Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

DPR Package No UP67146 With Approch

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 249
At a glance
Powered by AI
The document provides details about the proposed upgradation of the Windhamganj Piparkharr Road to Auradar in Sonebhadra district of Uttar Pradesh, India.

The road project is for the upgradation of the Windhamganj Piparkharr Road to Auradar under the Pradhan Mantri Gram Sadak Yojana (PMGSY) rural roads program in Uttar Pradesh.

Key details provided about the road include its length of 25.3 km, construction cost of 1478.74 lacs, maintenance cost of 147.71 lacs, block and division details, formation levels, existing and proposed widths etc.

UTTAR PRADESH

PUBLIC WORKS DEPARTMENT, SONEBHADRA

DETAILED PROJECT REPORT


FOR
UPGRADATION OF ROAD UNDER
RCPLWEA (ADDITIONAL)
YEAR :– 2019-20
PACKAGE NO. :- UP67146
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

NO. OF ROADS IN PACKAGE :- 1


ROAD LENGTH :- 25.300 K.M.
CONSTRUCTION COST :- 1478.74 LACS.
MAINTENANCE COST :- 147.71 LACS.
BLOCK :- CHOPAN / DUDDHI

PMGSY DIVISION, P.W.D.

SONEBHADRA (U.P.)
Percentilegreater than or equal to cbr value
NAME OF ROAD :-

FORMATION LEVELS

SL.NO.
SL.NO.

3.120 100.000 1
DISTRICT:- SONEBHADRA

3.150 96.000 2

0.000
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
90.000
100.000
3.120
3.200 92.000 3

3.150
3.420 88.000 4
3.200

Sonebhadra
3.820 84.000 5

Junior Engineer
3.420

PMGSY Division, PWD


3.850 80.000 6
3.820
4.120 76.000 7
3.850

4.120 4.150 72.000 8

Design CBR - as per 80 percentile for Rural Area =


4.150 4.260 68.000 9

4.260 4.280 64.000 10

3.64%
4.280
4.290 60.000 11
WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

4.290
4.320 56.000 12
4.320
BLOCK :- CHOPAN / DUDDHI

4.350 52.000 13
4.350

Sonebhadra
4.370 48.000 14

Assistant Engineer
4.370

PMGSY Division, PWD


4.390 44.000 15
4.390

4.650 4.650 40.000 16


RCPLWEA (ADDITIONAL)

4.850 4.850 36.000 17

4.860 4.860 32.000 18

4.890
Design CBR - as per 80 percentile for Rural Area

4.890 28.000 19

4.920
4.920 24.000 20
5.120
5.120 20.000 21
PACKAGE NO. :-

5.160
5.160 16.000 22
5.250
Sonebhadra

5.250 12.000 23
UP67146

5.420
Executive Engineer
PMGSY Division, PWD

6.540 5.420 8.000 24

6.540 4.000 25
CHANGE POINT
YEAR :– 2019-20
RCPLWEA (ADDITIONAL)
3
PMGSY DIVISION, P.W.D.
4 SONEBHADRA (U.P.) UTTAR PRADESH
1 DISTRICT:- SONEBHADRA SONEBHADRA
2 BLOCK :- CHOPAN / DUDDHI CHOPAN / DUDDHI
5 NAME OF ROAD :- WINDHAMGANJ PIPARKHARR
ROAD TO AURADAR.

6 FROM TO WINDHAMGANJ AURADAR.


PIPARKHARR
ROAD
7 PACKAGE NO. :- UP67146
8 ROAD LENGTH :- 25.300
9 REFERENCE PILLARS 506
10 IN BUILT UP AREA - 11.615
10
11 IN OPEN AREA - 13.685
12 LOCAL EARTH 39120.56
13 CARTED EARTH 14949.37

14 EXISTING SURFACE
S.NO. CH Width EXISTING LENGTH Width
SURFACE

1 4.850 18.300 3.00 3.00 M BT 13.450 3.00


3 21.800 25.300 3.00 3.00 M BT 3.500 3.00
3 3.00 3.00 M BT 0.000 3.00
TOTAL 16.950
2 0.000 4.850 3.75 3.75 M BT 4.850 3.75
4 3.75
3.75 M BT Ch. 0.00 to 4.85 0.000 3.75
TOTAL 4.850
2 18.300 21.800 EARTHEN 3.500 0.00
TOTAL 3.500
TOTAL= 25.300 0.000
Total length of PC work 25039.000
1 TYPE OF PROPOSAL U
2 EXISTING B.T.
3 SURFACE
FACILITIES ACCESSED TYPE
( USE A/B/C/D) A
4 EXISTING ROAD 3.00 TO 3.75 m
5 PROPOSED ROAD 3.75 m
6 ROADWAY 7.50 m

15 QUARRY RATE
QUARRY DISTANC ROBERTSG 0.00 TO TOTAL
E TO ANJ TO MIDDLE DISTANCE
ROBERTS STARTUNG OF ROAD
GANJ CHAINAGE
Sukrut 26 83 13 122 LOADING 35.000
Dalla 51 0 13 64 UNLOADING 18.000
Chopan 59 0 13 72

16 CARTAGE WITH CP
1 UPTO 50KM 647.20
2 51 to 75 9.00
3 76 to 100 8.00
4 101 to 200 7.50
5 >200 km 6.50
6 KACHCHA 15.90

17 BITUMEN RATE
REFINERY DISTANC ROBERTSG 0.00 TO TOTAL RATE DATE
E TO ANJ TO MIDDLE DISTANCE
ROBERTS STARTUNG OF ROAD
GANJ CHAINAGE
MATHURA 665 83 13 1522 1.74
Jhansi 580 83 13 1352 1.74 BITUMEN DATE
VG-30 28940.00
SS-1 32965.00

18 NO OF JUNCTION , CURVES
1 NO OF JUNCTION 39
2 AREA OF JUNCTION AT CH 0.000 49.23
3 AREA OF JUNCTION AT CHAKROADS 4.425
4 NO OF CURVES 272
5 TOTAL WIDENING OF CURVES 1858.28
6 5TH KM STONE 6
7 KM STONE 19
8 HECTOMETER STONES 102
9 TRAFFIC SIGNS 272
10 DIRECTION AND PLACE IDENTIFICATION SIGNS 544
WITH SIZE MORE THAN 0.9 SQM SIZE BOARD

11 INFORMATORY BOARDS WITH LOGO 1


12 LOGO BOARD WITH DIAMOND 2
13 CITIZEN INFORMATION BOARD 127
14 OVERHEAD @ 10%
15 CONTRACTOR PROFIT @ 10%
16 REDUCTION FACTOR ( RATE X1.125/1.21)= 0.9297520661
17 LABOUR CESS 1%

19 ABADI LENGTH
S.NO. Abadi Name Chaniage LENGTH POPULATION
1 KUDWA VILLAGE 0.000 1.350 1350.00 806.00
2 KUDWA YADAV BASTI 2.000 2.850 850.00 -
3 KUDWA TUNIYA BAS 3.525 6.075 2550.00 1258.00
4 PANDU CHATAW VIL 6.625 8.650 2025.00 687.00
5 GHICHORWA VILLAGE 9.100 9.625 525.00 180.00
6 NIMIYA SUKAR 14.025 14.625 600.00 109.00
7 NIMIYA SUKAR 15.075 15.500 425.00 -
8 GULARIYA 15.625 15.775 150.00 -
9 KARIYA VILLAGE 16.325 18.100 1775.00 511.00

10 AURADANDI VILLAGE 23.935 25.300 1365.00 687.00

TOTAL 11615.00 4238.00


20 U- TYPE DEEP DRAIN 400.000
S.NO. NAME LENGTH
1 KUDWA VILLAGE 100.000
2 KUDWA YADAV BASTI 50.000
3 KUDWA TUNIYA BASTI 50.000
4 PANDU CHATAW VILLAGE 0.000
5 GHICHORWA VILLAGE
6 NIMIYA SUKAR (KHARAIYA) VILL.
7 NIMIYA SUKAR (KHARAIYA) VILL.
8 GULARIYA
9 KARIYA VILLAGE 0.000
10 0
11 AURADANDI VILLAGE 0.000

21 KC DRAIN 1200.000
S.NO. NAME LENGTH
1 KUDWA VILLAGE 100.000
2 KUDWA YADAV BASTI 80.000
3 KUDWA TUNIYA BASTI 100.000
4 PANDU CHATAW VILLAGE 120.000
5 GHICHORWA VILLAGE 0.000
6 NIMIYA SUKAR (KHARAIYA) VILL. 0.000
7 NIMIYA SUKAR (KHARAIYA) VILL. 0.000
8 GULARIYA 0.000
9 KARIYA VILLAGE 100.000
10 0 0.000
11 AURADANDI VILLAGE 100.000

22 HUME PIPE RATE


S.NO. DIA OF PIPE Basic rate Cartage @15% total
1 100 MM NP-3 195.000 29.250 224.25
2 350 MM NP-3 870.000 130.500 1000.50
3 600 MM NP-3 1560.000 234.000 1794.00
4 900 MM NP-3 3385.000 507.750 3892.75
5 1000 MM NP-3 4000.000 600.000 4600.00
6 1200 MM NP-3 6000.000 900.000 6900.00
23 MAINT. COST FOR FIVE YEARS
1 Ist Year 54507.00
2 IInd Year 85609.00
3 IIIrd Year 116746.00
4 IV th Year 147937.00
5 V th Year 179021.00

24 EXISTING CULVERT
1X350 MM H.P. CULVERT
S.NO CH NO Type Span/ Dia. (m) Condition
1 1.490 1 H.P. CULVERT 1X0.350 Good.
2 1.820 1 H.P. CULVERT 1X0.350 Good.
3 2.310 1 H.P. CULVERT 1X0.350 Good.
4 2.880 1 H.P. CULVERT 1X0.350 Good.
5 4.140 1 H.P. CULVERT 1X0.350 Good.
6 15.260 1 H.P. CULVERT 1X0.350 Good.
Total 6
1X600 MM H.P. CULVERT
S.NO CH NO Type Span/ Dia. (m) Condition
1 16.500 1 H.P. CULVERT 1X0.600 Good.
2 16.600 1 H.P. CULVERT 1X0.600 Good.
Total 2
1x1000 MM H.P. CULVERT
S.NO CH NO Type Span/ Dia. (m) Condition
1 0.460 1 H.P. CULVERT 1X1.000 Good.
2 1.000 1 H.P. CULVERT 2X1.000 Good.
3 1.240 1 H.P. CULVERT 2X1.000 Good.
4 2.100 1 H.P. CULVERT 1X1.000 Good.
5 6.140 1 H.P. CULVERT 2X1.000 Good.
6 6.810 1 H.P. CULVERT 1X1.000 Good.
7 7.000 1 H.P. CULVERT 2X1.000 Good.
8 7.100 1 H.P. CULVERT 1X1.000 Good.
9 7.750 1 H.P. CULVERT 2X1.000 Good.
10 15.280 1 H.P. CULVERT 2X1.000 Good.
Total Total 10
1x1200 MM H.P. CULVERT
S.NO CH NO Type Span/ Dia. (m) Condition
1 3.480 1 H.P. CULVERT 5X1.200 Good.
Total Total 1
R.C.C. CULVERT 1x1.50 M
S.NO CH NO LENGTH NO Type Span/ Dia. (m)
1 4.760 1 1.50 1 R.C.C. CULVERT 1X1.500
2 17.780 1 1.50 1 R.C.C. CULVERT 1X1.500
3 18.190 1 1.50 1 R.C.C. CULVERT 1X1.500
Total 4.50 3
R.C.C. CULVERT 1x2.50 M
S.NO CH NO LENGTH NO Type Span / Dia. (m)
1 2.500 1 2.50 1 R.C.C. CULVERT 1X2.500
2 7.490 1 2.50 1 R.C.C. CULVERT 1X2.500
3 10.260 1 2.50 1 R.C.C. CULVERT 1X2.500
4 14.550 1 2.50 1 R.C.C. CULVERT 8X2.500
5 17.125 1 1 R.C.C. CULVERT 10X2.500
Total 7.50 5
G/TOTAL LENGTH OF CULVERTS 12.00
G/TOTAL NO OF EXISTING
CULVERTS 27

25 PROPOSED CULVERT
1X350 MM H.P. CULVERT
1 X 350MM NEW 3
1X600 MM H.P. CULVERT
1 X 600MM NEW 2
1X1000 MM H.P. CULVERT
1 X 1000MM NEW 3
R.C.C. CULVERT
1x2.50 m NEW 0
R.C.C. CULVERT
1x5.00 m NEW 1
TOTAL 9
RETAINING WALL
S.NO CH LENGTH
1 0.000 1.500 1500.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 1500.000
TOE WALL
S.NO CH LENGTH
1 0.000 0.150 300.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 300.00
BREAST WALL
S.NO CH LENGTH
1 0.000 0.100 100.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 100.00
CAUSEWAY
S.NO CH LENGTH
1 0.000 0.249 249.000
2 0.000 0.000 0.000
3 0.000 0.000 0.000
4 0.000 0.000 0.000
5 0.000 0.000 0.000
6 0.000 0.000 0.000
TOTAL= 249.00
BOX CULVERT
S.NO CH NO Size LENGTH
1 0.000 0 4x2x2 M 0
2 0.000 0 4x3x3 M 0
3 0.000 0 4x4x4 M 0
4 0.000 1 5x7.50x5 M 0

TOTAL= 1 0 0
MINOR BRIDGE
S.NO CH NO Size LENGTH
1 0.000 0
2 0.000 0
3 0.000 0
4 0.000 0
5 0.000 0 0 0
6 0.000 0 0 0
TOTAL= 0 0 0
PARAPET WALL
S.NO CH LENGTH NOS
1 0.000 0.600 300.000 133
2 0.000 0.000 0.000 0
3 0.000 0.000 0.000 0
4 0.000 0.000 0.000 0
5 0.000 0.000 0.000 0
6 0.000 0.000 0.000 0
TOTAL= 300.000 133
Junior Engineer Assistant Engineer Executive Engineer
PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
Crust Proposed Proposed GSB Proposed Width Proposed Width Propose
Width WIDENING G-2 G-3 d Width
Excvn Prime
Thickness Width Thickness Width Thickness Width
0.175 1.050 0.175 1.050 0.075 3.750 0.075 3.750 3.750
0.175 1.050 0.175 1.050 0.075 3.750 0.075 3.750 3.750
1.050 0.175 1.050 0.075 3.750 0.075 3.750 3.750

0.270 0.000 0.000 0.000 0.000 0.000 0.075 3.750 3.750


0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

0.000 0.000 0.175 4.050 0.075 3.750 0.075 3.750 0.000


CC ROAD
0.00
6

10

Condition
Good.
Good.
Good.
Condition
Good.
Good.
Good.
Good.
Damaged

CH-13.850 30 M 5 M SPAN
CH-17.000 40 M 5 M SPAN
CH-20.100 - 5 M SPAN
1.INTRODUCTION
1.1 Objectives of RCPLWEA (ADDITIONAL)
Rural road Connectivity is a key component of rural development of naxalite affected area by promoting access to economic
and social services of poor people living in naxlite areas and thereby generating increased agricultural income and productive
employment opportunities in remote area. It is also a key ingradient in ensuring poverty in Naxalite area and also in Country.

It was against this background of poor Connectivity that the ministry of Home affairs-Govt of India decided to develop the
better road connectivity in Naxlite area and to provide the all weather road access to Naxalite villages/habitations. In this
background, the need for Consolidation of existing network was felt to ensure that is fulfills the primary objective of
connectivity along with mobility to the extant possible for the local community and enables economical transportation of goods
and services to provide better livelihood opportunities as a part of poverty reduction strategy.

RCPLWEA Projects envisages consolidation of the existing Rural Road Network to improve its overall efficiency as a
provider of transportation service for people, goods and services. It aims to cover upgradation of existing selected rural roads in
Naxalite areas based on their economic potential and their role in facilitating growth of rural market centres and rural hubs.
Developments of growth centres and rural hubs are critical to the overall strategy of facilitating poverty alleviations through
creation of rural infrastructure. Growth centres/Rural hubs would provide markets, banking and other service facilities to
enhance self employment and livelihood facilities.
The existing pavement is old and consisting of materials of old pavement technology. for the present case, the existing
pavement in its thickness is considered equivalent to GSB thickness of current technology. therefore proposed top surface of
GSB shall match with the top surface of old Pavement after scrapping existing PC Surface.
1.2 All Weather Road
All-weather road is one which is negotiable during all weathers, with some permitted interruptions. Essentially this means that
at cross-drainage structures, the duration of overflow or interruption at one stretch shall not exceed 12 hours for ODRs and 24
hours for VRs in hilly terrain, and 3 days in the case of roads in plain terrain. The total period of interruption during the year
should not exceed 10 days for ODRs and 15 days for VRs.
1.4 Geography
SONEBHADRA district of State Uttar Pradesh has 8 blocks and 173 villages . The Topographical area of the DistricSONEBHADRA
is 6788.00 square KMs and the Total population is 10000000 Lacs
1.5 Climatic Condition
SONEBHADRA has a tropical climates have monthly mean temperature above 18° C (64° F) in every month of the year and

typically a pronounced dry season , with the driest month having precipitation less than 60 mm (2.36 inch) of precipitation . the
summer temperature is around 19° C-44° C and Winter temperature is 9° C-26° C. The average rainfall is about 1000 mm
annually. Wheet, Rice and sugarcane are the major agriculture crops.
1.6 The Sub-Project Road
The road passes through hill terrain starts at WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
SONEBHADRA District of U. P. State, India.
District: SONEBHADRA
Block: CHOPAN / DUDDHI

NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.


UP67146
PACKAGE NO. :-
ROAD LENGTH :- 25.300 K.M.
START POINT :- WINDHAMGANJ PIPARKHARR ROAD
END POINT :- AURADAR.
Population benefited Chaniage
Sl.No. Habitation benefited
Direct Indirect From To
1 KUDWA VILLAGE 806 0.000 1.350
2 KUDWA YADAV BASTI - 2.000 2.850
3 KUDWA TUNIYA BASTI 1258 3.525 6.075
4 PANDU CHATAW VILLAGE 687 6.625 8.650
5 GHICHORWA VILLAGE 180 9.100 9.625
6 NIMIYA SUKAR (KHARAIYA) VILL. 109 14.025 14.625
7 NIMIYA SUKAR (KHARAIYA) VILL. - 15.075 15.500
8 GULARIYA 192 15.625 15.775
9 KARIYA VILLAGE 511 16.325 18.100
10 0 - 0.000 0.000
11 AURADANDI VILLAGE 687 23.935 25.300

2. PLANNING AND BASIC DESIGN CONSIDERATION


2.1 Key map of indicating the project road.
2.2 Preliminary alignment investigation Attached separately
2.3 Site Photographs
3.1 General
Topographic survey, is one of the most important preliminary tasks in the road survey project. The Survey is conducted by
using Total Station. Survey is the technique, profession, and science of accurately determining the terrestrial or three-
dimensional position of points and the distances and angles between them.
The in-house standards, work procedures and quality plan prepared with reference to IRC: SP 19-2001, IRC: SP 20, IRC: SP 13
(in respect of surveys for rivers/streams) and current practices have been followed while conducting the above survey.
The survey work has been divided into the three basic sub divisions
* Reconnaissance
* Preliminary Survey and
* Final Location Surveys.
Reconnaissance starts with a field inspection by walking and all information of value, either in design, construction,
maintenance or operation of the facility has been collected.
During the preliminary survey all the requirements of cross-drainage works – type, number and length and other relevant
details are collected.
During the Final topographical survey has been conducted using a total station. The Bench marks have been established at
salient points and at regular intervals and the topographic survey has been conducted and all the features of the ground and the
road has been recorded.
*
Road length passing through different terrains
*
Cross sections and longitudinal section at regular intervals
*
Villages, hamlets and market centers and their location
*
Crossing with railway lines and other existing roads.
Position of ancient monuments, burial grounds, cremation grounds, religious
*
structures, hospitals and schools etc.
3.2 Traversing
Traverse has been using total station having angular measurement accuracy of ± 1 sec. Initially The Bench Marks have been
established and the same are connected using a GPS and the locations marked. The traverse is conducted and fly back leveling
is done for counterchecking the bench mark levels.
3.3 Leveling
Leveling has been using total station having angular measurement accuracy of ± 1 sec.
3.4 Cross Section & Detailing
Cross sections were taken at 25 m interval and at closer interval of 5 m to 10 m in curved portion of the existing road. All
physical features of the road have been recorded and the same is processed using software’s.
3.5 Data Processing
All data from topographic survey recorded by total station have been processed by appropriate software’s and the longitudinal
and cross section and other details.
3.6 Permanent reference pillars and TBMs including northing easting and levels
The bench marks have been established on salient and important locations on permanent objects and the Northing’s and
Easting’s of the locations of the Bench marks have been recorded using GPS.
List of TBM and RBM are Attached separately
3.7 Checklist
Reference Pillars given Yes No
TBM with northing-easting given Yes No
Traverse survey carried out Yes No
Cross section and detailing carried out Yes No
4. SOIL AND MATERIALS SURVEY
4.1 General
The soil and material investigations were done following the guidelines of IRC: SP: 20-2002 and IRC: SP: 72-2015 and other
relevant IS code. The potential sources of borrow areas for soil and probable quarry sites are identified with the section
Engineers.
4.2 Soil sample collection and Testing
Soil samples are collected along and around the road alignment at three (3) locations per km, from the adjoining borrow areas,
as well as one sample is collected from the existing road. Soil Classification tests like grain size analysis and Atterberg’s limit
are conducted for all the samples collected. Standard Proctor test and the corresponding 4 day soaked CBR test were conducted
for a minimum of one test per km for soil samples of same group or more tests due to variation of soil type. The following tests
have been conducted as detailed below:
· Grain size analysis as per IS : 272 (Part 4) – 1985
· Atterberg’s limit as per IS : 2720 (Part 5) – 1985
· Standard Proctor density test as per IS : 2720 (Part 7) – 1980
· 4 day soaked CBR test as per IS : 2720 (Part 16) – 1985
4.3 Analysis of Test Results
Table 4.1 CBR values for different stretches

Sl No Section in Km CBR %
1 4.95 3.15
2 9.85 3.24
3 14.5 3.64
4 19.125 3.44
4.4 Coarse and Fine Aggregates
The available information regarding the source of aggregate and sand have been gathered. The stone aggregates will be
procured from the nearest quarry whereas the locally available sand will be used. The source and the lead distance from the
quarry to project site has been finalized in discussion with the PIU. The aggregates and sand where available and acceptable are
recommended to be used for bituminous work, concrete works, other pavement works.
4.5 Sub-soil investigation for bridges
The Alignment of the road does not have any bridge at present and no bridge proposed in the DPR.
4.6 Checklist
Borrow pit suitable Yes No
Investigation for coarse/fine aggregate Yes No
Quarry map Yes No
5.TRAFFIC SURVEY
5.1 General
The traffic survey is conducted on the road for 3 day 24 hr. The Classified Volume Count survey has been carried out in
accordance with the requirements of the TOR and relevant codes (IRC: SP: 19-2001, IRC: SP: 20, IRC: SP: 72-2015).The
surveys have been carried out by trained enumerators manually under the monitoring of Engineering Supervisor
5.2 Traffic Data and Analysis
The traffic data obtained is classified into different vehicle category as given below:
· Motorized vehicle comprising of light commercial vehicle, medium commercial vehicle, heavy commercial vehicle, trucks,
buses, agricultural tractors with trailers, car, jeep, two wheelers etc.
· Non- motorized vehicles comprising of cycle, rickshaw, cycle van, animal drawn vehicle etc.
The number of laden and un-laden commercial vehicles recorded during the traffic counts. Traffic volume count for this project
road was done during the start of the rainy season. The seasonal variation is based on local enquiry.
· Average of 3 day traffic data is presented in DPR
5.3 Traffic Growth Rate and forecast
The average annual growth rate of 6% over the design life is adopted.
6.HYDROLOGICAL SURVEY
6.1 General
Hydrological data collection and the survey is necessary for design of Cross Drainage Structures so that the rain water can pass
as per natural slope. Hydrological survey of the proposed road is based on the available topographic maps of the Survey of India
and the catchment area of the cross drainage works has been derived and the analysis is done.
6.2 Rainfall Data
Rainfall Data has been obtained form the local authorities and the same is used in the computation of the flow across the cross
drainage works and the computation of the volume of flow .
6.3 Catchment Area
The Catchment area is calculated by local information and also studying the Topo sheets procured from Survey of India. The
location of the cross drainage works marked in the respective Topo sheets along with catchment area are attached to the DPR.
6.4 Time of Concentration
Time of concentration (Tc) in hours is calculated from the formula of (0.87 x L3/H)0.385, where L is distance from the critical
point to the structure site in km and H is the difference in elevation between the critical point and the structure site in meters.
6.5 Existing Cross Drainage Structures
There are 6 number of cross drainage structures along the existing project road as listed below:
Table-6.1: List and condition of existing culverts
Description of Existing Structure
Chainage
Sl.No
(km) Type Span/ Dia. (m) Condition
1X350 MM H.P. CULVERT
1 1.490 H.P. CULVERT 1X0.350 Good.
2 1.820 H.P. CULVERT 1X0.350 Good.
3 2.310 H.P. CULVERT 1X0.350 Good.
4 2.880 H.P. CULVERT 1X0.350 Good.
5 4.140 H.P. CULVERT 1X0.350 Good.
6 15.260 H.P. CULVERT 1X0.350 Good.
1X600 MM H.P. CULVERT
1 16.500 H.P. CULVERT 1X0.600 Good.
2 16.600 H.P. CULVERT 1X0.600 Good.
1X1000 MM H.P. CULVERT
1 0.460 H.P. CULVERT 1X1.000 Good.
2 1.000 H.P. CULVERT 2X1.000 Good.
3 1.240 H.P. CULVERT 2X1.000 Good.
4 2.100 H.P. CULVERT 1X1.000 Good.
5 6.140 H.P. CULVERT 2X1.000 Good.
6 6.810 H.P. CULVERT 1X1.000 Good.
7 7.000 H.P. CULVERT 2X1.000 Good.
8 7.100 H.P. CULVERT 1X1.000 Good.
9 7.750 H.P. CULVERT 2X1.000 Good.
10 15.280 H.P. CULVERT 2X1.000 Good.
1X1200 MM H.P. CULVERT
1 3.480 H.P. CULVERT 5X1.200 Good.
1X1.50m Span RCC CULVERT
1 4.760 R.C.C. CULVERT R.C.C. CULVERT Good.
2 17.780 R.C.C. CULVERT R.C.C. CULVERT Good.
3 18.190 R.C.C. CULVERT R.C.C. CULVERT Good.
1X2.500m Span RCC CULVERT
1 2.500R.C.C. CULVERT 1X2.500 Good.
2 7.490R.C.C. CULVERT 1X2.500 Good.
3 10.260R.C.C. CULVERT 1X2.500 Good.
4 14.550R.C.C. CULVERT 8X2.500 Good.
5 17.125R.C.C. CULVERT 10X2.500 Damaged
Terrain Classification Roadway Width (m)
Plain and Rolling 9.00
Roadway width for the project road is stated as below:
7.6 Carriageway Width
The width of carriageway for this project road adopted is 3.75 m.
7.7 Shoulders
The width of the shoulders adopted is 1.875 m wide on both sides.
7.8 Roadway width at cross-drainage structures
Width of the road at culvert locations for this project road is 7.50 For Hume pipe culvert and 7.50 m for RCC culvert in plain
terrain and existing culvert are of of 7.50 mtr width .
7.9 Sight Distance
The safe stopping sight distance is applicable in the geometric design. The sight distance values for this road as per IRC
recommendations are presented below:
Design Speed (km/hr.) Safe Stopping Sight Distance (m)
20 20
30 30
40 45
50 60
7.10 Radius of Horizontal Curve
According
To to IRC recommendations/standards, the minimum radius of horizontal curve for this project road is given below:
minimize
extra land Radius of Horizontal Curve (m)
arrangement, Terrain Category
Ruling Minimum Absolute Minimum
minimum
radius used is Plain 90 60
20 m and
design speed in
7.11 Camber & Super elevation
these curves
A camber adopted
are also on this road section is given below. The maximum super elevation is 5.0% for this project road.
restricted to 20 Camber (%)
km/hr. Surface type Low rainfall High rainfall
(Annual rainfall <1000mm) (Annual rainfall >1000mm)
Earth road 4 5
WBM Gravel road 3.5 4
Thin bituminous road 3 3.5
Rigid Pavement 2 2.5

7.12 Vertical Alignment


The present road is in plain terrain and vertical alignment has been designed well within ruling gradient. Minimum gradient of
0.3% for drainage purpose is considered for designing the vertical alignment of this road. Vertical curves are not required when
grade change is less than 1%, however a minimum vertical curve is provided to avoid vertical kink.
7.13 Vertical Curves
the minimum length of vertical curve for different design speed as given in IRC-SP 20:2002. Has been considered in the design.
And this project has got no vertical curves.
7.14 Side slope
The side slope for this project road is considered from the below table.
Condition Slope (H:V)
Embankment in silty/sandy/gravel soil 2:01
Embankment in clay or clayey silt or inundated
2.5:1 to 3:1
condition
Cutting in silty/sandy/gravelly soil 1:1 to 0.5:1
Cutting in disintegrated rock or conglomerate 0.5:1 to 0.25:1
Cutting in soft rock like shale 0.25:1 to 0.125:1
Cutting in medium rock like sandstone, phyllite 0.083:1 to 0.0625:1
Cutting in hard rock like quartzite, granite Near vertical

7.15 Extra Widening of Pavement


The Extra Widening of Pavement at Curve as per IRC guideline is given below:
Radius of Curve (m) Up to 20 21 - 60 Above 60

Extra Widening for 3.75 m wide single lane


0.9 0.6 Nil
carriageway, (m)

8.ALIGNMENT DESIGN
8.1General
As this project road is existing one care is taken to fit in the same alignment of the road. Basic aim of road design is to identify
technically sound, environment-friendly and economically feasible alignment. The ensuing sections deals with obligatory
points, which control highway alignment, design of cross-section, highway geometric design & methodology, design of
miscellaneous items.
The main components included in the highway design are:
Ø Cross-sectional elements
Ø Embankment
Ø Horizontal alignment
Ø Vertical profile
Ø Junctions and/or Interchanges
Ø Road furniture etc.
8.2 Horizontal Alignment
As the upgradation has been proposed on existing roads the centre line of the existing and proposed horizontal alignment
concides.
8.3 Vertical alignment
No vertical curves are proposed in the project road.
9. PAVEMENT DESIGN
9.1 General
Considering the sub grade strength , projected traffic and the design life, the pavement design for low volume PMGSY roads is
carried out as per guidelines of IRC: SP: 72 – 2015 or IRC SP:77 “Design of Gravel Road” and IRC SP:62-2004 “Cement
Concrete roads”. In built up area for hygienic and safety reasons, C.C. pavement is used with a hard shoulder and as per the
prevailing standards.
9.2 Pavement Design Approach
9.2.1 Design Life
A design life of 10 years is considered for the purpose of flexible pavement design.
9.2.2 Design Traffic
Average Annual Daily Traffic (AADT) is computed and presented in Table 5.2.
9.2.3 Determination of ESAL applications
Commercial vehicles with a gross laden weight of 3 tons or more are considered for the design. The design traffic is considered
in terms of cumulative number of standard axles to be carried during the design life of the road. The number of commercial
vehicles of different axle loads are converted to number of standard axle repetitions by a multiplier called the Vehicle Damage
Factor (VDF). An indicative VDF value considered as the traffic volume of rural road does not warrant axle load survey.
For calculating the VDF, the following categories of vehicles are considered as er paragraph IRC: SP: 72 – 2015.
· Laden heavy/medium commercial vehicles, Un-laden /partially loaded heavy/medium commercial vehicles and the over
loaded heavy/medium commercial vehicles
The VDF values considered 10% of laden MCV and 10% laden HCV as overloaded & given below:
Un-laden /Partially
Vehicle type Laden
laden
HCV 2.86 0.31
MCV 0.34 0.02
Lane distribution factor (L) for Single lane road = 1.0 Cumulative ESAL application = To x 4811 x L, where To = ESAL
application per day. The Cumulative ESAL application for the project road as per paragraph 3.5 of IRC: SP: 72 – 2015 is
appended to the DPR.
9.2.4 Subgrade CBR
CBR range considering the report and the CBR 3.64% range is considered and the traffic falls in the T-3 category.
9.3 Design Alternatives
Design alternatives considered and enumerated in the below table.
Chainage Design alternatives considered
Pavement Shoulder

