Assignment Communication and Schedulling
Assignment Communication and Schedulling
ASSIGNEMENT - 2
SUBMITTED BY
RAJNISH KUMAR
Student ID: 041024388
Submitted on 22-FEB-2021
1. INTRODUCTION ...............................................................................................................3
2. PURPOSE OF THE DOCUMENT ......................................................................................3
2.1. Issues during project execution .........................................................................................3
3. Bedroom 1 Egress Window widening ..................................................................................3
4. BUCKHEAD IN THE DRY WALL ....................................................................................4
5. Exiting plumping in the bathroom ........................................................................................4
6. DELAY IN EXTERIOR DOOR DELIVERY ......................................................................4
7. SCHEDULE AND MILESTONES ......................................................................................5
7.1. Milestone list ....................................................................................................................5
8. PROJECT COSTS ...............................................................................................................5
8.1. Budget summary ..............................................................................................................5
9. COMMUNICATION ...........................................................................................................7
Neetu Saini (OWNER) has recently contracted Kumar Renovators (CONTRACTOR), for basement
renovation project. During the project execution few issues appeared that may need evaluation for
possible changes to schedule and change orders.
Purpose of this document is to detail out the schedule impacts dur to extended lockdown on Ontario
and bad weather during February 2nd week on the project. The document will briefly summaries the
impact, present the revised schedule and list out the stakeholders for communication of the revised
schedule.
During the inspection by architect, it was noted that the window of bedroom one need widening to
meet the statutory requirements. The new window details have been advised by the architect to
owner. Owner has required an estimate of cost and schedule impact for the same.
Following is a list of activities foreseen at the moment for this additional scope.
1. Dig the grade from outside and install window well
2. Install Snow protection sheets
3. Remove Existing window
4. Setup temporary supports and widen the window opening
5. Install New Hopper window
6. Slope the trench and fill in two layers of gravel
7. Install Drip cap
It is expected that this additional work will take 3 days to complete the work with a cost impact of $ 4,500
While demolishing the dry wall between kitchen and the living room, it was noticed that the wall
contains a 6” x 6” load bearing column which cannot be removed. Removal of the wall was initially
planned to make space for island and two high chairs.
CONTRACTOR propose to leave the column as it is to be in centre of the Island. Column cane be covered
with wall paper all around to suit the interior design.
It is expected that this additional work will take 1 day to complete the work with a cost impact of $ 250
During project bidding, existing plumbing between bathroom and the mechanical room was considered
to be suitable for reuse. However, after demolition of bathroom and inspection, the existing plumping is
found not suitable for long term use. Owner requested to replace existing plumbing before installing
floor tiles
It is expected that this additional work will take 1 day to complete the work with a cost impact of $ 650
Exterior door manufacturer advised that due to extended lockdown, its manufacturing facility has a long
backlog to be completed before the door can be manufactured. Revised delivery date is advised as 7th
April-2021.
8. PROJECT COSTS
9. COMMUNICATION
This document is to be sent to Owner, Project manager and Architect for their approval. Once
approved, the information will be sent to all the stake holders as per following Matrix.
Project manager
Neighbour
Electrician
Carpenter
Labourer
Architect
Plumber
Supplier
Communication Owner
Change proposal C C A
Approved change
order I I I I I
Unpriced change order
Priced only to be shared