QA and QC Plan
QA and QC Plan
QA and QC Plan
DOC.NO. AYC-QA-P-001 1 OF 84
REV. 05
CONTENTS
1.1 INTRODUCTION
3.0 ORGANIZATION
DOC.NO. AYC-QA-P-001 2 OF 84
REV. 05
APPENDIXES
DOC.NO. AYC-QA-P-001 3 OF 84
REV. 05
1.1 INTRODUCTION
The aim of this Quality Plan is to define the processes that will effectively
demonstrate our commitment to Quality to both customer and employees.
Such processes are established, documented, implemented and maintained
thru the adoption of a Quality Management System based on ISO 9001:2000,
review and implementation and the application of the latest industry codes
and standards.
To this end, Al-Yamama Company has an obligation to ensure that the final
product i.e. results of activities or processes meets its fitness for purpose and
has been carried out in accordance with the job specification and is consistent
with design requirement.
DOC.NO. AYC-QA-P-001 4 OF 84
REV. 05
2.0 PROJECT SCOPE
Site Preparation:
c. Utilities :
Applicable References :
DOC.NO. AYC-QA-P-001 5 OF 84
REV. 05
3.0 ORGANIZATION
Position
Responsibilities
Reports to
Expected Duties/Outputs
The Job Descriptions shall be held by the Project Manager and he shall
ensure that personnel fully understand their responsibilities and
authorities. The Job descriptions include the following (the full
descriptions are found in APPENDIX A):
Project Manager
QA/QC Civil Inspector
QA/QC Piping Inspector
Safety Supervisor
Equipment Supervisor
DOC.NO. AYC-QA-P-001 6 OF 84
REV. 05
as necessary to maintain required QA/ QC coverage, the Project
Manager shall advise the Client of such coverage and QA/QC
coverage at least thirty (30) days in advance of schedules absences or
changes and as soon as possible for other changes.
- Meetings
- Reports
- Correspondence
- Records
- Site Instruction
- Request for Inspection (RFI)
DOC.NO. AYC-QA-P-001 7 OF 84
REV. 05
and resolving problems that arise at the interfaces between such
groups.
The company has documented their Policy for Quality, approved by the
General Manager, who in conjunction with his Management Team is
responsible for ensuring that this policy is understood, implemented
and maintained throughout all levels of the company.
All Managers are responsible for ensuring that adequate resources are
provided for managing, performing and verification of Quality activities.
DOC.NO. AYC-QA-P-001 8 OF 84
REV. 05
Establishing, implementation and maintenance of the Al-Yamama
Company Quality System, in accordance with the requirements of ISO
9001:2000.
Quality Manual
This document provides the company’s interpretation of ISO
9001:2000. It’s the document upon which all-subsequent
policies and procedures are based.
DOC.NO. AYC-QA-P-001 9 OF 84
REV. 05
Procedures Manual
Quality Plans
Quality Records
Company Standards and Specifications
National/International Standards
Supplier Procedures and Specifications
DOC.NO. AYC-QA-P-001 10 OF 84
REV. 05
Procedure: At Contract Award
A copy of the Original Proposal and estimate file with all back-up
documentation.
Amendments made during the negotiations (if any)
All THE CLIENT correspondence and meeting notes
All internal meeting notes
Technical and commercial documentations
Final contract
DOC.NO. AYC-QA-P-001 11 OF 84
REV. 05
b. The Project Manager will identify parts of the contract
documentation package including the Company’s Contract
Execution Strategy and determine the necessary distribution as
appropriate to all project team members.
c. The Project Manager will arrange for the distribution in accordance
to paragraph “b”.
d. Each project team member shall carefully review the supplied
document, list any items not fully understood or where possible
misunderstanding may arise and any information or clarification is
required from THE CLIENT.
e. These listing shall be made in the form of written specific queries.
f. Special attention shall be paid to ensure the following:
g. Work Scope: That the design criteria including the scope of work
which shall constitute the design database, are established, agreed
with THE CLIENT and issued and understood by those responsible
for the work.
