ACB Maintenance Procedure
ACB Maintenance Procedure
ACB Maintenance Procedure
III. Maintenance
1. Check the general condition of the device.
2. Cleaning of the device, Braking unit (arc chutes+main contact), mechanism, and control
unit.
3. Check and tighten loose bolts and connections.
4. Re-Lubrication of the mechanism.
5. Replace, if there are broken parts. Bring to the attention of the owner and get approval a
nd change order before proceeding.
6. Record all condition of the device.
IV. Testing
1. Open /Close device manually and electrically.
2. Charge device manually and electrically.
3. Tripping curve of the OCR
4. Rack-in and Rack-out operation for draw-out type.
5. Record all result of the testing