Electrical Switchgear Testing
Electrical Switchgear Testing
Electrical Switchgear Testing
The Most Important Tests For Medium Voltage Metal-Enclosed Switchgear You
MUST Perform
Moisture combined with dirt is the greatest deteriorating factor for insulation
systems because of leakage and tracking, which will result in eventual failure.
Therefore, it is important to maintain the switchgear insulation and to chart the
condition of the primary insulation system by routine testing.
The electrical switchgear may be tested with AC or DC voltage to check the
condition of the insulation of switchgear and circuit breakers. Before
conducting any other tests, an insulation resistance test (by Megger) should
always be conducted first to determine if it is safe to conduct other HV tests.
Also when testing circuit breakers, it is important to check the condition of the
circuit breaker contacts and circuit breaker operating mechanism to
assure that the circuit breaker is opening and closing as designed.
These tests are listed and discussed as follows:
1. Insulation resistance test
2. DC or AC hi-pot test
3. Power factor or dielectric loss test
4. Circuit breaker contact resistance test
5. Circuit breaker time–travel analysis test
<="" ins="" data-adsbygoogle-status="done" data-ad-status="filled"
style="margin: 0px; padding: 0px; box-sizing: border-box; display: block; height:
280px;">
Hi-pot tests are made with the circuit breaker in both open and closed
positions. The hi-pot test should be the last test conducted after all repairs
have been made, cleanup is finished, and the insulation resistance test has
been successfully passed.
Figure 3 – Typical connection for hi-pot test for circuit breaker in closed position
Procedures for the hi-pot test of the circuit breaker are as follows:
1. The test connection for the hi-pot test is as shown in Figure 3.
2. Circuit breaker in open position:
Connect HV lead to pole 6. Ground all other poles. Repeat for poles 1
through 5, in turn, with all other poles grounded. Apply the desired
high voltage in each case in
accordance with Table 2.
3. Circuit breaker in closed position:
Connect HV lead to pole 1 or 2 or phase 1 as convenient with either
pole of phases 2 and 3 grounded. Repeat for test for phases 2 and 3
with other phases grounded.
4. Stationary gear (buses):
Connect HV lead to phase 1 as convenient with phases 2 and 3
grounded. Apply the recommended voltage. Repeat the test for
phases 2 and 3 with other phases grounded.
Go back to contents ↑
Figure 4
– The Megger DLRO 200-115 High Current Digital Low Resistance Ohmmeter,
200 Amp is designed to check and measure contact resistance in high voltage
circuit breakers, disconnecting switches (isolators), busbar joints, or for any low
resistance measurement
Go back to contents ↑
Today, the electronic time-travel analyzers are replacing the old mechanical
time–travel analyzers. With either analyzer information on the breaker operating
mechanism is provided in form of charts or graphs which can be used to
assess the mechanical and electrical condition of the breaker.
There are eight tests that are usually conducted on the breaker with the circuit
breaker analyzer. These tests are:
For example, they will define the first point to be set to a distance above the
open position and a distance below the upper point where the contact motion
stops as indicated below.
5. Trip operation
The trip operation of a breaker is another name for an
open operation. Most utility companies and plant owners want to perform a
trip (or open) operation to monitor the speed of the opening mechanism and
contacts to make sure there is enough energy in the spring mechanism to open
under a fault condition.
The graph for a trip is similar to the one for a close operation, except the motion
of the mechanism is going in the opposite direction, i.e., from closed contacts to
fully open position as seen in Figure 7
Figure 7 – Graph showing speed of the contacts opening for trip (or open)
operation of a breaker
6. Trip-free operation
This operation simulates the condition when an open breaker is closed into a
fault and then it is tripped free by a protective relay.
8. Trip-reclose operation
In this test, the reclose operation of the breaker is checked to assure that the
breaker closing time is within specified limits after a trip operation. The
reclose time is measured either in milliseconds or cycles.
The trip-reclose operation of the breaker is shown in Figure 10.