Technical Proposal
Technical Proposal
Technical Proposal
Date
TECHNICAL PROPOSAL
TABLE OF CONTENT
Sl NO Description
1 Project Execution Strategy
2 Project Description
3 Material Supply
4 East Gas`s Responsibilities
5 EPC`s Responsibilities
6 Exclusion from EPC scope
7 Organization Details
8 Manpower List
9 Equipment List
10 Project Master Schedule
11 Quality Control Procedure
12 HSE Procedure
13 List of Similar Past Experience
14 Safety Instruction
15 House Keeping
TECHNICAL PROPOSAL Rev. Date
Currently, an existing gas supply network has been installed by East Gas Company Limited
(EGCL) to supply fuel gas (natural gas) for plants & factories in 2nd Industrial City,
Dammam.
EPC is fully committed to successfully complete this Project in the shortest possible time,
confident with the technical, operational, quality, safety and contractual requirements. The
basic frame work of our plan is founded on our extensive and recent experience on similar
projects.
Our management is fully aware of the various requirements to work in the Areas.
Following are the key areas, which have been taken into consideration to execute a
successful Project:
PROJECT DESCRIPTION:
Procure, construct, test and commission for the new gas supply branch line
to new three customers
Mobilization
Topographic surveys and other field reconnaissance required for proper construction of
the fuel gas (natural gas) pipeline system
Excavate and expose the existing 4”-FW-005-3CS1P2 line for the construction of new
valve box (VB # 31)
Construction of new valve box (VB # 31) to make the tie-in for CID 57 & CID 58
Excavate around 800 meter to run underground pipeline & FOC to CID 57, 58 & CID 59
Supply, fabrication & installation of underground 4” dia. Pipe about 341 meter length for
CID 57
Supply, fabrication & installation of underground 4” dia. Pipe about 100 meter length for
CID 58
Excavation and expose the existing 6”-FW-011-3CS1P2 line to make the tie-in for CID 59
Supply, fabrication & installation of underground 4” dia. Pipe about 345 meter length for
CID 59
The newly installed underground pipeline shall be made of carbon steel and shall be
protected from corrosion using fusion bonded epoxy (FBE) coating system
The newly installed underground pipeline shall be of existing impressed current cathodic
protection system.
The other end of the pipelines will be tie – in to the aboveground interface tie-in upstream
flange of new EGCL Metering Skids at CID 57, 58 & CID 59.
Construction of metering skid foundation, security fence with gates, structural supports,
sunshade foundation, pipe support & pipe support foundation.
Metering skid’s communication link via new fiber optic cable (FOC) connection to
existing FOC network of EGCL
Install and test one (1) new hot tap and stopple fittings. Assist Hot Tap vendor in
performing hot taps on 4”-FW-005-3CS1P2 mainline.
Isolate all pipe line between existing valve box #22 downstream of ball valve inside valve
box #22 up to new temporary stopple fitting.
Purge, inert and demolish portion of piping between tie-in #001 around 3.5 meters
All welds shall be subject to 100% X-Ray and shall be performed by Saudi Aramco
approved Agency or as required by EGCL
Magnetic Particle Testing and Liquid Penetrant Testing requirements for pressure
containing welds other than butt welds (including sockolets, weldolets and welding
bosses)
Hydro testing for the newly fabricated and installed line
TECHNICAL PROPOSAL Rev. Date
Supply and installation of Electrical Control Panel inside the sunshade for Customer
ID#57, Customer ID#58 & Customer ID#59
Supply & installation of area lighting pole for Customer ID#57, Customer ID#58 &
Customer ID#59 along with the foundation
Precommissioning
Commissioning
Demobilization
MATERIAL SUPPLY:
EPC will supply all Civil, structural, piping, instrumentation & electrical materials according to
the given MTO, SOW & IFC drawings
EPC`S RESPONSIBILITIES:
Construction of new gas supply branch to three customers CID no. 57, GCIR North, CID
no. 58 GCIR South & CID no. 59 GCIR New Plant
ORGANIZATION DETAILS:
The proposed Organization team will be arranged based on the principle that EPC
will bring the best technology and execution capabilities to the benefit of the
project. Overall team for the execution of this project will be performed by
specially arranged project management team and under the leadership & direction
of EPC’s Project In charge.
Project Manager
Site Supervisor
Permit Receiver
UT Inspector
Document Controller
Fire watch
Painter
Insulator
Driver
Semi-skilled labour
Un-skilled labour
MANPOWER LIST
Sl
Trade Qty
No
1 Project In-Charge 1
2 Site Supervisor 1
3 Permit Receiver 1
4 UT Inspector 1
5 Document Controller 1
6 Fire Watch 1
7 Painter 1
8 Insulator 2
9 Driver 1
10 Semi-Skilled Labour 3
11 Un-Skilled Labour 3
EPC confirms that the key personnel are available to work on this particular project to
support the Schedule and will be assigned on a full time basis. However, EPC may
request NGDC to consider alternative candidates if nominated key personnel are not
available due to unforeseen reasons
The Project management team will be organized immediately after receiving the notice of
award from NGDC. The Project In-charge will map out the mobilization plan based on
the requirements of the project at early stage. Key personnel will be organized from the
list approved by NGDC. EPC will request a prompt kick-off meeting with NGDC at
EPC`s Home Office or NGDC Office to confirm various project procedures within 2
weeks after the issue of Notice to Proceed from NGDC. From this meeting, EPC expects
to agree with NGDC the list of priorities and requirements that need to be submitted or
complied with within the first weeks of the project schedule
TECHNICAL PROPOSAL Rev. Date
EQUIPMENT LIST
1. Construction Schedule
The system is based upon compatible monitoring and analyzing techniques applied at
appropriate level of the works to meet the required degree of control. Elements of the
monitoring system are structured or coded in such a way as to reflect the philosophy of
the Work Breakdown Structure (WBS) and to satisfy the control and reporting needs of
the project.
2. Mechanical Completion
Stage 2: Project activities such as excavation, UT test, restoration of insulation & reinstate
TECHNICAL PROPOSAL Rev. Date
Stage 3: Completion
Introduction
This quality manual is a statement of the Organization, Policies, Objectives, Delegation and
Practices that Constitute the Quality Management System of Eastern Power Contracting Est. The
Quality System has been designed to comply with the requirement of ISO9001:2000
Scope
The quality Manual defines responsibilities and directs the controls applied to the procedure
services provided by Eastern Power Contracting Est This extends to all people who have been
given responsibility for implementing and maintaining the Quality System as directed by this
Quality Manuel and associated Quality Assurance Procedures and Departmental work
instructions.
Purpose
Formally document the policies, procedures and systems that are applied in the assurance of
product and service quality.
Consolidate the Quality System to accommodate changes in staff and processes.
Provide a documented reference for audit and performance measurement to identify
opportunities for improvement.
Demonstrate to customers of Eastern Power Contracting Est the total commitment to Quality
and Service.
The policy of the company is to maintain an effective “Quality Management System” to ensure
that the required level of services excellence if achieved to meet the requirements of
ISO9001:2000, Project Specifications and this Company’s quality assurance manual.
The objective is to assure an effective quality system which is maintained, documented and
efficiently implemented in accordance with ISO9001:2000.This quality system incorporates
Company quality management policy, objectives, organizations and procedures associated with
all of the company activities. The maintenance and operations of the company quality system will
be the responsibility of all employees within the company. The company has nominated a
responsible Quality Representative.
The policy is fully endorsed on behalf of the company by the General Manger. Company’s
Management Team who will, by direction and example, ensure that this policy is understood,
accepted and implemented; throughout the organization. Total quality management involves
everyone within our Company. Quality initiatives are management led, by example.
The General Manager has the overall responsibility of the quality of product and a service offered
by the Company. The General Manager is responsible for Management Review Meetings. The
General Manager delegates his responsibility through the management team who will ensure that
the Quality Policy is understood and implemented throughout the organization.
MANAGEMENT RESPONSIBILITY
General: The management responsibilities are: The structure for reporting relationships and
interfaces within the company are shown in Appendix A. All resource requirements shall be
identified and provided on an ongoing basis. Job responsibilities/authorities are defined in the
Quality Manual, Procedures and Work instructions for key personnel. A Quality Representative
shall be nominated by management to maintain the Quality system; he shall be responsible for
maintenance of the system through instigation of surveillance and review meetings to ensure its
suitability.
Management Review: This Quality Assurance Manual reference all activities, which made up
the companies quality system, responsibilities shall be clearly defined in the quality procedures. A
management review meeting shall be held at least annually which will assess adequacy of the
quality system. The management review shall be formally minted and controlled through a
prepared agenda, emphasizing - Customer complaints, Audit Review, Preventive Actions,
Safety, Training, Contract Review, Inspections & Testing, Purchase, Monthly Reports etc. Which
will include preventive actions using all available information as referenced in 4.14.The meeting
shall be attended by Managers and section heads and all elements of the agenda shall be
discussed. All actions required shall be placed on personnel who shall then accept responsibility
for the generation of new quality procedures or corrective actions which may have been raised at
previous audits or surveillances. In the event of difficulties
TECHNICAL PROPOSAL Rev. Date
Occurring in the quality system, ad-hoc meetings shall be arranged to assess and resolve these
difficulties. These meetings shall be conducted in the same manner as the formal review and
attended by appropriate personnel.
QUALITY SYSTEM
The company has based its quality around ISO9001:2000. The quality system has been
developed to produce an awareness that encompasses the elements in BS EN ISO 9002-1994 and
to provide a base from which to build on the efficiency of the quality system. The documents
which make up the quality system are defined at three levels:-
LEVEL 1 QUALITY ASSURANCE MANUAL: The quality assurance manual covers all of
the elements, which make up the quality system. This manual incorporates the company policy
statement and adequately references quality procedures.
CONTRACT REVIEW
The contract review shall commence at the contract award stage when the actual contract
document is reviewed against the inquiry and tender documents. Initially, the inquiry and tender
documents shall be reviewed by appropriate personnel who shall confirm proposed contract
conditions can be maintained, this consideration shall cover, equipment, resources and time
factors.
Upon receipt, the contract document shall be reviewed to ensure all terminology and any
ambiguities are clarified. Contract reviews are an ongoing process which continues throughout the
project. Any resulting changes shall be reviewed and distributed to relevant department heads as
per procedure records of reviews shall be maintained in the contract file as clarification that any
uncertainties have been verified and brought to a satisfactory conclusion.
DESIGN CONTROL
For all EPC projects a third party designer company will be assisting Eastern Power Contracting
Est and we will be aid them to get the Saudi Aramco, Sabic, SATORP, Ma`aden & SADARA
approval as Eastern Power Contracting Est is the key design controller.
revision, should a “Superseded” document need to be retained for reference purposes it will be
clearly marked. “Superseded” so personnel are aware they are for “Information Only “All
documentation shall be reviewed and approved by the original organization and the nature of the
changes highlighted for every reference wherever practicable. Master registers shall be
maintained within quality assurance archives showing the current status of the documents at all
times.
PURCHASING
Purchasing of materials shall be strictly in accordance with documented procedures to ensure
correct data is included on purchase orders and only companies on the approved vendor register
are used. Purchase orders shall be clear and precise on the goods and certification required. The
content of the purchase order shall be checked by authorized for adequacy prior to dispatch.
Vendor selection will be carried out and performances will be monitored to assess their ability to
meet stipulated requirements including the quality system and any required Quality Assurance
Requirements, also quality of product, delivery and price. Were applicable prearranged quality
audits or verification inspection will be carried out at vendor premises to ensure product
conference
PROCESS CONTROL
All stage of process shall be controlled through documented procedures and work
Procedures/Method Statements. Activities shall be planned to ensure suitable manpower and
equipment is available for any particular application. Equipment maintenance shall be scheduled
and carried out on an ongoing basis Personnel shall attend awareness talks on the quality system
so they are aware of project requirement and who is responsible for what. Personnel are
encouraged to contribute to the quality system through discussions and practical suggestions for
improvements. In case of activities being classed as special process. They will be carried out by
TECHNICAL PROPOSAL Rev. Date
qualified operators, the appropriate parameters being monitored to ensure specified requirements
are met. Records shall be maintained as on ongoing activity throughout the life of the project and,
as evidence that all processes, personnel and equipment are qualified and approved.
Documented procedures shall define control requirements form receipt through to final
inspection. The extent of inspection on receipt shall be as an absolute minimum a visual
inspection to ensure no transportation damage, quantities are correct and any identification marks
are apparent. In-process inspections and test shall be pre-determined through quality plans; all
stage inspections shall be verified as being successfully carried out and accepted prior to final
inspection. Final inspection and test shall be witnessed as being carried out to specified
requirements and accepted prior to release. Items shall not be released for dispatch until all
inspection and test activities have been confirmed and documentation complied and authorized.
Cords shall be maintained as evidence that all items have passed inspection and test to the defined
acceptance criteria.
To prevent non-conforming goods being inadvertently used in production, strict control shall be
exercised in accordance with documented procedures. Any goods that do not conform to project
requirements shall be clearly identified and where practical segregated from confirming items.
The proposed corrective action to rectify a non-conforming item shall be submitted to the
designated authority for review and approval. No corrective action shall be carried out until
written permission is obtained from the customer / designate authority. Records shall be
maintained to show how the non-conforming item shall be rectified to become acceptable and
denote the final as-built condition. All reworked non-conforming products shall be re-inspected in
accordance with the quality plan or documented procedures.
records, which are retained on computer, shall be controlled by a program, which facilities back
up and security.
TRAINING
Management and supervision shall maintain a training program to ensure all personnel are fully
competent to carry out their assigned tasks. Periodic assessments shall be carried out by section
heads / supervisors to assess the requirements of individual training needs. Records of
assessments, training provided and identified training needs, shall be retained in the personnel
department, unless required by the client on a project or sire basis. Safety training is provided for
all personnel at commencement of contract. Records of which are available. Induction training on
quality and safety shall be given to all new starters. Records of attendees shall be retained.
SERVICING
Although servicing is not part of the Company’s scope at this time, if in the future servicing
becomes part of the scope a relevant procedure will be formulated.
HSE PROCEDURE:
The company strongly believes that it should maintain an effective loss prevention Management
program to cover avoidance of human injury, material damage, and loss of production and
protection of environment throughout all the company’s activities. The objective of this program
is to assure an effective health, Safety & environmental management system that is maintained,
documented and efficiently implemented. The Company’s Safety Manual incorporates the
Objectives, Organizations and procedures associated with all of the company‘s activities related
to this policy. This policy is fully endorsed on behalf of our Company. The maintenance and
operation of the Health, Safety & environmental Management system will be responsibility of all
employees within the company
TECHNICAL PROPOSAL Rev. Date
As the President of the Company, I accept the responsibility for the Health Safety and
Environmental Management during all our Company’s activities. I will discharge my
responsibilities through the Company’s management team who will, by direction and example,
ensure that this policy is understood, accepted and implemented, throughout the organization.
Daily checks of the office to ensure that Battery recharging will be conducted in well-
walkways are not obstructed , carpet and ventilated areas, with no smoking signs and
other fittings are secure , fire doors kept fire extinguishers in place,
closed and that the means of escape are being Areas around pedestal grinders and other hot
maintained , work type activities are kept fresh of
Provision of metal filling cabinets for combustibles,
documents, stationary and other potentially Paints are stored in a well ventilated area
flammable items, away from other combustible material like
Liaise with the electrical / instrumentation scaffold boards,
services provider for the inspection , testing That flammable liquids such as gasoline ,
and servicing of fire alarms , smoke detection diesel etc, are not cleaning purpose,
units etc, Provision of adequate storage areas that are
Kitchen areas are a particular location for fire located in places where exits, passageways
hazards and shall be monitored to ensure that and stairways are not adversely affected.
electrical fittings are being turned off after
use and do not present a fire hazard, 2.2.2 General Instructions
Clear glass doors shall have the direction of The following general instructions shall be
opening e.g. Push / Pull and a warning strip followed and adhered to:
placed to prevent personnel running into
them, Materials and equipment shall be maintained
Training in the use of fire extinguishers shall in an orderly manner that reduces or prevents
be given and signs displayed highlighting the the possibility of fire spread,
emergency procedures. Materials shall not be stored in a manner that
Liaison will also take place with the HSE obstructs fire points, sprinkler heads, alarms,
staff for regular audits and inspections of the emergency exits, electrical panels and
office and surroundings areas including walkways.
muster points, external walkways etc. Materials shall not be stored close to , or in a
specifically, manner that conceals, floor opening or hoist
Ensure that personnel are informed not to ways,
interfere with fire detection equipment; That Consideration shall be given to the fire
a ‘NO SMOKING’ policy applies in the loading imposed in an area by the placement
bedrooms areas of residential facilities , of materials
Ensure that night security guards regular Doors provided for emergency escape will
patrol the residential camp areas and ensure open outwards in the direction of travel
that fire has not broken out, security lights Equipment will not be fuelled while the
are operable and identify any other potential engine is running,
area or risk “No smoking policy” will be applied. Provide
The Store Keeper shall ensure that the smoking areas away from the work site.
following control measures are in place; Smoking is prohibited whilst refueling
activities are taking place,
That warehouse and yard facilities are Incompatible materials will not be stored in
maintained in a neat and tidy manner and that proximity to each other,
waste oil, rags and other flammable materials The Warehouse In charge or Store- keeper
are removed at the end of each shift or as shall
necessary,
That warehouse personnel are instructed on Take particular care when carrying out hot
the use of fire extinguishers, raising the alarm work operations in locations where
and fire hazards in the work place, combustibles may be present. This will
TECHNICAL PROPOSAL Rev. Date
Class of Extinguishing
Combustible Materials
Fire Agent
Storage of flammable and combustible liquids and gases shall meet NFPA 30 sect, 4-8.
Area shall be posted with its contents and posted with signs “No smoking” or “No open
Flames”.
No source of ignition shall be allowed within 15 meters of the storage area,
Minimum of two Dry Powder fire extinguishers shall be available at the storage area. Area
shall be well ventilated.
Area shall be secured and only authorized personnel allowed access.
If electrical system is required it must meet requirements for hazardous locations.
3. HOUSEKEEPING
The purpose of this procedure is to outline the requirements for managing and controlling
house-keeping operations during for all Company’s Contracts and Projects. These procedures
must be applied to all facilities including workshops, offices, temporary accommodation and
construction areas.
3.2.0 DEFINITIONS
Housekeeping: The act of keeping the working environment cleared of all unnecessary waste,
thereby providing a first-line of defense against accidents and injuries.
TECHNICAL PROPOSAL Rev. Date
Housekeeping is the responsibility of all site personnel, and line management commitment
will be demonstrated by the continued efforts of supervising staff towards this activity.
3.3.0 Responsibilities
3.3.0 INSTRUCTIONS
These instructions shall apply equally to office, workshop, site or desert locations used by
consortium personnel or their contractors during the course of the project
All emergency exit passageways, exits, fire –doors, break- glass alarm points, firefighting
equipment, first aid stations, and other emergency stations shall be kept clean ,
unobstructed and in good working order.
All workers, accesses and means of escape shall be maintained clear of debris waste and
other rubbish , which shall be disposed of in segregated container for disposal
All spillages of liquids especially of oily or greasy liquid shall be immediately cleared by
absorption in insert sand or other suitable materials, toxic, corrosive or other hazardous
liquids shall be cleared up in accordance with manufactures instructions or safety data
sheet. All materials used to mop up spills be immediately removed to a safe place and
stored in closed containers for safe disposal.
Tools, equipment and raw materials at the workplace should be kept to a minimum
commensurate with efficient working practice. Finished work, tolls and equipment should
be removed as soon as possible to their defined storage area such that the workplace is
maintained clear.
Common –sense and good working practice shall be employed when storing or placing
materials. Boxes, pallets or containers such that they do not pose a threat to workers from
lifting, tripping or blocking egress route. Offices shall be regularly tidied and cleaned
Laboratories and workshops shall be maintained clear of debris, waste and other rubbish,
which shall be disposed.
Adequate time will be assigned to ensure that good housekeeping is maintained. This may
be carried out by the workers in a particulars office, workshop or site or, at the discretion
of the management, by a team of specialist cleaners.
Any instance of poor housekeeping that results in the creation of a tripping, slipping or
fire hazard shall be immediately dealt with,
TECHNICAL PROPOSAL Rev. Date
Materials shall be stacked or stored in a safe manner that prevents sliding, falling or
collapse.
When carrying out shuttering operations or any other activity that result in splinters, nails
or other sharp edges the activity will be controlled by removal or other method as
appropriate.
Arrangement shall be on place to ensure that cable management is controlled and that
walkways /stairways are kept clear of temporary electric’s and hoses.
Waste disposal containers shall be sited for food waste, and such areas as utilized for
eating shall be kept clean and tidy.
Where materials are being removed from elevated structures proper arrangements shall be
in place e.g. Barriers, signs winches, hoists etc. to eliminate the risk of injury to personnel
working in the area.
On a weekly basis, storage areas used for scarp trash and other waste will be removed
from the project areas and transported to approve dumping area.
4.1.0 SCOPE AND PURPOSE; the purpose of this procedure is to outline the
requirements for the effective use of safety signs during for all company’s Contracts and/or
Projects.
4.3.0 REFERENCE : The contents of this procedure are in accordance with British
Standards
Ensuring that Supervisor and subcontractor management are familiar with this procedure.
That signs and barriers are ordered in accordance with this procedure.
Monitoring site conditions to ensure that signs and barriers are being erected as
appropriate to the conditions.
Liaison with the commissioning team prior to start up on the requirements and ordering of
signs, warning tape, tags and barriers.
Identifying and ordering sufficient signs and barriers to control their areas of work.
Ensuring that signs and barriers are erected in accordance with this procedure.
Provision of instruction s required.
Ensuring that adequate barriers and signs are provided around areas where hazards may
exist.
Plan and make adequate allowance for the provision of signs and barriers etc.
Ensure that all items of commissioned and live plant are clearly indicated.
4.5.0 INSTRUCTIONS
These instructions shall apply equally to office, workshop, site or desert locations
All emergency exists passageways, fire doors first aid stations, eye wash stations
emergency muster point shall be highlighted with safety condition signs.
Warning signs shall be erected and displayed for fires hazards, electrical equipment,
opening s, overhead working , noisy areas, and other hazards
Mandatory signs shall be provided for enforcing the use of personal protective clothing
and equipment and providing specific instructions appropriate to the task condition.
Prohibition signs will be displayed for restricting access or entry, no smoking areas, no
parking, and any other unauthorized acts.
Fire signs shall be provided at areas where fire equipment has been sited e.g. fire
extinguishers, fire Points, fire blankets etc.
Barriers and warning tape will be provided as appropriate, only fixed and solid barriers
will be used for edge protection on excavations, floor openings and penetrations.
4.5.1 Specifications
The following specifications shall be followed when ordering signs.
Prohibition Background color shall be white with black symbol, centrally Signs placed
and red
Mandatory Background color shall be blue, with a triangular warning symbol edged
with a black band. The text or symbol will be in black & centrally located
Warning Background color shall be yellow with a triangular warning symbol edged with a
black band. The text or oblong and green shall cover at least 50% of the sign.
Fire sign Background color shall be red with white symbol or text. The shape of the sign
shall be square or oblong.
Barriers Barriers tape shall be suitable for external use and maybe either;
Where practicable fencing and signs will be erected to contain construction areas with the
following signs erected;
5.2.0 DEFENITIONS
5.3.0 INSTRUCTIONS
5.3.1 General requirements
Risks posed in any particular work activity shall be assessed, and adequate PPE selected in
accordance with the following criteria
TECHNICAL PROPOSAL Rev. Date
Gives protection against risk(s) with out in itself leading to any increased risk is suitable
for the personnel involved in the work including correct fitting
Is compatible with the work activity
Complies with a recognized national or international standard of design or
construction(such as BS/ANSI/DIN/ISO/NIOSH)
All employees shall be provided with the necessary PPE, as defined above, for their particular
work activity. They hall also be provided with the necessary instruction and training in its
correct use. PPE and the necessary training course shall be supplied to the employee by or on
behalf of the employer.
All employees shall be held responsible for the proper care and use of any PPE supplied to
them. Employers shall replace, free of change to the employee, any PPE which becomes
deficient in any way through normal work usage or wear and tear shall include the period of
effective use specified by the manufacturer and requirements of basic hygiene standards
Supervisors of any work-site shall be responsible for ensuring that all personnel on site are
trained in the use of, provided with , and wearing all PPE required for all particular activity
and environment of the work personnel not properly equipped, for whatever reason, shall not
start or continue working.
All employees shall wear the appropriate PPE supplied to then at all items while working at
their assigned tasks. Supervisors shall apply disciplinary action in accordance with contractor
procedure to any employee who fails comply.
Safety helmet, safety shoes and overall shall be worn within all industrial facilities and work
sites. These locations include, but are not limited to:
TECHNICAL PROPOSAL Rev. Date
Whenever notices are displayed stating that such PPE shall be worn. Such notices shall be
in English or Arabic. Visual signs shall also be displayed (outline drawing of
hardhat/boots etc)
Any production facility, inclusive of power plants and gathering stations
All well locations inclusive of locations in preparation, drilling ,production and work-over
phases
All construction sites inclusive of construction repairs to existing buildings
During all excavation work, inclusive if digging trenches, when working near excavating
equipment, or any work where the depth of excavation is such that materials could fall
into the excavation
During pipeline operations
While working with any machinery or equipment where a significant hazard of projection
of debris exists ( e.g. using portable power saws, heavy cutting machinery, etc)
All abrasive blasting operations
The only exception to the above which is considered acceptable is that of welders when
actually welding and cutting, where the necessary eye shield or heat protective cap prevents
the use of a hard-hat
Face/Head Protection scarves are only allowed if specify designed and worn in such a way
that there is no impairment of the wears vision
All personnel shall wear safety glasses with side shields while on the construction sites
(100% eye protection).
Work situations that require additional protection such as full-face shield etc., which
typically are:
o Grinding
o Blowing down with compressed air
o Spraying of abrasives
o Handing, using mix toxic or corrosive substances
Eye and face protection shall be manufactured in accordance with established national and
international standards such as:
users in a workshop. Personnel who require prescription glasses shall either be provided
with corrective safety lenses or the type of safety glasses that fit over prescription glasses.
Respiratory Protective Equipments shall be available to all persons who are exposed to any
situation in which there is a possibility to the atmosphere being or becoming deficient in
oxygen or containing any harmful substance, whether particle, dust mist, vapor or gas
including:
Work in containers or vessels where a danger of oxygen deficiency or harmful gases may
be present
Work in shafts, sewer or enclosed septic tanks
Grit or abrasive blasting operations
Work in refrigeration plants where the danger of escape of refrigerant gas exists
Adequate body protection such as special suits, aprons, leggings, etc., shall be provided for
any work that involves hazards. Specific and adequate body protection shall be supplied for
all work activities, which present these hazards, including but not limited to:
5.3.8 Fully Body Safety harnesses &Safety harnesses and lifelines shall be provided,
worn and properly secured in all work situations where any of the following dangers exist;
Falling from a height greater than 2m
Succumbing to toxic atmospheres or oxygen deficiency
Such situations include, but are not limited to
Working on scaffolding
Work on any high structure, whether in construction or maintenance, including petroleum
processing plant
Drilling rigs, storage tanks, etc.
Work over water
Rescue work, in firefighting, from high structures and from hazardous atmospheres Safety
belts shall not be used, only full body safety harnesses shall be used.
All such safety harness and lifelines shall be manufactures and inspected in conformance to a
recognized national or international standard such as:
The purpose of this procedure is to outline the requirements for Roads and Transport Safety
for all sites personnel on all company’s contracts and/ or Projects. The procedures applies to
all operations involving road or off road transportation
6.2.0 DEFINITIONS
Transport refers to all vehicles, plant or equipment used to transport personnel or materials
with in Saudi. Roads on all routes used by transport, whether they be asphalted, gravel, sand
or dirt.
6.3.0 RESPONSIBILITIES
The company shall ensure that all vehicles shall be of adequate capacity and of a design
suitable for the work to which they allocated. The company shall appoint an authorized person
who shall assume the following duties
Give overall direction and take responsibility for the application of this procedure
Shall check the records at least once a month to verify that the system is working.
The company will appoint nominated persons authorized to approve travel arrangements that
shall have the following responsibilities:
Initiating suitable procedures when the vehicles become due for maintenance by contracting
the transport Manager.
Driver responsibilities
Take responsibilities for the vehicles, the load and passengers being carried
Understanding of the travel arrangements and journey plan.
Checking of the vehicles prior to start of the journey.
Ensuring that all personnel in the vehicle are wearing seat belts
Notifications of any difficulties or problems encountered en-route.
At the destination to notify the concern person or department of his arrival
Drivers shall not pick up unauthorized persons.
6.4.0 INSTRUCTIONS
All personnel must hold an appropriate and Saudi Driving license for the vehicles or
equipment to be driven. The following general guidelines apply to the qualifications and
requirements for driving:
Professional drivers shall undergo a medical examination and be certified fit before taking up
a driver’s job. Subsequently they shall receive a bi- annual medical and eyesight examination
by a qualified doctor.
Company personnel shall not drive on graded roads during the hours of darkness, expect
under the following circumstances:
In response to an emergency.
For operational purposes, Only if prior approval has been obtained from the project Manager
Maximum driving time must be 10 hrs in a 12 hrs shift period, After 3 hours driving a
minimum of 15 minutes rest is needed
All vehicle movements shall be recorded in a register stating the vehicle type, registration
number, and driver’s name, number of passengers, Route details and planned stops.
All vehicles convey movements/major loads etc. shall be coordinated with the Company
Transport Department and the requirements of their procedures shall be complied with.
All drivers must attend and induction course before being allowed to operate or drive on
company business.
You have given the control room at Transport Department or your Section Head these details
a. Date and Time of departure
b. Name of driver and passengers
c. Vehicles type, registration and color
d. The route and destination of the journey
e. Estimated time arrival at your destination
The vehicle must be in good condition throughout and before proceeding check that;
a. Your vehicle is four wheel drives & well provided for desert trip.
b. Good oil level
c. Full fuel tank
d. Good radiator water level
e. Tires in good condition (2 mm of minimum tread on tire ) and of proper air pressure Bear in
mind that soft sand tire pressure should be reduced to around 15 psi .Keep strictly to your
planned route using recognized tracks observing markers and any other landmarks on the
way
Remember to check you have ;
a. Jack & Jack handle b. Wheel nut tool
c. Jack block d. Spare wheels
Desert survival kit complete with hand held flares, compass and insulated blanket (where
available )
Always keep recognizing tracks and should you become lost follow your own tire tracks
backs to knows landmark
Above all in the event that your vehicles does break down never attempt to reach any
location by foot, always stay with the vehicle unit help arrives
During adverse weather conditions pull the vehicle over until the conditions improve.
7. HYDROGEN SULFIDE
To outline and define and H2S monitoring and control program that complies with the
requirements of the company and safeguards personnel working on company’s Projects and/or
Contracts. This Procedure will apply to all personnel working in areas where H2S is present or
who are performing works with H2S is present or who are performing work with H2S
7.2.0 DEFENITIONS
Occupational Exposure Standards
TECHNICAL PROPOSAL Rev. Date
Limits at which a short term exposure of ten minutes are allowed without affecting the health of
the individual
7.3.0 REFERENCE AND GUIDELINES : Health and Safety Executive Publication EH4O.
7.4.0 RESPONSIBILITIES
The Project Manager shall be responsible for providing the following equipment;
Sufficient numbers of H2S detection equipment, the type of equipment to be compatible and
approved by Company.
Adequate calibration and test equipment, with spare parts that can be fitted on site. Sufficient
numbers of escape equipment as required by the numbers of person who may be exposed.
The HSE Manager will be responsible for;
Ensuring that Supervisors and foremen management are familiar with this procedure.
That any work carried out where the presence of H2S may occur is covered by this procedure.
Monitoring site conditions and ensuring that persons who may affect by this procedure are
aware of the hazards and precautions to be taken.
Arrange for the necessary training of personnel for testing , calibration and maintenance of
records
Updating this procedure as necessary.
Supervisors will be responsible for:
Ensuring that, when working in areas affected by the presence of H2S, the company site
representative has been consulted and that he s satisfied that all necessary precautions are in
place.
Planning the work, as far as practicable, to include contingency plan and arrangements.
To provide sufficient signs, barriers and flashing lights as appropriate to the area
Provision of instruction with regards to the hazards and arrangements in place
7.5.0 INSTRUCTIONS
Prior to any being carried out an analysis shall be carried out to determine the levels of H 2S
present in the area
All work will be covered by the permit to work system, which will state the frequency of
further tests
Instruction in the wearing and use of escape sets shall be emphasized in the task team
briefing
H2S is an explosive gas and all electrical equipment provided shall be low voltage and
intrinsically safe
TECHNICAL PROPOSAL Rev. Date
Wind socks shall be positioned in conspicuous locations to indicate the direction and strength
of the wind
The time – weighted average for H2S shall be 10 parts per million (ppm), with a short- term
exposure limit of 15 parts per million (ppm) for a maximum of 10 minutes duration. Portable
monitoring devices that are provided, for either personal or for an area, shall be calibrated to
alarm at 10 ppm
Don’t panic
Wear the breathing apparatus if available
Evacuate the area in an upwind direction using the windsocks provided for reference
Notify their supervision
Stay in the area and act as a guide for other personnel responding to the situations
The purpose of this procedure is to outline the steps to be taken for evacuating personnel
working on company’s Projects and /or Contracts site The scope of this procedure is intended
to be for emergency attention only which must be followed up by action from qualified
personnel
The indent controller will set up his headquarters in the Emergency Response Center nearest to
the scene of the emergency and control his team from there.
8.3.1 Introduction
Any emergency occurring at a site may cause serious injuries, loss of life, and extensive damage
to property. These situations may demand adequate rescue and relief measures to handle such
events quickly and effectively. The objective of this procedure is to reduce the severity of
loss and handle the situation in the best possible ways. It must be clearly understood that it is
not a substitute for maintaining good standard of health and safety requirements It is
therefore necessary to ensure that all personnel know what they have to do in the event of an
emergency. Through this procedure the responsibilities and duties of the key personnel and
of every individual shall be made clear. Testing of the system will be carried out by practical
training and a program of regular drills and exercises. The procedure, in addition to the duties
and responsibilities of the key personnel and individuals, shall describe the system of
Evacuation, Fire –fighting, Rescuing, Searching and Tacking other type of emergencies .It
shall also indicate the availability of facilities such as location of firefighting equipment,
assembly Points, exits and the procedure to take help from any outside agency in case of
need.
8.3.2 Planning
The basic and essential feature of any emergency procedure is to analyze and plan for potential
risks. This includes:
Fire bells provided at different locations shall be used to raised the alarm
At larger sites, the entire area will be sub- divided into different zones with each zone having
a color code. In this situation there may be more than one assembly point, which will be
color coded according to the color code of the area
The assembly pints shall also be clearly indicated in the Site office with fire instructions and
plot plans
On hearing an alarm all personnel shall vacate the work place. Before leaving the working
place the individual concern shall leave the work place as safe as possible like switching off
of welding machines, gas cylinders, running machines, gas burners, any electrical light or
appliance in their rooms.
All personnel shall assemble at the assembly point according to the color code of his area of
work.
Fire- wardens shall provide guidance and assistance for mustering at the correct assembly
point.
While responding to a fire alarm, kitchen staff shall ensure that all burners and other fire
hazards have been turned off. Similarly other personnel in residence shall ensure that they
leave everything in their rooms in safe condition.
All the members of respective teams shall report to their leaders
The leaders shall take directors from the incident controller.
The Incident controller shall be identified with his name clearly displayed in the project office
and shall have the following responsibilities (the senior person present at the site of an
incident shall act as accident controller, until the incident controller can take charge);
Fire fighting teams will be established and trained to deal with most eventualities.
The incident controller shall appoint fire team leaders who will give direction to personnel
under his control. Personnel appointed will have had some training and where possible
previous experience in emergency response actions. All the members of the fire team shall
report to the fire team leader and shall work according to his direction. The operation on fire
Extinction shall be taken according to fire fighting Procedure laid for which training shall be
given at regular interval
An electrician/instrument Technician will be included, where possible, as a member of the
fire squad with responsibility for the isolation of electrical power, if necessary. The
maintenance of fire fighting appliance shall be the responsibility of the Safety Advisor of the
area who shall make arrangement to recharge the used fire extinguisher or other equipment.
Search Party
Search Parties will be established and responsibilities assigned by the incident controller and
they will have following specific responsibilities:
As soon as the evacuation alarm is sounded, they will check all areas to confirm that all the
employee have left the premises; if they find a victim they shall inform the leader of the
rescue team.
The leader of the search team shall assist the incident controller by maintaining a muster
count and keep a record of all employees present. In the event of a no show ‘ they will alert
the fire-fighting party and rescue teams
Rescue Team/ First- Aid Team
Rescue teams shall be fully trained in different rescue techniques and procedures e.g.
removing a victim from electrical sources, different types of handling techniques, the ABC if
first aid etc.
The team shall be responsible for recovering a casualty and getting him to the Medical center
without aggravating his injuries
The first-Aid team shall also assist the Male Nurse on duty in rendering medical aid to
injured parties. If nursing staff is not available the leader of the First Aid team shall take
charge by administering First Aid and sending him for further treatment to the Company
Medical Center
Incident Completion
All clear signals shall be sounded by the incident Controller following a thorough examination of
the area, initiated by the incident controller and other team leaders. The project Manager &
field HSE supervisor shall visit all locations to ensure that the duties assigned to the
responsible parties are understood and adhered to
General Consideration
TECHNICAL PROPOSAL Rev. Date
Exercise in each facility shall be conducted at least once a month and the observation shall be
recorded. The report should be forwarded to the HSE Department and any remedial actions
required shall be identified.
Emergency procedure shall be updated from time to time depending on the observation made
Training shall be conducted on regular basis for the teams involved in the emergency
procedure.
Area plot plan shall be sited in conspicuous locations for the attention of each employee. This
layout plan shall clearly mark the alarm and fire points in the camp and in the industrial
Yard.
The location of the firefighting equipment shall be also very clearly marked on this plan.
Hand operated sirens shall be installed and used in case of an emergency in the camp
Muster points
Arrangements, through site management for the resources for conducting head counts
Identification and Mobilization of emergency response teams.
Training of emergency response teams
Setting up drills and exercises in co-ordination with emergency services
Procurement of fire and medical equipment
In the event of any emergency the HSE Manager a member of the HSE department shall take the
following actions;
Evaluate the scale of the incident and decide whether additional resources are required to
deal with it.
Liaison with site supervision for withdrawing permits. Give direction to site emergency
response teams
Liaise with site supervision for mobilization of any plant & equipment necessary to deal with
emergency.
Make safe the areas by installing barriers or other means of preventing unauthorized access.
Prepare a full report.
Provision of adequate resources in terms of personnel, time and finance for implementation
of the requirements for providing an emergency response service on site.
Active participation in the scheduling and enactment of drills and exercises.
Shall monitor the arrangement through the Safety Manager to satisfy Manager to satisfy them
that the services are satisfactory and adequate for the needs of the project.
TECHNICAL PROPOSAL Rev. Date
9. WORKING AT HEIGHTS
9.1.0 SCOPE AND PUPOSE: This Procedure has been developed to ensure that all site
personnel who will, or may, work at heights, do so in a safe manner.
9.2.0 DEFINITIONS: High structures refer to any permanent or temporary above ground
structure used by personnel for any purpose during the course of the construction works.
9.3.0 INSTRUCTIONS
9.3.1 Personnel: Personnel shall be adequately trained and experienced in their work,
specifically as applied to operating above ground level. Supervisors, adequate in number,
training and experience shall be provided for the control of work above ground level. In order
to minimize exposure to risk, the minimum practical number of personnel shall be assigned
to the job. The operations above ground level shall be carried out in such a way that non-
involved personnel, in the vicinity of the activity, are not at risk
9.3.2 Personal Protective Equipment: All personnel working above ground level shall be
provided with, and shall use, appropriate personal protection including, but not limited to, the
relevant requirements of procedure ‘Personal Protection Equipment’.
9.3.3. Means of Access: Means of access to elevated areas shall be of an approved type, of
sound construction, suitable for the purpose and shall be used in a safe manner. Where the
means of access is of a mobile or portable type, it shall not be moved either mechanically or
manually, whilst personnel are upon it unless it is specifically designed and approved for the
carriage of persons All of accesses shall be kept clear of any loose articles e.g. tools,
equipment, scaffolding boards, etc. shall be removed or securely lashed down, prior to the
means of access being moved.
Where personnel must transfer from/ to the means of access or from/ to the high structure,
the arrangements at the point of transfer shall be such that personnel are not at risk whilst
transferring.
The means of access shall adequate provide for safe means of egress, for all personnel, from
the high structure.
9.3.4. The High Structure: The integrity of the high structure shall be such that the required
operations can be performed safely. This includes, but is not limited to:
The loading of the structure e.g. men, equipment and materials
The environmental conditions,
The forces imposed upon it by any means of access which is connected to it ,
The forces imposed upon it by any lifting or winching operations in which the high structure
serves as an anchor point, counterweight or tie point.
TECHNICAL PROPOSAL Rev. Date
9.3.5. Pre- work checks : Before work commences, the supervisor in charge of the work shall
ensure:
That all necessary permits have been obtained
That all necessary electrical, mechanical and process isolations have been positively carried
out
That all static, moving ,lifting and anchoring equipment, integral to the means of access and
high structure, inclusive of those associated with the work task, are correctly fitted
conditionally sound and fit for the intended purpose
That all personnel have been provided with the required personal protection That all
personal are briefed between member of the work team have been rehearsed and all
communication drills between member of the work team have been adequately rehearsed and
all communications equipment id functioning
That suitable emergency transport is permanently available for use on site.
10. NOISE
10.1.0 SCOPE AND PURPOSE: The purpose of this procedure is to outline the hazards
associated with noise and the preventative measures to be taken to reduce risk to health. It
covers all areas where the work is being carried out and includes consideration for adjacent
populated areas.
10.2.0 DEFENITIONS: Noise is defined as unwanted sound, which at certain volume levels may
cause irreparable damage to hearing. Frequency is the pitch measures in Hertz, calculated
from the rate of pressure fluctuations of sound waves refers to a unit of sound pressure fed
into an electronic weighting network and providing an approximate sound level calculated
over the total frequencies. DB (A) refers to the characteristics of sound which are filtered to
replace the noise heard by the human ear. Attenuation is the reduction of noise achieved by
hearing protection, each type of ear protector should have attenuation tables which illustrate
the noise reduction at different frequencies .e.g. 30 dB(A) at 5,000 Hz
10.3.0 RESPONSIBILITIES
The HSE Manager must
Ensure adequate supervision when planning the taking in to account the anticipated ‘noise
levels that persons under their control may be exposed to.
Arrange for a noise analysis to take place, where any concern exists.
Ensure that all employees are provided with adequate and suitable hearing protection for the
work being performed recognizing the attenuation factors of different ear protectors
Advise on the procurement of hearing protection
Shall carry out noise assessments where and when necessary, and produce noise contour
maps with octave band frequencies analyzed.
Shall ensure that the appropriate sign are displayed for areas where high levels of noise exist.
Prepare toolbox talk and other training material for briefing the workforce.
10.4.0 INSTRUCTIONS
10.4.1 General
The phenomena of noise induced hearing loss has only, relatively speaking, been recently
analyzed and understood. The causation factors of working in industries where high levels of
noise are generated are now clearly understood, and the long term consequence created from
working in such high risk environments placing greater levels of care on employing
companies.
TECHNICAL PROPOSAL Rev. Date
The physiological damage of working in environments where high levels of noise exists can
be simply explained as the damage caused to the fine hairs in the Cochlea, part of the
hearing mechanism sited in the inner ear. These hairs are jointed to nerves transmitting the
sensation of hearing to the brain; prolonged exposure to high levels of noise will result in
auditory fatigue and eventual failure of function for those fine hairs. This may result in
temporary deafness called a ‘Temporary Threshold Shift’ or permanent dearness, which
includes the occupational illness of ‘Noise induced hearing loss’.
10.4.2 Action
The action point for noise on all company contracts and /or projects is 85 dB (A). Noise
levels 85 dB (A) and over require provision of signs, mandatory hearing protection and an
analysis of the noise emissions.
Under foreseeable working conditions, no person shall be exposed to steady noise levels
above 120 dB (A) irrespective of duration, or to impulse noise levels above 135 dB (A).
Instance where personnel are exposed to high levels of noise will require screening to assess
if any impairment has occurred.
In areas where noise may interfere with communications, suitable alternative arrangements
shall be in place for alerting the work parties in the events of an emergency
TECHNICAL PROPOSAL Rev. Date
Circular saws
105
subcontractors and visitors to company’s temperature rises so high that brain damage and
contract and /or project Sites death will result if the person is not cooled
quickly.
11.2.0 DEFENITIONS
Heat stress is usually the result of work being Symptoms Red, hot, dry skin, though the
performed at elevated temperature contributory person may have been sweating earlier; nausea;
factors may also include a decrease of natural dizziness; confusion; extremely high blood
body ventilation by protective clothing e.g. pressure, rapid respiratory and pulse rate;
chemical & impervious suits. unconsciousness
If the body’s physiological processes fail to Actions Casualty must be cooled down
maintain a normal body temperature because of and medical aid sought immediately with the
excessive heat, a number of physical reactions person transported to the site medical facilities.
can occur ranging from mild (such as fatigue,
irritability, anxiety, and decreased concentration
, dexterity, or movement ) to fatal. Because heat
11.4.2 Heat Exhaustion
stress is one of the most common and Heat exhaustion is a state of very definite
potentially serious illnesses that construction weakness or exhaustion caused by the loss of
workers encounter, in areas where high fluids from the body. This condition is much
temperature are normally encountered, regular less dangerous than heat stroke, but must be
monitoring and other preventative measures are treated early on to prevent eventual deterioration
vital. to heat stroke. Symptoms Pale, clammy, moist
skin, profuse perspiration, and extreme
weakness, Body temperature is normal, pulse is
11.3.0 RESPONSIBILITIES weak and rapid, and breathing is shallow. The
It is the responsibility of line Management and person may have a headache, may vomit, and
Supervision (contractors and Subcontractors) to may be dizzy.
ensure that personnel under their control are
educated in recognizing and understand the
treatment for the various forms of heat stress,
11.4.3 Heat cramps
and that supervision are actively monitoring the Heat cramps are caused by perspiration that is
work force for signs and symptoms of heat not balanced by adequate fluid intake. Heat
stress. cramps are often the first sign of a condition that
can lead to heat stroke. Symptoms: acute painful
spasms of voluntary muscles; e.g. abdomen and
11.4.1 TYPE OF HEAT STREE extremities
Where bayonet type light bulbs are used as volt single phase from a double- wound
stingers for illuminating passageways and transformer . Having the center tap of the
stairways, they shall be protected by cages. secondary winding earthed so that that the
Lights provided for this purpose shall be maximum voltage is only 35 volts.
sited to avoid glare and spaced to provide All portable electric tolls must have pressure
adequate light for the areas covered. release switch (dead man) in operation. All
The illumination shall be measured prior to cables and plug and socket connectors must
the work being carried out by a light meter be maintained in good condition. Cables
calibrated in Lux. must be effectively attached to the plug
Tower lighting shall be sited that illuminates connectors by efficient cord grips to reeve
all parts of the area where the work is taking all strain on the flexible cable. Damaged
place. cables should be replaced at once; spliced
Lighting provided shall be checked prior to cables are not allowed.
use to ensure they meet the requirements of
the Plant and Equipment procedure.
Lighting in confined spaces shall be in 13.3.2 Portable Electric Drills
accordance with specifications. Always provide a “starter” mark for the drill
Generator provided shall be checked prior to point.
use to ensure they meet the requirements of Always select correct bit for material being
the plant and Equipment procedure. drilled. If bit is long enough to pass through
Cables employed for the purpose of materials, protect against damage and injury
temporary lighting shall be routed to ensure on the far side
that they do not present a trip hazards or Small pieces of work should be clamped or
other obstruction. held down to prevent spinning by the drill
Lighting poles and other metal parts shall be and a warning
earthed and the circuit fitted with residual Care must be taken prevent sleeves and
current devices. other clothing from being wound around
drill. It is recommended that sleeves be
rolled up to above the elbow.
1. HAND TOOLS Telescopic or similar guarding must be used
when operating a bench drill
13.3.3 Portable Electric Grinders
13.1.0 SCOPE AND PURPOSE: The purpose Grinder’s operators must be equipped with
of this procedure is to provide guidance for eye shields and these must be worn.
use of hand-tools at the company’s contracts The wheel must be inspected and dressed
and/or Project Sites. regularly. Eye shields and respiratory must
be worn when dressing.
A cracked stone may fly to pieces and
13.2.0 INSTRUCTIONS should be discarded
13.2.1 Electric tools Tools rest should be used and adjusted
Portable electric tools, when used in normal correctly. The rest should not be adjusted
conditions, should be the 110 volts type with when the grinder is in motion.
single –phases supply from a double- wound Grinding wheels should have the same
transformer having the center tap of the maximum permissible working speed as the
secondary winding earthed so that the grinder or a higher safe speed.
maximum voltage to earth is 55 volts.
Where the noise level exceeds 85 dB (A),
Where more hazardous conditions exist, i.e., noise protection equipment shall be
where men have to work within boilers or provided to employees. Regularly inspection
metal tanks, the power supply, should be 50 and maintenance shall be carried out.
TECHNICAL PROPOSAL Rev. Date
Cutting pliers should be used only for maximum permissible speed marked on the
cutting soft metals , never hardened metals wheel.
or as nail pullers It must be remembered that centrifugal
Approved insulated pliers must be used for force, the ultimate cause of wheel bursts,
electrical work increases not directly with speed, but as the
13.2.10Wheel Barrows square of the speed. The speed at which the
Hand –trucks & wheel barrows should be grinding wheel revolves, is, therefore,
selected for the job. Their frames should be extremely important
strong and straight 14.2.2 Flanges
Wheels of hand –trucks and wheelbarrows Every abrasive must be mounted between
should be strong and well secured to frame suitable flanges, which should be not less
.The bodies must be kept clean and free of than one third the diameter of the wheel.
jagged edges. Extreme are must be exercised The flanges should be recessed on the side
when using ramps and walks–ways. Careful next to the wheel, to ensure that clamping
planning of wheelbarrow traffic can avoid pressure is not exerted near the hole
accident and prove economical. Flanges for wheelers with large holes should
not be recessed, but the corners of the wheel
seating should be undercut, so that the
14. ABRASIVE WHEELS corners of the wheels will not be subjected
to pressure. The inner(driving) flange should
be keyed , screwed, shrunk, or otherwise
secured to the spindle, and the flange
14.1.0 SCOPE AND PURPOSE bearing surface should run true with the
The purpose if this procedure is to provide spindle.
guidance for use of abrasive wheels at the 14.2.3 Washers
Company’s Contract and/ or Project sites. The purpose of washer to distribute the
clamping pressure evenly on the wheel, in
addition to the prevention of slipping with
less clamping pressure, washer tend to
14.2.0 INSTRUCTIONS reduce wear on the flanges.
14.2.1 General
Selecting the correct wheel for the job is
equally important for efficient production 14.2.4 Starting New wheels
and for safety as a rough and ready rule. Soft Before running the wheel, make sure the
wheels are more suitable for hard materials, guard is in proper adjustment.
and hard wheels for soft materials If the machine is fitted with a work rest,
With wheels of insatiable structure for the adjust this as possible to the surface of the
job, loading may result, i.e. the abrasive wheel; rotate the wheel by hand to make
wheel face becomes clogged with particles sure it is clear all the way round.
of the materials being ground .A wheel may New wheels should be run free at full
also be too hard too fine; “glazing”. The operating speed for a short period before
operator is then tempted to press the they are used; during the trial run everyone
workspaces to hard on the wheels , causing stand clear.
it to break .The best policy in selecting 14.2.5 Guards
grinding plant is to consult manufactures of Guards have four main functions:
machines and abrasive wheels, and not to
experiment with out competent advice. To contain the wheel parts in the event of a
Before mounting the wheel, check that the burst.
speed of the spindle does not exceed the
TECHNICAL PROPOSAL Rev. Date
The procurement department will conduct a pre and hazard identifications and analysis
bid meeting with all prospective activities
Subcontractors, vendors or suppliers to
ensure their understanding of the HSE
programs requirements on the project. 15.2.3 Weekly General HSE Meetings
The HSE meetings shall be organized to
Based on the complexity or potentials hazards,
regularly monitor and report the implantation of
the HSE Manager (or Construction
the specific areas of the HSE Manual, to
Manager) may be elected to attend
promote the safety of persons working at site
More than one Pre- bid meeting any be and to ensure safety practices in order to avoid
conducted as necessary for a given service accidents, injuries and loss of property .It will
or product. be preceded by a site “ walk around inspection”
by all the participants to the meeting .these of
The agenda shall include; meetings will be held in each constructions site
.The field HSE Coordinator will co-ordinate
Review of Contractor HSE program
Chain of command for HSE issues this meetings .the Field HSE coordinator ,
HSE requirements of the Subcontractor together with all Subcontractor’s HSE
,vendor or suppler Supervisors shall attend the meeting .Medical
Subcontractor , vendor or supplier questions staffs , where applicable , should also attend.
Other – generated issues.
The subjects of the meeting are as follows:
15.2.2 Monthly HSE committee Meetings Any matters arising from the previous
The company shall initiate and maintain a HSE minutes.
committee with the primary mandate to Action arising from the previous meeting
implement the HSE program quality Precautions instructions to prevent accidents
injuries and the loss of property, and
assessment .The HSE committee shall
comments for actions to be taken by
include; Subcontractors.
Instructions for fire prevention.
Project Manager (Chairman )
Review of any accidents/near misses and the
Company’s HSE Manager (Secretary ) circulations of any learning points to avoid
Company’s Fields HSE Coordinators recurrence of the same
Representative of Clients – Construction Discuss any other related matters in order to
Manager reduce or eliminate likely hazards and to
Representatives of Subcontractor’s ( one for suggest remedial measures, for any
each area) potentially hazardous operations
Representative of Subcontractor’s HSE Follow up any action points arising from
Supervisor (one for each area) any audits/ inspections.
The HSE committee shall meet at least on a HSE promotions methods, HSE awards,
monthly basis. safety campaigns, including recognition of
milestones and incentives.
Primary meeting agenda is the quality Sub-Contractor HSE training programs
assurance assessment of site HSE activities Daily “Tool box” meeting with sub-
with a special emphasis on the HSE meeting contractor’s work force –environment and
waste management.
