorine
concentration of 0.2 ppm continually for a minimum three-week period. For control, the treatment should
be applied at least for one period in the spring and one period in the fall, the clam’s primary spawning
periods.
d) A recommendation regarding sprinkler cutouts (coupons) has been included. Originally, the problem
became apparent after investigating a fire in a spray booth involving two obstructed sprinklers. About 37
cutouts ranging in size from 1 to 4 in. (2.5 to 10.0 mm) were recovered from the sprinkler piping. They
had fallen into the pipe when the hole was cut for the welding operation. At least seven other locations have
been discovered with the same problem.
TRIPPING RECORD
TRIPPING RECORD
INSTRUCTIONS 1. Conduct a Full Flow Test on each PRV on site in accordance with FM Global O.S. 3.11.
2. Use a separate form for each different valve model number.
3. Forward a copy of test form to the FM Global address shown above.
4. Keep a copy of form on site for review of test record.
Valve Manufacturer’s Model Number Type of Valve Installation At:
Name ❒ Pilot Operated ❒ Sprinkler System
❒ Direct Acting ❒ Hose Connection
❒ Fire Main
❒ Other
Year Installed
Date Location of Valve Setting Static Residual Flow Performance Red Tag Comments/
& Valve Per Pressure Pressure Rate S = Satis. Permits Corrective
Initials (e.g., Floor Manufacturer (gpm) U = Unsatis. Used Action
No. Specs. Needed
Standpipe
No.)
Inlet Outlet Inlet Outlet Yes No
(psi) (psi) (psi) (psi)
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
❒ ❒
The FM Global RED TAG PERMIT SYSTEM is used to guard against delayed reopening of valves. The FM Global RED TAG PERMIT
SYSTEM should be used every time a sprinkler control valve is closed. When the valve is reopened, the drain should be flowed wide open
to be sure there is no obstruction in the piping. The valve should then be relocked.
Address Date: