Project Exec & Quality Plan
Project Exec & Quality Plan
Project Exec & Quality Plan
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
PROJECT
EXECUTION &
QUALITY PLAN
Page: 1 of 7
PROJECT EXECUTION
& QUALITY PLAN
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
1 PURPOSE
The purpose of this Project Execution & Quality Plan (PEQP) is to describe & define the
procedures used to produce the deliverables listed in the supply and work provided by the client,
and to meet the quality and technical requirements as contractually defined for the project.
Specific quality activities, as detailed in the plan below, are utilised to achieve the quality
objectives required by client. This document is a living document and therefore will be updated
throughout the life of the project. Updates may be provided periodically with a final revision upon
project completion.
2 EXECUTION METODOLOGY
• Appoint a Project Co-ordinator, who shall be single point contact for the customer
• Do an internal review of the technical drawings/PO and transfer the job from sales to
Project.
• Call for a Kick-off meeting with customer
• Submit a Project organization chart with all details and escalation matrix (Typical Org
chart is attached as Annexure-A)
• Submit a Project progress review format (Typical format attached as Annexure-B)
• Submit a schedule bar chart (Typical format attached as Annexure-C)
The contract shall be reviewed and documented by Jasubhai in close cooperation and
agreement of the customer/contractor. A kick-off meeting is held with the customer to discuss
and to define the project implementation procedures.
The procurement process involves the review of quotation from an approved vendor. Quotations
received from approved vendors are evaluated upon approval, purchase requisition will be
raised. & Purchase Order will be generated accordingly.All suppliers are selected by the standard
procedures for vendor selection. The manager prepares a written contract that explicitly states all
commitments and responsibilities that are mutually agreed upon and will inform the Customer, if
required contractually.
Project Co-ordinator of the project shall ensure that above mentioned procedures are followed
effectively.
Customer supplied inventory – if any, shall be identified, verified, protected and safeguarded. A
customer supplied inventory list shall be maintained. If any customer property is lost, damaged
Page: 2 of 7
PROJECT EXECUTION
& QUALITY PLAN
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
or otherwise found to be unsuitable for use or incorporation into our product, it shall be reported
to the customer and records maintained. The detailed material handling procedure is attached as
Appendix-2
All inventory purchased from either factory or third party vendors are traceable through the
company purchasing system.
The procedure if followed as per the Manufacturing and Cabinet Integration Plan, attached as
APPENDIX-1.
Managing project quality requires an approved quality plan encompassing three major quality
processes defined in subsequent Section. The plan is developed and approved during the project
phase to confirm major deliverables/milestone acceptance criteria and manage approved project
processes.
• Quality Assurance
Quality assurance activities focus on the processes being used to manage and deliver the
solution to evaluate overall project performance on a regular basis. Quality assurance is a
method to ensure the project will satisfy the quality standards and will define and record
quality reviews, test performance, and customer acceptance.
• Quality Control
Quality control activities are performed continually to verify that project management and
project deliverables are of high quality and meet quality standards. Quality control also
helps uncover causes of unsatisfactory results and establish lessons learned to avoid
similar issues in this and other projects.
The Inspection and Test Plan essentially outlines the main test, review and inspection
activities of the project that form the quality control function. Check lists are used for
ensuring the quality as per customer drawings.
Page: 3 of 7
PROJECT EXECUTION
& QUALITY PLAN
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
Relevant Documents as per list the provided in the Project Document register
• Liaise with the project team on Project Quality awareness and requirements
• Assesses the project team’s conformance with the Project Quality Plan
Page: 4 of 7
PROJECT EXECUTION
& QUALITY PLAN
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
For the success of any project monitoring is very critical. Depending upon the size and duration
of project the frequency of review meetings, progress reports are decided in kick off meeting with
customer.
The review meetings shall monitor the progress of the project where the status of the project shall
be discussed as well as other items concerning timely production of deliverables to the
necessary quality standards.
Milestone Deliverable
UNIT Dispatch 1. Complete Installation wiring Testing & Despatch as per Project
Schedule
Control of Document procedures, sets the guideline to ensure that the correct, approved version
of all relevant documents is available and are being used at the right place at the right time.
Control of Document involves preparation, review, endorsement, control, distribution and retrieval
of all documents and information pertaining to the Project.
The Document Register Maintains the Record of Documents (Document No-JASUBHAI –XXXX-
DR-001) applicable in the Project and Project Drawings received is logged in Document No-
JASUBHAI/XXXXX-PDR-001)
Control of Non-conforming Product procedures set the guidelines to ensure that non-conforming
product is prevented from its original usage prior to relevant conscientious intervention. Product
can take the form of hardware defect, or customer complaint.
Corrective Action and Preventive Action Corrective Action procedures set the guidelines to
ensure that the cause of non-conformities is investigated and the corrective action needed to
Page: 5 of 7
PROJECT EXECUTION
& QUALITY PLAN
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
prevent recurrence. Preventive Action procedures set the guidelines to eliminate the causes of
nonconformities in order to prevent their reoccurrence.
If the project application specifications are changed after the approval cycle, a proposal
identifying the proposed change and the justification or the change is prepared and submitted to
the Customer. Each proposal is analysed and evaluated for:
The Business Development Manager shall be in-charge of Change Management, which result in
variation order(s) from customer. The Change Control guidelines as stipulated in the “Scope
Change Management Procedure” in MOS will be referenced when addressing this process
TEST CERTIFICATES Received along with materials shall be part of Material Incoming
Inspection.
Page: 6 of 7
PROJECT EXECUTION
& QUALITY PLAN
Date: 01.10.2008
Contractor : Jasubhai Rev: 00
Project coordinators are encouraged to discuss operating problems and noteworthy behaviours
(both positive and negative), which they observed personally while managing this project.
The primary purpose of the review meeting is to identify Off Schedule conditions so that
appropriate counter measures may be taken. The Review Meeting provides the Management
with a weekly forum, in which it can routinely probe into issues that have direct impact on the
performance of the organisation.
The results of Quality Audits and Reviews will be factored into project planning and
implementation. The benefits of lessons learned will be shared with project team as the project
continues.
In the event of an unresolved discrepancy or event by the project team then client may escalate
the situation within Jasubhai senior management. Contact details are already given in the org
chart.
Normally the Manager of Jasubhai will be able to resolve all issues pertaining to business within
the region.
Generally the Manager is responsible for all aspects of the project and so is ultimately
responsible for ensuring the quality assurance and quality control of the deliverables of the
project. Specific quality related tasks will be delegated to the relevant personnel within the
project for the specific deliverables under their responsibility.
Page: 7 of 7