DEVELOPMENT PACKAGES QUETTA CITY

WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
PC-1 FORM
(INFRASTRUCTURE SECTOR)

1. Name of project Clearing /Aligning & Reconstruction of Sariab


Road 7.6km.

2. Location

 Provide name of the District Quetta/ Baluchistan


district/province
 Attach a map of the area, Attached at Annexure A.
clearly indicating the project
location

3. Authorities responsible for

I. Sponsoring Government of Baluchistan


II. Execution Planning & Development Department, Quetta.
III. Operation and
maintenance Planning & Development Department, Quetta.
IV. Concerned
Provincial Ministry
N.A

4. a) Plan provision

 If the Project is included in


the medium term/five year plan, N/A
specify actual allocation.
 If not included in the
current plan, what warrants its N/A
inclusion and how it is now
proposed to be
accommodated? N/A
 If the project is proposed to
be financed out of block
provision, indicate:

Total block Amount already Amount proposed for this Balance Amount
Provisions committed project
Rs.5,443.96 Millions

b) Provisions in the current year Current PSDP


PSDP/ADP

5. Project objectives
 The objectives of the Quetta, Located in North-Western

1
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

sector/sub sector as indicated in Baluchistan near Pakistan-Afghanistan border is


the medium term/five year plan be the Ninth (09) largest city of Pakistan. The city
reproduced. Indicate objectives of lies on Bolan Pass route, being the only gateway
the project and develop a linkage from Central Asia to South Asia having a total
between the proposed project and area of 2,656 Sq. k. meter.
objectives.
Quetta is the provincial capital of Baluchistan.
People from every corner of Baluchistan shift to
Quetta because better educational and health
facilities are available there.

Currently private transport is the major means of


mobility comprising of Mazda, Toyota Hiace, and
Suzuki Vans plying on various routes.

Quetta is facing diverse range of challenging


issues regarding transportation and mobility.
Quetta roads have become congested with traffic
due to poor traffic planning and management. A
lot of time is wasted during traffic blocks
especially during peak hours. Projects is within
the urban suburbs of the city.
The rehabilitation aims to facilitate the inhabitants
of Quetta City.

 In case of revised projects, The Project namely “Clearing/Aligning &


indicate objectives of the project if Reconstruction of Sariab Road” with total length
different from original PC-1 of 10.6 KM at grade improvement
(3lane+Service/Parking Lane with Junction
Improvement) was approved in PDWP held on
25-08-2017 with cost of Rs. 4.217 Billion. It was
in Federal PSDP and Rs. 1500 Million was
approved as bridge financing by Chief Minister
through summery dated 21-11-2017. The tenders
were floated and authorized by P&D on 20 Feb
2018 and the Finance Department released the
funds of Rs. 1500 million on 7th March 2018. The
work order was issued on 8th March 2018. The
matter was expedited on the direction of Chief
Minister.

The Federal Government deleted the scheme in


the PSDP of 2018-19 but the work had been
awarded in anticipation. This revised PC-1 is
being submitted covering 7.6km of road from
Irrigation Colony to Custom (3lane+Parking
Lane). The Project Road Length is curtailed from
10.6km to 7.6km considering indecision on first
3km reach. First 3km reach is in congested area
with three major intersection which required huge
land acquisition in case of widening and Junction
Improvements.

In the revised PC-1 there is saving in Bill No 1, 5,


6 and 8 because of reduction in length whereas
2
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

Bill No 2,3 and 4 are marginally increased


because of Shifting of Centerline towards left.

.
6. Description and Justification of Refer Annexure – F
project (enclose feasibility study for
projects costing Rs. 300 million &
above).
 Describe the project and Being provincial capital and center of economic
indicate existing facilities in the and service activities, Quetta City attracts traffic
area and justify the establishment from all over the country. Roads have become
of the project. congested with traffic due to poor road
infrastructure, traffic planning and management.
The proposed QDP projects are planned to attain
objectives like alleviating congestion on the
arterials carrying traffic to city center, to improve
the operation of critical intersections in the city
and to reduce overall travel time along city
network.

The Project will be able to contribute in the socio-


economic development of city as the project will
help in the revival of local economy, it will bring
more population into the stream of benefits,
which in turn will change to the social appearance
of people around this, in addition to the time
saving. The project will transform the entire
pattern of transportation in the surrounding areas
resulting in the uplift of economic conditions of
local community.

This widening aims improvement in a stretch of


almost 7.6 Kms. Many other connecting roads
offshoot from Sariab Road which include roads
to, Link Badini Road, Hazar Ganj Road, and
Mastung Road. The junctions for all these roads
shall also be improved for easy flow of traffic. U
turns have also been provided along this length
to avoid traffic congestions on junctions.

 Provide technical parameters The Geometric Design of the project is governed


i.e. input and output of the project. by prevalent standard codes for highways design.
Also discuss technological aspect The Geometric design parameters shall be
of the project. implemented as per the site conditions.

Main Road
Right of Way = 43.3 m (142’)
No of Lanes =3
Lane Width = 3.6 m
Parking Lane = 4.5 m
Inner Shoulder = 0.6 m
Median Width = 1.5 m

Pavement Structure
3
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

 Main Carriageway
Asphaltic Wearing Course = 5 cm
Asphaltic Base Course = 14 cm
Agg. Base = 20 cm
Sub base = 15 cm

Subgrade with minimum soaked CBR of 20%


@95%M.D.D.