Soil stabilization and


Hard shoulder 0.875

available marginal
Earthen full width

Hard

Specify
use of locally
m each side

design Justificatio

materials.
Flexible

From To alternative n
Rigid

selected
Full width

Enclosedin the detailed estimate


Rigid Pavement
Cement Concrete pavement is proposed for the in the village limit.
9.5 Embankment Design
No high embankments are proposed in the proposed road section.
Calculation of additional Material Requirement at Entrance & Horizontal Curves
1. Widening Of Pavement at Entrance Curves
Assumed that at entrance a curve of 15 meters radus will be provided.(PL refer to of Entrance point attached in Annexure) as
calculated 220.70sqm
2. widening Of Pavement at Curves As per Table 2.18, lause 2.10.3 IRC SP 20-2002 Pe-39
Radius of upto 20mtr & 21-60 mt
Single Lane 0.90 0.60
Note From the above table,widening of curve required is 0.60 meters
3. Length Of Transition Curves
Table 2.17 IRC SP:20-2002, Pg-39
Design S 50 Km/Hr 40 Km /Hr 35 Km /Hr
SI,NO.
Radius(Meters)
1 45 N.A. N.A. 70
2 60 N.A. 50 40
3 90 75 50 40
Note -The speed at curves for Rural Roads has been assummed as 40 Km /Hr (AS PER Table 2.2 clause 2.4 Pg 29 SP-20:2002)
and the radius considering the land availability has been adopted as 60 (As per Table 2.15 clause 2.10.4,Ps 38;SP-20:2002)
meters
EXTRA AREA AS PER ATTACHED CALCULATION SHEET ON CURVES = 1858.28 sqm
Total No Of Curves to be provided on this Road = 272 Nos
10. DESIGN OF CROSS DRAINAGE
10.1 General
Based on the hydrological survey, Two new cross drainage structures are recommended for the project road and detail are
enumerated in the relevant design tables and indicted thereon.
10.2 Hydrological Design
The existing structures in poor condition that are proposed for replacement as listed in the relevant tables. Agricultural conduits
( field culverts) have been proposed where ever it is found required.
10.3 Design Features
Design Standards for culverts has been prepared based on standard codes and guidelines of IRC: SP: 20: 2002 and the general
consideration of the designed cross drainage structures are given below:
For Hume pipe culvert, minimum road width taken is 7.50 m, Width of RCC culvert: 7.50 m with parapet .
10.4 Justification for retaining/widening and replacement of culverts
The existing structures which are in poor condition that are proposed for replacement and where ever required
provision of retaining wall has been made in the project.
10.5 Hydraulic calculation for Culvert
The design discharge is calculated by the rational method considering peak runoff from catchment derived from the relevant
Toposheets of the Survey of India.
Causeways and submersible bridges – Design to be done as per SP-20 and SP-82:2005.
Note: detailed designs sheets attached
Table 10.2 Proposed Culverts
SL.NO Chainage Type of Structures Span / Dia Remarks
1 6.450 H.P. Culvert 1x0.350
2 16.150 H.P. Culvert 1x0.600
3 16.200 H.P. Culvert 2x0.350
4 19.100 H.P. Culvert 2x1.000
5 20.500 H.P. Culvert 1x1.000
6 21.375 R.C.C. Slab Culvert 1x5.000
7 23.700 H.P. Culvert 1x0.600
11. PROTECTIVE WORKS & DRAINAGE
11.1 General
Where the project road runs through the hilly terrain and where it is required , the protective works such as Gabbian walls ,RR
stone masonery in 1:5 Retaining walls / Breast wall and Plum concrete blocks has been adopted at different locations..
11.2 Road side drain
As the insufficient drainage of surface water leads to rapid damage of road, road side drain as shown in drawing volume has
been provided particularly on the location of habitation areas. Sketch for a standard roadside drain is made available.
11.3 Protective Works
No protection works are proposed in the road.
Table 11.1 List of protective works
Retaining Wall / Breast Wall /Toe Wall
Sl.No Chainage Length Type of Protective
From To (m) LHS Works RHS
1 5.100 5.200 100.00 100 0
2 5.500 5.800 300.00 300 0
3 6.000 6.400 400.00 400 0
4 6.200 6.300 100.00 0 100
5 8.300 8.450 150.00 0 150
6 8.550 8.650 100.00 100 0
7 8.850 8.950 100.00 100 0
8 14.400 14.500 100.00 100 0
9 14.75 14.950 200.00 200 0
10 17.200 17.500 300.00 300 0
11 17.600 17.750 150.00 150 150
12 18.300 18.450 150.00 0 150
13 24.700 24.900 200.00 0 200
Total 1750.00 750.00
G. Total 2500.00
12. LAND ACQUISITION
12.1 General
The project road is an existing road with BT road surface. The existing Right of Way (ROW) is varying from6.00 m to 9.00 m.
12.2 Proposed ROW
The width of carriageway has been considered as 3.75 m in accordance with the IRC-SP 20: 2002. The total roadway width is
limited to 7.50 m with 1.875 m earthen shoulder on either side of carriage way. The proposed ROW varies from 6.0 m – 7.5 m.
12.3 Additional Land
Local administration and local Panchayat need to apprise the villagers about requirement of minor areas in places for
development of the road. Villagers are generally highly enthusiastic during site visits for selection of the road.
13. UTILITY SHIFTING/RELOCATION
13.1 Existing utilities
The electric poles are proposed to be shifted from the road. The same shall be shifted in coordination with the local electricity
corporation authorities.
Table 13.1 Estimated Costs for Relocation of Utilities
Estimated Estimate
Sl. No. Utility Type Quantity
Rate d Cost
1 -Nil-
14. ROAD SAFETY AND TRAFFIC MANAGEMENT
The DPR will be subjected to a road safety audit by an independent third party.
14.1Road Furniture
Road Furniture proposed are
Ø KM stones and 200m stones
Ø Guard posts, crash barriers and speed breakers
Ø Cautionary, mandatory and information signs
Ø Delineators and object markers
14.1.1 Road Markings
Road markings perform the important function of guiding and controlling traffic on a highway. The markings serve as
psychological barriers and signify the delineation of traffic paths and their lateral clearance from traffic hazards for safe
movement of traffic. Road markings are therefore essential to ensure smooth and orderly flow of traffic and to promote road
safety. The Code of Practice for Road Markings, IRC: 35-1997 has been used in the study as the design basis. Road markings
are proposed in the estimate.
14.1.2 Cautionary, Mandatory and Informatory Signs
Mandatory, Cautionary and informatory sign boards are proposed depending on the location with reference to the IRC: 67-
2001 guidelines for Road Signs.
14.1.3 Kilometer Stone and Hectometer Stone
The details of kilometer stones are in accordance with IRC: 8-1980 guidelines. Both ordinary and fifth kilometer stones are
provided as per the schedule. Kilometer stones are located on both the side of the road.
The details of 200m stones conform to IRC: 26-1967. 200m stones are located on the same side of the road as the kilometer
stones. The inscription on the stones shall be the numerals 2,4,6 and 8 marked in an ascending order in the direction of
increasing kilometer age away from the starting station. Table 14.1 indicates the details of Km. stone.5 th km. stone and
boundary pillars provided.
Table 14.1Details of Km. stone.5th km. stone and boundary pillars
5th. Km. 200m Gaurd
Km. stone
Chainage stone stone stone
Sl. Name of Road (nos.)
(nos.) (nos.) (nos.)
(km)
WINDHAMGANJ
At required
1 PIPARKHARR ROAD 6 19 102 -
Chainages
TO AURADAR.
14.1.4 Delineators and Object Markers
Roadway delineators are intended to mark the edges of the roadway to guide drivers on the alignment ahead. Object markers
are used to indicate hazards and obstructions within the vehicle flow path, for example, channelizing islands close to the
intersections. Delineators and object markers are provided in accordance with the provisions of IRC: 79-1981. They are driving
aids and should not be regarded as substitutes for warning signs, road markings or barriers. No delineators are proposed.
14.1.5 Guard Posts, Crash Barriers and Speed Breakers
Guard posts are proposed on embankments of height more than 1.5m and bridge approaches. The spacing of guard post shall be
10.0m c/c in these areas. Typical Guard post consists of pre-cast (M20) CC post of size 200mm x 200mm and a height of
600mm above ground level. They are encased in M15 cement concrete to a depth of 450mm below ground level. Guard posts
are painted with alternate black and white reflective paint of 150mm wide bands. Table 14.2 gives the details of guard posts,
crash barrier and speed breakers. No Guard Posts, Crash Barriers and Speed Breakers are proposed.
Table 14.2 Details of guard posts, crash barrier and speed breakers
Crash Speed
Name of Chainag Guard
Sl. Barrier breakers
Road e (km) post (nos.)
(m) (nos)
NIL
14.2 Temporary traffic control
The road under consideration has to be widened along with the bridges and culvert. The list below
provides the C/D structures to be widened/reconstructed and temporary traffic control measures to be
implemented. There are no temporary traffic control facilities are proposed.
Table 14.3 Details of temporary traffic control measures to be adopted

Name of Chainag Temporary traffic control


Sl.
Road e (km) measures to be adopted

NIL
14.3 Checklist for Road Safety Measures
The key road safety issue pertaining to the road are the location of the traffic sign location such as cautionary and the mandatory
signs near the Schools and the road junctions . the same is taken care while preparing the detailed estimates
Road Safety Checklist
1- Hazard markers are installed at all pipe culvert headwalls.
Hazard markers are installed at each end of all box culverts, river crossing causeways
2-
and similar CD structures.
3- Hazard markers are installed at any discontinuity in the shoulder.
4- Directional sight boards are installed on all sharp curves and bends.
Speed breakers are provided at sharp curves and bends where the curve design speed
5- is less than 40 km/h in plain and rolling terrain, and less than 25 km/h in mountainous
and steep terrain.
Speed breakers are needed and directional sight boards installed at sites where
6-
reverse horizontal curves are closely spaced and speed reduction is required.
At a main road intersection, signs and pavement markings for STOP control on the
7- PMGSY village road are installed, side road warning signs on the main road and
intersection warning signs on the village road are to be installed.
This DPR will be subjected to a road safety audit by an independent third party.
15. SPECIFICATION
15.1 General
The “Specification for Rural Roads” published by IRC by the Ministry of Rural Development, Govt. of India has been
followed.
15.2 Construction Equipment
Construction by manual means and simple tools has been considered for the project as per the guideline of NRRDA. For
handling of bulk materials like spreading of aggregates in sub-base & base courses by mix-in-place method, use of motor grader
& tractor-towed rotavator has been allowed in line with the schedule of rate for PMGSY work. Compaction of all items shall be
done by ordinary smooth wheeled roller if the thickness of the compacted layer does not exceed 100 mm. It is also considered
that, hot mix plant of medium type & capacity with separate dryer arrangement for aggregate shall be used for bituminous
surfacing work that can be easily shifted. A self-propelled or towed bitumen pressure sprayer shall be used for spraying the
materials in
For structural works, concrete shall be mixed in a mechanical mixer fitted with water measuring device. The excavation shall be
done manually or mechanically using suitable medium size excavators.
15.3 Construction Methods
15.3.1 Preparation for Earthwork
After setting out existing ground shall be scarified to a minimum depth of 150 mm and leveled manually and compacted with
ordinary roller to receive the first layer of earthwork. In filling area, existing embankment will be generally widened on both
sides as per the alignment plan. Continuous horizontal bench, each at least 300 mm wide, shall be cut on the existing slopes for
bonding with the fresh embankment/ subgrade material as per Clause 301.7.
15.3.2 Embankment work
Material from borrow pits will be used for embankment construction as well as the approved material deposited at site from
roadway cutting and excavation of drain & foundation may be used. Layer of the earth shall be laid in not more than 25 cm
(loose) thick layers & compacted each layer of the soil up to 30 cm below the subgrade level at OMC to meet 97% of Standard
Proctor Density.
Material for embankment and sub-grade shall satisfy the requirements of Table 300-1 and 300-2 as per the Specification for
Rural Roads.
15.3.3 Sub-grade
Material from borrow pits will be used for construction of top 30 cm as sub-grade. Soil in these sections is quite good for road
construction. Top 30 cm upto the subgrade level and shoulder at OMC to meet 100 % of Standard Proctor Density by proper
control of moisture and by required compaction with a smooth wheeled roller
15.3.4 Sub-base
Sub base material in the form of stone aggregates and sand as available in the area to be used in GSB Grade III layer.
15.3.5 Base
Stone aggregates will be used in base course. 63 mm to 45 mm size (Grading 2) aggregate as been proposed for the bottom layer
and 53 mm to 22.4 mm (Grading 3) size has been proposed for the top layer
15.3.6 Shoulder
Earthen shoulder shall be constructed in layers and compacted to 100% of Proctor’s Density. First layer of shoulder shall be laid
after the sub–base layer is laid. Thereafter earth layer shall be laid with base layer of pavement and compacted
15.3.7 Surfacing
Slow setting bitumen emulsion will be applied as primer on water bound layer. Emulsion shall be sprayed on surface with
pressure distributor. Rapid setting bituminous emulsion shall be used for Tack coat.
Premixed carpet and mixed with equivalent viscosity grade bitumen shall be laid as surfacing course. 6 mm thick Type B seal
coat is considered for sealing of the premixed carpet.
15.3.8 Structural Works
Following grades of concrete are proposed for Structural works and comply with MORD and IRC specifications:
Concrete in superstructure of slab culvert – M20, M25 (RCC)
Concrete in abutment cap, dirt wall of slab culverts – M-15} (RCC)
Brickwork in abutment, return wall, headwall – M-15 (RCC)
Concrete below abutment, return wall, headwall – M10 (PCC)
16.ENVIRONMENTAL ISSUES
16.1 Alignment
The proposed road is planned to be designed considering the impact on environment. Proposed road alignment follows existing
path to the maximum extent so that land acquisition is not necessary for construction of the project road. Proposed road, when
completed, will be an addition to the aesthetics of this rural area.
16.2 Environmental Sensitive Area
There are no environmental sensitive area in the alignment
16.3 Construction Camp
Construction camps will be established away from forest area/water body. The minimum facilities such as water supply,
sanitation, storm water drainage, solid waste management and first aid box are be provided during the construction period of the
project.
16.4 Permit / Clearance required
No objection Certificate will have to be taken by PIU from concerned authorities required as per the statutory obligations.
16.5 Borrow area
The filling soil will have to be procured from borrow pit. Borrow area will have be so excavated that the lands can reused as
agricultural field. As far as possible the borrow pits shall not be dug close to the road embankment.
16.6 Erosion Control
Turfing of the embankment slopes and earthen shoulder to prevent erosion of slopes of the embankment, rain cuts and erosion
of shoulder is suggested.
16.7 Drainage
Required cross drainage structures have been provided on the basis of hydrological survey of the area. Road side drainage is
also duly considered in a manner so that surface water is led to the low points and is drained through the CD structures.
16.8 Use of Material
Cut back bitumen is not proposed in the project to avoid contamination with Kerosene. Bitumen emulsion is proposed for
primer coat and tack coat.
17 Analysis of Rates
17.1 General
Rates for various item of works of the project have been derived from the “Schedule of Rates issued by SE PWD of the District
for Road works, Culvert works & Carriage etc. and “Addendum & Corrigendum to Schedule of Rates”, if any. However in
general the basic rates of material have been taken from above SOR. The rates of different items have been worked out as per
Data Book issued by MoRD, Govt of India, inclusive of all labour charges, hire charges of Tools & Plants, Machineries and all
other cost estimates for the item of work, overhead and contractor’s profit @ 10% and 1% LabourCess on Complete rates..
17.2 Basic Rate of Material

The basic rates for stone materials & river bed materials have been taken from SOR issued by SE PWD of concerning Circle.
Copy of rates are attached with the Schedule of Rate.
For bituminous materials, basic rate at Mathura for equivalent viscosity grade bitumen and for emulsion the basic rate at Panipat
has been considered as issued by IOC have been considered
Basic rate of other materials like coarse & fine sand, cement are as per the latest from SE,PWD of the Circle.
Basic rate of steel materials at sub-divisional office has been considered in analysis after adding cost of carriage, loading &
unloading.
17.3 Lead for Materials

For stone aggregates and sand, lead from source to work site is calculated as per shortest route. The supply of different materials
to worksite is by road. Lead for bituminous & steel materials are similarly obtained using SOR.
Cost Estimate
18.1 General
Cost Estimate of project has been arrived based on the following basis
• Selection of Items of work

• Estimation of item wise quantities

• Analysis of Rates
18.2 Estimation of Quantities
All the relevant road and structure work Items will be identified as per survey, design and drawings. Following major item of
works considered are given below:

• Site clearance, dismantling and earthwork

• Pavement works (GSB, WBM, Bituminous layers)

• Cross drainage structure works

• Drainage and protective works

• Utility relocation

• Road safety and furniture

• Maintenance works

• Other essential works

Quantity of earthwork has been derived from the proposed cross section drawings. Volume of cut and fill has been obtained
directly using the design package software. Quantity derived from software will be manually verified. All other quantities has
been computed from the drawings of finished road, miscellaneous drawings & drawings of CD Structures. Earth work
calculation sheet has been attached with the DPR.
18.3 Abstract of Cost
Unit rates has been derived by using the “Standard Data Book issued by MoRD, Govt of India”. The abstract of Cost estimate is
given in the Proforma A and B attached in the DPR the copy of which is being attached on separate sheet.
18.4 Maintenance
Cost of Annual Maintenance for five years after completion of project has been estimated as per the PMGSY Guidelines.
Different activities of ordinary repairs are done as and when.
The abstract of Cost estimate of maintenance is also given in the Proforma A attached in the DPR the copy of which is being
attached above
19.CONSTRUCTION PROGRAM

19.1 General
It is proposed that the Construction of the road work will start 100 days of formal sanction by govt of india. However, the
construction program is based for a total working period of 12 months, it is anticipated that some activity like collection of
materials, CD works etc. will continue in monsoon period also.
19.2 Realistic duration
The work duration is 12 Months including Monsoon.
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR RENEWAL
F-6
PACKAGE NO :- UP67146
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
ROAD LENGTH :- 25.300 K.M.
Sl Description of Item No. L B D/H Quantity Unit Rate Amount
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
1 Providing and applying tack coat with 0.00
Bitumen emulsion (RS-1) mixed with organo
silane nano technology and water in the ratio
of 1.4:100:200 (Organo silane nano-
technology : Emulsion RS1 : Water) using
emulsion distributor at the rate of 0.30 kg per
sqm on the prepared granular/bituminous
surfaces treated with primer & cleaned with
Hydraulic broom as per Technical
Specification Clause 503.

Renewal 1 x 1 25300 3.750 94875.000 sqm


In widening of T-junctions starting 1 x 39 60 0.000 0.000 sqm
In widening of curves 1 x 1 1858 Sqm 1858.280 sqm
For Patch Repair before Renewal 1 x 10% 9673.328 sqm
Deduct culverts portion and causeway ### x 1 261.000 3.750 -978.750 sqm
,minor bridge
Total 105427.858 sqm 17.33 1827275.63
2 Providing, laying and rolling of open-graded 0.00
premix carpet of 20 mm thickness composed
of 13.2 mm to 5.6 mm aggregates either
using penetration grade bitumen or emulsion
Mixed with Nano Technology Based Organo
Silane Compound @ 0.1% by the weight of
bitumen for enhansed performance and
durability to required line, grade and level to
serve as wearing course on a previously
prepared base, including mixing in a suitable
plant, laying and rolling with a three wheel
80-100 kN static roller capacity, finished to
required level and grades to be followed by
seal coat of either Type A or Type B or Type
C as per Technical Specification Clause 508.

Renewal 1 x 1 25300 3.75 94875.00 sqm


In widening of T-junctions starting 1 x 39 60.00 0.00 0.00 sqm
In widening of curves 1 x 1 1858.28 Sqm 1858.28 sqm
For Patch Repair before Renewal 1 x 10% 9673.328 sqm
Deduct culverts portion and causeway ### x 1 261.000 3.750 -978.750 sqm
,minor bridge
Total 105427.858 sqm 192.15 20257962.91
3 Providing and laying seal coat with nano 0.00
technology based organo silane @ 0.1% by
the weight of bitumen, sealing the voids in a
bituminous surface laid to the specified
levels, grade and cross fall using Type B as
per Technical Specification Clause 510

Renewal 1 x 1 25300.000 3.750 94875.000 sqm


In widening of T-junctions starting 1 x 39 60.000 0.000 0.000 sqm
In widening of curves 1 x 1 1858.280 Sqm 1858.280 sqm
For Patch Repair before Renewal 1 x 10% 9673.328 sqm
Deduct culverts portion and causeway ### x 1 261.000 3.750 -978.750 sqm
,minor bridge
Total 105427.858 sqm 58.83 6202110.03
Grand Total 282.87
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS MAINTENANCE WORKS
PACKAGE NO. :- UP67146

NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.


ROAD LENGTH :- 25.300 KM
SCHEDULE OF WORKS
Rate in GROSS AMOUNT
Sl. Description of No.or AMOUNT
Unit
No. work Qty. Rs Rs. P
Rs. P
MAINTENANC
E

1st Year 25.300 Km 54507.00 1379027.10 1379027.10


2nd year 25.300 Km 85609.00 2165907.70 2165907.70
3rd year 25.300 Km 116746.00 2953673.80 2953673.80
4th year 25.300 Km 147937.00 3742806.10 3742806.10
5th year 25.300 Km 179021.00 4529231.30 4529231.30
14770646.00
Grand Total 14770646.00
Say Rs 147.71
Lacs
RCPLWEA (ADDITIONAL)
PROFARMA A

RCPLWEA (ADDITIONAL)
PROPOSALS

SL NO DISTRICTPACKAGE NO NO OF LENGTH VALUE(LACS) AV. COST/Km (Lacs)


HABITATI (Km) Construction Maint. Construction Maint.
ONS
COVERED

UP67146
SONEBHADRA

10 25.300 #VALUE! 147.71 #VALUE! 5.84


1
WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
RCPLWEA (ADDITIONAL)
PROFORMA-B
UP67146 PACKAGE SUMMARY
PACKAGE NO: State :-Uttar Pradesh DISTRICT:- SONEBHADRA

Sl. Name of Block Name Of Road Type Of Proposed Cost Of No of CD Cost of CD Total Estimated Cost Average Cost per Km
No Proposal length Pavement work work (Rs.) Lacs (Rs.) Lacs
Constructio Maintenance Constructio Maint
n Renewal General n General
Cost

From To N/U Km Rs in Lacs Nos Rs in Lacs Rs in Lacs Rs in Lacs


1 2 3 4 5 6 7 8 9 10 11 12 13 14
WINDHAMGA
CHOPAN / NJ
1
DUDDHI PIPARKHARR AURADAR. U 25.300 1282.09 10 #VALUE! #VALUE! 0.00 147.71 #VALUE! 5.84
ROAD

Total Estimated without GST (in Lacs) 25.300 1282.09 10 #VALUE! #VALUE! 0.00 147.71 #VALUE! 5.84

DPR Cost without GST (in Lacs) 2.53 0.10

Add 12% GST #VALUE! 0.00 #VALUE!

Total Cost with GST (In Lacs) Say #VALUE! 0.00 147.71 #VALUE! 5.84
RCPLWEA (ADDITIONAL)
PROFORMA-B
UP67146 PACKAGE SUMMARY
PACKAGE NO: State :-Uttar Pradesh DISTRICT:- SONEBHADRA

Sl. Name of Block Name Of Road Type Of Proposed Cost Of No of CD Cost of Cost of Cost of Total Estimated Cost Average Cost per Km
No Proposal length Pavement work CD work Protection CD+ (Rs.) Lacs (Rs.) Lacs
work Protection
Constructio Maintenance Construction Cost Maint
work
n Renewal General Without CD With CD & General
Cost & Protection
Protection work
work

Rs in Rs in
From To N/U Km Rs in Lacs Nos Rs in Lacs Rs in Lacs Rs in Lacs
Lacs Lacs

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
WINDHAMGA
CHOPAN / NJ
1
DUDDHI PIPARKHARR AURADAR. U 25.300 #VALUE! 10 #VALUE! 148.47 #VALUE! #VALUE! 0.00 147.71 #VALUE! #VALUE! 5.84
ROAD

Total Estimated without GST (in Lacs) 25.300 #VALUE! 10 ### 148.47 #VALUE! #VALUE! 0.00 147.71 #VALUE! #VALUE! 5.84

Add 12% GST #VALUE! 0.00 #VALUE! #VALUE!

Add 1% Labour Cess - #VALUE! 0.00 #VALUE! #VALUE!

Total Cost with GST (In Lacs) Say #VALUE! 0.00 147.71 #VALUE! #VALUE! 5.84

Prepared By: Technical Scrutiny Done By:


Signature Signature
Name: Name:

Checked By: Co-Ordinator STA


Signature Signature
Name: Name:

Scrutinized By:
Signature
Name:
Proforma C
RCPLWEA (ADDITIONAL)
CHECK LIST FOR P.I.U. & S.T.A.
( For Indvidual Road Works )
To be filled by PIU.
1. LocationState:
:- UTTAR District : SONEBHADRA Block CHOPAN / DUDDHI
PRADESH

2. Package No:- UP67146


3. Name of the Road: WINDHAMGANJ PIPARKHARR ROAD To AURADAR.
4. Total Length (Km) - 25.300 In Built up area - 11.615 Km In Open Area - 13.685 Km
5. Catigory of upgradation proposal A B C

If it is category 'C' road than indiacte


Year of sanction under PMGSY -NA- Year of completion -NA- Design Traffic ( -NA-
Whether road deteriorated due non maintenance Yes NO

6. Estimated Cost Rs :
Cost sharing pattern for this road Normal Area
Item Total Cost Average Cost
in Rs. per Km.
Flexible Pavement including side drain, road (lacs) (Lacs)
1109.22 43.84
furniture & cost of DPR
Rigid Pavement 0.00 0.00
Others ( CD Works & Protective works) #VALUE! #VALUE!

Cost due to higher specification such as carriage 0.00 -


way width, Higher Axle load , Hard shoulders,
Shifting of Utilities

Total Project Cost #VALUE! #VALUE!

MoRD Share,60% #VALUE!


State Share,40% #VALUE!
7. Is the road a part of DRRP
a) If Yes , Through Route/ MRL No. 0 or MRL-
b) Names of benefitted Growth points Name of Population Overall
Habitation Weightage
KUDWA VILLAGE 806
KUDWA YADAV
BASTI
KUDWA TUNIYA 1258
BASTI
PANDU CHATAW 687
VILLAGE
GHICHORWA 180
VILLAGE
KARIYA VILLAGE 511
NIMYA SUKAR 109
GULARIYA 192
AURADANDI 687
VILLAGE
Total
c) Utility value = Total weight/ Length of road
d) Does the Proposed Road lead up to the growth Yes No
centre /hub or the road is being made partially?
e)Whether the proposed road leads to MDR SH NH
f) Average PCI of the road to which proposed TR or MRL will be connected 5
g) Average PCI value of proposed road 2
h) If PCI of MDR / SH / NH is 3 or below , whether the Yes No
State's undertaking for simultaneouly upgrading it from State
fund is avaible -NA-

i) Age of the proposed road 10 years


j) Cummalative maintenance expenditure in last three years( in lacs)
8. a) Whether the Proposed Road has the carriage way Roadway Road land width
desired carriage way width,Roadway width and width
Road Land Width (RLW ) yes No Yes No yes No
b Indicate the actual widths of the following for the In the builtup open Area
proposed road. area
a Carriageway 3.75 3.75
b Roadway 7.5 7.5
c Road Land Width 7--8 09--12

( Plane Table sheet attached separately)


WINDHAMGANJ PIPARKHARR ROAD

Index Map WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.


25.3 Km.

0 1 2 3 4 5 6 7 8 9 10

AURADAR.
CD_EX CD_PR HABS

Name of Road : WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.


Cross Section details
a) Cross Section of The Existing road showing different component layers.

Approx 6.0 m
3.00 m
Items Thickness
Existing Shoulder PC 20 mm
G3 -
G2 -
G1/GSB 175 mm

Ex. Crust 175 mm in 3.00 Total 175 mm


m. Width

Approx 7.50 m
3.75 m
Items Thickness
Existing Shoulder PC 20 mm
G3 - 75 mm
G2 - 75 mm
G1/GSB 125 mm

Ex. Crust 275 mm in 3.75 Total 275 mm


m. Width

Passenger Car unit (PCU) 158


Traffic Details as per IRC:SP: 72:2015
ADT in the year of Traffic Count = 181 Base Year Traffic AADT (T) = 181
Growth rate adopted (%) = 0.06
Design Life = Year 10
Number of Harvesting Seasons = 2
No. of Days in Each Harvesting Season(t) 75 Cumulative ESAL = 78333
Value of n assumed 2 Traffic Category = T3
b Traffic Details in case degisn is done as per IRC 37-2001 /IRC 37 :2012
A= Intitial traffic in the year of completion of construction in terms of 181
the number of commericial vehicles per day
D= Lane distribution factor 0.75
F= Vehicle damage factor 2.5
n= Design life in years 10
r= growth rate adopted % 6
N= The cumulative number of standard axles to be catered for -
the design in terms of msa
CVPD 16
11. Subgrade CBR ( for Different Sections ) =
Chainage 4.950 9.850 14.50 19.125
Design 3.15 3.24 3.64 3.44
CBR %
12. Cost Details of upgradation proposal
A. Pavement Components
Description of layer Thickness in mm Quantity Rate Rs Cost Rs. Cost/ km (Rs)

Clearing & Grubbing 104256.00 4.22 439960.00 17389.72


Level Pillars 1011.00 343.90 347683.00 13742.41
Scrapping of BT 51717.75 18.51 957296.00 37837.79
Constrction of Embankment (Local) 23746.09 86.50 2054037.00 81187.23
Constrction of Embankment (Carted) 13474.70 165.82 2234376.00 88315.26
Hard Rock 18000.00 457.25 8230500.00 325316.21
Excavation for Roadway 8124.12 36.72 298318.00 11791.23
Construction of embankment with approved 8124.12 55.62 451863.00 17860.20
materials deposited
Sub-grade & Shoulder (Local) 7479.04 86.50 646937.00 25570.63
Sub-grade & Shoulder (Carted) 6359.21 165.82 1054484.00 41679.21
Granular Sub base 0.175 6951.97 3036.76 21111464.00 834445.22
WBM Gr -II 0.075 6984.64 3089.70 21580442.00 852981.90
WBM Gr -III 0.075 7469.06 3206.42 23948943.00 946598.54
Prime Coat 97768.76 35.67 3487412.00 137842.37
Tack Coat 97768.76 12.38 1210377.00 47840.99
OGPC 20 97768.76 137.25 13418762.00 530385.85
Seal Coat 97768.76 42.02 4108243.00 162381.15
Brick Edging 24.98 75000.00 1873500.00 74051.38
Gule 3 54799.99 164400.00 6498.02
Total cost of Flexible pavement 1076.19 Lacs 107618997.00
B: C D Works
Sl Similar Type of CD's may be grouped Type of CD & their Nos Total Length of Cost in Rs.( in lacs) Remrks
no together Culvert

1 Repair of culverts old H.P. CULVERT 1 1.33 Repair


2 Causeway RCC 249 23.06 Repair
Total cost of CD Repair & Widening of Existing Culverts 24.40

1 Ch. 16.15 & 23.70 H.P. CULVERT 2 1X600 MM #VALUE! New


2 Ch. 19.10 & 20.50 H.P. CULVERT 3 1X1000 MM 3.94 New
3 Ch. 21.375 RCC 1 5.00 M SPAN 26.68 New
4 17.125 RCC 0 40.1 m Box Culvert 0.00 New
Total cost of New/Re Construction Culverts and Causeways) #VALUE!
Total Cost of CD works in lacs (including Proposed repair of Existing Culverts / causeways) #VALUE!
C. Protection works Chainage
Fro To Length( m) Cost in Rs (Lacs) Average
m cost /Km
Parapet wall (Nos) 36 1.00 0.03
Toe wall
6.00 6.40 400.00 16.02 0.63
Retaining wall
5.10 5.20 100.00
5.50 5.80 300.00
6.20 6.30 100.00
8.30 8.45 150.00
8.55 8.65 100.00
8.85 8.95 100.00
14.40 14.50 100.00
17.20 17.75 300.00
17.60 17.75 300.00
18.30 18.45 150.00
24.70 24.90 200.00
Total 1900.00 91.46 3.62
Breast wall
14.75 14.95 200.00 21.82 0.86
Boulder apron laid in wire crates -
Cement Plum Concrete (Nos) 90 18.17 0.72
Pitching / turfing for slopes - 0.00
Total cost of protection works 148.47
D. Pucca Side Drains (if Provided) Chainage Length Cost in Rs (lacs) Average cost /
Fro To ( m) m
KC Drain m
KUDWA VILLAGE 0.00 0.10 100
KUDWA YADAV BASTI 2.00 2.16 160
KUDWA TUNIYA BASTI 3.50 3.70 200
PANDU CHATAW VILLAGE 6.60 6.74 140
KARIYA VILLAGE 16.30 16.40 100
Total 700
U Type Drain
KUDWA VILLAGE 0.30 0.40 55
KUDWA YADAV BASTI 2.50 2.60 100
KUDWA TUNIYA BASTI 3.60 3.70 70
Total 225 29.63 131.68
Grand Total 925
Total cost of side drains works 29.63 131.68
E. Road Logo, other Road Furniture including Road safety signs
Number Cost in Rs Average cost /
km
Total cost of road furniture 3.41 0.13
F. Cost of preparation of DPR 0 0
H. Electric Pole & Utility Shiffting
Total Cost of the Project (Excluding GST) #VALUE! Lacs
12% GST #VALUE! Lacs
Total Cost of the Project (Including GST & Labour Cess) #VALUE! Lacs
13. Five Year Routine Maintenance
To be estimated as per provision of Year Cost in lakhs % Cost Cost (Lacs)/km
Operation Manual I 13.79 #VALUE! 0.55
II 21.66 #VALUE! 0.86
III 29.54 #VALUE! 1.17
IV 37.43 #VALUE! 1.48
V 45.29 #VALUE! 1.79
Total Maintenance Cost 147.71
14. Renewal Coat after Five Years (after GOUP Policy Decision)

Total Renewal Cost 0.00 #VALUE! 0.00

Yes NO

14. Whether the road has Geometrics as per Rural Roads Manual RRM / Latest Circulars of
NRRDA.
Yes No
15.Whether C.D.works / Protection works are provided as per RRM / Latest Circulars of
NRRDA/ Respective Codes of IRC.
16.Does the Estimation Conform to Standard Rate Analysis and SSR generated Vetted at Year
for the current Phase NRRDA
Yes No
17. Sources and the Lead distances of Materials are as under
Material Source Lead Material Source Lead
Distance
(Km) Distance
Earth local 0 Cement Nearest Market
Grit DALA 64 Emulsion Jhansi 1352
Aggregate SUKRUT 122 Bitumen Panipat 1522
Sand CHOPAN 72 Steel Nearest Market
To be filled by State Technical Agency
Name of the STA:

Name of WINDHAMGANJ PIPARKHARR ROAD TO AURADAR. Yes / NO to be filled by STA in


Road : own handwriting
18 Is the Proposed Road entered on the OMMS under PMGSY II :

(Data entries to be verified by STA before Clicking the Propopsal)


19 Have you satisfied yourself that the proposed road is a part of DRRP

20 Are you satisfied with the following


Engineering Surveys (L section, X section on A3 size paper must be verified)
Soil/ Material ( CBR, Density, LL, PI, Gradation to be verified)
Investigation
Whether Traffic Surveys / count has been done by third party
Hydraulic Studi
( Catchment for structures with more than 2 Vents to be verified from topo sheet.
Location and requirement of all CD structures to be verified from L section )

21 In case , Traffic is projected beyond T 9 Category and road designed using


-NA-
IRC 37 are you satisfied with the reason given by PIU

22 In case, sub grade CBR is less than 5; has Soil Stabilisation etc. been
-NA-
proposed
( If not , specific Reasons given by PIU)

23 Is the design of the following elements as per Rural Roads Manul /


Circulars of NRRDA:
Alignment & Geometrics
Location and type of CD works and Side drains
Integration for Cross and longitudinal Drainage
Protection Works
24 Is the design of flexible Pavement as per IRC SP: 72- 2015 and design of Rigid
Pavement as per IRC SP:62- 2004 .
Is the design of flexible Pavement as per IRC 37 2001 and design of Rigid -NA-
Pavement as per IRC SP:58- 1998.

25 Does the proposal have provisions for


PMGSY Logo Sign Boards and Information Board
Km/Hm Stones
Guard Stones (where necessary )
Traffic Sign Boards (as necessary)

26 Secific Remarks, if any, by STA


( Specific remarks of STA about the overall project are necessary on each
DPR)

Certified that the Design and Estimation for the Proposed Road work are based on the data
and SSR provided by PIU Engineers . The Proposal after final Correction is entered on the
OMMS.The Propasal may be considered for clearance.

Technical Scrutiny at STA


done by:
Signature Co-ordinator STA:
Name Signature
Date Name

Date
Package No. UP 67146

Component wise cost of roads Proposed

Sl. Status District Block Package No. Carriage Carriagewa N/U Name of road Length in Km
No. way width y width in CC BT Total
in m m
(Existing) (Proposed)

1 2 3 4 5 6 7 8 10 11 12 13

WINDHAMGANJ
RCPLWEA CHOPAN UP67146 3.75/ PIPARKHARR
1 Sonebhadra 5.50 U 0 25.300 25.300
(Additional) / DUDDHI 3.00 ROAD TO
AURADAR.
Cost of Pavement (Rs in Lacs)
Earth work Sub Base Base Surfacing CC Pavement Total Cost Cost per KM
Prior After Prior After Prior After Prior After Prior After Prior After Prior After
Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutin Scrutiny Scrutiny Scrutiny Scrutiny
y

14 15 16 17 18 19 20 21 22 23 24 25 26 27

165.84 167.15 212.65 211.11 452.19 455.29 220.87 222.25 0.00 0.00 1051.55 1055.81 41.56 41.73
Pacca Drain Hume Pipe Slab Culvert Minor Bridges
Prior Scrutiny After Scrutiny Prior Scrutiny After Scrutiny Prior After Scrutiny Prior Scrutiny After Scrutiny
Length in Cost Length in Cost Nos Cost Nos Cost Scrutiny
Nos Cost Nos Cost Span Cost Span in M Cost
M M in M

28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43

1600.00 54.27 225 29.63 8.00 9.22 5.00 #VALUE! 1.00 25.96 1.00 26.68 40.10 241.95 40.10 0.00
Protection work Road Furnitures Others Total Total cost per Km Extra state share cost
Prior Scrutiny After Scrutiny Prior After Prior After Prior After Prior After Prior After
Length in M Cost Length in M Cost Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny

44 45 46 47 48 49 50 51 52 53 54 55 56 57

3367.00 284.68 306.00 148.47 6.29 3.41 74.99 44.77 1748.93 #VALUE! 69.13 #VALUE! 0.00 0.00
Total Total cost per Km 5 years Maintenance Surface Renewal Traffic CBR Remarks
Prior After Prior After Prior After Prior Cost After Category
Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny Scrutiny (MSA)

58 59 60 61 62 63 64 65 66 67 68

1748.93 #VALUE! 69.13 #VALUE! 147.71 147.71 301.54 335.83 5.00 3.24
ANNEXURE-7.1
FORMAT F-1
(See Para 7.2)
RCPLWEA (ADDITIONAL)
SUMMARY SHEET
Name of the Code Total No. of Unconnected Habitations
Block Habitations 1000 500-999 250-499 250 Total
Eligible
Habitations

UP67146 Total Eligble


CHOPAN / DUDDHI 4238.00 0 0

Total 4238 0 0 0 0

Total of No. of Total Length No. of Estimated Cost (Rs. Lakhs) No. of Unconnected
Proposal Roads of New CD Pavement CD Total Habitations Connected/
Roads (km) Structures from Structur {(5)+(6)} Connected Habitations
Format-F5 e benefited
from
Format
-F-6

1 2 3 4 5 6 7 8
New
Connectivity
Associated
Through Route
Upgradation 01 25.300 9 1282.09 ### #VALUE! 10
FORMAT F-2A
RCPLWEA (ADDITIONAL)
ROADS PROPOSED IN PMGSY FOR RURAL CONNECTIVITY(PAVEMENTS LAYERS) UP67146
DISTRICT:- SONEBHADRA BLOCK :- CHOPAN / DUDDHI PACKAGE NO. :-

Details of Thickness & cost for Pavement Layers

Exi
New construction (N0 Roa
Associated Through stin
d Cleari K.C Widenin
Route (A) upgradation Facility g Earth- Sub- Prime Road Total cost
Len ng Subg Drain Leve Protect g and CC

Details
(U) accasse Surf Earth- work in Base WBM WBM B.O.E Cd r& Seal Furniture/ for
gth Grubb rade / l ion repair of RO P.C
d ace work Should GSB G2 G3 EDGING Work Tack Coat DPR Pavement
typ ing/scr U- piller work existing AD
(km) er QR.-II Coat Prepration Rs. Lakhs
e afying Drain CD

N A U

5 5A 5B 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Thik
………
- - U A 0 B.T. ness
……
0.6 0.15 0 0.175 0.075 0.075 0.08 0.02
(m)

cost 17.45 132.691 17.0142 - 211.11 215.8 239.49 18.74 29.63 148.47 ### 26.0394 0 46.98 134.19 41.08 3.41 #VALUE!

