Professional Documents
Culture Documents
Mini Project Surabhi
Mini Project Surabhi
On
1. Work related to preparation of bill of quantity & tender document.
2. Work related to design & drawing of flat slab using IS Code method.
3. Work related to cost estimation of (including market survey of rates) earthwork for a highway.
4. Design & analysis of a G+5 residential building using structural design and analysis software Staad
Pro.
Submitted by
Surabhi Yadav
B.Tech IV Year
Affiliated to
INTRODUCTION
The bill of quantities (sometimes referred to as 'BoQ' or 'BQ') is a document prepared by the cost
consultant (often a quantity surveyor) that provides project specific measured quantities of the items
of work identified by the drawings and specifications in the tender documentation.
The quantities may be measured in number, length, area, volume, weight or time. Preparing a bill of
quantities requires that the design is complete and a specification has been prepared.
GENERAL INFORMATION
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill
of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means
all tendering contractors will be pricing the same quantities (rather than taking off quantities from
the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
The contractor tenders against the bill of quantities, stating their price for each item. This priced bill of
quantities constitutes the tenderer's offer. As the offer is built up of prescribed items, it is possible to
compare both the overall price and individual items directly with other tenderers' offers, allowing a
detailed assessment of which aspects of a tender may offer good or poor value. This information can
assist with tender negotiations.
USAGE
Bills of quantities are most useful to the contractor when they are prepared in work sections that reflect
likely sub-contract packages. This makes it easier for the contractor to obtain prices from sub-
contractors and is more likely to result in an accurate and competitive price.
The bill of quantities should identify the different kinds of work required, but should not specify them as
this can lead to confusion between information in the bill of quantities and information in
the specification itself.
Disputes can occur where there is discrepancy between the bill of quantities and the rest of the tender
documents (for example where an item is included in the drawings and specification but not in the bill of
quantities), or where there has been an arithmetical error.
A contingency sum is an item found within a bill of quantities (BoQ). The item refers to unforeseeable
cost likely to be incurred during the contract. There are two types of contingency sum. The first refers to a
specific item, e.g., "additional alterations to services when installing said shower unit", where an item for
alterations to existing services is not contained within the BoQ but some work is envisaged.
The second type of sum is where money can be allocated to any item, within the BoQ, in the same way as
the above example or used as "additional work to be undertaken by the contractor, at the request of the
contract administrator".
The first is usually approximated by the client’s PQS and the second by the contractors QS (or
commercial manager).
Do note that parts of a BOQ document can vary according to project size and agencies. For this article we
will only focus on the Measured Work aspect of BOQs – only actual or estimated work are measured and
tabulated.
These details are laid out in a tabular form that includes the item serial number, description of spec-in
contents, unit, quantity, rates and rupee amounts in different columns.
This part of the BOQ is the key element of the document as it provides detailed information about
individual items. To omit any data in the descriptions can affect the entire BOQ document, that’s why it is
crucial to write watertight descriptions.
Include columns for the item numbers, description, unit of measurement, quantity, rate for the
item, labor, and total cost for the item. Your item numbers will be consecutive, starting from 1.
Restart the item numbers for each section or category of the build.
The columns for the rate for each item and total costs will be filled in by contractors bidding on
the project. You typically won't have any values in those columns while you're drafting your
BoQ.
Prepare a list of materials you'll need to complete the project. Look at the architect's plans and
write a basic list of all the building materials required and the amounts needed of each. This
includes wiring, hardware, and other fixtures.
For example, if you're building a house, you might need framing materials, sheetrock, bricks,
concrete, flooring materials, wiring, lighting fixtures, and kitchen and bathroom fixtures.
Identify the unit of measurement for each of your materials. This may be a standard unit. For
example, if you've included paint on your list of materials, the unit of measurement may be
gallons or litres.
Once you've determined the materials you'll need, fill them in on your spreadsheet. For example,
if you need paint for your project, you might list "green paint" next to item #1. In the column for
unit of measurement, you would write "gallons." Then you would include the number of gallons
you needed in the quantity column.
Tip: When determining how much you'll need of a material, add 15 to 20 percent for waste. This
accounts for materials that are damaged or defective.
Break down the project into specific sections or categories. Since different parts of your project
will likely be handled by different contractors or subcontractors, split up your list of materials
into those sections. That way, each contractor or subcontractor will know exactly what their costs
will be for the project.
If you're building a house, some different parts might include "framing," "plumbing," "electrical,"
"kitchen," "bath," and "flooring."
Some materials may fall under more than one part. For example, if you have "framing" and
"flooring," they may both need to use the same nails. This means you need to divide the overall
number of nails you estimated between the two.
Estimate the labor required to complete each part. Based on the amount of work to be done,
determine the number of man-hours it will take to finish. This should be a conservative estimate
since some workers are more efficient than others.
You can talk to contractors to get an idea of how many hours it would take to finish a given part.
A quantity surveyor would usually be able to estimate this off the top of their head, based on their
experience with similar projects.
Make an initial cost estimate based on the architect's design. Look at the average prices for the
materials and labor in your area. You can find out materials prices by checking hardware stores.
To learn labor prices, you can talk to contractors in your area who work on similar projects.
When you total your material prices and your labor costs, you'll have a general idea of how much
money your project will cost to complete.
Print off a separate copy of the BoQ for your initial cost estimate. This information isn't usually
included on the official BoQ you submit to contractors for bids. Use it to compare bids you get
from contractors to find the best bid for your project.
Draft a schedule based on the estimates in the BoQ. Once you have labor estimates, it's possible
to determine how long it will take to complete your project. Keep this schedule loose to account
for things, such as weather, that could cause delays.
For example, if you've estimated it will take 1,000 man-hours to build your house, assuming the
contractors work 40 hours a week and there are no delays, it would take them 25 weeks to complete your
house. However, to allow for delays, you're better off planning for it to take 30 to 40 weeks.
PREPARATION OF TENDER
An invitation to tender provides prospective suppliers with tender documentation setting out the
information they need to prepare their offer. It is vital that tender documents are comprehensive and clear
if realistic prices are to be obtained, making it more likely that the project will adhere to the budget once
the works begin, and reducing the likelihood of misunderstandings, mistakes and claims.
It is important, when this is done, to ensure that the interfaces between packages are properly identified
and clearly allocated to one package or another. Having too many packages increases the number
of interfaces and so the potential problems.
The suppliers will need to appraise the tender documents themselves before sending them on to
any subcontractors for them to price and return. This can take time, so it is recommended that when
setting a timescale, to consider how complex the supply chain is likely to be and how important it is that
responses are received quickly.
Mid-tender interviews may be arranged to allow clarification of matters that might otherwise lead to an
inaccurate tender being submitted; they can also give the client insights into potential problems or
opportunities in the project as it is described by the tender documentation. Responses to queries raised
during the tender process can lead to clarification or amendment of the tender documentation which may
also result in an extension of the tender period. It is better to allow sufficient time during the tender
process to investigate opportunities and clarify problems, as the resulting tenders will then be better
prepared and will be likely to save time and money later.
There may be further interviews once the tenders have been received and assessed.
Once the preferred supplier has been identified there may be a tender settlement meeting to enter
into negotiations. This may result in further adjustment of the tender documents and the submission of a
revised tender.
REFERENCES
https://www.designingbuildings.co.uk/wiki/How_to_prepare_tender_documents
https://www.designingbuildings.co.uk/wiki/Bill_of_quantities_
https://m.wikihow.com/Prepare-a-Bill-of-Quantities?amp=1
2. Work related to design & drawing of flat slab using IS Code method.
INTRODUCTION
Flat slabs system of construction is one in which the beams used in the conventional methods of
constructions are done away with. The slab directly rests on the column and load from the slab is directly
transferred to the columns and then to the foundation. To support heavy loads the thickness of slab near
the support with the column is increased and these are called drops, or columns are generally provided
with enlarged heads called column heads or capitals.
Absence of beam gives a plain ceiling, thus giving better architectural appearance and also less
vulnerability in case of fire than in usual cases where beams are used.
GENERAL INFORMATION
In general normal frame construction utilizes columns, slabs & Beams. However it may be
possible to undertake construction without providing beams, in such a case the frame system would
consist of slab and column without beams. These types of Slabs are called flat slab, since their behavior
resembles the bending of flat plates. A reinforced concrete slab supported directly by concrete columns
without the use of beams
Flat Slab
Given data:
fck = 25 N/mm2
fy = 415 N/mm2
Thickness of slab:
= 12116/32
d = 378.62 mm ~ 380 mm
Take cover as 40mm
D = 380 + 40 = 420 mm
D = d + 40
= 1/3 x 12.116
=4m
Provide drop of 4 m x 4 m
D = 420 + 150
= 570 mm
= 14.25 KN/m2
Design load,
Wo = W u x l e x l x
Wo = 3975.7 KN
Mo = Wlx / 8
= (3975.7 x 11.36) / 8
= 5648.47 KNm
= 3671.51 KNm
= 1976.96 KNm
Negative moment 0.75 x 3671.51 = 2753 KNm 0.25 x 3671.51 = 917.87 KNm
Mulimit = 0.138fckbd2
= 9895.5 KNm
Mu = 5648.47 KNm
Mulimit > Mu
= 265 mm
= 1280 mm
= 3524.4 KN
= 1.298 N/mm2
Ks = 0.5 + c
c = L1/L2
= 12.11/10.21
= 1.19
Ks = 0.5 + 1.19
=1.7
c = 0.25fck = 0.2525
=1.25 N/mm2
v>c
Reinforcement:
Mu=2753.6KNm
d = 530mm
Mu = 0.87fyAstd [1-Astfy/bdfck]
2753.6 x 106 = 0.87 x 415 x Ast x 530 [1 – (Ast x 415) / (10211 x 530 x 25)]
Width = 10.211 mm
Mu=1186.18KNmm
d = 380 mm
Mu = 0.87fyAstd [1-Astfy/bdfck]
Mu=917.87KNm
d = 380 mm
Mu = 0.87fyAstd [1-Astfy/bdfck]
Width = 10211 mm
= 297.8 mm
Mu=790.784x106KNmm
d = 380 mm
Mu = 0.87fyAstd [1-Astfy/bdfck]
790.78x106 = 0.87 x 415 x Ast x 380 [1 - Astx415 / 10211x380x25]
a. Drops: To resist the punching shear which is predominant at the contact of slab and column
Support, the drop dimension should not be less than one -third of panel length in t hat direction.
