Delays in Work Completion and Liquidated Damages
Delays in Work Completion and Liquidated Damages
Delays in Work Completion and Liquidated Damages
Damages
Legal Reference:
IRR-A Section 68, Annex “E” and the Civil Code of the Philippines
Article 2226 provide the rules in relation to delivery and liquidated
damages.
The contractor must complete the work procured within the period
prescribed by the Procuring Entity as specified in the contract.
In all cases, the request for extension shall always be filed before the
expiry of the original completion date. Maximum allowable extension
shall not exceed the original construction period.