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
FORMAT F-2B
RCPLWEA (ADDITIONAL)
ROADS PROPOSED IN PMGSY FOR RURAL CONNECTIVITY (CROSS DRAINAGE STRUCTURES)
UP67146
DISTRICT:- SONEBHADRA PACKAGE NO. :-

S. Name Block Name of Habitations Papulation Road Existing CD Structure by type Cost Of Details of Proposed CD Structure by type
No. of Code Road connected/ Length Repair
Block Benifited (Km) Hume Box / Minor in Hume Box/ Length Minor Length Total Cost Total Cost Total Cost
pipe Culvert Arch Bridge pipe Culvert Arch Bridge of of of
culvert /RCC culvert/RC Proposed Pavement Road
slab C culvert CD from Format {(18+19)}
Structures F-5

No. Dia(mm) No. Length No. Length Lacs No. Dia No. m No. m Lacs Lacs
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
WINDHAMGAN
- UP67146 J PIPARKHARR
1
ROAD TO
10 4238 25.3 6 1X350 MM 3 1x1.50 M 3 1X350 MM 1 1x5.00m 0 0
AURADAR.
24.40 #VALUE! 1282.09 #VALUE!
2 1X600 MM 5 1X2.50 M 2 1X600 MM 1x40.10m 1 40.1
10 1X1000 MM 3 1X1000 MM
1 1X1200 MM

Total 19 8 8 1 1 40.10 #VALUE! 1282.09 #VALUE!


RCPLWEA (ADDITIONAL)
FORMAT F- 4
DETAILS OF EXISTING ROADS FOR UPGRADATION
PACKAGE NO. :- UP67146

BLOCK :- CHOPAN / DUDDHI

Name of Road Road Road connecting Facilities Traffic per day Existing road details
Length to accessed Total Total Truck/ Land width Road width Embankment WBM Width Bituminous Layer
Sl No.

(in km) ( Use Motorised tractor/Bus (m) (m) Height (m) Width (m) Width (m) Thickness Type Width (m) Thickness
A/B/C/D) (m) (mm)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

WINDHAMGA
NJ
1 PIPARKHARR 25.300 A A 18 16 12.00 9.00 0.60 6.00 3.0/3.75 0.175 PC/SC 3.0/3.75 20
ROAD TO
AURADAR.
Cost Estimate
Package Number UP67146 F-5
Block CHOPAN / DUDDHI
District SONEBHADRA
State UTTAR PRADESH

Cost of
Type of Proposed Cost of No. of CD
Name of the Road CD Total estimated cost Average cost per km
Proposal length Pavement works
works
S.No. Name of Block
Rs. Rs.
From To N/U Km Rs. Nos Rs.
const. Maint. const. Maint.
1 - U A U 25.3 1282.0852 10 #VALUE! ### 147.71 #VALUE! 5.84
RMR
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
PACKAGE NO. UP-67146
DISTRICT:- SONEBHADRA
Sl. Name of Basic Rate Loading and Royalty Quarry Rate Distance in Km. Total Distance Total Cost Total Total Total
No. Quarry / at Quarry unloading (Exclusive for cortage of Cartage 6+11 Round To
Crusher of charges Loading and (Km) 10 Paise
loading unloading.) (excluding
Station CP)
Kachcha Pakka Kachcha
1 2 3 4 5 6 7 8 9 10 11 12 13 14
45-63mm gauge stone ballast
1 Sukrut 520.00 35.00 110.00 375.00 1 122 0 123 1139.18 1514.18 1514.20 1514.20
22.4-53 mm gauge stone ballast
2 Sukrut 740.00 35.00 110.00 595.00 1 122 0 123 1139.18 1734.18 1734.20 1734.20
53-9.5 mm for GSB -Gr-I
3 Sukrut 820.00 35.00 110.00 675.00 1 122 0 123 1139.18 1814.18 1814.20 1814.20
9.5-2.36 mm for GSB -Gr-I
4 Sukrut 585.00 35.00 110.00 440.00 1 122 0 123 1139.18 1579.18 1579.20 1579.20
2.36 mm & below for GSB -Gr-I
5 Sukrut 495.00 35.00 110.00 350.00 1 122 0 123 1139.18 1489.18 1489.20 1489.20
Stone Dust
6 Sukrut 505.00 35.00 100.00 370.00 1 122 0 123 1139.18 1509.18 1509.20 1509.20
Boulder
7 Sukrut 485.00 35.00 110.00 340.00 1 122 0 123 1139.18 1479.18 1479.20 1479.20
40mm gauge stone ballast
8 Sukrut 830.00 35.00 110.00 685.00 1 122 0 123 1139.18 1824.18 1824.20 1824.20
Stone for random rubble masonry
9 Sukrut 485.00 35.00 110.00 340.00 1 122 0 123 1139.18 1479.18 1479.20 1479.20
loose Stone for back filling
10 Sukrut 435.00 35.00 110.00 290.00 1 122 0 123 1139.18 1429.18 1429.20 1429.20
19 mm gauge stone grit
11 Dalla 1450.00 35.00 160.00 1255.00 1 64 0 65 717.36 1972.36 1972.40 1972.40
13.2 mm gauge stone grit
Sl. Name of Basic Rate Loading and Royalty Quarry Rate Distance in Km. Total Distance Total Cost Total Total Total
No. Quarry / at Quarry unloading (Exclusive for cortage of Cartage 6+11 Round To
Crusher of charges Loading and (Km) 10 Paise
loading unloading.) (excluding
Station CP)
Kachcha Pakka Kachcha
1 2 3 4 5 6 7 8 9 10 11 12 13 14
12 Dalla 1150.00 35.00 160.00 955.00 1 64 0 65 717.36 1672.36 1672.40 1672.40
11.2 mm gauge stone grit
13 Dalla 1080.00 35.00 160.00 885.00 1 64 0 65 717.36 1602.36 1602.40 1602.40
Screening ’B’ type
14 Dalla 670.00 35.00 160.00 475.00 1 64 0 65 717.36 1192.36 1192.40 1192.40
2.36 mm & below
15 Dalla 600.00 35.00 160.00 405.00 1 64 0 65 717.36 1122.36 1122.40 1122.40
20mm gauge Stone Grit
16 Dalla 1450.00 35.00 160.00 1255.00 1 64 0 65 717.36 1972.36 1972.40 1972.40
10mm gauge Stone Grit
17 Dalla 800.00 35.00 160.00 605.00 1 64 0 65 717.36 1322.36 1322.40 1322.40
Fine Sand
18 Chopan 500.00 35.00 65.00 400.00 1 72 0 73 782.82 1182.82 1182.80 1182.80
Coarse Sand
19 Chopan 550.00 35.00 150.00 365.00 1 72 0 73 782.82 1147.82 1147.80 1147.80
Note:
1 Shortest Route taken in RMR.
2 Quarry Rates and cartage rates taken as per approved rates by competent authority.
3 Minimum Rates as compare to other RMR taken.
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROAD CONSTRUCTION
F-6
PACKAGE NO :- UP67146
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

ROAD LENGTH :- 25.300 K.M.


Sl L B D/H Quantity Unit Rate Amount
Description of Item No.
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
A Pavement Components
1 Clearing and grubbing road land including uprooting wild vegetation,
grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal
of stumps of such trees cut earlier and disposal of unserviceable
materials and stacking of serviceable material to be used or auctioned,
upto a lead of 1000 m including removal and disposal of top organic soil
not exceeding 150 mm in thickness as per Technical Specification Clause
201. (Including Labour cess & Excluding GST)

3.75 M BT Ch. 0.00 to 4.85 1 x 1 4850.000 2.000 9700.000 sqm


3.00 M BT Ch. 4.850 to 18.300, Ch. 21.800 to 25.300 1 x 2 16950.000 2.000 67800.000 sqm
EARTHEN PORTION Ch. 18.300 to 21.800 1 x 1 3500.000 8.000 28000.000 sqm
Deduct culverts portion and causeway ,minor bridge -1 x 2 261.000 2.000 -1044.000 sqm
Deduct Approch Road -1 x 2 30.000 2.000 -120.000 sqm
Deduct bridge lemgth -1 x 1 40.000 2.000 -80.000 sqm
Total 104256.000 sqm 4.22 439960.32
2 Providing and fixing of reference/ level pillars on ether side of the road @
50 m C/C as per standered drawing (150mmx150mmX900mm) and also
including reused on high embankment,sharp curves and safe guard on
structure etc and inclunding all material, t&p and labours and proper
completion as per direction of Engineer-incharge. (Including Labour cess
& Excluding GST)

1 x 2 506.000 1012.000 No
Deduct Approch Road and bridge -1 x 1 1.000 -1.000 No
Total 1011.000 No 343.90 347682.9
3 Scarifying existing bitumenus surface to a depth of 50 mm and disposal of
scarified material ,as per Technical Specification Clause 301.4. Reusable
material shall be sorted out from scarified material and shall be
compacted as per specifications. (Including Labour cess & Excluding
GST)

3.75 M BT Ch. 0.00 to 4.85 1 x 90% 4850.000 3.750 16368.750 sqm


3.00 M BT Ch. 4.850 to 18.300, Ch. 21.800 to 25.300 1 x 70% 16950.000 3.000 35595.000 sqm
Deduct Approch Road -1 x 70% 60.000 3.000 -126.000 sqm
Deduct bridge lemgth -1 x ### 40.000 3.000 -120.000 sqm
Total 51717.750 sqm 18.51 957295.55
4 Construction of embankment with approved material obtained from
availble land as permitted and approved by Engineer-in-Charge and as
per Technical Specitaion Clause 301.3.4.1, with all lifts and leads,
spreading, grading to required slope and compacting to meet requirement
of Tables 300.1and 300.2 as per Technical Specification clause 301.5
(Local earth) (Including Labour cess & Excluding GST)

As per calculation sheet 39120.560 Cum


Deduct qty of excavation as per Item No. 7 60% OF EXCAVATION -4874.469 Cum
Deduct for hard rock cutting as item No 8 (50%) -1 x 1 1200.000 10.000 1.500 -9000.000 Cum
Deduct Approch Road -1 x 2 30.000 10.000 1.500 -900.000 Cum
Deduct bridge lemgth -1 x 1 40.000 10.000 1.500 -600.000 Cum
Total 23746.091 Cum 86.50 2054036.86
5 Construction of embankment with approved material obtained from borrow
pits with a lift upto 1.5 m, transporting to site, spreading, grading to
required slope and compacting to meet requirement of Tables 300.1 and
300.2 with a Carted upto 1000 m as per Technical Specification Clause
301.5 (Carted) (Including Labour cess & Excluding GST)

Qty of earth work for Junction ch 0.00 49.231 Cum


Qty of earth work for Junction of Chakroads 1 x 39 44.250 1725.750 Cum
As per calculation sheet 14949.370 Cum
Deduct qty of excavation as per Item No. 7 40% OF EXCAVATION -3249.646 Cum
Total 13474.705 Cum 165.82 2234375.52
6 Construction of embankment with approved materials deposited at site
from roadway cutting and excavation from drain and foundation of other
structures graded and compacted to meet requirement of Tables 300.1
and 300.2 as per Technical Specification Clause 301.5 (Including Labour
cess & Excluding GST)

AS per itm no 7 8124.115 Cum


Total 8124.115 Cum 55.62 451863.29
Sl L B D/H Quantity Unit Rate Amount
Description of Item No.
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
7 Excavation for roadwork in soil with hydraulic excavator of 0.9 cum
bucket capacity including cutting and loading in tippers, trimming bottom
and side slopes, in accordance with requirements of lines, grades and
cross-sections, and transporting to the embankment location with a lift
upto 1.5 m and lead upto 1000 m as per Technical Specification Clause
302.3 (Including Labour cess & Excluding GST)
Sl L B D/H Quantity Unit Rate Amount
Description of Item No.
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
in widening
3.00 M BT 1 x 2 16950.000 0.525 0.175 3114.563 Cum
3.75 M BT 1 x 2 0.000 0.000 0.270 0.000 Cum
in T-junction 1 x 39 60.000 0.175 409.500 Cum
Deduct culverts portion and causeway and minor bridge -1 x 2 261.000 0.525 0.175 -47.959 sqm
in widening of curves Area = 1858.28 Sqm 0.175 325.199 Cum
Deduction for Retaining Wall/Toe Wall/Breast wall 1 x 1 1200.000 1/2*1.90x3 4332.000
.80
Deduct Approch Road -1 x 2 30.000 0.525 0.175 -5.513 Cum
Deduct bridge lemgth -1 x 1 40.000 0.525 0.175 -3.675 Cum
Total 8124.115 Cum 36.72 298317.51
8 Excavation for roadway in hard rock (blasting prohibited) with rock
breakers including breaking rock, loading in tippers and disposal with a lift
upto 1.5 m and lead upto 1000 metres, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross- sections as per
Technical Specification Clause 302.3.5 (Including Labour cess &
Excluding GST)

For smoothing of verticle curves 1 x 1 1200.000 10.000 1.500 18000.000


Total 18000.000 Cum 457.25 8230500.00
9 Construction of embankment in shoulder with approved material obtained
from availble land as permitted and approved by Engineer-in-Charge and
as per Technical Specitaion Clause 301.3.4.1, with all lifts and leads,
spreading, grading to required slope and compacting to meet requirement
of Tables 300.1and 300.2 as per Technical Specification clause 301.5
(LOcal earth) (Including Labour cess & Excluding GST)

1 x 2 13685.000 (1.875+2.0 0.150 7492.540


)/2 Cum
Deduct Approch Road (1.875+2.0 0.150
-1 x 2 30.000 )/2 -9.000 Cum
Deduct bridge lemgth (1.875+2.0 0.150
-1 x 1 30.000 )/2 -4.500 Cum
Total 7479.040 Cum 86.5 646936.96
10 Construction of embankment in shoulder with approved material obtained
from borrow pits with a lift upto 1.5 m, transporting to site, spreading,
grading to required slope and compacting to meet requirement of Tables
300.1 and 300.2 with a lead upto 1000 m as per Technical Specification
Clause 301.5 (Carted) (Including Labour cess & Excluding GST)

(1.875+2.0
1 x 2 11615.000 )/2 0.150 6359.210
Total 6359.210 Cum 165.82 1054484.20
11 Construction of granular sub-base by providing well graded material,
spreading in uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired density, complete as per
Technical Specification Clause 401. ( GSB Grade - III) (Including
Labour cess & Excluding GST)

3.00 M BT Ch. 4.850 to 18.300, Ch. 21.800 to 25.300 1 x 2 16950.000 0.525 0.175 3114.560 Cum
EARTHEN PORTION Ch. 18.300 to 21.800 1 x 1 3500.000 4.050 0.175 2480.630 Cum
deduct qty. of cutting length -1 x 2 1200.000 0.525 0.175 -220.500 Cum
for smoothing of vrticle curves 1 x 1 1200.000 4.050 0.175 850.500 Cum
In widening of T-junctions 1 x 39 60.000 0.175 409.500 Cum
In widening of curves Area = 1858.28 Sqm 0.175 325.200 Cum
Extra Qty of for Junction ch 0.00 1 x 1 49.231 0.175 49.230 Cum
Deduct culverts portion and causeway ,minor bridge -1 x 2 261.000 0.525 0.175 -47.960 Cum
Deduct Approch Road -1 x 2 30.000 0.525 0.175 -5.510 Cum
Deduct bridge lemgth -1 x 1 40.000 0.525 0.175 -3.680 Cum
Total 6951.970 Cum 3036.76 21111464.42
12 Providing, laying, spreading and compacting stone aggregates of specific 0.00
sizes to water bound macadam specification including spreading in
uniform thickness, hand packing, rolling with smooth wheel roller 80-100
kN in stages to proper grade and camber, applying and brooming, stone
screening/binding materials to fill-up the interstices of coarse aggregate,
watering and compacting to the required density grading 2 as per
Technical Specification Clause 405.Grading -II Material (63-45 mm size )
in base course with screening material Type B and binding material, 75
mm thick by Mechanical means. (Including Labour cess & Excluding
GST)
For Pot holes and undulation filling 1 x 10% 16950.000 3.000 0.075 381.380 cum
3.00 M BT Ch. 4.850 to 18.300, Ch. 21.800 to 25.300 1 x 1 16950.000 3.750 0.075 4767.190 cum
EARTHEN PORTION Ch. 18.300 to 21.800 1 x 1 3500.000 3.750 0.075 984.380 Cum
For correction of super elevation upto 7% 1 x 272 50.00 2.00 0.023 634.670 Cum
In widening of T-junctions 1 x 39 60.000 0.075 175.500 Cum
In widening of curves Area = 1858.28 Sqm 0.075 139.370 Cum
Extra Qty of for Junction ch 0.00 1 x 1 49.231 0.075 3.690 Cum
Deduct culverts portion and causeway ,minor bridge -1 x 1 261.000 3.750 0.075 -73.410 Cum
Deduct Approch Road -1 x 2 30.000 3.750 0.075 -16.880 Cum
Deduct bridge length -1 x 1 40.000 3.750 0.075 -11.250 Cum
Total 6984.640 cum 3089.700 21580442.21
Sl L B D/H Quantity Unit Rate Amount
Description of Item No.
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
13 Providing, laying, spreading and compacting stone aggregates of specific
sizes to water bound macadam specification including spreading in
uniform thickness, hand packing, rolling with smooth wheel roller 80-100
kN in stages to proper grade and camber, applying and brooming, stone
screening/binding materials to fill-up the interstices of coarse aggregate,
watering and compacting to the required density grading 2 as per
Technical Specification Clause 405 Grading -III Material (53-22.4 mm size
) in base course with screening material Type B , 75 mm thick by
Mechanical means. (Including Labour cess & Excluding GST)

For Pot holes and undulation filling 1 x 10% 4850.000 3.750 0.075 136.410 cum
Sl L B D/H Quantity Unit Rate Amount
Description of Item No.
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
For Strenthening coat Ch. 0.00 to 25.300 Km. 1 x 1 25300.000 3.750 0.075 7115.630 Cum 0.00
In widening of T-junctions 1 x 39 60.000 0.075 175.500 Cum
In widening of curves Area = 1858.28 Sqm 0.075 139.370 Cum
Extra Qty of for Junction ch 0.00 1 x 1 49.231 0.075 3.690 Cum
Deduct culverts portion and causeway ,minor bridge -1 x 1 261.000 3.750 0.075 -73.410 Cum
Deduct Approch Road -1 x 2 30.000 3.750 0.075 -16.880 Cum
Deduct bridge length -1 x 1 40.000 3.750 0.075 -11.250 Cum
Total 7469.060 cum 3206.420 23948943.37
14 Prime Coat : Preparing and applying of water for bitumen emulsion ###
application, IRC approved with cationic bitumen emulsion-SS1 and water
(<1000 ppm TDS) in the ratio of 1 kg silane : 100 kg cationic bitumen
emulsion and add 200 liter water while filling water in tanker/drum and
then add 100 kg cationic bitumen emulsion under circulation. Mix the
solution completely. Spray the solution at the rate of 1 liter per sqm on
compacted stone base. Check quality of bitumen emulsion before bulk
use. (Including Labour cess & Excluding GST)

1 x 1 25300.000 3.750 94875.000 sqm


In widening of T-junctions 1 x 39 60.000 2340.000 sqm
In widening of curves Area = 1858.28 Sqm 1858.280 sqm
Extra Qty of for Junction ch 0.00 1 x 1 49.231 49.230 sqm
Deduct culverts portion and causeway and CC roads -1 x 1 261.000 3.750 -978.750 sqm
Deduct Approch Road -1 x 2 30.000 3.750 -225.000 sqm
Deduct bridge length -1 x 1 40.000 3.750 -150.000 sqm
Total 97768.760 sqm 35.670 3487411.67
15 Providing and applying Tack Coat with Bitumen -VG-30 mixed with 0.00
organo silane nano technology and water in the ratio of 1.4:100:200
(Organo silane nano-technology ) with pressure distributor at the rate of
0.30 kg per sqm on the prepared granular/bituminous surfaces treated
with primer & cleaned with Hydraulic broom as per Technical Specification
Clause 503. (Including Labour cess & Excluding GST)

1 x 1 25300.000 3.750 94875.000 sqm


In widening of T-junctions 1 x 39 60.000 2340.000 sqm
In widening of curves Area = 1858.28 Sqm 1858.280 sqm
Extra Qty of for Junction ch 0.00 1 x 1 49.231 49.230 sqm
Deduct culverts portion and causeway ,minor bridge -1 x 1 261.000 3.750 -978.750 sqm
Deduct Approch Road -1 x 2 30.000 3.750 -225.000 sqm
Deduct bridge length -1 x 1 40.000 3.750 -150.000 sqm
Total 97768.760 sqm 12.380 1210377.25
16 Providing, laying and rolling of Open-Graded Premix Carpet of 20 mm 0.00
thickness composed of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumenVG-30 Mixed with Nano Technology Based
Organo Silane Compound @ 0.1% by the weight of bitumen for enhansed
performance and durability to required line, grade and level to serve as
wearing course on a previously prepared base, including mixing in a
suitable plant, laying and rolling with a three wheel 80-100 kN static roller
capacity, finished to required level and grades to be followed by seal coat
of either Type A or Type B or Type C as per Technical Specification Clause
508. (Including Labour cess & Excluding GST)

1 x 1 25300.000 3.75 94875.000 sqm


In widening of T-junctions 1 x 39 60.00 2340.000 sqm
In widening of curves Area = 1858.28 Sqm 1858.280 sqm
Extra Qty of for Junction ch 0.00 1 x 1 49.231 49.230 sqm
Deduct culverts portion and causeway ,minor bridge -1 x 1 261.000 3.750 -978.750 sqm
Deduct Approch Road -1 x 2 30.000 3.750 -225.000 sqm
Deduct bridge length -1 x 1 40.000 3.750 -150.000 sqm
Total 97768.760 sqm 137.25 13418762.31
17 Providing and laying Seal Coat with nano technology based organo 0.00
silane @ 0.1% by the weight of bitumen-VG-30, sealing the voids in a
bituminous surface laid to the specified levels, grade and cross fall using
Type B as per Technical Specification Clause 510 (Including Labour cess
& Excluding GST)

1 x 1 25300.000 3.750 94875.000


In widening of T-junctions 1 x 39 60.000 2340.000
In widening of curves 1 x 1 1858.280 Sqm 1858.280
Extra Qty of for Junction ch 0.00 1 x 1 49.231 49.230 sqm
Deduct culverts portion and causeway ,minor bridge -1 x 1 261.000 3.750 -978.750 sqm
Deduct Approch Road -1 x 2 30.000 3.750 -225.000 sqm
Deduct bridge length -1 x 1 40.000 3.750 -150.000 sqm
Total 97768.760 sqm 42.02 4108243.30
18 Providing and Laying brick edging with first class brick 8 cm wide and 12
cm deep laid on either side of the mettaled surface as per direction of
Engineer-in-charge including of all materials, labour, T&P etc required for
proper completion of work ( as per SI 765 of Shedule of Rate of UPPWD)
(Including Labour cess & Excluding GST)

1 x 1 25.300 25.300 Km
Deduct culverts portion and causeway ,minor bridge -1 x 1 261.000 -0.260 Km
Deduct Approch Road -1 x 2 30.000 -0.060 Km
Total 24.980 Km 75000.00 1873500.00
Sl L B D/H Quantity Unit Rate Amount
Description of Item No.
No. (m) (m) (m) ( Rs) Rs
1 2 3 4 5 6 7 8 9 10
B- CD Works
Repair of old Culverts (Including Labour cess & Excluding
GST)
19 Repairof old existing culverts
1 x 1 1.000 Job 133463.63 133463.63
Construction of New Culverts (Including Labour cess &
Excluding GST)
20 Providing/ Laying of 1x350mm dia NP-3 RCC hume pipe goole as per
approved drawing& design
1 x 3 3.000 No 54799.99 164399.97
21 Providing/ Laying of 1x600mm dia NP-3 RCC hume pipe as per approved
drawing& design
1 x 2 2.000 No #VALUE! #VALUE!
22 Providing/ Laying of 1x1000mm dia NP-3 RCC hume pipe as per
approved drawing& design

1 x 3 3.000 No 131195.97 393587.91


23 Construction of 1x5.0 m span RCC culvert as per drawing and technical
specification
1 x 1 1.000 No 2667545.14 2667545.14
24 OVER LAY ON EXISTING CAUSEWAY 0.00
1 249.00 249.00 RM
Total 249.00 249.00 RM 9261.35 2306075.09
C- Protection Works (Including Labour cess & Excluding GST)

26 CONSTRUCTION OF PARAPET WALL 0.00


1 36 36 NO
Total 36 36 NO 2788.14 100373.04
27 CONSTRUCTION OF TOE WALL 0.00
1 450.00 450.00 RM
Total 450.00 450.00 RM 3559.20 1601640.00
28 CONSTRUCTION OF RETAINING WALL 0.00
1 804.00 804.00 RM
Total 804.00 804.00 RM 11375.76 9146111.04
29 CONSTRUCTION OF BREAST WALL 0.00
1 240.00 240.00 RM
Total 240.00 240.00 RM 9090.90 2181816.00
30 CONSTRUCTION OF PLUM CONCRETE BLOCKS
100 3.00 1.250 1.250 468.75 Cum
3876.57 1817142.19
D- Side Drains (Including Labour cess & Excluding GST)

31 Construction of KC Drain on both side of abadi portionfor draiange of 0.00


water
KUDWA VILLAGE 1 x 2 50.000 100.000 RM
KUDWA YADAV BASTI 1 x 2 80.000 160.000 RM
KUDWA TUNIYA BASTI 1 x 2 100.000 200.000 RM
PANDU CHATAW VILLAGE 1 x 2 70.000 140.000 RM
KARIYA VILLAGE 1 x 2 51.000 102.000 RM
Total 351.000 702.000 RM 2244.54 1575664.13
32 Construction of U-Type Drain on both side of abadi portionfor draiange of 0.00
water (Including Labour cess & Excluding GST)

KUDWA VILLAGE 1 x 1 55.000 55.000 RM


KUDWA YADAV BASTI 1 x 1 100.000 100.000 RM
KUDWA TUNIYA BASTI 1 x 1 70.000 70.000 RM
Total 225.000 225.000 RM 6165.52 1387242.83
E- Road furniture and signage (Including Labour cess &
Excluding GST)
33 Road furniture and signage
a 5TH KM Stone 1 x 1 6 6 No. 3078.96 18473.76
b KM Stone 1 x 1 20 20 No. 1824.98 36499.60
c Hectometer Stones 1 x 1 100 100 No. 504.13 50413.00
d Traffic Signs 1 x 1 26 26 No. 3,098.29 80555.54
e Direction and Place Identification signs with size more than 0.9 sqm size 1 x 1 20 20 No. 3176.59 63531.80
f board
Logo board with diamond 1 x 1 13 13 No. 3176.59 41295.67
g Informatory boards with Logo 1 x 1 2 2 No. 10878.23 21756.46
i citizen information board 1 x 1 2 2 No. 8917.32 17834.64
i Maintenance Board 1 x 1 1 1 No. 10878.23 10878.23
F- DPR preparation
34 DPR preparation incl Soil Testing, Traffic Census,Surveying, Drawings and 0.00
Maps complete , @ 10000 per km 1 x 1 25.300 25.300 km 10000.00
Grand Total #VALUE!
say #VALUE!
RCPLWEA (ADDITIONAL) UP67146
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR. PACKAGE NO. :-
DISTRICT :- SONEBHADRA

Junction at take - off point / painted road Junction with Chak Road / Cattle Crossing

Road under construction

B C
R = 10.70 SOLING
NH / SH / MDR

A
D
7.50 m
7.5 4.50m m Chak Road

. 10 m

Extra area of widening at the junction = Area of B.O.E. = ( 7.50 + 4.50 ) / 2 X 10


. = 60.00 sqm.
area of rectangle ABCD = 10.70 10.70 114.49
area of quarter part of circle , CBD = 3.14 114.49 89.87 . Volume of earthwork =
Net area ABD = 24.62 assuming av ht = 0.50 m
X - sectional area at junction = 7.50 1.00 7.50
For both sides of junction = 2.00 24.62 49.23 sqm. X - sectional area at the end = 4.50 0.30 1.35
Volume of earth work average 1.0 m height 49.23 Cum average area = 4.425
Volume = 44.25 cum
Junior Engineer Assistant Engineer Executive Engineer
PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
BASIC RATES
(C) Material
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-001 AC pipe 100 mm /110mm PVC pipe m 299.25
M-002 Aggregate - For 37.5 mm Maximum size - 22.4 mm to 5.6 mm cum
M-003 Aggregate - For 37.5 mm Maximum size - 45 mm to 22.5 mm cum
M-004 Aggregate - For 37.5 mm Maximum size - Below 5.6 mm cum
M-005 Aggregate - For 53 mm Maximum size - 22.5 mm to 5.6 mm cum
M-006 Aggregate - For 53 mm Maximum size - 63 mm to 45 mm cum
M-007 Aggregate - For 53 mm Maximum size - Below 5.6 mm cum
M-008 Aggregate - Grading I (40 mm nominal Size) 10 mm - 5 mm cum
M-009 Aggregate - Grading I (40 mm nominal Size) 25 mm – 10 mm cum
M-010 Aggregate - Grading I (40 mm nominal Size) 37.25 mm - 25 mm cum
M-011 Aggregate - Grading I (40 mm nominal Size) 5 mm and below cum
M-012 Aggregate - Grading II (19 mm nominal Size) 10 mm - 5 mm cum
M-013 Aggregate - Grading II (19 mm nominal Size) 25 mm – 10 mm cum
M-014 Aggregate - Grading II (19 mm nominal Size) 5 mm and below cum
M-015 Aggregate 10 mm cum 770.00
M-016 Aggregate 20 mm cum 1,335.00
M-017 Aggregate 40 mm cum 830.00
Aggregate- Crushable type such as moorum or Gravel for
M-018 cum
Grading I
Aggregate- Crushable type such as moorum or Gravel for
M-019 cum
Grading II
Aggregate- Crushable type such as moorum or Gravel for
M-020 cum
Grading III
M-021 Aggregate-Grading I 90 mm to 45 mm cum 450.00
Aggregate-Grading I 90 mm to 45 mm cum 450.00
M-022 Aggregate-Grading II 63 mm to 45 mm cum 520.00
Aggregate-Grading II 63 mm to 45 mm cum 520.00
M-023 Aggregate-Grading III 53 mm to 22.4 mm cum 740.00
Aggregate-Grading III 53 mm to 22.4 mm cum 740.00
M-024 Aggregates 22.4 mm to 2.36 mm for wet mix macadam cum
M-025 Aggregates 45 mm to 22.4 mm for wet mix macadam cum
M-025 Aluminium sheeting (1.5 mm thick) sqm
M-026 Aluminium Studs 100 mm x 100 mm fitted with lense reflectors Nos.
Angle iron 50mm x 50mm x 5 mm for lugs kg 40.00
M-027 Bamboo (1st Class) 85 mm - 100 mm dia, 2.0 m long No.
M-028 Bamboo (1st Class) 85 mm - 100 mm dia, 2.5 m long No.
M-028 Bamboo (1st Class) 85 mm - 100 mm dia, 3.0 m long No.
M-029 Bamboo (1st Class) 85 mm - 100 mm dia, 4.5 m - 5.5 m long No.
M-028 Bamboo (2nd Class) 75mm dia, 1.8 m - 2.5 m long No.
M-029 Bamboo (2nd Class) 75mm dia, 2.1 m - 3.0 m long No.
M-030 Barbed wire kg 57.75
M-031 Binding Material cum 460.00
M-032 Binding wire kg 57.75
M-033 Bitumen (Crumb Rubber Modified) tonne
M-034 Bitumen (Natural Rubber Modified) tonne
M-035 Bitumen (Polymer Modified) tonne
M-036 Bitumen (VG-30) t 28,940.00
M-037 Bitumen (VG-10) t 0.00
M-038 Bitumen Emulsion (RS-1) t 0.00
M-039 Bitumen Emulsion (SS-1) t 32,965.00
M-040 Bituminous sealant litre 40.20
M-041 Blasted rubble cum 1,514.20
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-042 Blasting material kg
M-043 Bond stone (400 mm x 150 mm x 150 mm) No.
M-044 Brick 1st Class No. 6.19
Brick bats cum 1,238.00
M-045 Cement t 5,560.00
M-046 Cement Primer litre 68.25
M-047 Chlorprene Elastomer or Closed Cell Foam Sealing Element m
M-048 Compensation for earth taken from private land cum 14.00
M-049 Compressible Fibre Board sqm 682.50
M-050 Copper plate kg
M-051 Corbelling Stones (300 mm x 150 mm x 150 mm) No.
M-052 Corrosion Resistant Structural Steel Grating kg 69.00
M-053 Credit for excavated rock found suitable for use cum
M-054 Crow bars 40 mm dia (hire charges) hour
M-055 Crushed Sand or Grit Passing 2.36 mm and retained on 180 micro cum 480.00
M-056 Crushed Slag cum
22.4-53 mm sukrut cum 740.00
11.2 mm Dala cum 1,080.00
Dust cum 505.00
M-057 Crushed Stone Aggregate 26.5 mm to 75 micron cum 905.00
13.2 mm 1,150.00
11.2 mm Dala 1,080.00
Stone Chips 13.2 mm to 5.6 mm (2part 13.2mm+one part 1,126.70
M-058 cum
11.2mm)/3
Crushed Stone Chipping 6.7 mm size 100% passing 11.2 mm 760.00
M-059 cum
and retained on 2.36 mm
Crushed Stone Chipping 6.7 mm size 100% passing 9.5 mm and 755.00
M-060 cum
retained on 2.36 mm
M-061 Crushed Stone chipping 9.5 mm nominal size cum
Crushed Stone Coarse Aggregate Passing 53 mm and retained
M-062 cum
on 2.8 mm
M-063 Curing compound litre 63.50
M-064 Debonding strips m 100.00
M-065 Edge Stone (450 mm x 350 mm x 100 mm) No. 66.00
M-066 Edge Stone (450 mm x 350 mm x 200 mm) No. 66.00
M-067 Elastomeric bearing assembly Nos.
M-068 Electric Detonator each
M-069 Epoxy Paint litre 275.00
M-070 Epoxy Primer litre 126.00
M-071 Farmyard manure cum
M-072 Fevicol adhesive kg 215.30
M-073 Filter media cum 531.90
M-074 Fine aggregate/Crushed sand 2.36 mm to 75 micron cum
20 mm thick compressible fibre board 7.5 m long and 250 mm 682.50
sqm
deep
M-075 Galvanised angle kg
M-076 Galvanised angle Section 100 mm x 100 mm of 12 mm thickness kg
M-077 Gelatine 80 per cent kg
M-078 GI Pipe 100 mm dia m 299.25
M-079 GI Pipe 50 mm dia m
M-080 GI wires kg 440.00
M-081 Graded stone aggregate cum
Granular material (Natural occuring, soil gravel mixture / quarry
M-082 cum
waste, kankar, laterite, dhandla
Geroo quintel 2,500.00
M-083 Hand Broken Metal 40 mm size cum
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-084 Indigo kg 225.00
M-085 Interlocking Blocks with 60 mm thickness sqm
M-086 Interlocking Blocks with 80 mm thickness sqm 702.20
M-087 Joint filler board sqm 60.00
M-088 Jute netting, open weave 25 mm square opening sqm
M-089 Jute rope 12 mm dia m 51.70
M-090 Key Aggregates passing 22.4 mm and retained on 2.8 mm cum
M-091 Lime t 6,670.00
M-092 Lime putty t 6,000.00
M-093 Local Wood Piles (1st Class) 150-200 mm dia ,6m long No.
M-094 Local Wood Piles (1st Class) 100 mm x 75 mm cum
M-095 Loose stone cum 385.00
M-096 MS clamps Nos. 16.00
M-097 MS Flat / Structural Steel t 33,898.00
M-098 MS Sheet Tube (47 mm x 47 mm x 12 SWG Sheet) kg 60.00
M-098 2 nos. MS tubes 75mx75mm of 12 SWG sheet 2650 mm long kg 60.00
M-099 MS Sheet 1.5 mm thick sqm 176.40
M-100 MS Sheet 2 mm thick sqm 840.00
MS sheet 1.6 mm thick sqm 840.00
1 No. MS tube 47mm x 47mm of 12 SWG 1100 mm long kg 60.00
Angle iron 50mm x 50mm x 5 mm for lugs kg 40.00
M-101 Nuts, Bolts and Rivets t 65,000.00
M-102 Paint (Synthetic Enamel) litre 273.00
Paint conforming litre 198.55
Paint ready mixed litre 230.00
M-103 Plasticizer litre
M-104 Polythene sheet (125 micron) sqm 31.00
M-105 Polythene Sheething Nos. 20.00
M-106 Quarried Stone 150-200 mm size cum
M-107 RCC Pipe NP3 (1200 mm dia) m
M-108 RCC Pipe NP3 (1000 mm dia) m 3,996.00
M-109 RCC Pipe NP3 (750 mm dia) m
M-110 RCC Pipe NP3 (600 mm dia) m 1,560.00
M-111 RCC Pipe NP3 (500 mm dia) m 1,560.00
M-112 RCC Pipe NP4 (1200 mm dia) m
M-113 RCC Pipe NP4 (1000 mm dia) m
M-114 RCC Pipe NP4 (750 mm dia) m
M-115 RCC Pipe NP4 (600 mm dia) m
M-116 RCC Pipe NP4 (500 mm dia) m
Brick Edging KM 75,000.00
organo silane nano technology Nanotac KG 1,200.00
Nano Technology Based Organo Silane Compound @ 1,350.00
KG
0.1%Zycotherm
M-117 Red-oxide Primer litre 78.75
M-118 Road marking paint litre
Recron Fibre @ 100gm per 50 Kg cement KG 700.00
M-119 Sand (Coarse) cum 500.00
M-120 Sand (Fine) cum 450.00
M-121 Seeds kg
M-122 Steel Pipe 50 mm dia m
M-123 Steel Reinforcement (HYSD Bars) t 41,000.00
M-124 Steel Reinforcement (MS Round Bars) t
M-125 Steel Reinforcement (TMT Bars) t
M-126 Stone Boulder of size 150 mm and below cum
M-127 Stone Chips 12 mm size cum
Rate at Plant
Sl. No. Description Unit
(Rs.)
M-128 Stone Chips 13.2 mm to 5.6 mm cum
M-129 Stone Crushed Aggregate 11.2 mm to 0.09 mm cum
M-130 Stone for Coarse Rubble Masonry 1st Sort cum
M-131 Stone for Coarse Rubble Masonry 2nd Sort cum
M-132 Stone for Random Rubble Masonry cum 1,479.20
M-133 Stone for Stone Set Pavement (300 mm x 200 mm x 150 mm) No. 9.05
M-134 Stone Screening - Type A 13.2 mm for Grading-1 cum
M-135 Stone Screening - Type A 13.2 mm for Grading-2 cum
M-136 Stone Screening - Type B 11.2 mm for Grading-2 cum 1,040.00
M-137 Stone Screening - Type B 11.2 mm for Grading-3 cum 1,040.00
M-138 Stone spall cum 417.00
Through and bond stone No. 9.50
M-139 Traffic cones No.
M-140 Water kl 50.00
Water for mixing and curing for 14-days day 192.00
M-141 Well graded Granular Base Material - Grading A 2.36 mm below cum
Well graded Granular Base Material - Grading A 26.5 mm to 4.75
M-142 cum
mm
Well graded Granular Base Material - Grading A 53 mm to 26.5
M-143 cum
mm
M-144 Well graded Granular Base Material - Grading B 2.36 mm below cum
Well graded Granular Base Material - Grading B 26.5 mm to 4.75
M-145 cum
mm
M-146 Well graded Granular Base Material - Grading C 2.36 mm below cum
Well graded Granular Base Material - Grading C 9.5 mm to 4.75
M-147 cum
mm
M-148 Well Graded Material for Sub-Base - Grading I 2.36 mm below cum