b. Column Heads: Certain amount of negative moment is transferred from the slab to the column at
the support. To resist this negative moment the area at the support needs to be increased .this is
facilitated by providing column capital/heads.
Flat slabs are appropriate for most floor situations and also for irregular column layouts, curved
floor shapes, ramps etc. The benefits of choosing flat slabs include a minimum depth solution, speed of
construction, flexibility in the plan layout (both in terms of the shape and column layout), a flat soffit
(clean finishes and freedom of layout of services) and scope and space for the use of flying forms.
The flexibility of flat slab construction can lead to high economy and yet allow the architect great
freedom of form.
Examples are; solid flat slab, solid flat slab with drop panel, solid flat slab with column head,
coffered flat slab, coffered flat slab with solid panels, banded coffered flat slab.
Fig: 2.1 Solid Flat Slab Fig: 2.2 Coffered Flat Slab
5. Work related to cost estimation of (including market survey of rates) earthwork for a
highway.
INTRODUCTION
Earthworks are engineering works created through the moving and/or processing of massive quantities
of soil or unformed rock. Earthwork is done to reconfigure the topography of a site to achieve the design
levels. Earthwork involves cutting and filling to achieve the required topography.
Cutting: Cutting is the process of excavating earth material from a work location or borrow pits to
achieve the desired topography.
Filling: The filling is the process of moving the excavated material or additional earth material to a
work location to achieve the desired topography.
GENERAL INFORMATION
The area of sides which may require turfing or pitching, may be found by multiplying the mean sloping
breadth by the length.
APPLICATION
Road works
Railways
Irrigation projects such as canals and dams
Other common earthwork applications are land grading to reconfigure the topography of a site, or
to stabilize slopes
Estimate the cost of earthwork (Mid Sectional method) for a portion of highway from the following
data:
Chainage 1 2 3 4 5 6
RL of formulation level = 15
Chainage distance = 30 m
Width of formation = 10
1
For 30m chainage, decrease in RL (Fall) = 1200 x 30 = 0.025m
Whereas RL of ground = 10.750, 11.250, 12.355, 11. 130, 12.575 and 13.775
6. -
1.120 1.7225 17.225 2.967 5.934 23.159 30 694.77
Total = 7442 m3
INTRODUCTION
A building frame consists of number of bays and storey. A multistorey, multi-paneled frame is a
complicated statically intermediate structure. A design of R.C building of G+5storey frame work is taken
up. The building in plan (17.52*26.364) consists of columns built monolithically forming a network. The
size of building is 17.52*26.364m. The number of columns are 15. It is residential complex.
GENERAL INFORMATION
The design is made using software on structural analysis design (staad-pro). The building subjected to
both the vertical loads as well as horizontal loads. The vertical load consists of dead load of structural
components such as beams, columns, slabs etc and live loads. The horizontal load consists of the wind
forces thus building is designed for dead load, live load and wind load as per IS 875. The building is
designed as two dimensional vertical frame and analyzed for the maximum and minimum bending
moments and shear forces by trial and error methods as per IS456-2000. The help is taken by software
available in institute and the computations of loads, moments and shear forces and obtained from this
software.
USAGE
Geometry data
Give the length along shorter direction and length along longer direction. Then click on next. It displays
the slab structure on the right side of the geometry data
Material data
Enter the material data that is grade of concrete and grade of steel.
Loads
Enter the values of superimposed dead load and live load
Load combinations
Give factor for superimposed dead load and self weight.
Enter the factor for live load and click on next.
Reinforcement data
1. Give bar size along shorter dimension and bar size along longer dimension.
2. Provide clear cover according to codes.
REFERENCES:
1 IS 456:2000 Code of practice for plain and reinforced concrete
2. SP 16(S&T): 1980 Design aids for reinforced concrete to IS 456:1978
3. SP 23(S&T): 1982 Handbook on concrete mixes
4. SP 34(S&T): 1987 Handbook on concrete reinforcement and detailing
5. IS 875 (part 2)–1987 code of practice for live load
6. IS 875 (part 3)–1987 code of practice for wind load
7. IS 800-2007 code for steel
8. IS code 2502 - Code of Practice