QC-QA Plan
QC-QA Plan
QC-QA Plan
2016
APPROVAL
VERSION HISTORY
0 M.Sofyan.S - Suriyanto -
1.0 Purpose
This quality control plan has been prepared to establish the quality control and Test to
be conducted at the project work site and fabricator.
The codes and standards that the contractor will follow will be laid out. These includes
codes and standards for installation, construction, fabrication, inspection and/or testing
of materials, services, or equipment for LNG Re-gasification project is in accordance
with those specified in the contractual documents, purchase order, requisition
specification, data sheets and drawings.
The Construction contractor will refer queries Re-garding the referenced codes and
standards to the EPC CONTRACTOR and TPI for decision.
5.0 Organization
DIRECTOR
PROJECT MANAGER
DOCUMENT CONTROL
QC. COORDINATOR
PJIT
QC. INSPECTOR
4.1 Job Description
Responsibility
Structure of Coordination
Task
Responsibility
Carrying out quality control function and work stuff (quality control) in
conjunction with field monitoring reports (Inspection report) and progress
Mechanical Completion (MC) to the Quality Control Coordinator.
Collaborate with TPI and PJIT to carry out testing in field and fabricator
Coordinating with logistic section and contractors/vendors in order that
control can work well and accurately so that the installation can be run in
accordance with the project plan Re-garding cost, quality and time.
Structure of Coordination
Work with logistics section ensures that goods will come (incoming
material) and will be used for the installation of the project in accordance
with the specifications requested and required, if no quality control have
the authority to reject and return the goods to the vendor/contractor.
Ensure that the work carried out in accordance with the installation
contractor as required and in accordance with the standards as well as
images that have been approved by the project owner.
Create reports any Non Conformance Report (NCR) if at the time of
inspection to find any discrepancies during execution of work by the
contractor.
Reporting the NCR to QC coordinator and project coordinator will ask the
Site and the contractor to make the effort corrective action (Corrective
Action Request/CAR) for a job that does not fit and categorized
Major/serious.
Provide advice and technical and non- technical input on project operational
processes.
Controlling operational processes in order to run the project in accordance
with the rules and does not violate the guidelines that have been agreed
upon.
Prepare the following documents: Report of Inspection, Goods Receiving
Report (Material Receiving Report, Checklist Installation, Corrective Action
Report (CAR), Non Conformance Report (NCR) and others related to
project operations during job runs.
To monitor the progress of the project.
Coordinate with the site manager to report progress of work/Mechanical
completion status
4.1.3 Document Control
Responsibility
Coordinate and perform administrative activities on the receipt, recording, storage and
distribution of reports on the supervision/inspection of the quality of work, quality
management system documents.
Organizational Structure
Task
Identify the training needs of the controlling document. Fostering the ability
of the controlling document in various ways on a Re-gular basis.
Availability of preparation for the Management Review Meetings, minutes
and spread.
Collecting materials for the implementation of appropriate management
review schedule. Distribute technical meeting invitation
Develop and distribute minutes of meeting as directed by Quality Controller.
The quality control plan covers the general field of inspection and testing of piping,
equipment, pipeline and structural steel, electrical, instrumentation, insulation and
painting activities during construction, installation, pre-commissioning and,
commissioning at LNG Re-gasification Project.
The project quality objective begin with pre inspection until project completion, focused
in the subcontractor and vendor ability and competency.
Vendor and subcontractor selection is based on good track record in similar project.
The 3 phase of Inspection is as follows:
FLOWCHART 3 FASE INSPECTION
As soon as the equipment and materials are delivered to the site, receiving quality control
is performed by the material controller. After receiving quality control, the material
controller prepares the Material Receiving Report.
If any loss, damage or quality faults are found, a Shortage/Damage or Non-conformity
Report is made and reported to the site manager using the "Shortage/Damage or
Nonconformity Report".