Typical cross-sections are attached as


Annexure-B.

 Provide details of civil works, Refer Annexure – D for details of civil works.
equipment, machinery and other Resources to be arranged by the construction
physical facilities required for the firm.
project.

 Indicate governance issues of ---


the sector relevant to the project
and strategy to resolve them.

Transport & Communication

 Provide technical parameters Refer above Para-6 and Annexure - C


i.e. selected design features and
capacity of the proposed facilities
along with alternates available.

 For roads, provide Refer Annexure - B


information regarding lane width,
geometric and pavement design
including formation width,
pavement width.
 Design speed, traffic capacity 60km/hr
of road in terms of passenger car 1,53, 000 PCU/day
units per day.

 Saving in distance for


diverted traffic. Average daily Refer Annexure – F (Economic Analysis)
traffic of motor vehicles by
category as well as the car units
be provided.

 In case of improvement within Refer Annexure – B


the urban area, separate traffic
counts within that area should be
given. Brief information regarding
traffic and pavement width etc. in
adjoining section should also be
given.

4
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

 For bridges provide location, Nullah Bridge at km 6+125


total length of bridge, number of (L=26m, W=46m)
spans with length of each span, Single Span
width roadway and footpath, type
of sub and super structure and
load classification.
 Indicate date of estimation of July 2019
Project cost.

 Basis of determining the


capital cost be provided. It
includes market survey, schedule NHA – CSR 2014
rates, estimation on the basis of
previous work done etc.

 Provide year-wise estimation Refer Annexure – G


of physical activities

7. Annual Operating Cost

 Item-wise annual operating Source of financing will be


cost based on proposed Government of Baluchistan
capacity utilization be worked
out for 5 years and sources of its
financing.

8. Demand and supply analysis


 Existing capacity of services Refer Annexure – C
and supply/demand.
 Project demand for 10 ---
years.
 Capacity of the projects ---
being implanted in public/private
sector.
 Supply-demand gap. ---
 Designed capacity and ---
output of the proposed project.

9. Financial Plan

Sources of Financing

a) Equity
Indicate the amount of equity to be financed from each source.

Sponsor’s own resources Government of Baluchistan


Federal Government --
Provincial Government YES
DFT’s / banks --

5
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

General public --
Foreign public --
NGO’s / benefits --
Others --

b) Debt
 Indicate the local & Foreign debt, N/A
interest rate, grace period and
repayment for each been separately.
The loan repayment schedule be also
annex.
c) Grants N/A

d) Weighted cost of capital N/A

11. Benefits of the project and analysis


 Financial N/A
 Economic Annexure-F
 Social ---
 Environmental Annexure- E

Financial/Economic Analysis (with-assumptions)

 Quantifiable output of the project N/A


 Profit and loss account and Cash Flow statement N/A
 Net present value (NPV) and Benefit Cost Ratio N/A
 Internal financial rate of return (IFRR) N/A
 Unit cost analysis N/A
 Break even Point (BEP) N/A
 Payback period N/A
 Return on equity (ROE) N/A

 Economic analysis

 Provide taxes & duties separately in the capital and N/A


operating cost
 Net present value (NPV) and benefit cost ratio BCR) Refer Annexure-F
 Internal economic rate of Return (IERR) Refer Annexure-F
 Employment analysis
 Employment generation (direct and indirect) N/A
 Sensitivity analysis
 Impact of delay on project cost and viability N/A

12. Implementation Schedule

 Indicate starting and completion date of the Twenty Four (24)


project. Months
 Item-wise/year-wise implementation schedule Refer Annexure – G
in line chart correlated with the phasing of
physical activities.
13 Management Structure and Manpower Requirements

6
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

 Administrative arrangements Manager Admin 1 No.


for implementation of project. Office Engineer 1 No.

 The manpower requirements Soil Engineer 1 Nos.


by skills during execution and Design Engineer 3 Nos.
operation of the project be Civil Engineers 4 Nos.
provided. Electrical Engineer 1 Nos.
Mechanical Engineer 1 Nos.
Skilled 100 Nos.
Unskilled 50 Nos.
 The job description, --
qualification, experience, age
and salary of each post be
provided.
14 Additional project/decision required

 Indicate additional --
projects/decision required to
optimize the investment being
undertaken on the project.

15 Certificate

 The name, designation and Project Director


Phone # of the office Planning & Development
responsible for preparing and Department, Quetta.
checking be provided. It may
also be confirmed that PC-I
has been prepared as per
guidelines issued by the
Planning Commission for the
preparation of PC-I for
Infrastructure Sector projects.

 The PC-I alongwith certificate


must be signed by the Principal
Accounting Officer to ensure its
ownership.

7
DEVELOPMENT PACKAGES QUETTA CITY
WIDENING/ IMPROVEMENT OF SARIAB ROAD (km3 to km10.4).

Prepared by PM/RE
NESPAK

Forwarded by Project Director


P&D Deptt.
Development Packages, Quetta City.

Approved by Additional Chief Secretary


P&D Deptt.
Govt. of Baluchistan