DOC.NO. AYC-QA-P-001 12 OF 84
REV. 05
g. During the meeting, any changes required in relation to standard
working practices to satisfy the requirements of the project, will be
reviewed and responsibilities assigned for the preparation of
adequate project specific instructions, including procedures and
technical guidelines.
h. Project requirements for format of deliverables shall be identified
and explained including, document number, title blocks etc. where
specified by THE CLIENT as a contractual need.
DOC.NO. AYC-QA-P-001 13 OF 84
REV. 05
To indicate when, how, and by whom the design process is to be
carried out, controlled and documented.
To indicate the arrangements for the review, verification and
validation of design output conformity to design input requirements.
Where applicable, the extent to which the customer is to be
involved in design reviews and design verification.
DOC.NO. AYC-QA-P-001 14 OF 84
REV. 05
c. The document shall be date stamped on receipt and entered into
the corresponding log.
d. The document on issue shall be stamped “CONTROLLED COPY”.
e. Only controlled copy of the documents shall be used for
construction.
f. Photocopying of the controlled copy is not permitted. Sufficient
numbers of controlled copy shall issue to the construction crew to
perform their job.
g. The distribution shall be made under cover of a Document
Transmittal.
h. In case of revisions, copies shall destroy the previous issue or
clearly mark them as “SUPERSEDED”.
i. Any individual assigned to have a sensitive document (either the
original or a copy), will use it only at his designated workstation.
j. Sensitive documents are to be kept in the Head Office when not in
actual use.
k. The project office will be locked when not attended to.
l. All originals of THE CLIENT drawings shall be controlled in
accordance with the requirement.
Project Manager
Project Engineer
Engineering Manager
Technical/Procurement Manager
Engineering (Civil)
Engineering (Mechanical)
Engineering (Electrical / Communication)
Quality Assurance Manager
DOC.NO. AYC-QA-P-001 15 OF 84
REV. 05
Procedure: Shop Drawings
DOC.NO. AYC-QA-P-001 16 OF 84
REV. 05
Procedure: Document Disposal
4.7 Purchasing
DOC.NO. AYC-QA-P-001 17 OF 84
REV. 05
Where Company conducts verification of materials, products or
services at the suppliers or subcontractor’s premises, such
arrangements shall be clearly documented and the result recorded.
The requirements for use of Inspection Agencies will be documented
for each project.
2.1 Al-Yamama Company shall perform all activities and take action
required to assure the efficient procurement of materials and to
maintain material delivery schedules.
DOC.NO. AYC-QA-P-001 18 OF 84
REV. 05
2.2 Minimum requirements of the Procurement are as follows:
3.1 Responsibilities
DOC.NO. AYC-QA-P-001 19 OF 84
REV. 05
quotation, evaluate quotations, obtain approval to purchase and
issue Purchase Order.
3.1.2.3 Prepare spare requirements for the Project and ensure that
requirements are incorporated in request for quote and Purchase
Orders.
3.1.3 Expediter
DOC.NO. AYC-QA-P-001 20 OF 84
REV. 05
3.1.5 Warehouse Supervisor
3.1.5.2 Check and receive materials and equipment for the project.
3.1.5.4 Insure that stock and inventory control records are being
maintained for all materials purchased by the Contractor for the
Project.
a. Description of item
b. Quantity and unit
c. Technical Specifications
d. Specs stock number, if any
e. Recommendation for capital spare parts.
DOC.NO. AYC-QA-P-001 21 OF 84
REV. 05
4.2 Vendor Selection
4.2.2 Al-Yamama Company shall develop their own list of vendors for
materials for which THE CLIENT has not provided lists. Vendor
qualifications will be submitted to THE CLIENT for their review.
a. Name of Project
b. Equipment or materials description
c. Contractor’s requisition number
d. Technical specifications
e. Quantity required
f. Required delivery date
g. Information regarding spare parts data requirements and a
request for cost of capital spare parts.
h. Number of copies of Operating and Maintenance Manuals
required as well as other ‘final’ documents.
i. Quality Assurance and Quality Control requirements
j. The requirement for vendor’s submittal of all warranty and
guarantee information
k. The requirement for vendors to use the English language and the
units of measure as indicated in the job specification for all
information submitted.