TECHNICAL PROPOSAL Rev. Date
For the purpose of this procedure the accidents 16.3.2 Tripod accident Causation
as above defined are classified as follows; Sequences
Breached Defense What last-minute measure
failed or was Missing?
Unsafe Acts which acts or omissions led
Category 1 Fatalities /permanent total disability directly to the accident?
to person(s) involved. Damages in excess of US Preconditions which states of mind or of the
$ 150.000(inclusive) to properties, plants etc; or system allowed the unsafe acts?
massive environmental impact Latent Failures which underlying problems
led to the preconditions?
Fallible Decisions Which decisions created
the latent failure?
Category II Serious injuries to person(S)
involved resulting in Permanent partial
disabilities as well as working day lost. Damage 16.3.2 Analysis Process
more than US $ 15,000 (inclusive) to properties, The following list summarizes the serious of
Plant, etc., or major environmental impact. steps in the analysis process and help to
build an accident investigation tree;
can be established. it may help to motivate Investigation is one of the essential features
for preventions of litigation of effective Safety Management.
To meet the relevant statutory requirements The main objective is to prevent recurrence
on injury and accident reporting. of accidents by identifying deficiencies
Every incident should be investigated, although Most accidents have more than one cause
the level of investigation and Detail of The right approach to any accident is that it
investigation will vary and will depend on the could be an indication of deficiencies in the
actual or potential Injury, damage or loss. management of the operation
Following occurrence of any incident, an Management commitment is best
demonstrated when a through and objective
investigation team must be set-up to start
investigations is carried out by capable
immediate investigation at the location of the investigator and prompt action is taken to
accident. Investigations committee with the correct deficiencies
following members; Communications, within Organization and
other concerned and interested parties, the
lessons learned.
Team leader : HSE Manager
Team leader : Company Representative 16.4.2 Investigation Approach
Team leader : Field HSE coordinator;
Team leader : Project Manager
Team leader : Field HSE Supervisor This approach is to be used by the investigation
Team leader : Subcontractor committee at the scene of the incident as soon as
Representative possible after the incident At the initial stage the
Team leader : Sub contractor HSE committee will gather and record all the facts,
Superintendent which may be of interest in determining cause,
they should avoid reaching all the facts, which
For any another incident, the Project Manager may be of interest in determining causes they
shall decide, if the investigation will be carried should avoid reaching conclusions too early in
out by a specific committee .This committee the investigation process, and base their results
shall be composed by ; on positive factual findings.
1. Inadequate guards or barriers Note Unsafe act should describe the acts or
omissions, which led directly to the incidents
2. Failure to warn or educate Unsafe conditions should describe the situations
2. Inadequate/improper protective ,systems equipment or any other attribute that
equipment should have been provided to prevent the
incident.
3. Failure to secure
Duties and task not clear Lack of requirement to have task set I proper
Pressure of immediate tasks procedure
Responsibility not clear or understood Conflicting targets –caused by
Too many decision makers giving
instruction Conflict between production and safe
Authority inadequate to manage the working practices
situation Conflict between financial priorities and
Decision exceeds authority safe working practices
Decision avoidance Conflict between social and domestic
Instruction failed to produce desired result priorities on safe working practices
Subordinates failed to use initiative Conflict between individual priorities and
safe working practices
Morals, tension and stress causing
Communication –difficult caused by
situations.
Job descriptions not adequate Languages problems cultural barriers
Honest error ,wrong action taken Lack of clear lines of communication
Lack of co-ordination/team work Inadequate feedback (e.g. toolbox talk)
Poor cooperation No standardization of information formats
Faulty inspection and maintenance
Lines of communication overloaded
Poor work control /co-ordination leading to Hardware –quality, availability of tools and
poor site conditions
equipment caused by
Work load too much /too little
Staff shortage high turnover /absenteeism. Inadequate specification of equipment
Personality type e.g. impulsive ,excitable Wrong components purchased /used
,lazy etc Equipment may be not available learning to
Poor work habit ,taking short cuts, careless improvisation
with tools Defective equipment
Work assignment –unsuited for the Age of equipment compared to life
particular individual expectancy
Inadequate delegation or development or Design – inadequate design criteria of plant
subordinates
and equipment caused by
Health and impairment of the individual
Domestic or other external influence
Design not fully understood to operate
16.5.3 Root Causes safely
The General Failure types found in the incident Poor specifications leading to substandard
causation chain can be listed follows; materials and inherent weakness in the
system.
Procedures: Specification not completed with
Environmental conditions – A situation that may
Inadequate quality of existing procedures
regarding application, availability , realism influence the individual or the work place
and understanding caused by caused by
Inadequate team that developed the
procedure Poor moral ,this can be caused by a number
of situation e.g. unfair enforcement of rules
Inadequate feedback about procedure
,weak disciplines ,, rule changes etc
Inadequate indexing or filing system
Physical deterioration , caused by working
Personnel not informed about procedure.
long hours , subject to undue pressure etc
TECHNICAL PROPOSAL Rev. Date
Emergency of unusual situation with staff Financial and other constraint during design
unable with staff unable to cope or respond phase.
Information not correct or supplied Poor discipline and enforcement
Circumstantial factors such as domestic The root causes listed above have been
pressure, homesickness etc.. identified as the general and latent failure
Poor co-ordination between department attributable to organization that lead to
causing interface problems accidents. If should be noted that these failure
Training –shortcomings in skill and
are generally the result of policy decisions and
knowledge caused by
where possible these should also be identified
Ineffective pre-employment selection and form part of any action taken to remedy the
Prior education not compatible with job causation factors
requirements
No structures planning of training programs A contract may be under bid to the point where
No assessment of training effectiveness insufficient allocations of resources results,
Ineffective training or training not leading to the incident
appropriate for the personnel it is aimed at
Housekeeping and other site conditions that 16.5.0 IDENTIFYING CAUSES
may influence acts and omissions. Based on the accident classification, the
Organization – shortcoming in the structure of reporting activities are summarized in the table
the organization leading to inadequate operation below.
of a company or project caused by
The written investigation report (Annex D) prepared by the Investigation committee shall contain
the following issues.
Disciplinary Action
If disciplinary action is deemed necessary , the site Manager and Sub contractor representative of
the employee(s) involved , shall decide what the disciplinary action will be and shall inform the
HSE coordinator of any such decision prior to informing the employees(s)
electric shock. Since these hazards may cause burns, injury, or death, it is important to wear
proper PPE at all times.
Wear a helmet with filter lens and cover plate that complies with ANSI Z87.1 for protection
from radiant energy, flying sparks, and spatter.
Wear a fire-resistant welder’s cap or other head covering under your helmet. It will protect your
head and hair from flying sparks, spatter, burns, and radiation
FOOT PROTECTION
Select boots that meet the requirements of ASTM F2412 and ASTM F2413 (or the older ANSI
Z41 which has been withdrawn).
HAND PROTECTION
Always wear dry, hole-free, insulated welding gloves in good condition. They will help protect
your ands from burns, sparks, heat, cuts, scratches, and electric shock.
BODY PROTECTION
Wear oil-free protective clothing made of wool or heavy cotton. Heavier materials work best.
They are harder to ignite and resist wear and damage
Records
[EPC] Safety Department shall maintain records for all cranes, forklift and rigging equipment.
Period of
Sl No Contract No Work Description Client Name
contract
EPC supplied manpower, equipment, tools, and
supervision for the pipe line validation services part Will Provided
1 Jan-12 4500681374 during the emergency shutdown in SADAF MTBE T/A on Request
2012.
SAFETY INSTRUCTIONS:
During execution of the job all measure shall be adopted to ensure safe working.
The workers will be made aware of safety requirements related to this activity through
daily, weekly and monthly toolbox and safety talks.
TECHNICAL PROPOSAL Rev. Date
All safety measures shall be adopted prior to expose the pipe line
Ensure that equipment’s & barricades are properly wedged or blocked to avoid rolling
while shifting from one location to another.
Waste Management should be strictly followed to keep the job site neat and clean
HOUSE KEEPING:
Housekeeping will be carried out on daily basis to maintain cleanliness at working area
*************************************END************************************