M-149 Well Graded Material for Sub-Base - Grading I 53 mm to 9.5 mm cum

Well Graded Material for Sub-Base - Grading I 9.5 mm to 2.36


M-150 cum
mm
Well Graded Material for Sub-Base - Grading I (from Kabarai 905.00
stone crusher)
M-151 Well Graded Material for Sub-Base - Grading II 2.36 mm below cum
Well Graded Material for Sub-Base - Grading II 26.5 mm to 9.5
M-152 cum
mm
M-153 Well Graded Material for Sub-Base - Grading II 9.5 mm to 2.36 m cum
M-154 Well Graded Material for Sub-Base - Grading III 2.36 mm below cum
M-155 Well Graded Material for Sub-Base - Grading III 4.75 mm to 2.36 cum
M-156 Well Graded Material for Sub-Base - Grading III 9.5 mm to 4.75 m cum
Edge blocks 60 m x 2 m 105.33
M-157 Wooden sleepers (250 mm x 250 mm x 125 mm) (hire charges) No.
BASIC RATES
(A) Labour
Sl. No. Description of Labour Unit Rate (Rs.)
L-01 Bhisti day 260.00
L-02 Bitumen Sprayer day 280.00
L-03 Blacksmith day 350.00
L-04 Blaster day 390.00
Beldar day 235.00
Coolie day 235.00
L-05 Carpenter 1st Class day 400.00
L-06 Chips spreader day 222.00
L-07 Chiseller day 222.00
L-08 Dresser (Skilled) day 227.00
L-09 Driller day 390.00
L-10 Electrician day 350.00
L-11 Fitter day 285.00
Hammer Man day 200.00
L-12 Mason (1st class) day 380.00
L-13 Mason (2nd Class) day 350.00
L-14 Mate day 250.00
L-15 Mazdoor (Unskilled) day 235.00
L-16 Mazdoor (Semi skilled) day 235.00
L-17 Mazdoor (Skilled) day 250.00
L-18 Painter (Ist class) day 385.00
L-19 Plumber day 350.00
L-19 Riveter day 290.00
L-20 Surveyor day 320.00
Welder day 275.00
L-21 White Washer day 245.00
BASIC RATES
(B) USAGE RATES OF PLANT & MACHINERY
Description of Output of Machine Usage Rates in Rs.
Sr. No. Rate add
Machine Activity Unit Output Unit Rate
85%
Supplying compressed
PM-001 Air Compressor 210 cfm cfm 210.00 per hour 206.00 381.10
air
PM-002 Batch mix HMP 40-60 TPH BM, DBM, SDBC, PM t/h 50.00 per hour 7,150.00 13,227.50
PM-003 Batch type HMP 30/40 TPH BM, DBM, SDBC, PM t/h 35.00 per hour 7,150.00 13,227.50
PM-004 Bitumen boiler oil fired Heating of bi #VALUE!
200 litre Heating of bitumen litre / h 400.00 per hour 128.00 236.80
1000 litre litre / h 2000.00 per hour 138.00 255.30
Applying bitumen tack
PM-005 Bitumen emulsion pressure distributor sqm/h 1750.00 per hour 516.00 954.60
coat
PM-006 Concrete mixer 0.28/0.4 cum Mixing of ingradients cum/h 2.50 per hour 150.00 277.50
PM-007 Crane upto 8T Lifting of materials per hour 550.00 1,017.50
PM-008 cum/h 200.00 1,423.00 2,632.55
Dozer D 50 Dozing cutting per hour
cum/h 100.00 1,423.00 2,632.55
PM-009 Electric generator set, 125 KVA Electricity generation KVA 100.00 per hour 450.00 832.50
PM-010 Emulsion Sprayer with Tractor Spraying of Emulsion per hour 516.00 954.60
Applying bitumen tack Sqm/hou
PM-010 Bitumen Pressure Distributor 1750.00 Per hour 692.00 1,280.20
coat r
PM-011 Front end-loader 1 cum bucket capacity @ Loading Aggregates cum/h 45.00 520.00 962.00
per hour
45 cum/hour Loading Soil cum/h 100.00 520.00 962.00
PM-012 Hydraulic broom with tractor Surface cleaning sqm/h 1250.00 per hour 230.00 425.50
PM-013 Hydraulic Excavator 0.9 cum Excavation cum/h 100.00 per hour 840.00 1,554.00
PM-014 Hydraulic self propelled chip spreader Surface Dressing sqm/h 1500.00 per hour 1,700.00 3,145.00
Pavement breaking &
PM-015 Jack Hammer with tractor cum/h 05. to 1 per hour 83.00 153.55
rock drilling
PM-016 Joint Cutting Machine with 2-3 blades Cutting of Joints h per hour 405.00 749.25
Mixing of bituminous
PM-017 Mixall 6-10 t capacity t/h 8.00 per hour 810.00 1,498.50
materials
PM-018 200.00 1,545.00 2,858.25
Motor Grader Scarifier & levelling cum/h per hour
50.00 1,545.00 2,858.25
Vibrating cement
PM-019 Needle vibrator cum/h 3.50 per hour 101.00 186.85
concrete mix
PM-020 Paver finisher Laying/spreading t/h 75.00 per hour 629.00 1,163.65
PM-021 Plate compactor Compaction cum/h per hour 101.00 186.85
PM-022 Plate vibrator Compaction cum/h per hour 107.31 198.53
PM-023 Screed vibrator Compaction cum/h per hour 107.31 198.53
Compaction of Sub-base/
PM-024 Smooth wheeled 80-100 kN tandem roller cum/h 30.00 per hour 297.00 549.45
Asphalt
PM-025 Stone crusher (Integrated) of 200 TPH Crushing of Spalls t/h 200.00 per hour 11,760.00 21,756.00
PM-026 Three wheel 80-100 kN Static Roller Compaction/ Rolling 297.00 549.45
Earth:- Embankment or
sub-grade cum/h 80/70 297.00 549.45

Sub-base G-I cum/h 10.00 297.00 549.45


Sub-base G-II/G-III cum/h 8.00 297.00 549.45
WMM cum/h 16.00 297.00 549.45
BUSG cum/h 10.00 297.00 549.45
per hour
BM 50/75 mm cum/h 12.00 297.00 549.45
Premix 20 mm sqm/h 250.00 297.00 549.45
Seal Coat sqm/h 500.00 297.00 549.45
Surface Dressing 1st
sqm/h 400.00 297.00 549.45
Coat
Surface Dressing
sqm/h 500.00 297.00 549.45
2ndCoat
PM-027 Tipper 5.5 cum/10 t Carriage cum/trip 5.50 per hour 200.00 370.00
PM-028 Tractor with Disc Harrows Pulverisation of soil cum/h 80.00 per hour 234.00 432.90
Ripping Pavements,
PM-029 Tractor with ripper @ 60 cum per hour cum/h 60.00 per hour 234.00 432.90
uprooting trees
Transportation of
PM-030 Tractor with trolley t/trip 3 to 5 per hour 234.00 432.90
materials
PM-031 Tractor with Rotavator Scarifier cum/h 25.00 per hour 234.00 432.90
PM-032 Truck 10 t capacity Carriage cum/trip 5.50 per hour 200.00 370.00
PM-033 Compaction of soil WMM cum/h 100.00 994.00 1,838.90
Vibratory roller 80-100 kN per hour
Compaction of BM cum/h 60.00 994.00 1,838.90
Water tanker 6 kl capacity (Truck
PM-034 Carriage of water litre / h ### per hour 200.00 370.00
Mounted)
PM-035 Wet mix plant (Pug Mill) Wet Mix cum/h 25.00 per hour 777.00 1,437.45
RCPLWEA (ADDITIONAL)
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
BLOCK :- CHOPAN / DUDDHI DISTRICT:- SONEBHADRA PACKAGE NO. :-
Detail of Cartage Calculation
Loading + Unloading Charges 42.00
1st Km cartage -(Loading + Unloading Charges) 43.50
1/3 of Net Cartage_14.50
Km Rate amount Commulative Commulative Commulative
amount for Grit amount for Coarse amount for GSB ,
from Dala Sand from 45-63, 22.4-53 from
Chopan Sukrut
DISTANCE FORM QUARRY TO ROBERTSGANJ = 0 0 26
DISTANCE FORM ROBERTSGANJ TO ZERO OF SITE = 51 59 83
DISTANCE FORM ZERO TO MIDDLE SITE = 13 13 13
TOTAL DISTANCE = 64 72 122
Add for Kachcha Road = 15.90 15.90 15.90
1 1.00 100.70 100.70 100.70 100.70 100.70
2 1.00 24.10 24.10 124.80 124.80 124.80
3 1.00 21.40 21.40 146.20 146.20 146.20
4 1.00 19.50 19.50 165.70 165.70 165.70
5 1.00 17.00 17.00 182.70 182.70 182.70
6 1.00 16.50 16.50 199.20 199.20 199.20
7 1.00 15.50 15.50 214.70 214.70 214.70
8 1.00 14.60 14.60 229.30 229.30 229.30
9 1.00 13.90 13.90 243.20 243.20 243.20
10 1.00 13.20 13.20 256.40 256.40 256.40
11 1.00 12.70 12.70 269.10 269.10 269.10
12 1.00 12.30 12.30 281.40 281.40 281.40
13 1.00 12.00 12.00 293.40 293.40 293.40
14 1.00 11.70 11.70 305.10 305.10 305.10
15 1.00 11.30 11.30 316.40 316.40 316.40
16 1.00 11.10 11.10 327.50 327.50 327.50
17 1.00 10.90 10.90 338.40 338.40 338.40
18 1.00 10.70 10.70 349.10 349.10 349.10
19 1.00 10.50 10.50 359.60 359.60 359.60
20 1.00 10.40 10.40 370.00 370.00 370.00
21 1.00 10.20 10.20 380.20 380.20 380.20
22 1.00 10.10 10.10 390.30 390.30 390.30
23 1.00 10.00 10.00 400.30 400.30 400.30
24 1.00 9.90 9.90 410.20 410.20 410.20
25 1.00 9.70 9.70 419.90 419.90 419.90
26 1.00 9.60 9.60 429.50 429.50 429.50
27 1.00 9.50 9.50 439.00 439.00 439.00
28 1.00 9.50 9.50 448.50 448.50 448.50
29 1.00 9.40 9.40 457.90 457.90 457.90
30 1.00 9.30 9.30 467.20 467.20 467.20
31 1.00 9.00 9.00 476.20 476.20 476.20
32 1.00 9.00 9.00 485.20 485.20 485.20
33 1.00 9.00 9.00 494.20 494.20 494.20
34 1.00 9.00 9.00 503.20 503.20 503.20
35 1.00 9.00 9.00 512.20 512.20 512.20
36 1.00 9.00 9.00 521.20 521.20 521.20
37 1.00 9.00 9.00 530.20 530.20 530.20
38 1.00 9.00 9.00 539.20 539.20 539.20
39 1.00 9.00 9.00 548.20 548.20 548.20
40 1.00 9.00 9.00 557.20 557.20 557.20
41 1.00 9.00 9.00 566.20 566.20 566.20
42 1.00 9.00 9.00 575.20 575.20 575.20
Km Rate amount Commulative Commulative Commulative
amount for Grit amount for Coarse amount for GSB ,
from Dala Sand from 45-63, 22.4-53 from
Chopan Sukrut
43 1.00 9.00 9.00 584.20 584.20 584.20
44 1.00 9.00 9.00 593.20 593.20 593.20
45 1.00 9.00 9.00 602.20 602.20 602.20
46 1.00 9.00 9.00 611.20 611.20 611.20
47 1.00 9.00 9.00 620.20 620.20 620.20
48 1.00 9.00 9.00 629.20 629.20 629.20
49 1.00 9.00 9.00 638.20 638.20 638.20
50 1.00 9.00 9.00 647.20 647.20 647.20
51 1.00 9.00 9.00 656.20 656.20 656.20
52 1.00 9.00 9.00 665.20 665.20 665.20
53 1.00 9.00 9.00 674.20 674.20 674.20
54 1.00 9.00 9.00 683.20 683.20 683.20
55 1.00 9.00 9.00 692.20 692.20 692.20
56 1.00 9.00 9.00 701.20 701.20 701.20
57 1.00 9.00 9.00 710.20 710.20 710.20
58 1.00 9.00 9.00 719.20 719.20 719.20
59 1.00 9.00 9.00 728.20 728.20 728.20
60 1.00 9.00 9.00 737.20 737.20 737.20
61 1.00 9.00 9.00 746.20 746.20 746.20
62 1.00 9.00 9.00 755.20 755.20 755.20
63 1.00 9.00 9.00 764.20 764.20 764.20
64 1.00 9.00 9.00 773.20 773.20 773.20
65 1.00 9.00 9.00 782.20 782.20
66 1.00 9.00 9.00 791.20 791.20
67 1.00 9.00 9.00 800.20 800.20
68 1.00 9.00 9.00 809.20 809.20
69 1.00 9.00 9.00 818.20 818.20
70 1.00 9.00 9.00 827.20 827.20
71 1.00 9.00 9.00 836.20 836.20
72 1.00 9.00 9.00 845.20 845.20
73 1.00 9.00 9.00 854.20
74 1.00 9.00 9.00 863.20
75 1.00 9.00 9.00 872.20
76 1.00 8.00 8.00 880.20
77 1.00 8.00 8.00 888.20
78 1.00 8.00 8.00 896.20
79 1.00 8.00 8.00 904.20
80 1.00 8.00 8.00 912.20
81 1.00 8.00 8.00 920.20
82 1.00 8.00 8.00 928.20
83 1.00 8.00 8.00 936.20
84 1.00 8.00 8.00 944.20
85 1.00 8.00 8.00 952.20
86 1.00 8.00 8.00 960.20
87 1.00 8.00 8.00 968.20
88 1.00 8.00 8.00 976.20
89 1.00 8.00 8.00 984.20
90 1.00 8.00 8.00 992.20
91 1.00 8.00 8.00 1000.20
92 1.00 8.00 8.00 1008.20
93 1.00 8.00 8.00 1016.20
94 1.00 8.00 8.00 1024.20
95 1.00 8.00 8.00 1032.20
96 1.00 8.00 8.00 1040.20
97 1.00 8.00 8.00 1048.20
98 1.00 8.00 8.00 1056.20
Km Rate amount Commulative Commulative Commulative
amount for Grit amount for Coarse amount for GSB ,
from Dala Sand from 45-63, 22.4-53 from
Chopan Sukrut
99 1.00 8.00 8.00 1064.20
100 1.00 8.00 8.00 1072.20
101th to 200 Km 22.00 7.50 165.00 1237.20
201th to 250 Km 50.00 6.50 325.00
251th onward 0.00 6.50 0.00
Total 789.10 861.10 1253.10
After Deductuction of 10% CP 717.36 782.82 1139.18
ANALYSIS OF CARTAGE FOR BITUMEN AND BITUMEN EMULSION
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
BLOCK :- CHOPAN / DUDDHI DISTRICT:- SONEBHADRA
SI. No. Item Basic Rate Rs.
I Supply of Bitumen Emulsion ( SS-1) from Jhansi 1352 32965.00
Distance from Jhansi to site 1352
V Cartage for SS-1 @ 1.74 /mt/km 2352.48
Say (Rs.) 35317.48
ANALYSIS OF BITUMEN (VG-30) PACKED
SI. No. Item Basic Rate Rs.
I Supply of Bitumen (VG-30) from Mathura 1522 28940.00
Distance from Mathura to site 1522
V Cartage for VG-30 1.74 /mt/km 2648.28
Say (Rs.) 31588.28
RATE ANALYSIS
UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
2.2 201 Clearing and Grubbing Road Land
Clearing and grubbing road land including
uprooting wild vegetation, grass, bushes,
shrubs, saplings and trees of girth upto 300
mm, removal of stumps of such trees cut earlier
and disposal of unserviceable materials and
stacking of serviceable material to be used or
auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not
exceeding 150 mm in thickness as per
Technical Specification Clause 201.

Unit = hectare
Taking output = 1 hectare
(I) By Manual Means
(A) In area of non-thorny jungle
a) Labour
Mate day 6.00 250.00 1,500.00
Mazdoor (Unskilled) day 150.00 235.00 35,250.00
b) Machinery

Tractor with trolley hour 1.00 432.90 432.90


c) Overheads @ 10% on 3,718.29

d) Contractor Profit @ 10% on 4,090.12


Rate per hectare = a+b+c+d 44,991.31
Rate per sqm = a+b+c+d 4.5
Rate with Reduction factor=1.125/1.21 4.18
Add 1% Labour cess 0.04
Say (Rs.) 4.22
3.1 301.4 Preparation of Foundation for Embankment
Scarifying Existing Granular Surface to a
Depth of 50 mm by Manual Means
Scarifying existing granular surface to a depth
of 50 mm and disposal of scarified material with
a lift upto 3 m and leads upto 1000 m as per
Technical Specification Clause 301.4.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.16 250.00 40.00
Mazdoor (Unskilled) day 4.00 235.00 940.00
b) Machinery
Tractor with trolley hour 1.50 432.90 649.35
c) Overheads @ 10% on 162.94
d) Contractor Profit @ 10% on 179.23
Rate for 100 sqm = a+b+c+d 1,971.51
Rate for per sqm = (a+b+c+d)/100 19.72

Rate with Reduction factor=1.125/1.21 18.33


Add 1% Labour cess 0.18
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Say (Rs.) 18.51
3.5 302 (i) Excavation in Cutting in Soil by
manual means with lead upto 50 m
Excavation for roadway in soil using
manual means for carrying of cut earth to
embankment site with a lift upto 1.5 m
and lead upto 50 m as per Technical
Specification Clause 302.3
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.80 250.00 450.00
Mazdoor (Unskilled) day 45.00 235.00 10,575.00
b) Overheads @ 10% on 1,102.50
c) Contractor Profit @ 10% on 1,212.75
Rate for 120 cum= a+b+c 13,340.25
Rate for per cum = (a+b+c)/120 111.17
Rate with Reduction factor=1.125/1.21 103.36
Add 1% Labour cess 1.03
Say (Rs.) 104.39
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
3.5 302 (i) Excavation in Soil using Hydraulic
Excavator and Tippers with disposal
upto 1000 m
Excavation for roadwork in soil with
hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in
tippers, trimming bottom and side slopes,
in accordance with requirements of lines,
grades and cross-sections, and
transporting to the embankment location
with a lift upto 1.5 m and lead upto 1000
m
Unitas= per
cumTechnical Specification Clause
302.3
Taking output = 360 cum
a) Labour
Mate day 0.08 250.00 20.00
Mazdoor (Unskilled) day 2 235.00 470.00
b) Machinery

Hydraulic excavator 0.9 cum bucket hour 3.6 1554 5,594.40


capacity @ 100 cum per hour
Tipper 5.5 cum capacity, 4 trips per h hour 15 370 5,550.00

c) Overheads @ 10% on 1,163.44


d) Contractor Profit @ 10% on 1,279.78
Rate for 120 cum= a+b+c 14,077.62
Rate for per cum = (a+b+c)/360 39.10
39.10
Rate with Reduction factor=1.125/1.21 36.36
Add 1% Labour cess 0.36
Say (Rs.) 36.72
3.3 301.5 Construction of Embankment with Material
Obtained from Roadway Cutting
Construction of embankment with approved
materials deposited at site from roadway
cutting and excavation from drain and
foundation of other structures graded and
compacted to meet requirement of Tables
300.1 and 300.2 as per Technical Specification
Clause 301.5
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.02 250.00 5.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
b) Machinery
Dozer D-50 for spreading @ 200 cum per hour 0.50 2,632.55 1,316.28
Motor grader for grading @ 200 cum per h hour 0.50 2,858.25 1,429.13
Water tanker 6 kl capacity hour 2.00 370.00 740.00
Three wheel 80-100 kN Static Roller hour 1.25 549.45 686.81
c) Material
Water kl 12.00 50.00 600.00
d) Overheads @ 10% on 489.47
e) Contractor Profit @ 10% on 538.42
Rate for 100 cum = a+b+c+d+e 5,922.61
Rate for per cum = (a+b+c+d+e)/100 59.23
Rate with Reduction factor=1.125/1.21 55.07
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Add 1% Labour cess 0.55
Say (Rs.) 55.62
3.4 301.5 Construction of Embankment with Material
Obtained from local earth
Construction of embankment with approved
material obtained from availble land as
permitted and approved by Engineer-in-
Charge and as per Technical Specitaion Clause
301.3.4.1, with all lifts and leads, spreading,
grading to required slope and compacting to
meet requirement of Tables 300.1and 300.2 as
per Technical Specification clause 301.5 (Local
earth)

Unit = cum
Taking output = 100 cum
a) Labour
Mate Day 0.04 250.00 10.00
Mazdoor (Unskilled) Day 1 235.00 235.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket hour 1.67 1,554.00 2,595.18
capacity @ 60
Dozer D-50 forcum per hour
spreading @ 200 cum per hour 0.5 2,632.55 1,316.28
Motor grader for grading @ 200 cum per h hour 0.5 2,858.25 1,429.13
Water tanker 6 kl capacity hour 2 370.00 740.00
Three wheel 80-100 kN Static Roller @ 80 hour 1.25 549.45 686.81
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
c) Material
Water kl 12.00 50.00 600.00
d) Overheads @ 10% on (a+b+c) 761.24
e) Contractor’s profit @ 10% on (a+b+c+d) 837.36
Cost for 100 cum = a+b+c+d+e 9,210.99
Rate per cum = (a+b+c+d+e)/100 92.11
Rate with Reduction factor=1.125/1.21 85.64
Add 1% Labour cess 0.86
Say (Rs.) 86.50
3.4 301.5 Construction of Embankment with Material
Obtained from Borrow Pits
Construction of embankment with approved
material obtained from borrow pits with a lift
upto 1.5 m, transporting to site, spreading,
grading to required slope and compacting to
meet requirement of Tables 300.1 and 300.2
with a lead upto 1000 m as per Technical
Unit = cum Clause 301.5
Specification
Taking output = 100 cum
a) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket hour 1.67 1,554.00 2,595.18
capacity @cum
Tipper 5.5 60 cum
with per
10 thour
capacity hour 4.50 370.00 1,665.00
Dozer D-50 for spreading @ 200 cum per hour 0.00 2,632.55 0.00
Motor grader for grading @ 200 cum per h hour 0.50 2,858.25 1,429.13
Water tanker 6 kl capacity hour 0.00 370.00 0.00
Three wheel 80-100 kN Static Roller @ 80 hour 1.25 549.45 686.81
Add cartage of 1km without CP
=( Cartage of 1 km 100.7-35.00(loadi cum 100.00 59.73 5,972.73
c) Material
Water kl 0.00 50.00 0.00
Compensation for earth taken from private cum 100.00 20.00 2,000.00
d) Overheads @ 10% on (a+b+c) 1,459.38
e) Contractor’s profit @ 10% on (a+b+c+d) 1,605.32
Cost for 100 cum = a+b+c+d+e 17,658.55
Rate per cum = (a+b+c+d+e)/100 176.59
Rate with Reduction factor=1.125/1.21 164.18
Add 1% Labour cess 1.64
Say (Rs.) 165.82
4.1 401 Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by
providing well graded material, spreading
in uniform layers with motor grader on
prepared surface, mixing by mix in place
method with rotavator at OMC, and
compacting with smooth wheel roller to
achieve the desired density, complete as
per
(i) Technical Specification
For GradingIII Clause 401.
Material
Unit = cum
Taking output = 300 cum
a) Labour
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Mate day 0.40 250.00 100.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
b) Machinery
Motor Grader 110 HP @ 50 cum p hour 6.00 2,858.25 17,149.50
Three wheel 80-100 kN static ro hour 30.00 549.45 16,483.50
Tractor with Rotavator 25 cum pe hour 12.00 432.90 5,194.80
Water tanker 6 kl capacity hour 5.00 370.00 1,850.00
c) Material
Well graded granular sub-base material as per Table 400.1
53 mm to 9.5 mm @ 50 per cent cum 180.00 1,814.20 326,556.00
9.5 mm to 2.36 mm @ 20 per cen cum 72.00 1,579.20 284,256.00
2.36 mm below @ 30 per cent cum 108.00 1,489.20 107,222.40
Water kl 30.00 50.00 5,400.00
d) Overheads @ 10% on 76,659.22
e) Contractor Profit @ 10% on 84,315.14
Rate for 300 cum = a+b+c+d+e 927,566.56
Rate for per cum = (a+b+c+d+e)/300 3,091.89
Rate with Reduction factor=1.125/1.21 2,874.69
Add Royalty per cum for 53 mm t cum 360 110 132.00
Add 1% Labour cess 30.07
Say (Rs.) 3,036.76
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
4.7 405 Water Bound Macadam Sub-base/base
2) WBM Grading 2
Providing, laying, spreading and
compacting stone aggregates of specific
sizes to water bound macadam
specification including spreading in
uniform thickness, hand packing, rolling
with smooth wheel roller 80-100 kN in
stages to proper grade and camber,
applying and brooming, stone
screening/binding materials to fill-up the
interstices of coarse aggregate, watering
and
(A) Bycompacting to the required density
Manual Means
grading 2 as per Technical Specification
ClauseUnit = cum
405.
Taking output = 360 cum
a) Labour
Mate day 10.08 250.00 2,520.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 250.00 235.00 58,750.00
b) Machinery
Three wheel 80-100 kN hour 45.00 549.45 24,725.25
static roller @ 8 cum per hour
Water tanker 6 kl capacity hour 24.00 370.00 8,880.00
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 2 63 mm to 45 mm @ cum 435.60 1,514.20 659,585.52
0.91 cum per 10 sqm for compacted
thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading cum 96.01 1,192.40 114,482.32
2 @ 0.20 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum cum 28.80 1,509.20 43,464.96
per 10 sqm for Grading 2
material
Water kl 144.00 50.00 7,200.00
d) Overheads @ 10% on 92,010.81
e) Contractor Profit @ 10% on 101,211.89
Rate for 360 cum = a+b+c+d+e 1,113,330.75
Rate for per cum = (a+b+c+d+e)/360 3,092.59
Rate with Reduction factor=1.125/1.21 2,875.34
Add Royalty per cum for 45-63 mm cum 435.6 110 133.10
Add Royalty per cum for type B 1 cum 96.01 160 42.67
Add Royalty per cum binding mater cum 28.8 100 8.00
Add 1% Labour cess 30.59
Say (Rs.) 3,089.70
3) WBM Grading 3
Providing, laying, spreading and
compacting stone aggregates of specific
sizes to water bound macadam
specification including spreading in
uniform thickness, hand packing, rolling
with smooth wheel roller 80-100 kN in
stages to proper grade and camber,
applying and brooming, stone screening
to fill-up the interstices of coarse
aggregate, watering and compacting to
the required density Grading 3 as per
Technical Specification Clause 405.
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
(A) By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.08 250.00 2,520.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 250.00 235.00 58,750.00
b) Machinery
Three wheel 80-100 kN hour 45.00 549.45 24,725.25
static roller @ 8 cum per hour
Water tanker 6 kl capacity hour 24.00 370.00 8,880.00
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 3 53 mm to 22.4 cum 435.60 1,734.20 755,417.52
mm @ 0.91 cum per 10
sqm for compacted
thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading cum 86.40 1,192.40 103,023.36
3 @ 0.18 cum per 10 sqm
Water kl 144.00 50.00 7,200.00
d) Overheads @ 10% on 96,101.61
e) Contractor Profit @ 10% on 105,711.77
Rate for 360 cum = a+b+c+d+e 1,162,829.5
Rate for per cum = (a+b+c+d+e)/360 3,230.08
Rate with Reduction factor=1.125/1.21 3,003.18
Add Royalty per cum for 45-63 mm cum 435.60 110 133.10
Add Royalty per cum for type B 1 cum 86.40 160 38.40
Add 1% Labour cess 31.75
Say (Rs.) 3,206.42
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
6.4 1500 Cement Concrete Pavement
Construction of un-reinforced, plain cement
concrete pavement, thickness as per design,
over a prepared sub base, with 43 grade
cement or any other type as per Clause
1501.2.2 M30 (Grade), coarse and fine
aggregates conforming to IS:383, maximum
size of coarse aggregate not exceeding 25 mm,
mixed in a concrete mixer of not less than 0.2
cum capacity and appropriate weigh batcher
using approved mix design, laid in approved
fixed side formwork (steel channel, laying and
fixing of 125 micron thick polythene film,
wedges, steel plates including levelling the
formwork as per drawing), spreading the
concrete with shovels, rakes, compacted using
needle, screed and plate vibrators and finished
in continuous operation including provision of
contraction and expansion, construction joints,
applying debonding strips, primer, sealant, near
approaches to bridge/culvert and construction
joints, admixtures as approved, curing of
concrete slabs for 14-days,using curing
compound (where specified) and water
finishing to lines and grade as per drawing and
Technical Specification Clause 1501
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour

Mate day 7.00 250.00 1,750.00


Mason (1st class) day 5.00 380.00 1,900.00

Mason (2nd class) day 5.00 350.00 1,750.00

Mazdoor (Unskilled) day 129.00 235.00 30,315.00

Mazdoor (Skilled) day 6.00 250.00 1,500.00

Surveyor day 0.00 0.00 0.00

Mazdoor (Semi-Skilled) day 6.00 235.00 1,410.00

Bhisti day 14.00 260.00 3,640.00

Blacksmith for cutting of dowel bars day 1.00 0.00


including removal of burrs,
fabrications & fixing of dowel bars.
b) Machinery
Concrete mixer 0.28 / 0.4 cum hour 36.00 277.50 9,990.00
capacity (6 mixers) with weigh batcher
and suitable
Needle capacity calibrated water
vibrator hour 9.00 186.85 1,681.65
tank
Screed vibrator hour 0.00 198.53 0.00
Plate vibrator hour 9.00 198.53 1,786.75
Concrete joint cutting machine for initial hour 4.00 749.25 2,997.00
Water tanker 6 kl capacity hour 5.00 370.00 1,850.00
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Air Compressor (1 hour initial + 1 hour f hour 2.00 381.10 0.00
c) Material
(i) Crushed stone coarse cum 67.50 1,972.40 133,137.00
aggregates, grading will be as per
Clause 1501.2.4.1 (Table 1500.1)
of specifications @ 0.90 cum/cum
(ii) Sand as per IS:383 and
of concrete cum 33.75 1,147.80 38,738.25
conforming to Clause 1500.2.4.2
@ 0.45 cum/cum of concrete
(iii) Cement @ 310 kg/cum of concret t 26.25 5,560.00 145,950.00

(iv) Polythene sheet 125 micron sqm 412.50 31.00 12,787.50


Recron Fibre @ 100gm per 50 Kg cem Kg 0.86 700.00 602.00
(v) Mild steel dowel bar 25 mm dia of
grade S 240. 500 mm long 20
Nos. at culvert/bridge slab and at
construction joint including 5 per
(4 x 20
cent x 0.500) + 5 per cent
wastage. kg 117.60 0.00
wastage = 42 m @ 2.80 kg per m
= 117.6 kg.
Bitumen primer @ 200 ml per joint f t 0.005 35,317.48 176.59
Bituminous sealant 800 ml per joint litre 19.00 40.20 763.80
Jute rope 12 mm dia including 5 p m 0.00 51.70 0.00
Debonding strips 3.75 m (length) m 90.00 100.00 9,000.00
x 10 mm (width) x 5 mm (thick)
cut-out of rubber filler board or
similar material including 5 per
Polythene sheathing, covering No. 483.00 0.00
cent wastage
2/3rd dowel bars (20x23) and
tight fit including 5 per cent
Plasticizer
wastage 0.5 per cent by weight litre 0.00 450.00 0.00
of cement
Curing compound (if used) @ 0.33 litre 131.25 63.50 0.00

Water for curing kl 18.00 50.00 900.00


Joint filler board 20 mm thick as sqm 3.00 60.00 180.00
per IS:1838
d) (4 x 3.75
Formwork @ x3%0.200 = 3 sqm)
of (a+b+c) 12,084.17
e) Overheads @ 10% on (a+b+c+d) 41,488.97

f) Contractor’s profit @ 10% on (a+b+c+d+e) 45,637.87

Cost for 75 cum = a+b+c+d+e+f 502,016.55

Rate per cum = (a+b+c+d+e+f)/75 6,693.55


Rate with Reduction factor=1.125/1.21 6,223.35
Add Royalty per cum for 19 mm nocum 67.5 160 144.00
Add Royalty per cum for Coarse cum 33.75 150 67.50
Add 1% Labour cess 64.35
Say (Rs.) 6,499.19
4.19 413 Stone Set Pavement
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Providing and laying stone set pavement
on prepared surface with sub-base 100
mm thick compacted Granular Sub-base
as per Clause 401.4 and base 75 mm thick
compacted water bound macadam grading
2 as per Clause 405.3. The 150 mm thick
hammer desired stones are laid in the
herring one or stretched bond pattern. The
stones are compacted into the bedding
sand of 40 mm over the WBM base
bounded by edge stone using suitable
compacting device. The gaps are filled
with fine sand stone dust as per Technical
Unit = sqm Clause 413.4
Specification
Taking output = 360 sqm
(a) Labour
Mate day 2.16 250.00 540.00
Mazdoor (Unskilled) day 51.00 235.00 11,985.00
Mason 2nd class for laying sett stone day 13.00 350.00 4,550.00
(b) Machinery
Three wheel 80-100 kN static roller hour 2.00 549.45 1,098.90
Water tanker 6 kl capacity hour 1.00 370.00 370.00
(c) Material
(1) Collection of fine sand
3.4x0.285x0.150x1.20 = 0.174 cum 0.174 1,182.80 205.81
(2) Coarse sand
96x3.35x0.04x1.20 = 15.437 cum cum 15.437 1,147.80 17,718.59
(3) Collection of stone sett stone
300 mmx200 mmx150 mm Nos 5,168.00 9.05 46,770.40
(4) Collection of edge stone
450 mmx200 mmx350 mm Nos 464.00 9.05 4,199.20
(5) Water kl 6.00 50.00 300.00
d) Overheads @ 10% on 8,773.79
e) Contractor Profit @ 10% on 9,651.17
Rate for 360 sqm = a+b+c+d+e 106,162.85
Rate for per sqm = (a+b+c+d+e)/360 294.90
Rate with Reduction factor=1.125/1.21 274.18
Add Royalty per cum for Fine Sa cum 0.174 65 0.03
Add Royalty per cum for Coarse cum 15.437 150 6.43
Add Royalty per cum cut stone cum 5632 0.91 14.16
Add 1% Labour cess 2.95
Say (Rs.) 297.75
5.1 502 Prime Coat
Providing and applying primer coat with
bitumen emulsion on prepared surface of
granular base including cleaning of road
surface and spraying primer at the rate of 0.70-
1.0 kg/sqm using mechanical means as per
Technical Specification Clause 502
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour 1.40 425.50 595.70
Air compressor 210 cfm hour 1.40 381.10 533.54
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Bitumen emulsion pressure hour 1.00 954.60 954.60
Water tanker 6 kl capacity 1 trip pe hour 0.50 370.00 185.00
c) Material
Bitumen emulsion (SS-1) @ 0.85 t 1.48 35,317.48 52,269.87
Water kl 3.00 50.00 150.00

d) Overheads @ 10% on 5,493.37


e) Contractor Profit @ 10% on 6,042.71
Rate for 1750 sqm = a+b+c+d+e 66,469.79
Rate for per sqm = (a+b+c+d+e)/1750 37.98
Rate with Reduction factor=1.125/1.21 35.31
Add 1% Labour cess 0.35
Say (Rs.) 35.67
5.2 503 Tack Coat
(ii) Providing and applying Tack Coat with
Bitumen VG-30 using emulsion/ bitumen
pressure distributor at the rate of 0.30 kg
per sqm on the prepared
granular/bituminous surfaces treated with
primer & cleaned with Hydraulic broom as
per Technical Specification Clause 503.

Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour 1.40 425.50 595.70
Air compressor 210 cfm hour 1.40 381.10 533.54
Pressure distributor @1750 sqm p hour 1.00 954.60 954.60
c) Material
Bitumen VG-30 @ 0.30 kg per sq t 0.53 31,588.28 16,741.79
d) Overheads @ 10% on 1,907.06
e) Contractor Profit @ 10% on 2,097.77
Rate for 1750 sqm = a+b+c+d+e 23,075.46
Rate for per sqm = (a+b+c+d+e)/1750 13.19
Rate with Reduction factor=1.125/1.21 12.26
Add 1% Labour cess 0.12
Say (Rs.) 12.38
5.9 508 Open Graded Premix Carpet
20mm thick Open-Graded Premix Carpet
using Bituminous
Providing, (penetration
laying and rolling of open-graded
premix carpet of 20 mm thickness composed of
13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or emulsion Mixed
the weight of bitumen for enhansed
performance and durability to required line,
grade and level to serve as wearing course on
a previously prepared base, including mixing in
a hot mix plant, laying with paver and rolling
with a three wheel 80-100 kN static roller
capacity, finished to required level and grades
to be followed by seal coat of either Type A or
Type B or Type C as per Technical
Specification Clause 508.

Case - II By Mechanical Means


Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
(I) Bitumen (VG-30)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day 0.52 250.00 130.00
Mazdoor (Unskilled) day 10.00 235.00 2,350.00
Mazdoor (Skilled) day 3.00 250.00 750.00
b) Machinery
HMP 30/40 t per hour hour 6.00 13,227.50 79,365.00
Electric generator set 125KVA hour 6.00 832.50 4,995.00
Front end loader 1 cum bucket hour 6.00 962.00 5,772.00
Tipper 5.5-10 capacity hour 3.64 370.00 1,346.80
Paver finisher hour 6.00 1,163.65 6,981.90
Three wheel 80-100 kN static rolle hour 16.00 549.45 8,791.20
c) Material
Bitumen VG-30 @ 14.60 kg per 10 t 5.84 31,588.28 184,475.56
Crushed stone chipping, 13.2 mm @ cum 72.00 1,672.40 120,412.80
Crushed stone chipping, 11.2 mm @ cum 36.00 1,602.40 57,686.40
d) Overheads @ 10% on 41,537.03
e) Contractor Profit @ 10% on 51,459.37
Rate for 4000 sqm = a+b+c+d+e 566,053.05
Rate for per sqm = (a+b+c+d+e)/4000 141.51
Rate with Reduction factor=1.125/1.21 131.57
Add Royalty per cum for 13.2 cum 108 160 4.32
mm
Add &11.2 mm stone
1% Labour cess grit 1.36
Say (Rs.) 137.25
5.12 510 Seal Coat
Providing and laying seal coat the weight
of bitumen, sealing the voids in a
bituminous surface laid to the specified
levels, grade and cross fall using Type B as
per Technical Specification Clause 510
(I) Bitumen (VG-30)
Unit = sqm
Taking output = 5000 sqm
a) Labour
Mate day 0.20 250.00 50.00
Mazdoor (Unskilled) day 5.00 235.00 1,175.00
b) Machinery
HMP 30/40 t per hour hour 2.00 13,227.50 26,455.00
Electric generator set 125KVA hour 2.00 832.50 1,665.00
Paver finisher hour 2.00 1,163.65 2,327.30
Tipper 5.5-10 capacity hour 1.36 370.00 503.20
Front end loader 1 cum bucket cap hour 2.00 962.00 1,924.00
Three wheel 80-100 kN static roller 10.00 549.45 5,494.50
c) Material
Bitumen (VG-30) @ 6.80 kg per 1 t 3.40 31,588.28 107,400.15
Crushed sand or grit as passing cum 30.00 1,122.40 33,672.00
d) Overheads @ 10% on 18,066.62
e) Contractor Profit @ 10% on 19,873.28
Rate for 5000 sqm = a+b+c+d+e 218,606.04
Rate for per sqm = (a+b+c+d+e)/5000 43.72
Rate with Reduction factor=1.125/1.21 40.65
Add 1% Labour cess 0.41
Add Royalty per cum forstone cum 30 160 0.96
grit
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Say (Rs.) 42.02
9.2 1100 & 800Bedding for Pipe
(i) Type A (Concrete Cradle) Bedding
Laying concrete cradle bedding with M15
Grade Cement Concrete as per Clause
1105 (i)
Unit = cum
Rate as per Item No.11.4 (II)(i) of Chap cum 1.00 5,265.17 5,265.17
Say 5,265.20
(ii) Type B (First Class) Bedding
Laying (First Class) bedding on well
compacted sand, moorum or approved
granular
Unit material as per Clause 1105 (ii)
= cum
Rate as per Item No.11.2 of Chapter 11 cum 1.00 1,774.47 1,774.47
Say 1,774.50
10.1 1700 Printing New Letters and Figures of any Shade
Printing new letter and figures of any shade
with synthetic enamel paint black or any other
approved colour to give an even shade as per
drawings and Technical Specification Clause
1701
i) Hindi (Matras commas and the like not
to be measured
Details and paid
for 100 letters for. mm
of 160 Half height, i.e., 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.12 250.00 30.00
Painter 1st Class day 2.00 385.00 770.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Material
Paint litre 0.70 198.55 138.99
c) Overheads @ 10% on 117.40
d) Contractor Profit @ 10% on 129.14
Rate for cm height per letter 1600 m = a+b+c+d 1,420.52
Rate for cm height per letter = (a+b+c+d)/1600 0.89
Rate with Reduction factor=1.125/1.21 0.83
Add 1% Labour cess 0.01
Say (Rs.) 0.83
ii) English and Roman
Hyphens, commas and the like not to
be measured and paid for. Detail for
100 letters of 160 mm height, i.e.,
1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 250.00 17.50
Painter Ist class day 1.25 385.00 481.25
Mazdoor day 0.50 235.00 117.50
b) Material
Paint litre 0.50 198.55 99.28
c) Overheads @ 10% on 71.55
d) Contractor Profit @ 10% on 78.71
Rate for cm height per letter 1600 m = a+b+c+d 865.79
Rate for cm height per letter = (a+b+c+d)/1600 0.54
Rate with Reduction factor=1.125/1.21 0.50
Add 1% Labour cess 0.01
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)

Say (Rs.) 0.51

10.4 1700,
800 &
300
B. Semi-Reflective Traffic signs
Direction and place identification signs
more than 0.90 sqm sign board
Providing and erecting direction and place
identification of semi reflective sign
boards as per IRC-67 made of 2 mm
thick M.S. Sheet duly stove enameled
Unit
paint =white
eachcolour in front and grey colour
on backoutput
Taking = 1.5 sqm
with reflective border of 70 mm
width and required message, letters,
(i)
figuresExcavation for foundations
with reflective as
tape of engineering
grade as per MORD specifications of 11
As per item no. 11.1 Chapter cum 0.252 100.00 25.20
(ii) Cement Concrete M15
required shade and colour. Supportedgrade
As peron
and welded item
twoNo.11.4
nos. 47 ofmmChapter
x 47 mm11 cum 0.252 4122.78 1,038.94
of 12 SWG square tube of 3050
(iii) Painting M.S. tube posts with mm
heightprimer
duly strengthened by 25
and two coats of epoxymm x5
mm MS flat iron on edges
paint as per specificationon back firmly
fixed to the ground by means of properly
As per
designed item No.with
foundations 10.7M-15
of chapter
grade 10 sqm 0.92 81.10 74.61
cement concrete 450 mm x 450 mm x 600
a) Labour (fox fixing at site)
mm, 600 mm below ground level as per
approvedMatedrawing and Technical day 0.02 250.00 5.00
Specification Clause 1701
Mazdoor (Unskilled) day 0.50 235.00 117.50
b) Material
i) Support of MS Sheet tubes kg 24.80 60.00 1,488.00
47 mm x 47 mm x 12 SWG
sheet 3050 mm long
ii) Angle iron 50 mm x 50 mm x kg 2.12 40.00 84.80
6 mm for lugs
iii) 2 mm thick MS Sheet sqm 1.50 840.00 1,260.00
strengthened by 25 mm x 5
mm M.S. flat iron and painted
with
Add 3% stove
cost enameled
of MS sheetpaint
and 84.98
including lettering, signs,
angle iron towards the cost of
messages, border holes,
fabrications, drilling, with
c)
reflective
nuts,
Machinery boltstape
etc. of engineering
grade of required size, shade
Tractor
andwith trolleyas per MORD
colour hour 0.16 432.90 69.26
d) specifications Overheads @ 10% on 310.95
e) Contractor Profit @ 10% on 342.05
Cost for 1.5 sqm board = (i+ii+iii+a+b+c+d+e) 4,901.31
Rate per sqm = (i+ii+iii+a+b+c+d+e) / 1.5 3,267.54
Rate with Reduction factor=1.125/1.21 3,038.00
Add Royalty per cum for Sand cum 0.121 150 12.10
Add Royalty per cum for 20mm &10mm Stone cum
grit 0.081 160 8.64
Add Royalty per cum for 40mm Stone ballast
cum 0.121 110 8.87
Add 1% Labour cess 30.68
Say (Rs.) 3,098.29
10.5 1700 Painting Two Coats on New Concrete Surfaces
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Painting two coats including primer coat
after filling the surface with synthetic
enamel paint in all shades on new,
plastered / concrete surfaces as per
drawing and Technical Specification Clause
Unit = sqm
1701
Taking output = 40 sqm
a) Labour
Mate day 0.20 250.00 50.00
Painter (1st Class) day 3.00 385.00 1,155.00
Mazdoor (Unskilled) day 2.00 235.00 470.00
b) Material
Cement Primer as per specifications litre 3.00 68.25 204.75
Paint conforming to requirement of Cla litre 6.00 198.55 1,191.30
Add for scaffolding @ 1 per cent of 16.75
d) Overheads @ 10% on 308.78
e) Contractor Profit @ 10% on 339.66
Cost for 40 sqm = a+b+c+d+e 3,736.24
Rate per sqm = (a+b+c+d+e)/40 93.41
Rate with Reduction factor=1.125/1.21 86.84
Add 1% Labour cess 0.87
Say (Rs.) 87.71
10.7 1700 Painting on Concrete/Steel Surfaces with Epoxy
Painting two coats including prime coat
with epoxy paint of approved brand on
concrete/steel surfaces after through
cleaning of surface to give an even shade
as per drawing and Technical Specification
Unit = sqm
Clause 1701
Taking output = 10 sqm
a) Labour
Mate day 0.25 250.00 62.50
Painter (1st Class) day 0.60 385.00 231.00
Mazdoor (Unskilled) day 0.40 235.00 94.00
b) Material
Epoxy primer/Red-oxide litre 0.60 126.00 75.60
Epoxy paint litre 1.25 275.00 343.75
Add @ 1 per cent on cost of material 4.19
d) Overheads @ 10% on 81.10
e) Contractor Profit @ 10% on 89.21
Cost for 10 sqm = (a+b+c+d+e) 981.36
Rate per sqm = (a+b+c+d+e)/10 98.14
Rate with Reduction factor=1.125/1.21 91.24
Add 1% Labour cess 0.91
Say (Rs.) 92.15
10.10 1700 Kilometre Stone
Reinforced cement concrete M15 grade
kilometre stone/local stone of standard
design as per IRC:8 fixing in position
including painting and printing, etc as per
drawing and Technical Specification Clause
i)
17035th Kilometre Stone (precast)
Unit = each
Taking output = 6 Nos.
a) M-15 grade of concrete
As per item No.12.5 of Chapter 12 cum 2.35 4,516.58 10,613.95
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
b) Steel reinforcement @ 5 kg per sqm
As per item No.13.2 of Chapter 13 kg 22.08 52.89 1,167.92
c) Excavation in soil for foundation
As per item No.11.1 of Chapter 11 cum 1.68 100.00 168.00
d) Painting two coats on concrete surface
As per item No.10.5 of Chapter 10 sqm 9.85 77.20 760.42
e) lettering on km post (average 30
As per item No.10.1 of Chapter 10 per cm 1,800.00 0.73 1,314.00
Transportation and fixing high
per litre
f) Labour
Mate day 0.26 250.00 65.00
Mason (1st Class) day 0.60 380.00 228.00
Mazdoor (Unskilled) day 6.00 235.00 1,410.00
g) Machinery
50 HP Tractor with trolley hour 6.00 432.90 2,597.40
h) Overheads @ 10% on 430.04
I) Contractor Profit @ 10% on 473.04
Cost for 6 Nos. 5th km stone = a+b+c+d+e+f+g+h+i 19,227.77
Rate for each 5th km stone = (a+b+c+d+e+f+g+h+i)/6 3,204.63
Rate with Reduction factor=1.125/1.21 2,979.51
Add Royalty per cum for Sand cum 1.13 150 28.25
Add Royalty per cum for 20mm &10mm Stone cum
grit 0.75 160 20.00
Add Royalty per cum for 40mm Stone ballast
cum 1.13 110 20.72
Add 1% Labour cess 30.48
Say (Rs.) 3,078.96
ii) Ordinary Kilometer Stone (Precast)

Unit = each
Taking output = 14 Nos.
a) M15 grade of concrete
As per item No.12.5 of Chapter 12 cum 3.77 4,516.58 17,027.49
b) Steel reinforcement @ 5 kg per sqm
As per item No.12.6 of Chapter 12 kg 26.32 52.89 1,392.19
c) Excavation in soil for foundation
As per item No.11.1 of Chapter 11 cum 2.77 100.00 277.00
d) Painting two coats on concrete surface
As per item No.10.5 of Chapter 10 sqm 11.41 77.20 880.85
e) lettering on km post (average 12
As per item No.10.1 of Chapter 10 per cm 1,680.00 0.73 1,226.40
Transportation and fixing high
f) Labour per
letter
Mate day 0.32 250.00 80.00
Mason (1st Class) day 1.00 380.00 380.00
Mazdoor (Unskilled) day 7.00 235.00 1,645.00
g) Machinery
50 HP Tractor with trolley hour 6.00 432.90 2,597.40
h) Overheads @ 10% on 470.24
I) Contractor Profit @ 10% on 517.26
Cost for 14 Nos. ordinary km stone = (a+b+c+d+e+f+g+h+i) 26,493.84
Rate for each ordinary km stone = (a+b+c+d+e+f+g+h+i)/14 1,892.42
Rate with Reduction factor=1.125/1.21 1,759.48
Add Royalty per cum for Sand cum 1.8096 150 19.39
Add Royalty per cum for 20mm &10mm Stone cum
grit 1.21 160 13.83
Add Royalty per cum for 40mm Stone ballast
cum 1.81 110 14.22
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Add 1% Labour cess 18.07
Say 1,824.98
iii) 200 m stone (precast)
Unit = each
Taking output = 33 Nos.
a) M15 grade of concrete
As per item No.12.5 of Chapter 12 cum 1.58 4,516.58 7,136.19
b) Steel reinforcement @ 5 kg per sqm
As per item No.12.6 of Chapter 12 kg 66.00 52.89 3,491.05
c) Excavation in soil for foundation
As per item No.11.1 of Chapter 11 cum 1.39 100.00 139.00
d) Painting two coats on concrete surface
As per item No.10.5 of Chapter 10 sqm 6.27 77.20 484.04
e) lettering on km post (average 1
As per item No. 10.1 of Chapter 10 per cm 330.00 0.73 240.90
Transportation and fixing per
f) Labour litreette
r
Mate day 0.34 250.00 85.00
Mason (1st Class) day 1.50 380.00 570.00
Mazdoor (Unskilled) day 7.00 235.00 1,645.00
g) Machinery
50 HP Tractor with trolley hour 6.00 432.90 2,597.40
h) Overheads @ 10% on 489.74
I) Contractor Profit @ 10% on 538.71
Cost for 33 Nos. 200 m stone = (a+b+c+d+e+f+g+h) 17,417.04
Rate for each 200 m stone = (a+b+c+d+e+f+g+h)/33 527.79
Rate with Reduction factor=1.125/1.21 490.71
Add Royalty per cum for Sand cum 0.76 150 3.45
Add Royalty per cum for 20mm &10mm Stone cum
grit 0.51 160 2.45
Add Royalty per cum for 40mm Stone ballast
cum 0.76 110 2.53
Add 1% Labour cess 4.99
Say 504.13
Note: 1 The rate for excavation, cement concrete,
steel reinforcement, painting and lettering
may be taken from respective Chapters.
2 In case local stone is to be used in place
of precast RCC stones, then rate of
cement concrete and steel reinforcement
may be deleted.
10.4 B. Semi-Reflective Traffic signs
1700, 80 Direction and place identification
signs more than 0.90 sqm sign
board
Sr. Reference
1700, 80 Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Providing and erecting direction and place
identification of semi reflective sign
boards as per IRC-67 made of 2 mm
thick M.S. Sheet duly stove enameled
paint white colour in front and grey colour
on back with reflective border of 70 mm
width and required message, letters,
figures with reflective tape of engineering
grade as per MORD specifications of
required shade and colour. Supported
and welded on two nos. 47 mm x 47 mm
of 12 SWG square tube of 3050 mm
height duly strengthened by 25 mm x 5
mm MS flat iron on edges on back firmly
fixed to the ground by means of properly
designed foundations with M-15 grade
cement concrete 450 mm x 450 mm x 600
mm, 600 mm below ground level as per
approved drawing and Technical
Specification Clause 1701
Unit = each
Taking output = 1.5 sqm
(i) Excavation for foundations as
As per item no. 11.1 Chapter 11 cum 0.252 100.00 25.20
(ii) Cement Concrete M15 grade
As per item No.11.4 of Chapter 11 cum 0.252 4,122.78 1,038.94
(iii) Painting M.S. tube posts with
primer and No.
As per item two10.7
coats
of of epoxy10 sqm
chapter 0.92 81.10 74.61
a) Labour (fox fixing at site)
Mate day 0.02 250.00 5.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
b) Material
i) Support of MS Sheet tubes kg 24.80 60.00 1,488.00
47 mm x 47 mm x 12 SWG
sheet 3050 mm long
ii) Angle iron 50 mm x 50 mm x kg 2.12 40.00 84.80
iii) 6
2 mm
mmfor lugs
thick MS Sheet sqm 1.50 840.00 1,260.00
strengthened by 25 mm x 5
mm M.S. flat iron and painted
with stove enameled paint
including lettering, signs,
messages, border with
Add 3% cost
reflective tapeofof
MS sheet and
engineering 84.98
angle
grade iron towardssize,
of required the cost of
shade
fabrications, drilling,
and colour as per MORD holes,
nuts,
c) Machinery bolts etc.
specifications
Tractor with trolley hour 0.16 432.90 69.26
d) Overheads @ 10% on (a+b+c) 424.83
e) Contractor Profit @ 10% on (a+b+c+d) 353.44
Cost for 1.5 sqm board = (i+ii+iii+a+b+c+d+e) 5,026.57
Rate per sqm = (i+ii+iii+a+b+c+d+e) / 1.5 3,351.05
Rate with Reduction factor=1.125/1.21 3,115.64
Add Royalty per cum for Sand cum 0.12 150 12.10
Add Royalty per cum for 20mm &10mm Stone cum
grit 0.08 160 8.53
Add Royalty per cum for 40mm Stone ballast
cum 0.12 110 8.87
Add 1% Labour cess 31.45
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Say (Rs.) 3,176.59
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
### 1700 Providing and Fixing 'Logo' of PMGSY Project
Providing and fixing of typical PMGSY
informatory sign board with Logo as per
MORD specifications and drawing. Three
MS Plates of 1.6 mm thick, top and middle
plate duly welded with MS flat iron 25mm x
5m size on back on edges. The lower
plate will be welded with MS angle iron
frame of 25mm x 25mm x 5mm. The angle
iron frame of the lower most plate and flat
iron frame of middle plate will be welded to
2 nos. 75mm x 75 mm of 12 SWG sheet
tubes posts duly embedded in cement
concrete M-15 grade blocks of 450mm x
450mm x 600mm, 600mm below ground
level. The top most diamond plate will be
welded to middle plate by 47mm x 47mm
of 12 SWG steel plate tube. All M.S. will be
stove enameled on both sides. Lettering
and printing arrows, border etc. will be
painted with ready mixed synthetic enamel
paint of superior quality in required shade
and colour. All sections of framed posts
and steel
Unit = Eachtube will be painted with primer
and
Taking out coats
two of typical
put = one epoxy board
paint as per
drawing Clause 1701 and Annexure
(i) Excavation for foundations
1700.1
As per item No. 11.1 of Chapter 11 cum 0.252 100.000 25.20
(ii) Cement Concrete M15 grade
As per item No. 11.4 of Chapter 11 cum 0.252 4,122.78 1,038.94
(iii) Painting on MS Steel tubes with primer
and two coats
2x2.05x.30 of epoxy paint
= 1.23
1x1.10x188 = 0.21
As per item no. 10.7 of Chapter 10 sqm 1.80 81.10 145.98
iv) Printing new letters and figures of any
shade with synthetic
Logo Border 60x4x5 enamel
= 1200 paint
per cm height per letter
Figure 60x10 = 600 per cm height per letter
Middle plate words 28x5 = 140 per cm height per letter
Bottom plate border 150x2x5 = 1500 per cm height per letter
Bottom plate border 60x2x5 = 600 per cm height per letter
Words 101x2.5 = 252.5
Words 80x3 = 240.00
Total 4532.5 per cm height per letter
As per item No.10.1 of Chapter 10 per cm 4,532.50 0.73 3,308.73
a) Labour (for fixing at site) height
per litre
Mate day 0.03 250.00 7.50
Mazdoor (Unskilled) day 0.75 235.00 176.25
b) Material
2 nos. MS tubes 75mx75mm of kg 63.15 60.00 3,789.00
1 No. MS tube 47mm x 47mm of kg 4.47 60.00 268.20
Angle iron 50mm x 50mm x 5 mm f kg 2.12 40.00 84.80
1.6 mm thick MS sheet sqm 1.44 840.00 1,209.60
Add 3% cost of MS tube and 160.55
c) Machinery
Tractor with trolley hour 0.24 432.90 103.90
d) Overheads @ 10% on 579.98
e) Contractor Profit @ 10% on 637.98
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Cost for one Board= (i+ii+iii+iv+a+b+c+d+e) 11,536.60
Rate with Reduction factor=1.125/1.21 10,726.17
Add Royalty per cum for Sand cum 0.12 150 18.14
Add Royalty per cum for 20mm &10mm Stone cum
grit 0.08 160 12.90
Add Royalty per cum for 40mm Stone ballast
cum 0.12 110 13.31
Add 1% Labour cess 107.71
Say 10,878.23
Note: Printing and lettering for blank spaces on the
11.1 300 lower plate will
Excavation for be written as required and paid
Structures
Earthwork in fondation in ordinary soil
(loam clay,sand) including filling upto 1.50
m and lead upto 30 m and including
filling,watering and ramming of excavated
earth into the trnches or into the sapce
between the building/ structure and the
side of fondation trenches or plinth and
removel andUnit disposal
= cum of surface earth as
directed Asby Per
Engineer in charge
SOR Chapter upto
-4, Earth a
Work 100.00
distance of Add 30 1%
m Labour
from the
cess foundation 1.00
trenches including all T& P and material etc
complete as per UPPWD specification Say (Rs.) 101.00
11.2 300 & Sand Fillling in foundation trenches as per
SNo.1-251..
1200 drawing and technical specification Clause
305.3.9
I. Sand filling
Unit = cum
a) Labour
Mate day 0.01 250.00 2.50
Mazdoor (Unskilled) day 0.30 235.00 70.50
b) Material
Sand (assuming 20 per cent voids) cum 1.20 1,182.80 1,419.36
c) Overheads @ 10% on 149.24
d) Contractor Profit @ 10% on 164.16
Rate for per cum= a+b+c+d 1,805.76
Reduction factor=1.125/1.21 1,678.91
Add Royalty per cum for sand cum 1.2 65 78.00
Add 1% Labour cess 17.57
Say (Rs.) 1,774.47
11.4 800 & Providing concrete for plain/reinforced concrete
1200 in open foundations complete as per drawings
and technical specifications Clause 802, 803,
1202 & 1203 (PCC 1:3:6 concrete)

I. P.C.C grade M 10
(ii) Nominal mix 1:3.6 (Hand mixing)
Unit = cum
a) Material
Cement t 0.250 5,560.00 1,390.00
Coarse sand cum 0.48 1,147.80 550.94
40 mm aggregate cum 0.576 1,824.20 1,050.74
20 mm aggregate cum 0.288 1,972.40 568.05
10 mm aggregate cum 0.096 1,322.40 126.95
b) Labour
Mate day 0.09 250.00 22.50
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 2.00 235.00 470.00
Bhisti day 0.27 260.00 70.20
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
c) Formwork @ 3% on cost of 171.50
material (a) and labour (b)
d) Overheads @ 10% on 445.89
d) Contractor Profit @ 10% on 490.48
Rate for per cum = a+b+c+d 5,395.25
Reduction factor= 1.125/1.21 5,016.24
Add Royalty per cum for coarse sand cum 0.48 150 72.00
Add Royalty per cum for40mm cum 0.58 110 63.36
Add Royalty per cum for20mm & 10 mmcum 0.38 160 61.44
Add 1% Labour cess 52.13
Say (Rs.) 5,265.17
11.5 600 & Brick masonry work in cement mortar in
1200 foundation complete excluding pointing and
plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
Unit = cum
I. Brick masonry in 1:3 cement mortar
a) Material
Brick Nos. 500.00 6.19 3,095.00
Cement mortar 1:3 cum 0.24 4,283.09 1,027.94
(Rate as per Sub-analysis)
b) Labour
Mate day 0.09 250.00 22.50
Mason (1st Class) day 0.80 380.00 304.00
Mazdoor (Unskilled) day 1.60 235.00 376.00
Bhisti day 0.20 260.00 52.00
c) Overheads @ 10% on 482.54
d) Contractor Profit @ 10% on 536.00
Rate for per cum = a+b+c+d 5,895.98
Reduction factor=1.125/1.21 5,481.80
Add Royalty per cum for coarse cum 0.25 150 37.80
Add 1% Labour cess 55.20
Say (Rs.) 5,574.80
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
a) Material
Cement t 0.51 5,560.00 2,835.60
Sand cum 1.05 1,147.80 1,205.19
b) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 0.90 235.00 211.50
Bhisti day 0.08 260.00 20.80
Total material and labour = (a+b) 4,283.09
12.2 600 Pointing with cement mortar (1:3) on stone
masonary as per drawing and technical
specification Clauses 613.3 and 1204

Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1.3 (Rate as in item 11.5 cum 0.03 4,283.09 128.49
b) Labour
Mate day 0.04 250.00 10.00
Mason 1st Class day 0.50 380.00 190.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Bhisti day 0.20 260.00 52.00
c) Overheads @ 10% on 49.80
d) Contractor Profit @ 10% on 54.78
Rate for 10 sqm = a+b+c+d 602.57
Rate for per sqm = (a+b+c+d)/10 60.26
Reduction factor=1.125/1.21 56.02
Add Royalty per cum for finesand cum 0.03 150 0.47
Add 1% Labour cess 0.56
Say (Rs.) 57.06
12.3 600 Plastering with cement mortar (1:4), 15 mm
thick on stone masonary in substructure as
per technical specification Clauses 613.4 &
1204
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:4 (Rate as in item 11.5 II cum 0.24 3,560.29 854.47
b) Labour
Mate day 0.06 250.00 15.00
Mason 1st Class day 0.60 380.00 228.00
Mazdoor (Unskilled) day 0.60 235.00 141.00
Bhisti day 0.30 260.00 78.00
c) Overheads @ 10% on 131.65
d) Contractor Profit @ 10% on 144.81
Rate for 10 sqm = a+b+c+d 1,592.93
Rate for per sqm = (a+b+c+d)/10 159.29
Reduction factor=1.125/1.21 148.10
Add Royalty per cum for coarse cum 0.25 150 3.78
Add 1% Labour cess 1.52
Say (Rs.) 153.40
11.5 600 & Sub-Analysis 1200
II Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
a) Material
Cement t 0.38 5,560.00 2,112.80
Sand cum 1.05 1,147.80 1,205.19
b) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 0.90 235.00 211.50
Bhisti day 0.08 260.00 20.80
Total material and labour = (a+b) 3,560.29
11.5 III 600 & Sub-Analysis 1200
Cement mortar 1:5 (1 cement, 5 sand)
a) Material
Cement t 0.31 5,560.00 1,723.60
Sand cum 1.05 1,147.80 1,205.19
b) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 0.90 235.00 211.50
Bhisti day 0.08 260.00 20.80
Total material and labour = (a+b) 3,171.09
12.4 700 Stone masonry in cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
I. Coursed rubble masonry (1st sort)
(i) In 1:3 cement mortar
Unit = cum
a) Material
Stone for CR masonry 1st sort cum 1.10 1,479.20 1,627.12
Cement mortar (Rate as in item cum 0.30 4,283.09 1,284.93
b) Labour
Mate day 0.14 250.00 35.00
Mason (1st Class) day 1.50 380.00 570.00
Mazdoor (Unskilled) day 2.10 235.00 493.50
Bhisti day 0.08 260.00 20.80
Add for scaffolding @ 5 per 0.00
cent of cost of material (a)
and labour (b) (a+b)
c) Overheads @ 10% on 403.13
d) Contractor Profit @ 10% on 443.45
Rate per cum = a+b+c+d 4,877.93
Reduction factor=1.125/1.21 4,535.27
Add Royalty per cum for sand cum 0.32 150 47.25
Add Royalty per cum for stone cum 1.10 110 121.00
Add 1% Labour cess 47.04
Say (Rs.) 4,750.55
(ii) In 1:4 cement mortar
Unit = cum
a) Material
Stone for CR masonry 1st sor cum 1.10 1,479.20 1,627.12