4.3.3 For each requirement whose value exceeds US$ 10,000 and for
which THE CLIENT manufacturer list, Al-Yamama Company
shall request quotation from at least three Manufacturers. If less
DOC.NO. AYC-QA-P-001 22 OF 84
REV. 05
than three are listed in the Report, then all shall receive request
for quote.
DOC.NO. AYC-QA-P-001 23 OF 84
REV. 05
4.4.5 Al-Yamama Company purchase order shall include requirements
for special tools supplied by vendor, capital and start-up spare
parts, spare parts data, drawings and related services (if
required).
4.5.1 Scope
4.5.2 Definitions
DOC.NO. AYC-QA-P-001 24 OF 84
REV. 05
4.5.3 Summary of Spare Parts Procurement Process
4.5.4.1 Instruction for the supply of spare parts for parent equipment will
be attached to the Purchase Order to the vendor.
4.5.4.2 Each vendor will provide the following lists with the parts data:
DOC.NO. AYC-QA-P-001 25 OF 84
REV. 05
for the procurement of materials, except where specifically noted
for spare parts procurement.
4.5.5.1 The procurement process will follow the same process for the
procurement of Parent Equipment.
4.5.5.3 Six copies of Parts Data Package will be forwarded to the Spare
Parts Coordinator to review for compatibility with construction,
commissioning and start-up planning procedures. If any revision
is required it shall be noted by the Coordinator and returned to
the Procurement Manager.
4.5.5.4 Procurement Manager will confirm the order to the vendor for the
list of spares for commissioning and start-up to include revision
made by the Spare Parts Coordinator.
DOC.NO. AYC-QA-P-001 26 OF 84
REV. 05
4.5.6.3 Al-Yamama Company will submit an original and one copy of the
Spare Parts Data Package within 30 days after receipt of
manufacturer’s Data Package from the vendor or within 90 days
of the Purchase Order placement date.
THE CLIENT will purchase and ship all Operating Spare Parts
for all company furnished and contractor furnished Parent
Equipment or Capital Spares.
5.1 General
5.1.1 The Procedure and policies contained in this Plan are to serve as
instruction and guidelines for all authorized Al-Yamama
Company personnel involved in the performance of procurement
functions.
DOC.NO. AYC-QA-P-001 27 OF 84
REV. 05
5.2.2 Al-Yamama Company will utilize additional Out-of-Kingdom
Procurement Agents for the procurement of equipment and/or
materials in U.S.A., U.K. and other European Countries.
DOC.NO. AYC-QA-P-001 28 OF 84
REV. 05
c. All Requests for Quotation (RFQ) will originate from the
Procurement Department and quotations will be returned to
same.
5.3.1 Expediter
5.3.1.2 The Expediter will liaison with the buyer and discipline engineers
as to terms and condition of the Purchase Orders, expedite
delivery of materials according to Project schedule, submit to
Procurement Supervisor expediting reports and advise of
possible delays in delivery, deviations and problems areas in
meeting required delivery schedules.
DOC.NO. AYC-QA-P-001 29 OF 84
REV. 05
5.3.1.4 Critical items will be identified for close attention and monitoring
by the Expediter to insure timely fabrication, inspection, testing
and release for shipment, as well as, transport to the site.
5.3.1.5 The Expediter will maintain active files of all purchase orders,
specifications, vendor data requirements, drawings and other
data pertaining to the Purchase Order.
DOC.NO. AYC-QA-P-001 30 OF 84
REV. 05
e. Approved revisions and/or amendments regardless of source
shall be delivered to the vendor and shall be made a part of the
Purchase Order.
5.4.2 Responsibilities
DOC.NO. AYC-QA-P-001 31 OF 84
REV. 05
5.4.3 Purchase Order Request
5.5 Transportation
5.5.1 General
DOC.NO. AYC-QA-P-001 32 OF 84
REV. 05
5.5.1.4 Transport will be planned and scheduled based on information
and data provided by the Procurement Expediter.
b. Insure that all materials and equipment are packed and marked
correctly.
c. Insure that loading and unloading are properly carried out, with
particular attention to heavy lifts.
