Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Assessment (Project Operation) 2

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

ASSESSMENT

PROJECT (OPERATION)
OPERATION & IMPLEMENTATION

Candidate Name:
Interview Date:

REV 01
ASSESSMENT | PROJECT | OPERATION | EXECUTIVE / SENIOR EXECUTIVE

QUESTION 1
Company A plan to develop one (1) Apartment building on a piece of land (3 acres) in Kuala Lumpur City
comprised of 500-unit Type A with 3 bedroom and 2 bathroom and standard size of 1000sqft.

No Item Detail
1. Selling price of Apartment (Type A) RM 500/sqft
2. Total Construction Cost (TCC) @ GFA = 900,000sqft RM 200/sqft
3. Marketing Cost 2% of GDV
4. Professional Fees 6% of TCC
5. Land Price RM 1mil / acre
6. Land Cost & Land Related Cost RM 1 mil
7. Authority Fees / Related Charges RM 2 mil
Table 1: Development Information

Board of Director for Company A decide to develop the Apartment if they can obtain 25% of Profit Margin.
Based on information given above, calculate item a, b, c, d and predict management decision either to proceed
or not to proceed with this development.

a) Gross Development
Value (GDV) (RM)

b) Gross Development
Cost (GDC) (RM)

c) Gross Development
Profit (GDP) (RM)

d) Profit Margin (%)

Management Decision

2
TEMOKIN DEVELOPMENT SDN. BHD. (PRIVATE & CONFIDENTIAL)
ASSESSMENT | PROJECT | OPERATION | EXECUTIVE / SENIOR EXECUTIVE

QUESTION 2
a) Describe is short (simple point would be advisable) with example (if necessary) on your understanding of
the item below:

i) Relationship of
Liquidated Ascertain
Damages (LAD) and
Extension of Time
(EOT)

ii) Different of Non-


Conformance Report
(NCR) and Corrective
Action Request (CAR)

b) Based on issue below, come out with your idea / strategy / action plan should be taken to resolved it.

Project A is based on PAM Contract 2006. During construction of ground beam, client realized that contractor
putting sand blinding (as per BQ) instead of concrete blinding (as per tender & construction drawing). The
concrete casting work for the beam has been done. Client just realized there are different in drawing and BQ
after they went to site. As per C&S requirement, the ground beam need to be installed with concrete blind
instead of sand blinding.

c) A developer company just bought a piece of Agricultural land (freehold) located in Selangor (City Council)
with price of RM 2.3 mil (under Agricultural title). They plan to develop a residential development for the
said land after knowing that the land zoning is under Residential. After conducting land valuation, the market
price of the land is RM 5.6 mil (under Residential title).
Based on Town and Country Planning Act 1976 (Act 172) – Development Charge Rules 2010, calculate
the estimated amount of development charges that may need to be paid by the developer to change in use
of the said land.

3
TEMOKIN DEVELOPMENT SDN. BHD. (PRIVATE & CONFIDENTIAL)
ASSESSMENT | PROJECT | OPERATION | EXECUTIVE / SENIOR EXECUTIVE

QUESTION 3
Company YYY Development Sdn. Bhd. would like to develop a parcel of land located in Kuala Lumpur. The
general task and budget required is as per table below. Board Director would like to see the summary planning
and how the budget to be spend for this development.

Duration Start Date Budget


No Task Remarks
(Month) (Month) (RM)
1 Purchased of Land 1 1st January 22 4 mil -
Appointment of Consultant Budget to be prorate by
2 2 1st February 22 2.2 mil
Team month
3 Design Development 4 1st April 22 - -
Submission & Approval of Half of budget to be paid
4 Planning and BP by 6 1st August 22 2.6 mil at first month, another half
Authority to be paid on last month
Tender Documentation -
5 2 1st February 23 -
Preparation
6 Award Contract - 1st April 23 - Milestone
Site Possession & -
7 1 1st April 23 0.6 mil
Preliminary Work
8 Earthwork 1 1st May 23 1.2 mil -
Budget to be prorate by
9 Piling & Structure Works 6 1st June 23 3 mil
month
Budget to be prorate by
10 C&S and Architecture Works 8 1st September 23 20 mil
month
Budget to be prorate by
11 Electrical Works 8 1st November 23 4 mil
month
Budget to be prorate by
12 Infra Works 4 1st April 24 6 mil
month
Completion of Construction Milestone
13 - 1st July 24 -
Works (CPC)
14 Process & Obtained CCC 4 1st August 24 - -
15 Vacant Possession - 1st December 24 - Milestone
Table 2: Project Information
Based on information given in Table 2,
a) By using highlighter, prepare Gantt Chart by transferring information in Table 2 into Gantt Chart template
provided in Appendix A.
b) On the same sheet (Appendix A), key in budget (in RM mil) inside the box based on construction cost
required for the task and sum the figure inside Amount and Cumulative amount cell.
c) Based on task done for item (a) and item (b), what is the total budget required on the Month of November
2023?
d) Finance managers inform that based on the company forecast from January 2022 up to April 2024,
company only able to inject budget of RM 30mil to be spent for this project.

Does the budget provide by Finance is enough? If No, how much additional budget required in April 2024?
4
TEMOKIN DEVELOPMENT SDN. BHD. (PRIVATE & CONFIDENTIAL)
ASSESSMENT | PROJECT | OPERATION | EXECUTIVE / SENIOR EXECUTIVE

APPENDIX A

Y1 (2022) Y2 (2023) Y3 (2024)


No Task
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

1 Purchased of Land

2 Appointment of Consultant Team

3 Design Development

4 Submission & Approval of Planning

5 Tender Documentation Preparation

6 Award Contract

7 Site Possession & Preliminary

8 Earthwork

9 Piling & Structure Works

10 C&S and Architecture Works

11 Electrical Works

12 Infra Works

13 Completion of Construction Works

14 Process & Obtained CCC

15 Vacant Possession

Amount (RM mil)

Cumulative Amount (RM mil)

You might also like