Cement mortar (Rate as in item cum 0.30 3,560.29 1,068.09


b) Labour
Mate day 0.14 250.00 35.00
Mason (1st Class) day 1.50 380.00 570.00
Mazdoor (Unskilled) day 2.10 235.00 493.50
Bhisti day 0.08 260.00 20.80
Add for scaffolding @ 5 per 190.73
cent of cost of material (a)
and labour (b) 5% on (a+b)
c) Overheads @ 10% on 400.52
d) Contractor Profit @ 10% on 440.58
Rate per cum = a+b+c+d 4,846.33
Reduction factor=1.125/1.21 4,505.89
Add Royalty per cum for sand cum 0.315 150 47.25
Add Royalty per cum for stone cum 1.1 110 121.00
Add 1% Labour cess 46.74
Say (Rs.) 4,720.88
(iii) In cement mortar (1:5)
Unit = cum
a) Material
Stone for CR masonry 1st so cum 0.60 1,479.20 887.52
Spalls/blasted rubbles cum 0.50 1,429.20 714.60
Cement mortar (Rate same cum 0.33 3,171.09 1,046.46
as in item 12.1 III)
b) Labour
Mate day 0.14 250.00 35.00
Mason 1st Class day 1.30 380.00 494.00
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Mazdoor (Unskilled) day 2.00 235.00 470.00
Bhisti day 0.08 260.00 20.80
Add for scaffolding @ 5 per 183.42
cent of cost of material (a)
c)
and labour (b) 5% on (a+b)
Overheads @ 10% on 385.18
d) Contractor Profit @ 10% on 423.70
Rate per cum = a+b+c+d 4,660.68
Reduction factor=1.125/1.21 4,333.27
Add Royalty per cum for sand cum 0.35 150 51.98
Add Royalty per cum for stone cum 1.1 110 121.00
Add 1% Labour cess 45.06
Say (Rs.) 4,551.31
Hand Packed stone filling in back of walls
including cost of all materials, royality, T&P etc
complete as per direction of Engineer-in-
Charge
Unit = Cum
Taking output = 10 Cum
Resource
a) Labour
Bhisti day 0.40 260.00 104.00
Mate day 0.28 250.00 70.00
Beldar/Mazdor day 10.00 235.00 2,350.00
b) Material
Loose stone Cum 12.00 1,429.20 17,150.40
c) Overheads @ 10% on 1,967.44
d) Contractor Profit @ 10% on 2,164.18
Rate per cum =(a+b+c+d)/10 2,380.60
Reduction factor=1.125/1.21 2,213.37
Add Royalty per cum for stone cum 12 110 132.00
Add 1% Labour cess 23.45
Say (Rs.) 2,368.82
12.5 800 Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204
For height upto 5 m
Unit = cum
I. P.C.C grade M 15
Unit = cum
a) Material
Cement t 0.275 5,560.00 1,529.00
Coarse sand cum 0.48 1,147.80 550.94
40 mm aggregate cum 0.48 1,824.20 875.62
20 mm aggregate cum 0.24 1,972.40 473.38
10 mm aggregate cum 0.08 1,322.40 105.79
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.10 380.00 38.00
Mazdoor (Unskilled) day 1.63 235.00 383.05
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum c hour 0.40 150.00 60.00
d) Formwork @ 3% on cost of 410.60
material, labour and
machinery (a+b+c)
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
e) Overheads @ 10% on 451.66
f) Contractor Profit @ 10% on 496.82
Rate for 1 cum = a+b+c+d+e+f 5,465.06
Reduction factor=1.125/1.21 5,081.15
Add Royalty per cum for Sand cum 0.48 150 72.00
Add Royalty per cum for 20mm cum 0.32 160 51.20
&10mm Stone
Add Royalty grit
per cum for 40mm cum 0.48 110 52.80
Stone ballast
Add 1% Labour cess 52.57
Say (Rs.) 5,309.72
IV. R.C.C. grade M 25
Unit = cum
a) Material
Cement t 0.404 5,560.00 2,246.24
Coarse sand cum 0.45 1,147.80 516.51
20 mm aggregate cum 0.54 1,972.40 1,065.10
10 mm aggregate cum 0.36 1,322.40 476.06
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.12 380.00 45.60
Mazdoor (Unskilled) day 1.73 235.00 406.55
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capac hour 0.40 277.50 111.00
d) Formwork @ 3% on (a+b+c) 148.72
e) Overheads @ 10% on 510.60
f) Contractor Profit @ 10% on 561.66
Rate for 1 cum = a+b+c+d+e+f 6,178.23
Reduction factor=1.125/1.21 5,744.23
Add Royalty per cum for Sand cum 0.45 150 67.50
Add Royalty per cum for cum 0.90 160 144.00
20mm &10mm Stone grit
Add 1% Labour cess 59.56
Say (Rs.) 6,015.28
13.1 800 Providing and laying reinforced cement
concrete in superstructure as per drawing
and technical specifications Clauses 800,
1205.4 and 1205.5 (With Recron Fibre @0.20
%)
III. R.C.C. Grade M 30
Unit =cum
a) Material
Cement t 0.43 5,560.00 2,390.80
Sand cum 0.45 1,147.80 516.51
Recron Fibre @ 100gm per 50 Kg cem Kg 0.86 700.00 602.00
20 mm aggregate cum 0.54 1,972.40 1,065.10
10 mm aggregate cum 0.36 1,322.40 476.06
b) Labour
Mate day 0.08 250.00 20.00
Mason (1st Class) day 0.12 380.00 45.60
Mazdoor (Unskilled) day 1.73 235.00 406.55
Bhisti day 0.27 260.00 70.20
c) Machinery
Concrete mixer 0.4/0.28 cum capac hour 0.40 277.50 111.00
d) For formwork 3% of (a+b+c) 171.11
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
e) Overheads @ 10% on 587.49
f) Contractor Profit @ 10% on 646.24
Rate for 1 cum = a+b+c+d+e+f 7,108.67
Reduction factor=1.125/1.21 6,609.30
Add Royalty per cum for Sand cum 0.45 150 67.50
Add Royalty per cum for 20mm cum 0.90 160 144.00
&10mm Stone grit
Add 1% Labour cess 68.21
Say (Rs.) 6,889.01
Cement Plum Concrete with 40% plum & 60% 1:3:6 Cement Concrete including Su
Unit =cum
Taking output 1 cum
a) Material
Stone for RR Masonry cum 0.4 1479.2 591.68
b) Sub item M-10 (136)
PCC grade M-10 (1:3:6) cum 0.6 4458.88 2675.33
c) Overheads @ 10% on 326.70
d) Contractor Profit @ 10% on 359.37
Rate for 1 cum = a+b+c+d 3,953.08
Reduction factor=1.125/1.21 3,675.38
Add Royalty per cum for stone cum 0.40 110 44.00
Add Royalty per cum for 40mm St cum 0.35 110 38.50
Add Royalty per cum for 20mm & cum 0.23 160 36.80
Add Royalty per cum for coarse cum 0.29 150 43.50
Add 1% Labour cess 38.38
Say (Rs.) 3,876.57
13.2 1000 Supplying, fitting, and placing HYSD bar
reinforcement in superstructure complete
as per drawing and technical specifications
Clauses 1002, 1010 and 1202
Unit = t
a) Material
HYSD bars including 5 per cent for lap t 1.05 41,000.00 43,050.00
Binding wire kg 8.00 57.75 462.00
b) Labour for cutting, bending, tying and
placing
Mate in position day 0.44 250.00 110.00
Blacksmith day 3.00 350.00 1,050.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
c) Overheads @ 10% on 4,655.20
d) Contractor Profit @ 10% on 5,120.72
Rate for per Tonne = a+b+c+d 56,327.92
Reduction factor=1.125/1.21 52,371.00
Add 1% Labour cess 523.71
Say (Rs.) 52,894.71
14.5 1300 Providing and laying pitching on slopes laid
over prepared filter media as per drawing
and technical specifications Clause 1302
I. Stone/Boulder
Unit = cum
a) Material
Stone boulder (25 kg minimum) cum 1.00 1,479.20 1,479.20
Stone spalls of minimum 25 mm si cum 0.20 1,429.20 285.84
b) Labour
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Mate day 0.04 250.00 10.00
Mason 1st Class day 0.35 380.00 133.00
Mazdoor (Unskilled) day 0.75 235.00 176.25
c) Overheads @ 10% on 208.43
d) Contractor Profit @ 10% on 229.27
Rate for 1 cum = a+b+c+d 2,521.99
Rate for 1 cum = (a+b+c+d)/1 2,521.99
Reduction factor=1.125/1.21 2,344.83
Add Royalty per cum for stone cum 1.20 110 132.00
Add 1% Labour cess 24.77
Say (Rs.) 2,501.59
14.5 1300 Providing and laying boulder apron for bed
protection with stone boulders of minimum size
and weight as per Table 1300.1, no fragment
weighing less than 25 kg laid dry complete as
per drawing and technical specifications Clause
1301

I. Stone/Boulder
Unit = cum
a) Material
Stone boulder (25 kg minimum) cum 1 1479.2 1479.2
Stone spalls of minimum 25 mm size cum 0.2 1429.2 285.84
b) Labour
Mate day 0.04 250 10
Mason 1st Class day 0.35 380 133
Mazdoor (Unskilled) day 0.75 235 176.25
c) Overheads @ 10% on 208.43
d) Contractor Profit @ 10% on 229.27
Rate for 1 cum = a+b+c+d 2,521.99
Rate for 1 cum = (a+b+c+d)/1 2,521.99
Reduction factor=1.125/1.21 2,344.83
Add Royalty per cum for stone boucum 1.2 110 132.00
Add 1% Labour cess 24.77
Say (Rs.) 2,501.59
14.6 1300 Providing and laying filter material
underneath pitching in slopes complete as
per drawing and technical specifications
Clause 1302
Unit = cum
a) Material
Graded stone aggregate of required siz cum 1.20 1,429.20 1,715.04
b) Labour
Mate day 0.05 250.00 12.50
Mazdoor (Skilled) day 0.25 250.00 62.50
Mazdoor (Unskilled) day 1.02 235.00 239.70
c) Overheads @ 10% on 202.97
d) Contractor Profit @ 10% on 223.27
Rate for 1 cumsqm = a+b+c+d 2,455.99
Rate for 1 cum = (a+b+c+d)/1 2,455.99
Reduction factor=1.125/1.21 2,283.46
Add Royalty per cum for stone boulder & spalls
cum 1.20 110 132.00
Add 1% Labour cess 24.15
Say (Rs.) 2,439.61
Providing and Fixing Citizen information Board of PMGSY Project
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Providing and fixing of typical PMGSY Citizen information
board (Nagrik Suchana Board) as per standard drawing of
NRRDA with two 18SWG MS sheets of size 900x750mm
duly welded with 4 nos, MS Flat iron frame of size
1000x75x5mm & 2 nos. MS flat iron frame on back side of
board. The flat iron frame will be welded with two nos
75x75mm of 12SWG horizontal sheets in square are tube
posts of 1000mm length & two nos 75x75mm of 12 SWG
verticle steel tubes in square are round post of 3050mm
length dully embed nominal hand mixed ass per IRC:67
upto 600mmx600mmx750mm blocks 600mm below ground
level. all M:S will be stove enabled on both sides lettering &
Painting and arrows, border etc will be painted with ready
mixed synthetic enamled paint of superior quality section of
framed posts and steel tube will be painted with primer and
two coats of epoxy paint as per drawing & information on
the road shall also be mentioned as per direction of E/I
including all labour, material & T&P etc.
1 Supply of 75x5mm MS Iron plate. Kg 22.53 60.00 1,351.80
2 Supply of 75x5mm dia steel tube Rm 8.50 256.10 2,176.85
3 Supply of 18 guage iron plate Kg 14.11 105.96 1,495.10
4 Lettering/painting by superior paint Sqm 4.17 87.00 362.79
5 Fixing of Board in CC 1:2:4 as per IRC Cum 0.54 4,122.78 2,226.30
6 Labour rate for cutting/welding/primer 0.00
Add 3% cost of MS tube and angle 150.71
c) Overheads @ 10 % on (a+b) 776.35
d) Contractor Profit @ 10 % on (a+b+c) 853.99
Rate for 1 cumsqm = a+b+c+d 9,393.89
Rate for 1 cum = (a+b+c+d)/1 9,393.89
Reduction factor=1.125/1.21 8,733.99
Add Royalty per cum for Sand cum 0.26 150 38.88
Add Royalty per cum for 20mm & cum 0.17 160 27.65
Add Royalty per cum for 40mm St cum 0.26 110 28.51
Add 1% Labour cess 88.29
Say (Rs.) 8,917.32
White washing two coats on parapet
walls and tree trunks including
preparation of surface by cleaning scraping
etc. as per technical specifications Clause
1915
Unit = sqm
Taking output = 9 sqm
a) Labour
Mate day 0.01 250.00 2.50
Mazdoor (Unskilled) day 0.143 235.00 33.57
White washer day 0.143 245.00 35.00
b) Materials
Lime quintel 0.045 667.00 30.02
Fevicol adhesive kg 0.10 215.30 21.53
Indigo kg 0.013 225.00 2.93
c) Overheads @ 10% on 12.55
d) Contractor Profit @ 10% on 13.81
Cost for 9 sqm = a+b+c+d 151.91
Rate per sqm = a+b+c+d/9 16.88
Reduction factor=1.125/1.21 15.69
Add 1% Labour cess 0.16
Say (Rs.) 15.85
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
14.2 1300 Providing and laying of boulder apron laid
in wire crates with 4 mm dia GI wire
conforming to IS:280 and IS:4826 in 100 mm x
100 mm mesh (woven diagonally) including 10
per cent extra for laps and joints laid with stone
boulders weighing not less than 25 kg each as
per drawing and technical specifications Clause
1301
Unit = cum
Taking ouput = 3 m x 1.5 m x 1.25 m = 5.63 cum
a) Material
Stone boulder (25 kg minimum) cum 5.63 1,479.20 8,327.90
Stone spalls cum 1.13 1,429.20 1,615.00
GI wires 4 mm dia @ 32 kg/10 sqm kg 64.00 440.00 28,160.00
b) Labour
Mate day 0.18 250.00 45.00
Mazdoor (Skilled) day 1.50 250.00 375.00
Mazdoor (Unskilled) day 3.00 235.00 705.00
Add for labour for weaving the wire 22.50
c) Overheads @ 10% on 3,925.04
d) Contractor Profit @ 10% on 4,317.54
Cost for 5.63 cum = a+b+c+d 47,492.97
Rate per cum = (a+b+c+d)/5.63 8,435.70
Reduction factor=1.125/1.21 7,843.11
Add Royalty per cum for stone cum 6.76 110 132.08
Add 1% Labour cess 79.75
Say (Rs.) 8,054.94
Note: 1 Nominal cost of trimming for preparation
of bed has been included in the cost of
2 labour
The analysis will by & large hold good for gabions
4.18 412 Brick Soling
Laying brick soling layer on prepared sub-
grade with brick on end edging according
to lines, graded and cross-section shown
on the drawing filling joints with sand and
earth, spreading 25 mm thick layer of earth
over brick soling, watering and rolliing the
same with three wheel road roller 80-100
kN as per Technical Specification Clause
412
Unit = sqm
Taking ouput = 150 sqm
(a) Labour
Mate day 0.52 250.00 130.00
Mazdoor (Unskilled) day 10.00 235.00 2,350.00
Mason 1st Class day 3.00 380.00 1,140.00
(b) Machinery
Three wheel 80-100 kN static roller hour 1.00 549.45 549.45
Water tanker hour 1.00 370.00 370.00
(c) Material
Brick 1st Class No. 8,160.00 6.19 50,510.40
Brick 1st Class on edging No. 1,100.00 6.19 6,809.00
Fine Sand cum 5.66 1,182.80 6,694.65
Water kl 6.00 50.00 300.00
(d) Overheads @ 10% on (a+b+c) 6,885.35
(e) Contractor’s profit @ 10% on (a+b+c+d) 7,573.88
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Cost for 150 sqm = a+b+c+d+e 83,312.73
Rate per sqm = (a+b+c+d+e)/150 555.42
Reduction factor=1.125/1.21 516.40
Add Royalty per cum for fin cum 5.66 65 2.45
Add 1% Labour cess 5.19
Say (Rs.) 524.04
2.5 202 Dismantling of Structures
Dismantling of existing structures like
culverts, bridges, retaining walls and other
structure comprising of masonry, cement
concrete, wood work, steel work, including
T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the
serviceable material with all lifts and lead of
1000 m as per Technical Specification
Clause 202.
Unit = cum
Taking output = 1.25 cum
(I) By Manual Means
(A) Lime Concrete
a) Labour
Mate day 0.04 250.00 10.00
Mazdoor (Unskilled) day 1.00 235.00 235.00
b) Machinery
Tractor with trolley hour 0.27 432.90 116.88
c) Overheads @ 10 % on (a+b) 36.19
d) Contractor’s profit @ 10 % on (a+b+c) 39.81
Cost for 1.25 cum = a+b+c+d 437.88
Rate per cum = (a+b+c+d)/1.25 350.30
Reduction factor=1.125/1.21 325.69
Add 1% Labour cess 3.26
Say (Rs.) 328.95
(B) Cement Concrete
a) Labour
Mate day 0.05 250.00 12.50
Mazdoor (Unskilled) day 1.25 235.00 293.75
b) Machinery
Tractor with trolley hour 0.27 432.90 116.88
c) Overheads @ 10 % on (a+b) 42.31
d) Contractors profit @ 10 % on (a+b+c) 46.54
Cost for 1.25 cum = a+b+c+d 511.99
Rate per cum = (a+b+c+d)/1.25 409.59
Reduction factor=1.125/1.21 380.82
Add 1% Labour cess 3.81
Say (Rs.) 384.63
(C) Reinforced Cement Concrete
a) Labour
Mate day 0.15 250.00 37.50
Blacksmith day 0.25 350.00 87.50
Mazdoor (Unskilled) day 3.50 235.00 822.50
b) Machinery
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Tractor with trolley hour 0.27 432.90 116.88
c) Overheads @ 10 % on (a+b) 102.69
d) Contractor's profit @ 10% on (a+b+c) 112.96
Cost for 1.25 cum = a+b+c+d 1,242.53
Rate per cum = (a+b+c+d)/1.25 994.02
Reduction factor=1.125/1.21 924.19
Add 1% Labour cess 9.24
Say (Rs.) 933.44
(II) By Mechanical Means
(A) Cement Concrete
a) Labour
Mate day 0.02 250.00 5.00
Mazdoor (Unskilled) day 0.50 235.00 117.50
b) Machinery
Air compressor 210 cfm hour 0.83 381.10 316.31
with 2 leads of pneumatic
breaker trolleycum per hour
@1.5
Tractor with 0.27 432.90 116.88
c) hour
Overheads @ 10 % on (a+b) 55.57
d) Contractor's profit @ 10% on (a+b+c) 61.13
Cost for 1.25 cum = a+b+c+d 672.39
Rate per cum = (a+b+c+d)/1.25 537.91
Reduction factor=1.125/1.21 500.13
Add 1% Labour cess 5.00
Say (Rs.) 505.13
(B) Reinforced Cement Concrete
a) Labour
Mate day 0.05 250 12.5
Mazdoor (Unskilled) day 0.91 235 213.85
Blacksmith day 0.25 350 87.5
b) Machinery
Air compressor 170-210 cfm w hour 1.25 381.1 476.375
Tractor with trolley hour 0.27 432.9 116.88
c) Overheads @ 10 % on (a+b) 90.71
d) Contractor's profit @ 10% on (a+b+c) 99.78
Cost for 1.25 cum = a+b+c+d 997.82
Rate per cum = (a+b+c+d)/1.25 798.26
Reduction factor=1.125/1.21 742.18
Add 1% Labour cess 7.42
Say (Rs.) 749.60
12.9 600 Providing weepholes in brick
masonry/stone masonry, plain/reinforced
concrete abutment, wing wall, return wall
with75 mm dia pvc pipe extending through the
full width of the structures with slope of
1(V):20(H) towards drawing face complete as
per drawing and technical specification Clauses
Unit = Nos
614, 709, 1204.3.7
Taking output = 30 Nos
a) Material
AC pipe 100 mm dia including wastage @ m 31.50 100.00 3,150.00
5
MSper cent. Average length of weep hole
clamps Nos. 30.00 16.00 0.00
Cement mortar 1:3 (For rate refer to item 11 cum 0.05 0.00 0.00
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
b) Labour
Mate day 0.03 250.00 7.50
Mason 1st Class day 0.50 380.00 190.00
Mazdoor (Unskilled) day 0.25 235.00 58.75
c) Overheads @ 10% on (a+b) 340.63
d) Contractor’s profit @ 10% on (a+b+c) 374.69
Cost for 30 Nos = (a+b+c+d) 4,121.56
Rate per No = (a+b+c+d)/30 137.39
Reduction factor=1.125/1.21 127.73
Add Royalty per cum for coarse cum 0.05 150 0.00
Add 1% Labour cess 1.28
Say (Rs.) 129.01
12.10 1200 Backfilling behind abutment, wing wall and
return wall complete as per drawings &
technical specification Clause 1204.3.8
Unit = cum
Taking output = 10 cum
I) Granular material
a) Material
Granular material cum 12.00 1,429.20 17,150.40
b) Labour
Mate day 0.28 250.00 70.00
Mazdoor (Unskilled) day 10.00 235.00 2,350.00
Bhisti day 0.40 260.00 104.00
c) Overheads @ 10% on (a+b) 1,967.44
d) Contractor’s profit @ 10% on (a+b+c) 2,164.18
Cost for 10 cum of granular backfill = a+b+c+d 23,806.02
Rate per cum = (a+b+c+d)/10 2,380.60
Reduction factor=1.125/1.21 2,213.37
Add Royalty per cum for Granular cum 12 110 132.00
Add 1% Labour cess 23.45
Say (Rs.) 2,368.82
### 1200 Providing and laying filter media with
granular crushed aggregates as per
specification to a thickness of not less than 600
mm with smaller size towards the soil and
bigger size towards the wall and providing over
the entire surface behind abutment, wing wall,
return wall to the full height, compacted to firm
condition complete as per drawing and
technical specification Clause 1204.3.8
Unit = cum
Taking output = 10 cum
a) Material
Filter media as per specification cum 12.00 1,429.20 17,150.40
b) Labour
Mate day 0.40 250.00 100.00
Mazdoor (Unskilled) day 9.00 235.00 2,115.00
Mazdoor (Skilled) day 1.00 250.00 250.00
Bhisti day 0.50 260.00 130.00
c) Overheads @ 10% on (a+b) 1,974.54
d) Contractor’s profit @ 10% on (a+b+c) 2,171.99
Cost for 10 cum of filter media = a+b+c+d 23,891.93
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Rate per cum = (a+b+c+d)/10 2,389.19
Reduction factor=1.125/1.21 2,221.36
Add Royalty per cum for Granular cum 12.00 110 132.00
Add 1% Labour cess 23.53
Say (Rs.) 2,376.89
9.20 1100 Laying Reinforced Cement Concrement
Pipe NP3
Laying on Firstcement
reinforced Class Bedding in Single
concrement pipe for
culverts on first class bedding of granular
material in single row including fixing collar with
cement motar 1:2 but excluding
excavation,protection works,back
filling,concrete and masonary works in head
Unit =and
walls metre
parapets
Taking output = 7.5 metre
100 mm dia
a) Labour
Mate Day 0.032 250.00 8.00
Mason Day 0.088 380.00 33.44
Mazdoor Day 0.720 235.00 169.20
b) Material
coarse Sand at site cum 0.020 1147.80 22.96
Cement at site tonne 0.010 5560.00 55.60
RCC pipe including collar at site mtr 7.500 224.25 1681.88
c) Overheads @ 10% on (a+b) 197.11
d) Contractor’s profit @ 10% on (a+b+c) 216.82
Cost for 7.5 RM = a+b+c+d 2,385.00
Rate per cum = (a+b+c+d)/7.5 318.00
Reduction factor=1.125/1.21 295.66
Add Royalty per cum for coarse cum 0.02 150 0.40
Add 1% Labour cess 2.96
Say (Rs.) 299.02
9.20 1100 Laying Reinforced Cement Concrement
Pipe NP3
Laying on Firstcement
reinforced Class Bedding in Single
concrement pipe for
culverts on first class bedding of granular
material in single row including fixing collar with
cement motar 1:2 but excluding
excavation,protection works,back
filling,concrete and masonary works in head
Unit =and
walls metre
parapets
Taking output = 7.5 metre
350 mm dia
a) Labour
Mate Day 0.032 250.00 8.00
Mason Day 0.088 380.00 33.44
Mazdoor Day 0.720 235.00 169.20
b) Material
coarse Sand at site cum 0.020 1147.80 22.96
Cement at site tonne 0.010 5560.00 55.60
RCC pipe including collar at site mtr 7.500 1000.50 7503.75
c) Overheads @ 10% on (a+b) 779.29
d) Contractor’s profit @ 10% on (a+b+c) 857.22
Cost for 7.5 RM = a+b+c+d 9,429.46
Rate per cum = (a+b+c+d)/7.5 1,257.26
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Reduction factor=1.125/1.21 1,168.94
Add Royalty per cum for coarse cum 0.02 150 0.40
Add 1% Labour cess 11.69
Say (Rs.) 1,181.04
9.50 1100 Laying Reinforced Cement Concrement
Pipe NP3 on First Class Bedding in Single
Row
Laying reinforced cement concrement pipe for
culverts on first class bedding of granular
material in single row including fixing collar with
cement motar 1:2 but excluding
excavation,protection works,back
filling,concrete and masonary works in head
Unit =and
walls metre
parapets
Taking output =7.5 metre
600 mm dia
a) Labour
Mate Day 0.040 250.00 10.00
Mason Day 0.120 380.00 45.60
Mazdoor Day 0.960 235.00 225.60
b) Material
coarse Sand at site cum 0.040 1147.80 45.91
Cement at site tonne 0.030 5560.00 166.80
RCC pipe including collar at site mtr 7.500 1794.00 13455.00
c) Overheads @ 10% on (a+b) 1,394.89
d) Contractor’s profit @ 10% on (a+b+c) 1,534.38
Cost for 7.5 RM = a+b+c+d 16,878.18
Rate per cum = (a+b+c+d)/7.5 2,250.42
Reduction factor=1.125/1.21 2,092.34
Add Royalty per cum for coarse cum 0.04 150 0.80
Add 1% Labour cess 20.93
Say (Rs.) 2,114.07
9.20 1100 Laying Reinforced Cement Concrement
Pipe NP3 on First Class Bedding in Single
Row
Laying reinforced cement concrement pipe for
culverts on first class bedding of granular
material in single row including fixing collar with
cement motar 1:2 but excluding
excavation,protection works,back
filling,concrete and masonary works in head
walls
Unit =and parapets
metre
Taking output = 7.5 metre
900 mm dia
a) Labour
Mate Day 0.050 250.00 12.50
Mason Day 0.150 380.00 57.00
Mazdoor Day 1.200 235.00 282.00
b) Material
coarse Sand at site cum 0.024 1147.80 27.55
Cement at site tonne 0.018 5560.00 100.08
RCC pipe including collar at site mtr 7.500 3892.75 29195.63
c) Overheads @ 10% on (a+b) 2,967.48
d) Contractor’s profit @ 10% on (a+b+c) 3,264.22
Cost for 7.5 RM = a+b+c+d 35,906.45
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Rate per cum = (a+b+c+d)/7.5 4,787.53
Reduction factor=1.125/1.21 4,451.21
Add Royalty per cum for coarse cum 0.04 150 0.80
Add 1% Labour cess 44.52
Say (Rs.) 4,496.53
9.30 1100 Laying Reinforced Cement Concrement
Pipe NP3 on First Class Bedding in Single
Row
Laying reinforced cement concrement pipe for
culverts on first class bedding of granular
material in single row including fixing collar with
cement motar 1:2 but excluding
excavation,protection works,back
filling,concrete and masonary works in head
Unit
walls=andmetre
parapets
Taking output = 7.5 metre
1000 mm dia
a) Labour
Mate Day 0.090 250.00 22.50
Mason Day 0.250 380.00 95.00
Mazdoor Day 2.000 235.00 470.00
b) Material
coarse Sand at site cum 0.040 1147.80 45.91
Cement at site tonne 0.030 5560.00 166.80
RCC pipe including collar at site mtr 7.500 4600.00 34500.00
c) Overheads @ 10% on (a+b) 3530.02
d) Contractor’s profit @ 10% on (a+b+c) 3883.02
Cost for 7.5 RM = a+b+c+d 42713.26
Rate per cum = (a+b+c+d)/102.5 5695.10
Reduction factor=1.125/1.21 5295.03
Add Royalty per cum for coarse cum 0.04 150 0.80
Add 1% Labour cess 52.96
Say (Rs.) 5348.79
9.30 1100 Laying Reinforced Cement Concrement
Pipe NP3 on First Class Bedding in Single
Row
Laying reinforced cement concrement pipe for
culverts on first class bedding of granular
material in single row including fixing collar with
cement motar 1:2 but excluding
excavation,protection works,back
filling,concrete and masonary works in head
Unit =and
walls metre
parapets
Taking output = 7.5 metre
1200 mm dia
a) Labour
Mate Day 0.090 250.00 22.50
Mason Day 0.250 380.00 95.00
Mazdoor Day 2.000 235.00 470.00
b) Material
coarse Sand at site cum 0.040 1147.80 45.91
Cement at site tonne 0.030 5560.00 166.80
RCC pipe including collar at site mtr 7.500 6900.00 51750.00
c) Overheads @ 10% on (a+b) 5255.02
d) Contractor’s profit @ 10% on (a+b+c) 5780.52
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Cost for 7.5 RM = a+b+c+d 63585.76
Rate per cum = (a+b+c+d)/7.5 8478.10
Reduction factor=1.125/1.21 7882.53
Add Royalty per cum for coarse cum 0.04 150 0.80
Add 1% Labour cess 78.83
Say (Rs.) 7962.17
9.4
Cement Plum Concrete with 40% plum &
60% Unit
1:3:6=cum
Cement Concrete including
Taking output 1 cum
Material
a) Stone for RR Masonry cum 0.40 1,479.20 591.68
b) Sub item M-10 (1:3:6)
PCC grade M-10 (1:3:6) cum 0.60 4,458.88 2,675.33
c) Overheads @ 10% on 326.70
d) Contractor Profit @ 10% on 359.37
Rate for 1 cum = a+b 3,953.08
Reduction factor=1.125/1.21 3,675.38
Add Royalty per cum for stone cum 0.40 110.00 44.00
Add Royalty per cum for 40mm Stcum 0.58 110.00 63.36
Add Royalty per cum for 20mm & cum 0.38 160.00 61.44
Add Royalty per cum for coarse cum 0.48 150.00 72.00
Add 1% Labour cess 39.16
Say (Rs.) 3955.35
Analysis of Hard Rock cutting
EARTHWORK, EROSION CONTROL AND DRAINAGE
Sr. Reference Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
(ii) Excavation in Hard Rock (blasting prohibited)
Excavation for roadway in hard rock
(blasting prohibited) with rock breakers
including breaking rock, loading in tippers
and disposal with a lift upto 1.5 m and
lead upto 1000 metres, trimming bottom
and side slopes in accordance with
requirements of lines, grades and cross-
sections as per Technical Specification
Clause 302.3.5

(B) Mechanical Means


Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.4 250 100
Mazdoor (Unskilled) day 10 235 2350
b) Machinery
Hydraulic excavator 0.9 cum with hour 6 1596 9576
Tipper 5.5 cum capacity tipper, 1 thour 6.5 380 2470
Credit for excavated rock found s cum 18 -0.5 -9
c) Overheads @ 10% on (a+b) 1448.7
d) Contractor’s profit @ 10% on (a+b+c) 1593.57
Cost for 36 cum = a+b+c+d 17529.27
Rate per cum = (a+b+c+d)/36 486.9241667
Reduction factor=1.125/1.21 452.71875
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Add 1% Labour cess 4.53
Say (Rs.) 457.25
4.1 401 Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by
providing well graded
(i) For GradingIII material, spreading
Material
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 250.00 100.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
b) Machinery
Motor Grader 110 HP @ 50 cum p hour 6.00 2,858.25 0.00
Three wheel 80-100 kN static ro hour 30.00 549.45 0.00
Tractor with Rotavator 25 cum pe hour 12.00 432.90 0.00
Water tanker 6 kl capacity hour 5.00 370.00 0.00
c) Material
Well graded granular sub-base material as per Table 400.1
53 mm to 9.5 mm @ 50 per cent cum 180.00 1,814.20 326,556.00
9.5 mm to 2.36 mm @ 20 per cen cum 72.00 1,579.20 284,256.00
2.36 mm below @ 30 per cent cum 108.00 1,489.20 107,222.40
Water kl 30.00 50.00 5,400.00
d) Overheads @ 10% on 72,591.44
e) Contractor Profit @ 10% on 79,840.58
Rate for 300 cum = a+b+c+d+e 878,346.42
Rate for per cum = (a+b+c+d+e)/300 2,927.82
Rate with Reduction factor=1.125/1.21 2,722.15
Add Royalty per cum for 53 mm t cum 360 110 132.00
Add 1% Labour cess 28.54
Say (Rs.) 2,882.69
4.1 401 Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by
providing well graded
(i) For GradingIII material, spreading
Material
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.40 250.00 100.00
Mazdoor (Skilled) day 2.00 250.00 500.00
Mazdoor (Unskilled) day 8.00 235.00 1,880.00
b) Machinery
Motor Grader 110 HP @ 50 cum p hour 6.00 2,858.25 0.00
Three wheel 80-100 kN static ro hour 30.00 549.45 0.00
Tractor with Rotavator 25 cum pe hour 12.00 432.90 0.00
Water tanker 6 kl capacity hour 5.00 370.00 0.00
c) Material
Well graded granular sub-base material as per Table 400.1
53 mm to 9.5 mm @ 50 per cent cum 180.00 1,814.20 326,556.00
9.5 mm to 2.36 mm @ 20 per cen cum 72.00 1,579.20 284,256.00
2.36 mm below @ 30 per cent cum 108.00 1,489.20 107,222.40
Water kl 30.00 50.00 5,400.00
d) Overheads @ 10% on 72,591.44
e) Contractor Profit @ 10% on 79,840.58
Sr. Reference
Description
to Unit Quantity Rate Amount (Rs.)
No. MORD Specifications (Rs.)
Rate for 300 cum = a+b+c+d+e 878,346.42
Rate for per cum = (a+b+c+d+e)/300 2,927.82
Rate with Reduction factor=1.125/1.21 2,722.15
Add Royalty per cum for 53 mm t cum 360 110 132.00
Add 1% Labour cess 28.54
Say (Rs.) 2,882.69
RCPLWEA (ADDITIONAL)
PACKAGE NO. :- UP67146 Format F-7
COST ESTIMATE FOR CONSTRUCTION OF LEVEL PILLAR
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
DISTRICT:- SONEBHADRA
SI. Length Width Depth Amount
No Description of Item Nos Unit Quantity Rate (Rs.)
(m) (m) (m) (Rs.)
.
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal of 1x1 0.30 0.30 0.30 Cum 0.027 101 2.73
surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including all T& P and
material etc complete as per UPPWD
specification SNo.1-251..

2 Providing concrete for plain/reinforced concrete in 5265.2


open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 & 1x1 0.30 0.30 0.20 Cum 0.018 94.77
1203 (PCC 1:3:6 concrete)

3 Plain/reinforced cement concrete in substructure 6015.3


complete as per drawings and technical
specification Clauses 802, 804, 805, 806, 807, 1x1 0.15 0.15 0.90 Cum 0.020 121.81
1202 and 1204 R.C.C. grade M 25

4 Supplying, fitting, and placing HYSD bar 5289.5


reinforcement in superstructure complete as per
drawing and technical specifications Clauses 1002, 0.02 @1.5% 0.024 124.57
1010 and 1202

Total 343.88
Say (Rs.) 343.90
CONSTRUCTION OF KC- DRAIN
PACKAGE NO. :- UP67146
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

Sl.
Description of Item Unit No L (m) B (m) H (m) Qty.
Rate Amount (Rs.)
No. (Rs.)
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and lead
upto 30 m and including filling,watering and
ramming of excavated earth into the trnches or into
the sapce between the building/ structure and the
side of fondation trenches or plinth and removel
and disposal of surface earth as directed by
Engineer in charge upto a distance of 30 m from
the foundation trenches including all T& P and
material etc complete as per UPPWD specification
SNo.1-251..

Cum 1 1.00 1.10 0.50 0.55


Total 0.55 101.00 55.55
2 Construction of granular sub-base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB Grade -
III) (Including Labour cess & Excluding GST)

Cum 1 1.00 1.10 0.10 0.11


Total 0.11 2882.69 317.10
3 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and technical specifications Clause
802, 803, 1202 & 1203 (PCC 1:3:6 concrete)
Cum 1 1.00 1.10 0.100 0.11
Total 0.11 5265.17 579.17
4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204

Cum 1 1.00 0.50 0.35 0.18


Total 0.18 4750.55 855.10
5 Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 R.C.C. grade M 25

bottom Cum 1 1.00 0.60 0.05 0.03


top Cum 1 1.00 0.50 0.050 0.03
Total 0.060 6015.28 360.92
6 Plastering with cement mortar (1:4), 15 mm
thick on stone masonary in substructure as
per technical specification Clauses 613.4 &
1204
Sqm 1 1.00 0.50 0.50
Total 0.50 153.40 76.70
Cost For 1.00 m Total (Rs.) 2244.54
CONSTRUCTION OF U-DRAIN
UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

Sl.
No. Description of Item Unit No L (m) B (m) H (m) Qty. Rate (Rs.) Amount (Rs.)