5.5.2.2 All equipment and materials must be packed for export shipment.
parts or tools with highly finished surfaces must be processed in
accordance with standard export packing procedures to protect
against damage in transit, rough handling and/or contamination
from the elements
DOC.NO. AYC-QA-P-001 33 OF 84
REV. 05
Packages shall be numbered consecutively starting with number
1. Each package must contain a PACKING LIST and a duplicate
copy of the packing list must be placed in a waterproof envelope
securely fastened to the outside of the package.
5.6 WAREHOUSE
DOC.NO. AYC-QA-P-001 34 OF 84
REV. 05
d. MATERIAL RECEIVING REPORT (MRR)
5.6.1.6 All material and equipment receipts are posted to stock record
cards for inventory control.
5.6.1.8 Al-Yamama Company will file one copy of the MRR together with
packing list and is filed with the warehouse copy of the purchase
order. Storage locations of all materials received must be shown
on the MRR.
DOC.NO. AYC-QA-P-001 35 OF 84
REV. 05
Also, a copy of the OS & D Report will be forwarded to the
Contractor’s Procurement Department.
5.6.3 Storage
5.6.3.1 This section outlines the procedures for the storage of materials,
both outside in Laydown Area and inside Warehouse. The
Warehouse Supervisor is responsible for the orderly storage,
maintenance and issue of all materials and equipment delivered
to the jobsite. He will also, be responsible for maintaining an up-
to-date inventory.
DOC.NO. AYC-QA-P-001 36 OF 84
REV. 05
5.6.3.2 Materials, equipment and supplies must be stored in the
warehouse when possible. There are certain items that must be
protected from weather and stored inside, such as, instruments,
pressure gauges, delicate equipment items, etc.
5.6.4 Issue
5.6.4.4 All issue transactions will be posted to the stock record cards.
DOC.NO. AYC-QA-P-001 37 OF 84
REV. 05
6.1.2 Quotation of the Recommended Spare Parts for each Equipment
Items.
6.1.4 List of components and its Part No. if the Spare Part is a “Kit” or
“Assembly”.
DOC.NO. AYC-QA-P-001 38 OF 84
REV. 05
7.7 Material Receiving Report will be issued by storekeeper who will
receive the materials on site and will notify the Main Office in
case of damage/short or not as specified in the Purchase Order.
8.1 This section describes the forms and reports which will be
prepared by the Contractor in fulfilling the requirements of the
contract and those required by the Contractor’s own company for
its daily purchasing and material activities.
8.1.1.1 Standard forms which will be used for the duration of the project
and an explanation of their intended uses are as follows:
e. Field Warehouse
Issue/Requisition
DOC.NO. AYC-QA-P-001 39 OF 84
REV. 05
Used as request by field personnel to withdraw material and
equipment from storage; and, as issue document to record
material and equipment which have been issued from storage
locations.
a. Expediting Report
DOC.NO. AYC-QA-P-001 40 OF 84
REV. 05
e. Material Procurement Status Report
DOC.NO. AYC-QA-P-001 41 OF 84
REV. 05
d. Quantity damaged, or unusable materials, will be shown in the
Materials Receipt Inspection Report Form
e. Material items damaged, or unsuitable during installation will be:
DOC.NO. AYC-QA-P-001 42 OF 84
REV. 05
h. THE CLIENT will then issue the material / item ensuring that no
damage or loss of identification is incurred during any loading, off-
loading, sling or other handling operation.
Details:
DOC.NO. AYC-QA-P-001 43 OF 84
REV. 05
4.10 Process Control
DOC.NO. AYC-QA-P-001 44 OF 84
REV. 05
Procedure: Inspection of Material
At least twenty four (24) hours prior to the time of the inspection for
normal work hours (7:00 AM – 4:00PM, Saturday to Wednesday).
Forty Eight (48) hours for weekends or holidays.