Based on Migas Re-gulation (SK Dirjen 84.K th 1999) for the project which is under control
of Migas, such as pressure vessel shall be certified. The process cerification is prior to
Inspection Testing Plan (ITP) approval by Migas.
Certification and verification is a standard practice in the international oil & gas business. It
serves to assure an owner and other relevant parties that the plant intended to be put into
operation meets a set of technical requirements and can be operated during all phases of
the life cycle in a manner which is safe for the personnel on site and the public in the
closer vicinity of the installation.
7.2.2.2 Certificate of Individual Equipment Worthiness (SKPP):
The certification covers equipments and facility operates in LNG Re-gasification Project:
Inspections during equipment fabrication and plant construction are carried out by
Independent Technical Inspection Company (Perusahaan Jasa Inspeksi Teknis/PJIT) which
appointed by the contractor/owner and approved by Direktorat Jenderal Migas. These
inspections include the following:
All of the Inspection item for SKPP shall be stated in the Inspection Testing Plan (ITP)
and must be submitted to Ditjen Migas for verification and approval.
ITP for Pressure Vessel, rotating equipment, electrical equipment and piping system can be
seen on annex 1.
Certification is carried out upon the completion of plant with all process equipment.
Verification will be conducted while plant in commissioning stage.
This including:
Inspection During plant commissioning for Facility Worthiness Certification (SKPI) will be
carried out by Independent Technical Inspection Company (PJIT) which appointed by the
contractor/owner and approved by Ditjen Migas.
All of the Inspection item for SKPI shall be stated in the Inspection Testing Plan (ITP) and
must be submitted to Migas for verification and approval. The ITP for SKPI can be seen in
annex 2.
The quality control and test of field construction are carried out based on the inspection
and test plan (ITP) issued by EPC Contractors and endorsement of the plant owner.
Inspection and test that are not covered by the ITP shall be defined in conformity with
issued drawings, specifications, codes and standards during the progress of the work
execution stage depending upon specific WORK requirements.
Alteration is made in the form of changes as per specific WORK requirements from time to
time.
The construction contractor informs in writing the EPC Contractor and ITP of the inspection
points (WITNESS & HOLD), which are required to be witnessed before execution of any
stage of the work.
7.3.1.1 Civil
NC FINDING BY QC.INSPECTOR
MAJOR
TECHNICAL REPORT HO
WORK IN “HOLD”
MEETING
STATUS
HO DECISION
MINOR
WORK TO PROCEED
9.0 Documentation
The quality records control (including Quality Control Records) is the responsibility of the
Project Manager. The quality records include:
The person in charge for specific items
The identification of Regulatory and CLIENT requirements for permanent records
Retrieval, filing and indexing of the fabrication record books
Submission format, quality of reproductions, number of copies and archive
requirements
Final disposition at completion of the work
Results of reviews, inspections, tests, audits and materials certificates
Qualification of personnel, procedures and equipment
Non-conforming and corrective action reports
Other documentation, such as drawings, specifications
Test reports are prepared within 7 working days of test completion and are submitted on
an immediate basis.
All repair procedure, specific method statements and Test Equipment Calibration
Certificates, as required by the requisition, are reviewed approved prior to use.
In case of conflict, the orders of precedence are as follows:
Contract
AFC Drawings
Project Specification
Other relevant Project Specification
Applicable Codes and Standards
The EPC Contractor inspection and test plan has been considered in this quality control
plan.
The construction contractor controls the individual inspection procedure for in-process or
final quality control/testing, and records it. The records are Procedures cheklists and test
records that give evidence that the work has passed quality control and/or testing with
defined acceptance criteria.
The construction contractor holds pre-inspection meeting(s) with the EPC Contractor to
resolve questions concerning compliance with the individual quality control procedure,
specific quality control requirements, and related specification. The construction contractor
arranges for meeting attendance by all necessary means to achieve resolution of technical
questions, schedules, and quality control requirements.