1 Earthwork in fondation in ordinary soil (loam


clay,sand) including filling upto 1.50 m and lead
upto 30 m and including filling,watering and
ramming of excavated earth into the trnches or into
the sapce between the building/ structure and the
side of fondation trenches or plinth and removel
and disposal of surface earth as directed by
Engineer in charge upto a distance of 30 m from
the foundation trenches including all T& P and
material etc complete as per UPPWD specification
SNo.1-251..

Cum 1 1.00 1.65 0.83 1.36


Total 1.36 101.00 137.36
2 Construction of granular sub-base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB Grade -
III) (Including Labour cess & Excluding GST)

Cum 1 1.00 1.65 0.10 0.17


Total 0.17 2882.69 490.06
3 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and technical specifications Clause
802, 803, 1202 & 1203 (PCC 1:3:6 concrete)

Cum 1 1.00 1.65 0.100 0.17


Total 0.17 5265.17 895.08
4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204
Cum 2 1.00 0.50 0.65 0.65
Total 0.65 4750.55 3087.86
5 Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 R.C.C. grade M 25
bottom Cum 1 1.00 0.45 0.05 0.02
top Cum 2 1.00 0.50 0.025 0.03
Total 0.050 6015.28 300.76
6 Plastering with cement mortar (1:4), 15 mm
thick on stone masonary in substructure as
per technical specification Clauses 613.4 &
1204 Sqm 2 1.00 0.60 1.20
Total 1.20 153.40 184.08
7 Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804, 805, cum 1 1 1.45 0.15 0.09 6015.28 541.38
806, 807, 1202 and 1204 (M-25)(40% of total
length) for drain cover.

8 Suplying, Fixing, and placing HYSD bar 0.087*1.5%*7850


reinforcement in superstructure as per
drawing and technical specifications Clause Qtl 0.100 5289.47 528.95
1002,1010,1202 @ 1.5% of R.C.C. Work.

Cost For 1.00 m Total (Rs.) 6165.52


RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS
FORMAT F- 7
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

PACKAGE NO. :- UP67146


ROAD LENGTH :- 25.300 KM

D/H Rate In
S.No Description of Item No. L(m) B(M)
(M)
Quantity Unit
Rs
Amount in Rs

1 2 3 4 5 6 7 8 9 10

Repair work for existing


structures
1 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702,
704, 1202 and 1204

1 10 5.000 0.500 0.900 22.500


22.500 cum 4750.55 106887.38
2 Plaster with cement mortar 1:4 C:CS 15
thick on brick work in substructure as
per Technical specification clause 613.4
and 1204 standard Data Book for
analysis of rates for rural roads, Sr. No.
12.3, Pg-12-4 [MORD Specification 2 10 5.000 1.500 150.000
600]
150.000 sqm 153.40 23010.00
3 White washing two coats on parapet
walls including preparation of surface
by cleaning scraping etc. as per
technical specifications Clause 1915
2 10 5.000 2.250 225.000
225.000 sqm 15.85 3566.25
Grand Total 133463.63
Say Rs 133463.63

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
HP-100 widening 110
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF HP GULE WORKS
FORMAT F- 6

NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

ROAD LENGTH :- 25.30 KM PACKAGE NO. :- UP67146


Widenning of 100 mm NP-3 Hume Pipe Gule
D/H Amount in
S.No Description of Item No. L(m) B(M)
(M)
Quantity Unit Rate In Rs
Rs
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and lead upto
30 m and including filling,watering and ramming of
excavated earth into the trnches or into the sapce
between the building/ structure and the side of
fondation trenches or plinth and removel and
disposal of surface earth as directed by Engineer in
charge upto a distance of 30 m from the foundation
trenches including all T& P and material etc complete
as per pipe
below UPPWD specification SNo.1-251..
1 x 2 2.500 0.300 0.850 1.275 cum
Total 1.275 cum 101.00 128.78
2 Construction of granular sub-base by providing
well graded material, spreading in uniform
layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel
roller to achieve the desired density, complete
as per Technical Specification Clause 401.
( GSB Grade - III) (Including Labour cess &
Excluding GST) Under Pipe 1 x 2 2.500 0.300 0.150 0.225 cum
Total 0.225 cum 3,036.76 683.27
3 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 &
1203 (PCC 1:3:6 concrete)
Below Head wall 1 x 2 2.50 0.30 0.100 0.150 sqm
Total 0.150 sqm 5,265.17 789.78
4 Providing and laying 100mm reinforced cement
concrete pipe NP3 for culverts on first class bedding
of granular material in single row including fixing
collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets
Clause 1106.

1 x 2 2.500 5.000 Rm
Total 5.000 Rm 299.02 1495.10
Total cost of HP gule 3096.92

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
HP-350 new111
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF HP GULE WORKS
FORMAT F- 6
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

ROAD LENGTH :- 25.30 KM PACKAGE NO. :- UP67146


Construction of 350 mm NP-3 Hume Pipe Gule
D/H Amount in
S.No Description of Item No. L(m) B(M)
(M)
Quantity Unit Rate In Rs
Rs
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and lead upto
30 m and including filling,watering and ramming of
excavated earth into the trnches or into the sapce
between the building/ structure and the side of
fondation trenches or plinth and removel and
disposal of surface earth as directed by Engineer in
charge upto a distance of 30 m from the foundation
trenches including all T& P and material etc complete
as
Forper UPPWD specification SNo.1-251..
foundation 1 x 2 2.55 0.91 0.750 3.480 cum
below pipe 1 x 1 6.300 0.750 0.850 4.020 cum
Total 7.500 cum 101.00 757.50
2 Construction of granular sub-base by providing
well graded material, spreading in uniform
layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel
roller to achieve the desired density, complete
as per Technical Specification Clause 401.
( GSB Grade - III) (Including Labour cess &
Excluding GST) Below Parapet 1 x 2 2.550 0.910 0.000 0.000 cum
Under Pipe 1 x 1 6.300 0.750 0.150 0.710 cum
Total 0.710 cum 2,882.69 2046.71
3 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 &
1203 (PCC 1:3:6 concrete)
Below Head wall 1 x 2 2.55 0.910 0.150 0.700 sqm
Total 0.700 sqm 5,265.17 3685.62
4 Stone masonry in 1:3 cement mortar for substructure
complete as per drawing & technical specification
Clauses 702, 704, 1202 and 1204
Head Wall 1 x 2 2.400 0.850 1.800 7.340
Parapet 1 2 2.400 0.400 0.450 0.860
deduction for hume pipe 0.45*0.
1 x 2 3.140 0.625 -0.200
45/4
Total 8.000 cum 4,750.55 38004.40
5 Providing and laying 350mm reinforced cement
concrete pipe NP3 for culverts on first class bedding
of granular material in single row including fixing
collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets
Clause 1106.

1 x 3 2.500 7.500 Rm
Total 7.500 Rm 1,181.04 8857.80
6 Pointing with cement mortar (1:3) on Stone work as
per drawing and technical specification Clauses
613.3 and 1204
Head Wall back side with Parapet 1 x 2 2.400 2.250 10.800
Parapet Top 1 x 2 2.400 0.400 1.920
Parapet inner face 1 x 2 2.400 0.450 2.160 sqm
Parapet sides 2 x 2 0.400 0.450 0.720 sqm
deduction for hume pipe 1 x 2 0.785 0.450 0.450 -0.320 sqm 0.000
Total 15.280 sqm 57.06 871.88
7 White washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915
1 x 2 2.400 4.800 sqm 15.85 76.08
8 Painting, writing, lettering etc. on number plates on
culverts including all materials, labour T&P etc.
required for proper completion of work (Lump sump)

LS 1 Job 500.00 500.00


Total cost of HP gule 54799.99
HP-350 widening112
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF HP GULE WORKS
FORMAT F- 6

NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

ROAD LENGTH :- 25.30 KM PACKAGE NO. :- UP67146


Widenning of 350 mm NP-3 Hume Pipe Gule
D/H Amount in
S.No Description of Item No. L(m) B(M)
(M)
Quantity Unit Rate In Rs
Rs
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and lead upto
30 m and including filling,watering and ramming of
excavated earth into the trnches or into the sapce
between the building/ structure and the side of
fondation trenches or plinth and removel and
disposal of surface earth as directed by Engineer in
charge upto a distance of 30 m from the foundation
trenches including all T& P and material etc complete
as
Forper UPPWD specification SNo.1-251..
foundation 1 x 2 3.00 0.60 1.825 6.570 cum
below pipe 1 x 2 2.500 0.600 0.850 2.550 cum
Total 9.120 cum 101.00 921.12
2 Construction of granular sub-base by providing
well graded material, spreading in uniform
layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel
roller to achieve the desired density, complete
as per Technical Specification Clause 401.
( GSB Grade - III) (Including Labour cess &
Excluding GST) Below Parapet 1 x 2 3.000 0.600 0.000 0.000 cum
Under Pipe 1 x 2 2.500 0.600 0.150 0.450 cum
Total 0.450 cum 2,882.69 1297.21
3 Providing concrete for plain/reinforced concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 &
1203 (PCC 1:3:6 concrete)
Below Head wall 1 x 2 3.00 0.600 0.150 0.540 sqm
Total 0.540 sqm 5,265.17 2843.19
4 Stone masonry in 1:5 cement mortar for substructure
complete as per drawing & technical specification
Clauses 702, 704, 1202 and 1204
Parapet 1 2 3.000 0.500 1.500 4.500
deduction for hume pipe 0.275*
1 x 2 3.140 0.500 -3.140
0.275
Total 1.360 cum 4,551.31 6189.78
6 Providing and laying 350mm reinforced cement
concrete pipe NP3 for culverts on first class bedding
of granular material in single row including fixing
collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets
Clause 1106.

1 x 2 2.500 5.000 Rm
Total 5.000 Rm 1,181.04 5905.20
7 Pointing with cement mortar (1:3) on Stone work as
per drawing and technical specification Clauses
613.3 and 1204
2 x 2 3.000 2.450 29.400 sqm
sides 2 x 2 0.500 1.500 3.000 sqm
deduction for hume pipe 1 x 2 3.140 0.275 0.275 -0.475 sqm 0.000
Total 31.925 sqm 57.06 1821.64
8 White washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915
1 x 2 3.000 0.500 3.000 Sqm 15.85 47.55
10 White washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915

LS 1 Job 500.00 500.000


Total cost of HP gule 19525.70

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
RCPLWEA (ADDITIONAL)
600mm Dia NP-3 Hume Pipe Culvert
UP67146
PACKAGE NO. :-

NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

SL Item of Work No L B H/D QTY. UNIT Rate Amount


1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal of
surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including all T& P Wall
Head and 2 4.20 1.14 0.95 9.10 cum
material etc complete as per UPPWD
specification SNo.1-251.. Under Pipe 1 5.40 1.05 1.80 10.21 cum
Total 19.31 cum 101.00 1950.31
2 Construction of granular sub-base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB Grade -
III) (Including Labour cess & Excluding GST)
For Head Wall 2 4.20 1.14 0.00 0.00 cum
Under Pipe 1 5.40 1.05 0.15 0.85 cum
Total 0.85 cum 2,882.69 2450.29
3 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and technical specifications Clause
802, 803, 1202 & 1203 (PCC 1:3:6 concrete)
For Head Wall 2 4.20 1.05 0.15 1.32 cum
Below Pipe 1 5.40 1.05 0.00 0.00
Total 1.32 cum 5,265.17 6950.02
4 Providing and laying 600mm reinforced
cement concrete pipe NP3 for culverts on first
class bedding of granular material in single
row including fixing collar with cement mortar
1:2 but excluding excavation, protection
works, backfilling, concrete and masonry
works in head walls and parapets Clause
1106.

600mm dia NP3 Hume pipe 3 2.50 7.50 Rm 2114.07 15855.53


4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
For Head Wall 2 4.00 0.67 2.15 11.52
Parapet wall rect. Portion 2 4.00 0.40 0.45 1.44
SL Item of Work No L B H/D QTY. UNIT Rate Amount
Deduction for pipe 1X2X 3.14x0.75x0.75x0.69/4 -0.61
Total 12.35 cum 4,750.55 58669.29
5 Pointing with cement mortar (1:3) on Stone
work as per drawing and technical
specification Clauses 613.3 and 1204
Outside 2 4.00 1.50 12.00
Inside 2 4.00 0.45 3.60
Top 2 4.00 0.40 3.20

Deductions 1X2X 3.14x0.75x0.75/4 -0.88


Total 17.92 Sqm 57.06 1022.52
6 Plastering with cement mortar (1:4), 15 mm
thick on stone masonary in substructure as
per technical specification Clauses 613.4 &
1204
4 0.40 0.45 0.72
Total 0.72 Sqm 153.40 110.45
7 White washing two coats on parapet walls and
tree trunks including preparation of surface by
cleaning scraping etc. as per technical
specifications Clause 1915
Same as above item Pointing 6.80 Sqm
Total 6.80 Sqm 15.85 107.78
8 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper completion
of work (Lump sump)
LS 1 Job 1 Job 500.00 #VALUE!
Total (Rs.) #VALUE!
RCPLWEA (ADDITIONAL)

Widenning of 600mm Dia NP-3 Hume Pipe Culvert


UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

SL Item of Work No L B H/D QTY. UNIT Rate Amount


1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal of
surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including Below
all T& Parapet
P and 2 3.10 1.05 1.50 9.77 cum
material etc complete as per UPPWD
specification SNo.1-251.. Under Pipe 2 2.50 1.00 1.20 6.00 cum
Total 15.77 cum 101.00 1592.77
2 Construction of granular sub-base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB Grade -
III) (Including Labour cess & Excluding GST)
Below Parapet 2 3.10 1.05 0.15 0.98 cum
Under Pipe 2 2.50 1.00 0.15 0.75 cum
Total 1.73 cum 2,882.69 4987.05
3 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and technical specifications Clause
802, 803, 1202 & 1203 (PCC 1:3:6 concrete)
Below Parapet 2 3.10 1.05 0.15 0.98 cum
Below Pipe 2 2.50 1.00 0.15 0.75
Total 1.73 cum 5,265.17 9108.74
4 Providing and laying 600mm reinforced
cement concrete pipe NP3 for culverts on first
class bedding of granular material in single
row including fixing collar with cement mortar
1:2 but excluding excavation, protection
works, backfilling, concrete and masonry
works in head walls and parapets Clause
1106.

600mm dia NP3 Hume pipe 2 2.50 5.00 Rm 2114.07 10570.35


4 Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
2 3.00 0.90 0.35 1.89
2 3.00 0.69 1.10 4.55
2 3.00 0.50 0.50 1.5
Parapet wall rect. Portion 2 3.00 0.50 0.50 1.5
Deduction for pipe (area calculated in H/D column) 1X2X 3.14x0.35x0.35x0.69 -0.62
Total 8.82 cum 4,551.31 40142.55
5 Pointing with cement mortar (1:3) on Stone
work as per drawing and technical
specification Clauses 613.3 and 1204
Outside 2 3.00 2.00 12.00
SL Item of Work No L B H/D QTY. UNIT Rate Amount

Inside 2 3.00 0.50 3.00


Top 2 3.00 0.50 3.00
Ends 4 0.35 0.35 0.49
Deductions 1X2X 3.14x0.35x0.35x0.69 -0.69
Total 17.80 Sqm 57.06 1015.67
6 Plastering with cement mortar (1:4), 15 mm
thick on stone masonary in substructure as
per technical specification Clauses 613.4 &
1204 0.5 0.50 1.00 Sqm
4
Total 1.00 Sqm 153.40 153.4
7 White washing two coats on parapet walls and
tree trunks including preparation of surface by
cleaning scraping etc. as per technical
specifications Clause 1915
Same as above item Pointing 17.80 Sqm
Total 17.80 Sqm 15.85 282.13
8 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper completion
of work (Lump sump)
LS 1 Job 1 Job 500.00 500.00
Total (Rs.) 68352.70

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
RCPLWEA (ADDITIONAL)

Widenning of 900mm Dia NP-3 Hume Pipe Culvert


UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

SL Item of Work No L B H/D QTY. UNIT Rate Amount


1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal of
surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including Below
all T& Parapet
P and 2 3.10 1.05 1.50 9.77 cum
material etc complete as per UPPWD
specification SNo.1-251.. Under Pipe 2 2.50 1.50 1.50 11.25 cum
Total 21.02 cum 101.00 2123.02
2 Construction of granular sub-base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB Grade -
III) (Including Labour cess & Excluding GST)
Below Parapet 2 3.70 1.05 0.15 1.17 cum
Under Pipe 2 2.50 1.50 0.15 1.13 cum
Total 2.30 cum 2,882.69 6630.19
3 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and technical specifications Clause
802, 803, 1202 & 1203 (PCC 1:3:6 concrete)
Below Parapet 2 3.70 1.05 0.15 1.17 cum
Below Pipe 2 2.50 1.50 0.15 1.13
Total 2.30 cum 5,265.17 12109.89
4 Providing and laying 900mm reinforced
cement concrete pipe NP3 for culverts on first
class bedding of granular material in single
row including fixing collar with cement mortar
1:2 but excluding excavation, protection
works, backfilling, concrete and masonry
works in head walls and parapets Clause
1106.

600mm dia NP3 Hume pipe 2 2.50 5.00 Rm 4496.53 22482.65


4 Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
2 3.50 0.90 0.35 2.21
2 3.50 0.69 1.10 5.31
2 3.50 0.50 0.50 1.75
Parapet wall rect. Portion 2 3.50 0.50 0.50 1.75
Deduction for pipe (area calculated in H/D column) 1X2X 3.14x0..55x0.55x0.69 -1.52
Total 9.50 cum 4,551.31 43237.45
5 Pointing with cement mortar (1:3) on Stone
work as per drawing and technical
specification Clauses 613.3 and 1204
Outside 2 3.50 2.00 14.00
SL Item of Work No L B H/D QTY. UNIT Rate Amount

Inside 2 3.50 0.50 3.50


Top 2 3.50 0.50 3.50
Ends 4 0.50 0.50 1.00
Deductions 1X2X 3.14x0.55x0.55x0.69 -1.71
Total 20.29 Sqm 57.06 1157.75
6 Plastering with cement mortar (1:4), 15 mm
thick on stone masonary in substructure as
per technical specification Clauses 613.4 &
1204 0.5 0.50 1.00 Sqm
4
Total 1.00 Sqm 153.40 153.4
7 White washing two coats on parapet walls and
tree trunks including preparation of surface by
cleaning scraping etc. as per technical
specifications Clause 1915
Same as above item Pointing 20.29 Sqm
Total 20.29 Sqm 15.85 321.6
8 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper completion
of work (Lump sump)
LS 1 Job 1 Job 500.00 500.00
Total (Rs.) 88715.90

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS
FORMAT F- 7
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
PACKAGE NO. :- UP67146

Type of Cross drainage Works : Construction of 1000 mm NP-3 Hume Pipe Culvert
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal
of surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including all T& P and
material etc complete as per UPPWD
specification SNo.1-251..

For foundation 1 x 2 4.20 1.25 0.950 9.980 cum


For sand filling below pipe 1 x 1 5.400 1.500 1.900 15.390 cum
Total 25.370 cum 101.00 2562.37
2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with motor
grader on prepared surface, mixing by
mix in place method with rotavator at
OMC, and compacting with smooth
wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB
Grade - III) (Including Labour cess &
Below Parapet 1 x 2 4.200 1.250 0.000 0.000 cum
Excluding GST)
Under Pipe 1 x 1 5.400 1.500 0.200 1.620 cum
Total 1.620 cum 2,882.69 4669.96
3 Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC 1:3:6
concrete)

Below head wall 1 x 2 4.20 1.250 0.150 1.580 cum


Under Pipe 1 x 2 5.40 1.500 0.000 0.000 cum

Total 1.580 cum 5,265.17 8318.97


4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204
parapet wall 1 x 2 4.000 0.400 0.450 1.440
Head wall
1 2 4.000 0.730 2.600 15.180

deduction for hume pipe 1.2*1.2


1 x 2 3.140 -1.650
*.73/4
Total 14.970 cum 4,750.55 71115.73
5 Providing and laying 1000mm reinforced
cement concrete pipe NP3 for culverts on
first class bedding of granular material in
single row including fixing collar with cement
mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and
masonry works in head walls and parapets
Clause 1106.
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
1 x 3 2.500 7.500 Rm
Total 7.500 Rm 5,348.79 40115.93
6 Providing and laying M-25 plain cement 0.000
concrete in superstructure as per drawing
and technical specifications Clauses 800,
1205.4 and 1205.5
guard stone 1 x 4 0.200 0.200 0.500 0.080 cum
1 x 2 0.400 0.400 1.000 0.320 cum
Total 0.400 cum 6,015.28 2406.11
7 Pointing with cement mortar (1:3) on Stone
work as per drawing and technical
specification Clauses 613.3 and 1204
out side 1 x 2 4.000 1.950 15.600 sqm
inside 1 x 2 4.000 0.450 3.600 sqm
Top 1 x 2 4.000 0.400 3.200 sqm
deduction for hume pipe 1 1.2*1.2 0.000
x 2 3.140 -2.260 sqm
/4
Total 20.14 sqm 57.06 1149.19
8 Plastering with cement mortar (1:4), 15
mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204

1 x 4 0.400 0.450 0.720 sqm


0.72 sqm 153.40 110.45
9 White washing two coats on parapet walls
including preparation of surface by cleaning
scraping etc. as per technical specifications
Clause 1915
1 x 2 4.000 1.950 15.600 sqm
Total 15.6 sqm 15.85 247.26
10 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper
completion of work (Lump sump)
LS 1 Job 500.00 500.00
Total cost of culvert 131195.97
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS
FORMAT F- 7
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

PACKAGE NO. :- UP67146


ROAD LENGTH :- 25.300 KM
Type of Cross drainage Works : Widenning of 1000 mm NP-3 Hume Pipe Culvert
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal
of surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including all T& P and
For foundation 1 x 2 4.15 1.50 2.505 31.187 cum
material etc complete as per UPPWD
below pipe SNo.1-251..
specification 1 x 2 2.500 1.530 1.900 14.535 cum
Total 45.722 cum 101.00 4617.95
2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with motor
grader on prepared surface, mixing by
mix in place method with rotavator at
OMC, and compacting with smooth
wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB
Grade - III) (Including Labour cess &
Excluding GST)
Below Parapet 1 x 2 4.150 1.500 0.150 1.868 cum
Under Pipe 1 x 2 2.500 1.530 0.150 1.148 cum
Total 3.015 cum 2,882.69 8691.31
3 Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC 1:3:6
concrete)

Below Head wall 1 x 2 4.15 1.400 0.150 1.743 cum


Under Pipe 1 x 2 2.50 1.400 0.150 1.050 cum
for haunching 1 x 2 2.50 area= 0.356 1.781 cum
Total 4.574 cum 5,265.17 24083.96
4 Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204
Parapet 1 2 4.000 0.500 0.450 1.800
Head wall 1 2 4.000 0.825 1.950 12.870
deduction for hume pipe 1 x 2 3.140 0.378 0.755 -1.793
Total 12.877 cum 4,750.55 61171.33
5 Providing and laying 1000mm reinforced
cement concrete pipe NP3 for culverts on
first class bedding of granular material in
single row including fixing collar with cement
mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and
masonry works in head walls and parapets
Clause 1106.

1 x 2 2.500 5.000 Rm
Total 5.000 Rm 5,348.79 26743.95
6 Providing and laying M-20 plain cement 0.000
concrete in superstructure as per drawing
and technical specifications Clauses 800,
1205.4 and 1205.5
guard stone 1 x 4 0.200 0.200 0.500 0.080 cum
1 x 2 0.400 0.400 1.000 0.320 cum
Total 0.400 cum 5,265.17 2106.07
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
7 Pointing with cement mortar (1:3) on Stone
work as per drawing and technical
specification Clauses 613.3 and 1204
1 x 2 4.000 3.755 30.040 sqm
sides 2 x 2 0.750 2.955 8.865 sqm
deduction for hume pipe 1 x 2 3.140 0.615 0.615 -2.375 sqm 0.000
Total 36.530 sqm 57.06 2084.39
8 Plastering with cement mortar (1:4), 15
mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204
1 x 4 0.500 0.500 1.000 sqm
1.000 sqm 153.40 153.40
9 White washing two coats on parapet walls
including preparation of surface by cleaning
scraping etc. as per technical specifications
Clause 1915
1 x 2 4.000 2.505 20.040 sqm
1 x 2 4.000 2.505 20.040 sqm
2 x 2 0.450 0.800 1.440 sqm
2 x 2 0.750 2.955 8.865 sqm
Total 50.385 sqm 15.85 798.60
10 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper
completion of work (Lump sump)
LS 1 Job 500.00 500.000
Total cost of culvert 130950.96

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS
FORMAT F- 7
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

PACKAGE NO. :- UP67146


ROAD LENGTH :- 25.300 KM
Type of Cross drainage Works : Widenning of 1200 mm NP-3 Hume Pipe Culvert
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering
and ramming of excavated earth into the
trnches or into the sapce between the
building/ structure and the side of fondation
trenches or plinth and removel and disposal
of surface earth as directed by Engineer in
charge upto a distance of 30 m from the
foundation trenches including all T& P and
For foundation 1 x 2 5.20 1.50 2.505 39.078 cum
material etc complete as per UPPWD
below pipe SNo.1-251..
specification 1 x 2 2.500 1.800 1.900 17.100 cum
Total 56.178 cum 101.00 5673.98
2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with motor
grader on prepared surface, mixing by
mix in place method with rotavator at
OMC, and compacting with smooth
wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB
Grade - III) (Including Labour cess &
Excluding GST)
Below Parapet 1 x 2 5.200 1.500 0.150 2.340 cum
Under Pipe 1 x 2 2.500 1.800 0.150 1.350 cum
Total 3.690 cum 2,882.69 10637.13
3 Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC 1:3:6
concrete)

Below Head wall 1 x 2 5.00 1.400 0.150 2.100 cum


Under Pipe 1 x 2 2.50 1.400 0.150 1.050 cum
for haunching 1 x 2 2.50 area= 0.366 1.832 cum
Total 4.982 cum 6,015.28 29967.98
4 Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204
Parapet 1 2 5.000 0.500 0.450 2.250
Head wall 1 2 5.000 0.825 2.505 20.666
deduction for hume pipe 1 x 2 3.140 0.378 0.755 -1.793
Total 21.123 cum 4,551.31 96137.02
5 Providing and laying 1000mm reinforced
cement concrete pipe NP3 for culverts on
first class bedding of granular material in
single row including fixing collar with cement
mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and
masonry works in head walls and parapets
Clause 1106.

1 x 2 2.500 5.000 Rm
Total 5.000 Rm 7,962.17 39810.85
6 Providing and laying M-20 plain cement 0.000
concrete in superstructure as per drawing
and technical specifications Clauses 800,
1205.4 and 1205.5
guard stone 1 x 4 0.200 0.200 0.500 0.080 cum
1 x 2 0.400 0.400 1.000 0.320 cum
Total 0.400 cum 5,265.17 2106.07
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
7 Pointing with cement mortar (1:3) on Stone
work as per drawing and technical
specification Clauses 613.3 and 1204
1 x 2 5.000 3.755 37.550 sqm
sides 2 x 2 0.750 2.955 8.865 sqm
deduction for hume pipe 1 x 2 3.140 0.615 0.615 -2.375 sqm 0.000
Total 44.040 sqm 57.06 2512.91
8 Plastering with cement mortar (1:4), 15
mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204
1 x 4 0.500 0.500 1.000 sqm
1.000 sqm 153.40 153.40
9 White washing two coats on parapet walls
including preparation of surface by cleaning
scraping etc. as per technical specifications
Clause 1915
1 x 2 5.000 2.505 25.050 sqm
1 x 2 5.000 2.505 25.050 sqm
2 x 2 0.450 0.800 1.440 sqm
2 x 2 0.750 2.955 8.865 sqm
Total 60.405 sqm 15.85 957.42
10 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper
completion of work (Lump sump)
LS 1 Job 500.00 500.000
Total cost of culvert 188456.75

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
Indicative Drawing for 1.50 m.Span RCC Culvert as per IRC SP-20-2002(Plate-7.02) Page-1
Abutment Section for Span- 1500 mm. Height- 2000 mm. From Bed Level, Formation Width - 12000
Under Package No. UP-6982 Link Road :- Para road Wing Wall - mm.
Reduced level of Black top- m. River Bed Level- 0 Total cost - Rs.
Length :- 1.000 Km. Block :-Malihabad Required Culverts :- 1 No. Location At Chainage :-
(Applicable for Span 1.50m. To 3.00m. Span)

300
400 150 400

B.T. Level
150
210 210
200

700 400

Height Adopted=2000
2260
2000 2260

1:3
1:3
###

2410
Clear Span- 1500 m. 1153 800
1367
###
100
100
###
###
###
###
###

100
100
100

100

100
100

100

100
###
###

100

100
Bed Bed

1567 1353
1667 1453
1767 200 1553 200
###

1600 1867 1400 1653


1967 1600 1753
2067 1853
2167 1953
###

200

2367 2153
Top Half Plan
Indicative Drawing for 1.50 m.Span RCC Culvert as per IRC SP-20-2002(Plate-7.02)
900 Centre Line
-1467 2367
900

700
600
500
400
300
200
2153
1953

100
###
###
1653
0
1553

400
1453
-700

1353

1153

800
###

-50
100
700

###
100
###
-767

750

12000
12200

12400

12600
12800
13000

13200

13400
13600
9294

853
47

-700
2153
Centre Line
Page-3

DETAILED COST ESTIMATE FOR RCC CULVERT ( as per Plate 7.02 of IRC:SP20-2002 )
Link Road Name- 0 Block- 0
Total Length- 1.000 Km. Total No. Of Culvert- 1 No. Chainage- 0.500 Km.
Serial Refence Detailed Measurments in metre for 1no. Cost for 1 no.
Description of Works No.
No. Length Width Height Unit Quantity Rate Amount Total Amount
1 2 3 4 5 6 7 8 9 10 11 For 1 No.

Earthwork in Excavation for structures as per


Drawing and technical specification Clause
-305.1 including setting out, construction of
1 300
shoring and bracing , removal of slumps and
other deletorious material and disposal upto a
lead of 50 metre, dressing of

Central portion 2 13.600 2.367 1.60 103.01


Return portion 4 -1.467 2.153 1.60 -20.21
Certain wall 2 1.500 0.400 1.60 1.92
Total Cum 84.72 101 8556.72 8556.72
800 & Providing concrete Reinforced concrete in
open foundation complete , as per drawing
2 and technical specification clause
802,803,1203 P.C.C. grade M-10, Nominal
mix 1:3:6

Central portion 2 13.600 2.367 0.200 12.880


Return portion 4 -1.467 2.153 0.200 -2.530
Certain wall 2 1.500 0.400 0.200 0.240
Flooring 1 12.040 1.500 0.150 2.710
Total cum 13.300 5265.17 70026.76 70026.76

Stone masonry in 1:3 cement mortar for


substructure complete as per drawing &
3 12.5
technical specification Clauses 702, 704,
1202 and 1204

Central portion
7th. Step 2 13.400 2.167 0.200 cum 11.615
6th. Step 2 13.200 2.067 0.200 10.914
5th. Step 2 13.000 1.967 0.200 10.228
4th. Step 2 12.800 1.867 0.200 9.559
3rd. Step 2 12.600 1.767 0.200 8.906
2nd. Step 2 12.400 1.667 0.200 8.268
1st. Step 2 12.200 1.567 0.200 7.647
Rectangular portion upto bed block level 2 12.000 0.700 2.000 33.600
Trangular portion upto bed block level 2 12.000 0.334 2.000 16.008 4750.55 0.00 0.00
Return portion Page-4
7th. Step 4 -0.767 1.953 0.200 -1.198
6th. Step 4 -0.767 1.853 0.200 -1.137
5th. Step 4 -0.767 1.753 0.200 -1.076
4th. Step 4 -0.767 1.653 0.200 -1.014
3rd. Step 4 -0.767 1.553 0.200 -0.953
2nd. Step 4 -0.767 1.453 0.200 -0.892
1st. Step 4 -0.767 1.353 0.200 -0.830
Rectangular portion upto bed block level 4 -0.700 0.400 2.260 -2.531
Trangular portion upto bed block level 4 -0.700 0.3765 2.260 -2.382
Certain wall
Up stream and down stream 2 1.500 0.46 0.23 0.317
Parapet above slab Round portion 2 2.42 0.46 0.23 0.512
2 2.42 0.35 0.37 0.627
Total Cum. 106.188 4750.55 504449.61 504449.61

Providing and laying reinforced cement


concrete in superstructure as per drawing and
4 800
technical specifications Clause 800,1205.4
and1205.5 (M-25)

In Bed Block above Abutment 2 12.000 0.700 0.200 3.360


Dirt wall beside Slab 2 12.000 0.400 0.210 2.016
(0.250
For crash barrier 2 2.100 +0.15)/ 0.600 0.504
2
For couping of return wall 4 -0.700 0.400 0.150 -0.168
Total Cum. 5.712 6015.28 34359.28 34359.28

Providing and laying reinforced cement


concrete in superstructure as per drawing and
5 800
technical specifications Clause 800,1205.4
and1205.5
In Slab 1 2.100 12.000 0.210 cum. 5.292
In Pillars 6 0.750 0.250 0.250 cum. 0.281
Total - Total - 5.573 6015.28 33524.66 33524.66
Suplying, Fixing, and placing HYPD bar 8.85892
reinforcement in superstructure as per
6 1000
drawing and technical specifications Clause
1002,1010,1202 @ 1.0% of R.C.C. Work. 11.285 @ 0.9% of RCC QTL 5289.5 46859.01 46859.01
Pointing with Cement Mortar (1:3) 15mm. Page-5
Thick on stone work in superstructure as per
8
technical specification Clauses 613.4 and
1204
Abutment 2 12.000 1.60 38.40
Return wall 4 0.00 1.13 0.00
4 0.85 1.13 3.84
Parapet 2 2.42 0.95 4.60
4 0.46 0.23 0.42
4 0.35 0.37 0.52
Total Sqm. 47.78 57.06 2726.40 2726.40

Plastering with cement mortar (1:4) 15 mm.


thick on stone work in superstructure as per
9
technical specification Clauses 613.4 and
1204

4 0.35 0.37 0.52


12 0.46 0.37 2.04
Providing weepholes in brick masonry/stone Total Sqm. 2.56 153.40 392.77 392.77
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC
pipe extending through the full width of the
10 12 no. 12 129.01 1548.12 1548.12
structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and
technical specification Clauses 614, 709,
Hand Packed stone filling in back of walls
1204.3.7
including cost of all materials, royality, T&P
11 2 6.70 1.00 2.50 cum 33.5 2368.82 79355.47 79355.47
etc complete as per direction of Engineer-in-
Charge
Cement Plum Concrete with 40% plum &
60% 1:3:6 Cement Concrete including Supply
of All material, labour,T&P etc. required for
12 2 3.00 1.50 1.50 cum 13.5 3876.57 52333.70 52333.70
proper completion of the work as per
drawing/Technical specifications clause
802,803,1202 & 1203 Grand Total - 781798.8 781798.8
Per R/Mtr for widenning 62543.904
For 5.00 Mtr widenning 312719.52
Page-6
Page-7
Details Of Reinforcement In RCC Slab 1200.00 cm. Wide
For 1.50 m. Span Slab Thickness - 21.00 cm.
4 cm. Cover (Dimmenssions are in Cm.)
Main Bottom Bars
12 mm. Dia. @ 12.00 cm. C/C.
40 30 Total Number - 100 No. 12 mm. Expantion Joint 30 40
###

21
Distribution Bottom Bars Both Top Bars

20
20

8 mm. Dia. @ 16.0 cm. C/C. 10 mm. Dia. @ 30 C/C


Total Number - 14 No. Total Number - 43 No.
70 150 70
Note- Only one bar is to be cranked in each side in four bars. 10 mm. Dia. @ 30 C/C
for 1 to 3m. Span of RCC culverts only. 10 No.
Total Number -
A. Bottom Main Bars - 12 mm. Dia. 100 No.
205.20

Aprox. Total Bar Length - 220 Cm.