DOC.NO. AYC-QA-P-001 45 OF 84
REV. 05
Procedure: Initial Inspection and Test
Methods
Techniques
Workmanship planned or conducted
DOC.NO. AYC-QA-P-001 46 OF 84
REV. 05
b. Civil Works
c. Mechanical Works
Equipment foundations
Location, level and alignment
Equipment assemblies
Functioning of controls and valves
d. Piping Works
DOC.NO. AYC-QA-P-001 47 OF 84
REV. 05
Trench before installation of sand pad
Cable during placing operation
Marker tape placement
Underground conduit
Trench before installation of the conduit
Conduit before concrete encasement including mandrel
testing
Orange dye placement
- Manholes
- Cable Testing
DOC.NO. AYC-QA-P-001 48 OF 84
REV. 05
Depending in the level of inspection, and where THE CLIENT may
requires third party inspectors, the contractor shall get the services
of third party inspectors and shall keep track on all the activities as
required.
1) Type test
2) Witness testing (including on-site acceptance)
3) Product verification
4) Product validation
5) Material, product, process or personnel certification.
DOC.NO. AYC-QA-P-001 49 OF 84
REV. 05
direct traceability to national/international standards, or standards
recognized within the Kingdom of Saudi Arabia.
The plan should indicate the control system to be used for inspection,
measuring and test equipment specifically intended for use for the
product, project or contract, including;
DOC.NO. AYC-QA-P-001 50 OF 84
REV. 05
c. The approved metrology laboratory provides calibration reports with
the following information as a minimum:
Report number
Control number of test equipment
Condition of equipment at time of calibration
Description of repair, if any
Calibration standards used
Calibration data
Environment condition at time of calibration
Calibration procedure used
Calibration date
Signature of calibration technician
Calibration Services:
DOC.NO. AYC-QA-P-001 51 OF 84
REV. 05
Such an approved laboratory applies weather resistant calibration
labels with the following information, as a minimum:
a. Report number
b. Control number of test equipment
c. Condition of equipment at time of calibration
d. Description of repair, if any
e. Calibration standards used
f. Calibration data
g. Environment condition at time of calibration
h. Calibration procedure used
i. Calibration date
j. Signature of calibration technician
This insures that only product that has been passed the necessary
inspection and tests is released to the next operation and is subject to
formal handover to the customer.
The plan should indicate any specific requirements and methods for
the identification of the inspection and test status of the products,
documents and data.
DOC.NO. AYC-QA-P-001 52 OF 84
REV. 05
d. Only “accepted” equipment and materials shall be issued for
construction activities.
Our Quality System has established controls to ensure that all non-
conforming products are clearly identified and segregated to prevent
inadvertent use or dispatch.
DOC.NO. AYC-QA-P-001 53 OF 84
REV. 05
The plan should address how and under what circumstances the
supplier would request a concession for a product, which does not
meet, specified requirements. In doing so, the plan should indicate;
Procedure: Non-conformance
DOC.NO. AYC-QA-P-001 54 OF 84
REV. 05
Quality Manager or his designated nominee prior to close out for
the NCR. Further copies will go to the Procurement Department for
information and a copy will be maintained in the Project File.
g. When a non-conformance is noted during production/construction, a
NCR will be raised by the Quality Assurance Manager or his
nominee and the corrective action taken (see para. b) as defined by
the Discipline Manager.
h. If rework is within the specification requirements, the rework will be
carried out as defined in the NCR. The Engineering manager will be
responsible for defining the rework requirements.
i. If a rework is outside the specification requirements a corrective
action request shall be raised quarantining the item.
j. A waiver request, including the proposed repair procedure, shall be
forwarded to THE CLIENT for their approval or recommendations.
The item will remain quarantined until the disposition of the
corrective action has been agreed in line with paragraph “b” of this
procedure.
k. Items considered not acceptable for correction, rework or repair
shall be tagged “REJECTED” and shall be removed as soon as
possible from the work site and destroyed if and when necessary.
Rejected materials shall be kept in a suitable and properly delimited
segregation area until their final destination has been decided.
l. The QC Inspector shall inspect all rework against the original
standards or specifications and the original acceptance criteria shall
be used to verify the acceptability of the rework. The NCR will then
be signed-off when found to be acceptable. If the item has been
rework, the rework procedures will be noted on the NCR.
m. All information’s relevant to rejected materials shall be noted for
materials reconciliation purposes. The Project quality Assurance
Manager shall ensure the follow-up of the corrective action. The
Quality Assurance Manager may check on the remedial or
corrective action completion by a check visit on site or through
notes from the concerned responsible personnel informing him on
the achievement of the action.
n. The Quality Organization shall maintain records of all non-
conformance and corrective action forms, this shall include:
Objective evidence or remedial actions to substantiate that
corrected / reworked items have been re-inspected and/or
re-tested according to applicable procedures.
o. In case of re-occurrence of specific nonconformity (trend), the
Quality organization shall provide for auditing of the activity. Audit
Report, and if necessary, corrective Action Request shall be issued
in this respect.
p. All NCR’s will be filed and maintained for each project. These
NCR’s will form a part of the project quality records.
DOC.NO. AYC-QA-P-001 55 OF 84
REV. 05
q. All NCR’s, including THE CLIENT issued NCR, will be logged in the
non-conformance report register by the Quality Assurance Manager
or his designated representative.
DOC.NO. AYC-QA-P-001 56 OF 84
REV. 05
f. This analysis includes data on all critical non-conformities, time
required to process non-conformities, trend analysis and excessive
delays in resolving non-conformities.
g. The objective of the analysis is to establish confidence in the
system and product quality.
h. The implementation of all corrective and preventive action shall be
verified by the Quality Assurance Manager.
i. The Corrective Action Request form shall be used to record the
deficiency observed on a process or procedure and proposal from
the originator on the required improvements.
j. The Corrective Action Request can also be the result of either an
internal or external audit. In this case, the Quality Assurance
Manager shall propose the required corrective actions.
k. The Corrective Action Request shall be discussed in the
management review meeting and necessary decisions are taken for
process improvement.
l. The board considers number of factors such as cost/benefit
scheduling priority and resources, before deciding the improvement.
m. The requited changes to the procedure and processes shall be
recorded and revised procedures shall be issued to all concerned.
DOC.NO. AYC-QA-P-001 57 OF 84
REV. 05
c. The preventive action taken shall be suitable to magnitude the
problem.
d. The analysis of preventive action taken shall be reviewed in the
subsequent management review meeting.
Procedure: Handling
Dollies
Manual lift and cranes for heavy equipment
Procedure: Storage
a. Tags and labels affixed to the outer box or storage rack identifying
the contents and physical characteristics of stored items.
b. The material controller shall perform regular monitoring on the
material stored to verify their condition.
Procedure: Preservation
DOC.NO. AYC-QA-P-001 58 OF 84
REV. 05
b. Heat sensitive items shall be stored under temperature control.
c. Materials provided with preservatives during storage shall be
verified for proper packing and storage.
d. The material controller, based in input from the equipment supplier,
will prepare and maintain a list of all equipment subject to
preservation, including frequency and the type of preservation to be
used. Condition of equipment and material in storage will be
checked periodically to prevent deterioration and identify non-
conforming conditions.
Procedure: Preservation
DOC.NO. AYC-QA-P-001 59 OF 84
REV. 05
e. No corrections shall be made after the client has signed off a
document.
f. The document shall be filed in accordance with individual discipline
or activity.
g. The documents shall be compiled on standard box 2” or 3”.
h. An index shall be prepared on top of the file.
Procedure: Storage
DOC.NO. AYC-QA-P-001 60 OF 84
REV. 05
All audits will be executed by Quality Assurance (QA) personnel not
directly responsible for the area being audited or by an approved third
party agency. Audits shall be performed in accordance with pre-
established written procedures and checklists.
The Management Team will review the results of the Internal Audits, at
each Management Meeting.
Such audits may include;
DOC.NO. AYC-QA-P-001 61 OF 84
REV. 05
requirements as well as the audit history. The date on review shall
be recorded on the Audit Schedule. The General Manager shall
authorize any significant changes to the Audit Schedule.
a. The Quality Assurance Manager defines the audit team size and
composition, and formally assigns a Lead Auditor and any other
team member(s). The Lead Auditor shall be normally an experience
/ trained auditor of at least QA Engineer status. Exceptionally,
engineers from other disciplines may be asked to assist in audits
and it may also be necessary to obtain specialist support from
group supervisors when auditing outside the audit team’s direct
working experience. Auditors shall be experience / training
commensurate with the scope, complexity or special nature of the
activities to be audited. The audit team will normally be informed of
their selection at least two weeks before the audit.
DOC.NO. AYC-QA-P-001 62 OF 84
REV. 05
unscheduled audit. When completed the unscheduled audit shall
also be shown on the Audi Schedule as having taken place.
a. The Lead Auditor shall convene a brief meeting between the audit
team and appropriate representatives of the Auditees
Management.
b. The purpose of the meeting shall be to:
Effect introductions
Circulate attendance sheet
Investigate all outstanding actions from previous audits and secure
their close out (applicable for second audit schedule)
Discuss brief scope and purpose of audit
Confirm the audit timetable and work program
Establish the sequence of events and individuals involved
Arrange escorts for the audit team and the use of an office for audit
team meetings
Establish a provisional time for the exit meeting and invite the
Auditees management to attend.
DOC.NO. AYC-QA-P-001 63 OF 84
REV. 05
Procedure: Post Audit Meeting
DOC.NO. AYC-QA-P-001 64 OF 84
REV. 05
Procedure: Audit Reporting
a. Following the completion of the audit, the Lead Auditor with the
assistance of other members of the audit Team, shall prepare the
formal report.
b. The result of the audit shall be summarized on the Lead Sheet and
any audit findings shall be itemized.
c. The audit shall be reported on the report sheets and shall include
some or all of the following:
d. Before the formal Audit Report is released and distributed the entire
Audit Team shall review it to check that the statements made are
fair, complete and true.
e. After this review, the Lead Auditor shall sign the complete audit
report on the cover sheet on behalf of the entire Audit Team an d
shall forward the report to the QA Manager for review. After the
report has been reviewed and the contents are acceptable, the QA
Manager shall sign off the lead sheet.
f. The QA Manager shall file the original of the audit report and audit
checklist. This will enable further copies to be produced at a later
date if they are needed.
g. The original Corrective Action Request raised as a result of the
audit shall accompany the copy of the audit report sent to the
auditee.
h. The QA Manager shall ensure that a copy of the complete audit
report is issued to the auditee under a covering memorandum
within seven days of the final date of the audit. The internal
memorandum shall identify the final date by which responses are
required for any Corrective Action Request.
i. When the audit report has been issued and copies distributed as
specified by the QA Manager, he will complete the following:
DOC.NO. AYC-QA-P-001 65 OF 84
REV. 05
Audit report status log
Audit schedule
Corrective action request status log
4.19 Training
DOC.NO. AYC-QA-P-001 66 OF 84
REV. 05
Special attention shall be given to the initial training of new employees,
or employees assigned to new tasks while gaining the required levels
of proficiency.
The plan should address any specific training required for the
personnel carrying out a process that is a subject of the plan and how
such training is to be accomplished. This should include;
DOC.NO. AYC-QA-P-001 67 OF 84
REV. 05
The Training Plan will Typically Cover the following training
activities:
4.20 Servicing
DOC.NO. AYC-QA-P-001 68 OF 84
REV. 05
maintained and will be subject to audit. This record will form part of the
document data to be handed-over at mechanical completion.
During the construction phase, the QA/QC Supervisor shall ensure that
the appropriate schedules/test reports/plans from vendors /
subcontractor have been prepared and submitted to the Project
Manager for review.
The Project Manager shall ensure that all inspection, measuring and
test equipment utilized during the pre-commissioning process is
suitably calibrated and that the record of such calibration are available
and maintained by Al-Yamama Company and/or vendors.
DOC.NO. AYC-QA-P-001 69 OF 84
REV. 05
APPENDIX A
- Project Manager
- QA/QC Manager
- QC Civil Inspector
- QC Piping Inspector
- QC Welding Inspector
- QC Electrical Inspector
- Safety Supervisor
DOC.NO. AYC-QA-P-001 70 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
DOC.NO. AYC-QA-P-001 71 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
To ensure that the Quality Plan, procedures and objectives are understood
and implemented within the quality assurance functions.
Review and ensure that Quality Procedures comply with the requirements of
ISO 9001:2000.
Maintain quality records and ensure those produce are collated and compiled
into records.
DOC.NO. AYC-QA-P-001 72 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
Maintain quality records and ensure those produce are collated and
compiled into records.
DOC.NO. AYC-QA-P-001 73 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
Maintain quality records and ensure those produce are collated and
compiled into records.
DOC.NO. AYC-QA-P-001 74 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
Maintain quality records and ensure those produce are collated and
compiled into records.
DOC.NO. AYC-QA-P-001 75 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
Maintain quality records and ensure those produce are collated and
compiled into records.
DOC.NO. AYC-QA-P-001 76 OF 84
REV. 05
JOB DESCRIPTION
Duties/Output:
Maintain safety records and ensure those produce are collated and
compiled into records.
DOC.NO. AYC-QA-P-001 77 OF 84
REV. 05
APPENDIX B
I. MANAGEMENT STANDARDS
Standard -1 - Introduction
DOC.NO. AYC-QA-P-001 78 OF 84
REV. 05
APPENDIX C
QUALITY CONTROL PROCEDURE
QA-WIP-1-001 = Scaffolding
QA-WIP-1-002 = Rigging
QA-WIP-2-001 = Excavation, Trenching, Backfilling and Compacting
QA-WIP-2-002 = Demolition
QA-WIP-2-003 = Base Course and Asphalt Concrete Paving
QA-WIP-2-004 = A/G Steel Piping Valve Appurtenances
QA-WIP-2-005 = U/G Water System (UPVC/PVC and Fittings)
QA-WIP-2-006 = Sanitary Sewer System ( UPVC/PVC)
QA-WIP-2-007 = Raw Water System ( PVC Pipes and Fittings)
QA-WIP-2-008 = Fire Water System ( RGS Pipes)
QA-WIP-2-009 = Landscaping
QA-WIP-3-001 = Concrete Formwork
QA-WIP-3-002 = Concrete Reinforcement
QA-WIP-3-003 = Construction, Expansion and Contraction Joints
QA-WIP-3-004 = Cast-in Place Concrete
QA-WIP-4-001 = Concrete Masonry Units and Plastering
QA-WIP-5-001 = Space Frame Installation
QA-WIP-8-001 = Hollow Metal Doors and Frames
QA-WIP-8-002 = Aluminum Windows
QA-WIP-8-003 = Gypsum Boards, Studs and Runners
QA-WIP-8-004 = Glazing
QA-WIP-8-005 = Suspended Acoustical Ceiling
QA-WIP-9-001 = Metal Stud Framing System
QA-WIP-9-002 = Gypsum Wallboard System
QA-WIP-9-003 = Ceramic Tiles and Accessories
QA-WIP-9-004 = Suspended Acoustical Ceiling
QA-WIP-9-005 = Carpeting
QA-WIP-9-006 = Painting
QA-WIP-14-001 = Elevators and Escalators
QA-WIP-15-011 = Air Handling Unit / Air Cooled Condensing Unit
QA-WIP-15-012 = Exhaust Fan
QA-WIP-16-001 = Electrical Works -General
QA-WIP-16-002= Raceways
QA-WIP-16-003= Underground Electrical Services
QA-WIP-16-004= Wire and Cables
QA-WIP-16-005 = Cabinets, Boxes, Auxiliary Gutters and & Wireways
QA-WIP-16-006 = Panel boards
QA-WIP-16-007 = Over Current Protective Devices
QA-WIP-16-008 = Grounding
DOC.NO. AYC-QA-P-001 79 OF 84
REV. 05
QA-WIP-16-009 = Exterior Lighting
QA-WIP-16-010 = Building Lighting
QA-WIP-16-011 = Telephone /Communication System
QA-WIP-16-012 = Substation Equipment
DOC.NO. AYC-QA-P-001 80 OF 84
REV. 05
APPENDIX D
DOC.NO. AYC-QA-P-001 81 OF 84
REV. 05
APPENDIX E
DOC.NO. AYC-QA-P-001 82 OF 84
REV. 05
APPENDIX F
ORGANIZATIONAL CHART
DOC.NO. AYC-QA-P-001 83 OF 84
REV. 05
APPENDIX G
QUALITY AUDIT
DOC.NO. AYC-QA-P-001 84 OF 84
REV. 05