###

17

12

37.7 12 ### cm.

B. Bottom Distrbution Bars - 8 mm. Dia. 14 No.

### cm.

C. Top Bars Along Main Bars - 10 mm. Dia. 43 No.

cm.

D. Top Along Distribu. Bars - 10 mm. Dia. 10 No.

### cm.
Name of Work -

1.5 m. Span RCC Culvert. Height - 2 m.


DETAILS OF FOUNDATION LAY OUT PLAN
1700
900 900
###

853 47 -100 47 853

###

Road Centre Line

###
###

FoundationTrench

###

River,Canal,Nala etc. Centre Line


Indicative Drawing for 2.50 m.Span RCC Culvert as per IRC SP-20-2002(Plate-7.02) Page-1
(Applicable for Span 1.50m. To 3.00m. Span)

300
400 150 400

B.T. Level
150
270 270
200

700 400

Height Adopted=2500
2820
2500 2820

1:3
1:3
###

2970
Clear Span- 2500 m. 1340 800
1533
###
100
100
###
###
###
###
###

100
100
100

100

100
100

100

100
###
###

100

100
Bed Bed

1733 1540
1833 1640
1933 200 1740 200
###

1600 2033 1840

1400
2133 1600 1940
2233 2040
2333 2140
###

200

2533 2340
Top Half Plan
Indicative Drawing for 2.50 m.Span RCC Culvert as per IRC SP-20-2002(Plate-7.02)
900 Centre Line
-1633 2533
900

700
600
500
400
300
200
2340
2140

100
###
###
1840
0

1740

400
1640
-700

1540

1340

800

450
###
100
700

###
100
###
-933

1250

12000
12200

12400

12600
12800
13000

13200

13400
13600
8920

1040
-140

-700
2340
Centre Line
Page-3

DETAILED COST ESTIMATE FOR RCC CULVERT ( as per Plate 7.02 of IRC:SP20-2002 )

Total Length- 1.000 Km. Total No. Of Culvert- 1 No. Chainage- 0.500 Km.
Serial Refence Detailed Measurments in metre for 1no. Cost for 1 no. Total
Description of Works No.
No. Length Width Height Unit Quantity Rate Amount Amount
1 2 3 4 5 6 7 8 9 10 11 For 1 No.
1 300 Earthwork in Excavation for structures as per
Drawing and technical specification Clause
-305.1 including setting out, construction of
shoring and bracing , removal of slumps and
other deletorious material and disposal upto a
lead of 50 metre, dressing of

Central portion 2 13.600 2.533 1.60 110.24


Return portion 4 -1.633 2.340 1.60 -24.46
Certain wall 2 2.500 0.400 1.60 3.2
Total Cum 88.98 101 8986.98 8986.98
2 800 & Providing concrete Reinforced concrete in
open foundation complete , as per drawing
and technical specification clause
802,803,1203 P.C.C. grade M-10, Nominal
mix 1:3:6

Central portion 2 13.600 2.533 0.200 13.780


Return portion 4 -1.633 2.340 0.200 -3.060
Certain wall 2 2.500 0.400 0.200 0.400
Flooring 1 12.040 2.500 0.150 4.520
Total cum 15.640 5265.17 82347.26 82347.26
3 12.5 Stone masonry in 1:5 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204

Central portion
7th. Step 2 13.400 2.333 0.200 cum 12.505
6th. Step 2 13.200 2.233 0.200 11.790
5th. Step 2 13.000 2.133 0.200 11.092
4th. Step 2 12.800 2.033 0.200 10.409
3rd. Step 2 12.600 1.933 0.200 9.742
2nd. Step 2 12.400 1.833 0.200 9.092
1st. Step 2 12.200 1.733 0.200 8.457
Rectangular portion upto bed block level 2 12.000 0.700 2.500 42.000
Trangular portion upto bed block level 2 12.000 0.417 2.500 24.990 4750.55 118716.24 118716.24
Return portion Page-4
7th. Step 4 -0.933 2.14 0.200 -1.597
6th. Step 4 -0.933 2.04 0.200 -1.523
5th. Step 4 -0.933 1.94 0.200 -1.448
4th. Step 4 -0.933 1.84 0.200 -1.373
3rd. Step 4 -0.933 1.74 0.200 -1.299
2nd. Step 4 -0.933 1.64 0.200 -1.224
1st. Step 4 -0.933 1.54 0.200 -1.149
Rectangular portion upto bed block level 4 -0.700 0.400 2.820 -3.158
Trangular portion upto bed block level 4 -0.700 0.47 2.820 -3.711
Certain wall
Up stream and down stream 2 2.500 0.46 0.23 0.529
Parapet above slab Round portion 2 3.42 0.46 0.23 0.724
2 3.42 0.35 0.37 0.886
Total Cum. 125.733 4750.55 597298.85 597298.85
4 800 Providing and laying reinforced cement
concrete in superstructure as per drawing and
technical specifications Clause 800,1205.4
and1205.5 (M-25)

In Bed Block above Abutment 2 12.000 0.700 0.200 3.360


Dirt wall beside Slab 2 12.000 0.400 0.270 2.592
(0.250
For crash barrier 2 3.100 +0.15)/ 0.600 0.744
2
For couping of return wall 4 -0.700 0.400 0.150 -0.168
Total Cum. 6.528 6015.28 39267.75 39267.75

5 800 Providing and laying reinforced cement


concrete in superstructure as per drawing and
technical specifications Clause 800,1205.4
and1205.5
In Slab 1 3.100 12.000 0.270 cum. 10.044
In Pillars 8 0.750 0.250 0.250 cum. 0.375
Total - Total - 10.419 6015.28 62673.20 62673.20
6 1000 Suplying, Fixing, and placing HYPD bar 13.3034
reinforcement in superstructure as per
drawing and technical specifications Clause
1002,1010,1202 @ 1.0% of R.C.C. Work. 16.947 @ 0.9% of RCC QTL 5289.5 70367.92 70367.92
8 Pointing with Cement Mortar (1:3) 15mm. Page-5
Thick on stone work in superstructure as per
technical specification Clauses 613.4 and
1204
Abutment 2 12.000 2.10 50.40
Return wall 4 0.00 1.41 0.00
4 0.85 1.41 4.79
Parapet 2 3.42 0.95 6.50
4 0.46 0.23 0.42
4 0.35 0.37 0.52
Total Sqm. 62.63 57.06 3573.85 3573.85
9 Plastering with cement mortar (1:4) 15 mm.
thick on stone work in superstructure as per
technical specification Clauses 613.4 and
1204

4 0.35 0.37 0.52


12 0.46 0.37 2.04
Providing weepholes in brick masonry/stone Total Sqm. 2.56 153.40 392.77 392.77
masonry, plain/reinforced concrete abutment,
10 wing wall, return wall with 100 mm dia AC
pipe extending through the full width of the
12 no. 12 129.01 1548.12 1548.12
structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and
technical specification Clauses 614, 709,
11 Hand Packed stone filling in back of walls
1204.3.7
including cost of all materials, royality, T&P
2 6.70 1.00 2.50 cum 33.5 2368.82 79355.47 79355.47
etc complete as per direction of Engineer-in-
Charge
Cement Plum Concrete with 40% plum &
60% 1:3:6 Cement Concrete including Supply
12 of All material, labour,T&P etc. required for
2 3.00 1.50 1.50 cum 13.5 3876.57 52333.70 52333.70
proper completion of the work as per
drawing/Technical specifications clause
802,803,1202 & 1203 Grand Total - 1064528 1064528
Per R/Mtr for widenning 85162.27
For 5.00 Mtr widenning 425811
Page-6
Page-7
Details Of Reinforcement In RCC Slab 1200.00 cm. Wide
For 2.50 m. Span Slab Thickness - 27.00 cm.
4 cm. Cover (Dimmenssions are in Cm.)
Main Bottom Bars
16 mm. Dia. @ 18.75 cm. C/C.
40 30 Total Number - 65 No. 12 mm. Expantion Joint 30 40
###

27
Distribution Bottom Bars Both Top Bars

20
20

10 mm. Dia. @ 21.3 cm. C/C. 10 mm. Dia. @ 30 C/C


Total Number - 15 No. Total Number - 43 No.
70 250 70
Note- Only one bar is to be cranked in each side in four bars. 10 mm. Dia. @ 30 C/C
for 1 to 3m. Span of RCC culverts only. 13 No.
Total Number -
A. Bottom Main Bars - 16 mm. Dia. 65 No.
305.20

Aprox. Total Bar Length - 322 Cm.


###

26

18
46.1 19 ### cm.

B. Bottom Distrbution Bars - 10 mm. Dia. 15 No.

### cm.

C. Top Bars Along Main Bars - 10 mm. Dia. 43 No.

cm.

D. Top Along Distribu. Bars - 10 mm. Dia. 13 No.

### cm.
Name of Work -

2.5 m. Span RCC Culvert. Height - 2.5 m.


DETAILS OF FOUNDATION LAY OUT PLAN
2700
900 900
###

1040 ### 900 -140 1040

###

Road Centre Line

###
###

FoundationTrench

###

River,Canal,Nala etc. Centre Line


Indicative Drawing for 5 m. Span RCC Culvert as per IRC SP-20-2002(Plate-7.03) Page-1
Abutment Section for Span- 5000 mm. Height- 2500 mm. From Bed LevelFormation Width - 12000 mm.
(Applicable for 4.00m. To 7.00m. Span) Total Cost of 1 No. Culverts ---- Rs. 2667545.14
Section Of Abutment 1 Section Of Return Wall
300 400 400
200
630

430

430
200 200
Expantion Joint

2500
12mm.

3130
###
Clear Height Of Culvert .
2500

1:3 1:3 1:10


H=

1:6
4930
3130

Abutment Wall Return Wall


Span 5000

50 River Bed Level 50


833 700 417
1950 1:2 1043 400 313 1:2
1800
1600

2000 1806

1800

1600
2800 2606
800
800
200
200 200
2800 2606
3200 3006
Abutment Section Return Wall Section 200
Indicative Drawing for 5 m. Span RCC Culvert as per IRC SP-20-2002(Plate-7.02)
Abutment Section for Span- 5000 mm. Height- 2500 mm. From Bed Level to B.T.Level Formation Width - 12000 mm.
1/4th.Plan
6617 C/L Notes -
1.-ALL DIMENTION ARE IN mm. UNTIL & UNLESS STATED
200 2.-COPING, DIRT WALL FOR ABUTMENT & COPING FOR
RETURN OF CULVERT & SMALL BRIDGES IS P.C.C COPING

800
1313 5417 PROVIDE SURFACE STEEL 8MM DIA. 200MM. C/C BOTHWAY
5000 ON EXPOSED SURFACE OF ALL PCC MEMBER.

313
4300 700 1417 3.-THE HEIGHT IN THIS DRAWING IS TAKEN FROM BED
LEVEL OF RIVER OR NALA OR CANAL TO LOWER LEVEL OF
3006

400 BED BLOCK OF SLAB.


4.-THE WEARING COAT OVER THE DECK SLAB & BETWEEN
RETURN SHALL BE 20MM. PRE MIX CARPET WITH 5MM,
3417 2000 SEAL COAT.ALSO PROVIDE 6MM. THICK PRE MOULDED
1043 BITUMINOUS PAD ON THE ABUTMNT CAP & BETWEEN DECK
SLAB AND DIRT WALL FOR EXPANTION JOINT.
5.-PROVIDE ONE WATER SPOUT AT THE CENTRE OF SLAB
50 IN PARAPET WALL.PROVIDE 1 ROW OF WEEO HOLES AT
7313

200 2000 C/C AND AT 1000 C/C HEIGHT ABOVE BED LEVEL

6000
50 FOR ABUTMENT.

###
833 700 417 800 6.-LENGTH OF RETURN WALL FOR 5.20M. TO 6.00M
7313

3467 HEIGHT SHALL BE 5.00 AND 6.00M TO 7.00M.


3417 3200
2500

4307 1083

C/L C/L
DETAILED COST ESTIMATE FOR RCC CULVERT ( as per Plate 7.02 of IRC:SP20-2002 )

(Ministry of Rural Development,( Govt. of India )


S. No. Refence Description of Works No. Detailed Measurments in metre Cost for 1 no. Cost for 1 No
for 1no.
Leng Widt Heigh Unit Quantity Rate Amount Qty. Amount.
1 2 3 4 th
5 h
6 7t 8 9 10 11 12 13
1 Dewatering of running water during ls 228 110 25080
construction including cost of pump with
oprator and fuel etc complete
Hrs 110.00 25080.00
2 Earthwork in Excavation for structures as per
Drawing and technical specification Clause
-305.1 including setting out, construction of
shoring and bracing , removal of slumps and
other deletorious material and disposal upto a
lead of 50 metre, dressing of
Central portion 1 14.63 3.2 1.8 cum. 84.25
Return portion 4 3.417 3.006 1.8 cum. 73.95
Curtain wall 2 5 0.45 0.6 cum. 2.70
Total cum. 160.90 101 16250.9 110.00 11110.00
3 Providing concrete Reinforced concrete in
open foundation complete , as per drawing
and technical specification clause
802,803,1203 P.C.C. grade M-10, Nominal mix
1:3:6
Central portion 1 14.63 3.2 0.2 cum. 9.36
Return portion 4 3.417 3.006 0.2 cum. 8.22
Curtain wall 2 5 0.45 0.2 cum. 0.90
Flooring 1 12 5 0.2 cum. 12.00
Total cum. 30.48 5265.17 160482.38 30.48 160482.38
4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
Below Bed Level For Abutment
Traingular Portion 0.5 13.43 0.8 0.8 cum. 4.30
Rectangular portion 2 13.43 2 1.6 cum. 85.93
Below Bed Level For Pier
Straigt Portion 2 13.43 1.83 1.8 cum. 88.45
Return Wall 4 3.417 2.581 1.6 cum. 56.44
Total cum. 235.12 4750.55 1116949.32 235.12 1116949.32
5
Stone masonry in 1:3 cement mortar for super
structure complete as per drawing & technical
specification Clauses 702, 704, 1202 and 1204

Above Bed Level For Abutment


Traingular Portion Inside 0.5 12.31 0.417 2.5 cum. 6.42
Rectangular portion 2 12.31 0.7 2.5 cum. 43.10
Traingular Portion outside 2 10.56 0.417 2.5 cum. 21.98
Return Wall 4 3.884 1.078 3.13 cum. 52.41
Curtain wall 0.00
Up stream and down stream 2 6 0.5 0.5 cum. 3.00
Parapet above slab Round portion 2 5.8 0.5 0.5 cum. 2.90
Total cum. 129.81 4750.55 616668.9 129.81 616668.90
6
Providing and laying reinforced cement
concrete in superstructure as per drawing and
technical specifications Clause 800,1205.4
and1205.5 (M-25)

In Bed Block above Abutment 2 12 0.4 0.2 cum. 1.92


Dirt wall beside Slab 2 12 0.3 0.43 cum. 3.10
For couping of return wall 4 4.3 0.4 0.1 cum. 0.69
Total cum. 5.71 6,015.28 34347.25 5.71 34347.25
7 Providing and laying reinforced cement
concrete in superstructure as per drawing and
technical specifications Clause 800,1205.4
and1205.5
In Slab 1 12 5.8 0.43 cum. 29.93
(0.250+0.1 1.39
For crash barrier 2 5.800 0.600
5)/2
In wearing Course 1 12 5.8 0.075 cum. 5.22
Total - cum. 36.54 6015.28 219798.33 36.54 219798.33
8 Suplying, Fixing, and placing HYSD bar 230635.88
reinforcement in superstructure as per drawing
and technical specifications Clause
1002,1010,1202 @ 1.50% of R.C.C. Work. QTL 43.60 5289.47 43.60 230635.88
9 Numbering/ white wasing of parapet walls of L.S. 500
Culvert with specified Paint 1 500 1.00 500.00
Pointing with Cement Mortar (1:3) 15mm.
10
Thick on stone work in superstructure as per
technical specification Clauses 613.4 and
1204
Abutment Faces 2 12 2.535 Sqm. 30.41
Return wall 4 5 3.146 Sqm. 15.73
Parapet Faces 2 5.8 1.5 Sqm. 8.70
Side of Parapet 4 0.35 0.6 Sqm. 0.21
End Face of Return Wall 4 1.078 3.13 Sqm. 13.50
Inside of Return Wall 4 0.522 3.13 Sqm. 6.53
outside of Return Wall 4 2.709 2.5 Sqm. 27.09
Total - cum. 102.17 57.06 5829.82 102.17 5829.82
11 Plastering with cement mortar (1:4) 15 mm.
thick on stone work in superstructure as per
technical specification Clauses 613.4 and
1204
4 0.5 0.5 Sqm. 1.00
Total - Sqm. 1 153.4 153.4 1.00 153.40
12 Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the
structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and
technical specification Clauses 614, 709,
1204.3.7
24 rm 24 129.01 3096.24 24.00 3096.24

13 Hand Packed stone filling in back of walls 2 10.5 1 2.5 cum. 52.50 2368.82 124363.05 52.50 124363.05
including cost of all materials, royality, T&P etc
complete as per direction of Engineer-in-
Charge

14 Cement Plum Concrete with 40% plum & 60% 2 6.5 1.5 1.5 cum. 29.25 3876.57 113389.67 29.25 113389.67
1:3:6 Cement Concrete including Supply of All
material, labour,T&P etc. required for proper
completion of the work as per
drawing/Technical specifications clause
802,803,1202 & 1203

Total Cost 2667545.14 2667545.14


Per R/M for Widening 213403.611 187963.447778418
For 5.00 Mtr widenning 939817.238892091
5 m. Span RCC Culvert.
DETAILS OF FOUNDATION LAY OUT PLAN
15400
6617 6617
###

3417 3200 2166 3200 3417


###

Road Centre Line

###
FoundationTrench
###
###

River,Canal,Nala etc. Centre Line


ABUTMENT WALL SECTION RETURN WALL SECTION
SPAN - 2 M
HEIGHT , CLEAR BETWEEN SLAB BOTTOM AND BED LEVEL- 3 M
GHT BETWEEN ROAD TOP LEVEL AND TOP OF FOOTING - 4.66 M
LENGTH OF RETURN WALL- 5 M mention

face painted and gap filled with bitumen


SPAN SLAB THICKNESS Wearing Coat - 20 mm premix carpet with seal coat PCC M15
1.5 1.5 210 400 300 400
2 2.0 240
2.5 3.0 300 PCC M20 ### ###
3 4.0 370 with surface reinf.
5.0 430 200
6.0 480
Top painted with bitumen

1:3
VERTICAL
1:3
2820 3260

100
1640 ### 1487

1400 1400

100 100 100 100


### ###

2440 2287

2640 2487
450 400 X 400 X 1000 RCC M20
450 X 375 KERB IN BRICK MASONRY IN 1:4
6600
SLAB 600 ABOVE GL

7500

X-SECTION SLAB

7500
END PILLARS

5000 DIRT 2000 DIRT 5000


RW SLAB RW
PLAN

SLAB REINFORCEMENT DETAILING NOTES :


1 Concrete - 1:1.5:3 .
10 DIA @ 300 C/C BOTH LONGITUDENAL AND TRANSVERSE DIRECTION 2 Steel - HYSD bars as per IS:1786
3 Cover - 40 mm at bottom and eac
88 NO. MAIN BARS 12 DIA @ 85 C/C 4 Only one bar to be cranked in each
DISTRIBUTION BARS 10 DIA @ 250 C/C
150 1688 150 5 All bars are cranked at one end on

. . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . 240 6 Design Loading - 2 Lanes IRC Cl
7 Bricks crushing strength > 7 MPa
8 Foundation concrete - M15.
300 2000 300 9 Abut. cap and cap on dirt wall and

416

160 1960

2 M SPAN
QUANTITY CALCULATION :
COMPONENT
SL NO ITEM QTT UNIT SUMMARY

1 FOUNDATION EXCAVATION RCC GRADE M25 4.68 CUM


ABUTMENTS 65.05 CUM 7.7 x 2.6 x 1.6 x 2 PCC GRADE M20 4.24 CUM
RETURN WALLS 79.58 CUM 5.0 x 2.5 x 1.6 x 2 X 2 REINFORCEMENT HYSD 723.2 KG
PCC GRADE M15 18.0792 CUM
2 ABUTMENT WALL BW 1:4 213.1832 CUM
PCC_FOUNDATION M15 8.13 CUM 7.7 X 2.64 X 0.2 X 2
BW 1:4 43.89 CUM ( 2.44 + 1.74 ) / 2 X 1.4 X 7.5 X 2 FOUNDATION EXCAVATION 144.6336 CUM
BW 1:5 49.49 CUM ( 1.64 + 0.7 ) / 2 X 2.82 X 7.5 X 2 POINTING 115.396 SQM

3 DIRT WALL AND ABUTMENT CAP


CONCRETE PCC M20 3.54 CUM ( 0.4 + 0.3 ) x ( 0.24 + 0.2 ) - ( 0.3 X 0.24 )X 7.5 X 2.0
REINFORCEMENT HYSD 108.00 KG 8 dia bars at 200 mm c/c on exposed faces.

4 RETURN WALL
PCC_FOUNDATION M15 9.95 CUM 5.0 X 2.487 X 0.2 X 2 X 2
BW 1:4 54.24 CUM ( 2.287 + 1.587 ) / 2 X 1.4 X 5.0 X 2 X 2
BW 1:5 61.52 CUM ( 1.487 + 0.4 ) / 2 X 3.26 X 5.0 X 2 X 2
PCC_COPING M20 0.06 CUM as per RRM
REINFORCEMENT HYSD 0.24 KG as per RRM

5 SLAB
CONCRETE RCC M25 4.68 CUM 1 X ( 2 + 2 X 0.3 ) X 7.5 X 0.24
REINFORCEMENT HYSD 478.00 KG as per RRM

6 KERB
BW 1:4 4.05 CUM ( 2 X 0.45 X 0.375 ) X 12

7 RC PILLARS AT THE ENDS


PCC M20 0.64 CUM 0.4 x 0.4 x 1x 4
REINFORCEMENT HYSD 136.96 KG 8 # 8 dia bars each 1 m long + 6 stirrups each 3.6 m long

8 POINTING
ABUT FACE WALL 42.3 SQM 2.82 x 7.5 x 2
ABUT SIDE WALL 7.90 SQM 0.7 x 2.82 x 4
RETURN FACE WALL 65.2 SQM 3.26 x 5 x 4
TYPICAL PROPOSED X-SECTION FOR UPGRADATION FORMAT - 3

IN CH.0.00 TO 6.075 Km

WBM Grade -II (75mm)and WBM Grade -III (75mm)in layers 3.75 m width
BASE COURSE
Premix carpet followed by seal coat type C GSB 200mm thick in widing only

Road way 7.5 m

Shoulder at 4% slope Carriageway 3.75 m at 3 % slope 1.875 m wide shoulder


Existing Embankment

Existing pavement

J.E. A.E. E.E.


CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow
TYPICAL EXISTING X-SECTION FOR UPGRADATION FORMAT - 3

IN CH.0.00 TO 6.075 Km

WBM- 200mm layers 3.00 m width


BASE COURSE
###

Road way 5.00 m

Carriageway 3.00 m 1.00 m wide shoulder


Existing Embankment

Existing pavement

J.E. A.E. E.E.


CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow CD-3(PP), PWD, Lucknow
Construction of 2x2 m span of 4 cells RCC Box culvert

S. Item of work No. Length Width Height Quantity Rate Amount


No (m) (m)
(m)
1 2 4 5 6 7 8 9
1 Earthwork in Excavation for structures as per Drawing and
technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps and
other deletorious material and disposal upto a lead of 50 metre,

For Below of Raft Length of Raft 1 11.45 12.50 2.00 286.25


For Cut off walls U/s and D/S 2 11.45 0.75 1.00 17.18
For cut off walls L/s and R/S 2 12.50 0.75 1.00 18.75
Deduct for existing profile of drain /Nala -1 12.50 10.00 1.50 -187.50
For Bed protection walls U/s and D/S 2 11.45 0.75 1.00 17.18
Total 151.85 Cum 101.00 15336.85
2 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with smooth wheel roller to achieve
the desired density

For Below of Raft Length of Raft 1 11.45 12.50 0.15 21.47


For Cut off walls U/s and D/S 2 11.45 0.75 0.15 2.58
For cut off walls L/s and R/S 2 12.50 0.75 0.15 2.81
For Bed protection walls U/s and D/S 2 11.45 0.75 0.15 2.58
Total 29.43 Cum 2882.69 84848.38
3 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-15, Nominal mix 1:3:6
For Below of Raft Length of Raft 1 11.45 12.50 0.10 14.31
For Cut off walls U/s and D/S 2 11.45 0.75 0.10 1.72
For cut off walls L/s and R/S 2 12.50 0.75 0.10 1.88
For Bed protection walls U/s and D/S 2 11.45 0.75 0.10 1.72
Total 19.62 Cum 5265.17 103315.8
4 Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 and 1204 (M-25)
Box Upper and Bottom Slab 2 11.45 12.50 0.25 71.56
Box Upper and Bottom Slab 2 11.45 0.75 0.00 0.00
Abutment 2 12.50 0.25 2.00 12.50
Pier 3 12.50 0.25 2.00 18.75
Haunch 0.5*8 12.50 0.15 0.15 1.13
Approach Slab 2 4.50 12.50 0.30 33.75
Wearing Coat 1 11.45 12.50 0.025 3.58
Wing Walls 4 4.50 0.25 2.00 9.00
Total 150.27 Cum 6015.28 903889.81
5 Suplying, Fixing, and placing HYPD bar reinforcement in
superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.0% of R.C.C. Work.
Total 146.69 Cum Excluding wearing coa
Total weight of Steel @1.0%= 115.15 Qtl 5289.47 609080.93
6 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

30 30.00 Nos. 389.29 11678.70


7 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301
U/S 1 11.45 3.00 0.60 20.61 Cum
D/S 1 11.45 5.00 0.60 34.35 Cum
Total 54.96 Cum 2501.59 137487.39
Total ###

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra

file:///conversion/tmp/scratch/454781501.xls2x2 box
Construction of 3x3 m span of 4 cells RCC Box culvert

S. Item of work No. Length Width Height Quantity Rate Amount


No (m) (m)
(m)
1 2 4 5 6 7 8 9
1 Earthwork in Excavation for structures as per Drawing and
technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps and
other deletorious material and disposal upto a lead of 50 metre,

For Below of Raft Length of Raft 1 16.95 12.50 3.00 635.63


For Cut off walls U/s and D/S 2 16.95 0.75 1.00 25.43
For cut off walls L/s and R/S 2 12.50 0.75 1.00 18.75
Deduct for existing profile of drain /Nala -1 12.50 10.00 1.50 -187.50
For Bed protection walls U/s and D/S 2 16.95 0.75 1.00 25.43
Total 517.73 Cum 101.00 52290.23
2 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with smooth wheel roller to achieve
the desired density

For Below of Raft Length of Raft 1 16.95 12.50 0.15 31.78


For Cut off walls U/s and D/S 2 16.95 0.75 0.15 3.81
For cut off walls L/s and R/S 2 12.50 0.75 0.15 2.81
For Bed protection walls U/s and D/S 2 16.95 0.75 0.15 3.81
Total 42.22 Cum 2882.69 121710.78
3 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-15, Nominal mix 1:3:6
For Below of Raft Length of Raft 1 16.95 12.50 0.10 21.19
For Cut off walls U/s and D/S 2 16.95 0.75 0.10 2.54
For cut off walls L/s and R/S 2 12.50 0.75 0.10 1.88
For Bed protection walls U/s and D/S 2 16.95 0.75 0.10 2.54
Total 28.15 Cum 5265.17 148201.37
4 Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 and 1204 (M-25)
Box Upper and Bottom Slab 2 16.95 12.50 0.40 169.50
Abutment 2 12.50 0.40 3.00 30.00
Pier 3 12.50 0.30 3.00 33.75
Haunch 0.5*8 12.50 0.15 0.15 1.13
Approach Slab 2 4.50 12.50 0.30 33.75
Wearing Coat 1 16.95 12.50 0.025 5.30
Wing Walls 4 4.50 0.40 3.00 21.60
Total 295.02 Cum 6015.28 1774639.18
5 Suplying, Fixing, and placing HYPD bar reinforcement in
superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.0% of R.C.C. Work.
Total 289.73 Cum Excluding wearing coa
Total weight of Steel @1.0%= 227.43 Qtl 5289.47 1203006.21
6 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

30 30.00 Nos. 389.29 11678.70


7 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301
U/S 1 16.95 3.00 0.60 30.51 Cum
D/S 1 16.95 5.00 0.60 50.85 Cum
Total 81.36 Cum 2501.59 203529.36
Total ###

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra

file:///conversion/tmp/scratch/454781501.xls3x3 box
Construction of 4x4 m span of 4 cells RCC Box culvert

S. Item of work No. Length Width Height Quantity Rate Amount


No (m) (m)
(m)
1 2 4 5 6 7 8 9
1 Earthwork in Excavation for structures as per Drawing and
technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps and
other deletorious material and disposal upto a lead of 50 metre,

For Below of Raft Length of Raft 1 22.05 12.50 4.00 1102.50


For Cut off walls U/s and D/S 2 22.05 0.75 1.00 33.08
For cut off walls L/s and R/S 2 12.50 0.75 1.00 18.75
Deduct for existing profile of drain /Nala -1 12.50 10.00 1.50 -187.50
For Bed protection walls U/s and D/S 2 22.05 0.75 1.00 33.08
Total 999.90 Cum 101.00 100989.9
2 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with smooth wheel roller to achieve
the desired density

For Below of Raft Length of Raft 1 22.05 12.50 0.15 41.34


For Cut off walls U/s and D/S 2 22.05 0.75 0.15 4.96
For cut off walls L/s and R/S 2 12.50 0.75 0.15 2.81
For Bed protection walls U/s and D/S 2 22.05 0.75 0.15 4.96
Total 54.08 Cum 2882.69 155892.27
3 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-15, Nominal mix 1:3:6
For Below of Raft Length of Raft 1 22.05 12.50 0.10 27.56
For Cut off walls U/s and D/S 2 22.05 0.75 0.10 3.31
For cut off walls L/s and R/S 2 12.50 0.75 0.10 1.88
For Bed protection walls U/s and D/S 2 22.05 0.75 0.10 3.31
Total 36.05 Cum 5265.17 189822.54
4 Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 and 1204 (M-25)
Box Upper and Bottom Slab 2 22.05 12.50 0.45 248.06
Abutment 2 12.50 0.45 4.00 45.00
Pier 3 12.50 0.35 4.00 52.50
Haunch 0.5*8 12.50 0.15 0.15 1.13
Approach Slab 2 4.50 12.50 0.30 33.75
Wearing Coat 1 22.05 12.50 0.025 6.89
Wing Walls 4 4.50 0.45 4.00 32.40
Total 419.73 Cum 6015.28 2524782.2
5 Suplying, Fixing, and placing HYPD bar reinforcement in
superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.0% of R.C.C. Work.
Total 412.84 Cum Excluding wearing coa
Total weight of Steel @1.0%= 324.08 Qtl 5289.47 1714198.21
6 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

30 30.00 Nos. 389.29 11678.70


7 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301
U/S 1 22.05 3.00 0.60 39.69 Cum
D/S 1 22.05 5.00 0.60 66.15 Cum
Total 105.84 Cum 2501.59 264768.29
Total ###

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra

file:///conversion/tmp/scratch/454781501.xls4x4 box
Construction of 5x5 m span of 4 cells RCC Box culvert

S. Item of work No Length Width Height Quantity Rate Amount


No .
(m) (m) (m)
1 2 4 5 6 7 8 9
1 Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking
the serviceable material with all lifts and lead of 1000 m as
per Technical Specification Clause 202.

For Below of Raft Length of Raft 1 249.00 5.00 3.00 3735.00


3735.00 Cum 505.13 1886660.55
Total

2 Earthwork in Excavation for structures as per Drawing and


technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps
and other deletorious material and disposal upto a lead of
50 metre,

For Below of Raft Length of Raft 1 27.30 12.50 5.00 1706.25


For Cut off walls U/s and D/S 2 27.30 0.75 1.00 40.95
For cut off walls L/s and R/S 2 12.50 0.75 1.00 18.75
Deduct for existing profile of drain /Nala -1 12.50 10.00 1.50 -187.50
For Bed protection walls U/s and D/S 2 27.30 0.75 1.00 40.95
1619.40 Cum 101.00 163559.4
Total

3 Construction of granular sub-base by providing well graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with smooth wheel
roller to achieve the desired density

For Below of Raft Length of Raft 1 27.30 12.50 0.15 51.19


For Cut off walls U/s and D/S 2 27.30 0.75 0.15 6.14
For cut off walls L/s and R/S 2 12.50 0.75 0.15 2.81
For Bed protection walls U/s and D/S 2 27.30 0.75 0.15 6.14
66.29 Cum 2882.69 191079.11
Total

4 Providing concrete Reinforced concrete in open foundation


complete , as per drawing and technical specification
clause 802,803,1203 P.C.C. grade M-15, Nominal mix 1:3:6

For Below of Raft Length of Raft 1 27.30 12.50 0.10 34.13


For Cut off walls U/s and D/S 2 27.30 0.75 0.10 4.10
For cut off walls L/s and R/S 2 12.50 0.75 0.10 1.88
For Bed protection walls U/s and D/S 2 27.30 0.75 0.10 4.10
44.19 Cum 5265.17 232667.86
Total

5 Plain/reinforced cement concrete in substructure complete


as per drawings and technical specification Clauses 802,
804, 805, 806, 807, 1202 and 1204 (M-25)
Box Upper and Bottom Slab 2 27.30 12.50 0.50 341.25
Abutment 2 12.50 0.50 5.00 62.50
Pier 3 12.50 0.40 5.00 75.00
Haunch 0.5 1.13
12.50 0.15 0.15
*8
Approach Slab 2 4.50 12.50 0.30 33.75
Wearing Coat 1 27.30 12.50 0.025 8.53
Wing Walls 4 4.50 0.50 5.00 45.00
567.16 Cum 6015.28 3411603.65
Total

6 Suplying, Fixing, and placing HYPD bar reinforcement in


superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.0% of R.C.C. Work.
Total 558.63 Cum Excluding wearing co
Total weight of Steel
438.52 Qtl 4197.95 1840889.41
@1.0%=
7 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall
with 100 mm dia AC pipe extending through the full width of
the structures with slope of 1(V):20(H) towards drawing
face complete as per drawing and technical specification
Clauses 614, 709, 1204.3.7

30 30.00 Nos. 129.01 3870.30


8 Providing and laying boulder apron for bed protection with
stone boulders of minimum size and weight as per Table
1300.1, no fragment weighing less than 25 kg laid dry
complete as per drawing and technical specifications
Clause 1301

U/S 1 27.30 3.00 0.60 49.14 Cum


D/S 1 27.30 5.00 0.60 81.90 Cum
131.04 Cum 2501.59 327808.35
Total

Total 8058138.63
say 2014534.658
Engineer
Junior Engineer PMGSY Division, Executive Engineer
PMGSY Division, PWD PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
Construction of 16.80 m span of RCC Box culvert

S. Item of work No. Length Width Height Quantity Rate Amount


No (m) (m)
(m)
1 2 4 5 6 7 8 9
1 Dismantling of existing structures like culverts, bridges, retaining
walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with
all lifts and lead of 1000 m as per Technical Specification Clause
202.

1 16.80 5.00 1.00 84.00


Total 84.00 Cum 505.13 42430.92
2 Dewatering of water trenches during excavation, concreting,
masonary work upto sub soil/water level including hire charges of
5 HP Pump
1 1.00 Job
Total 1.00 Job 25000.00 25000.00
3 Earthwork in Excavation for structures as per Drawing and
technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps and
other deletorious material and disposal upto a lead of 50 metre,

Bridge 1 16.80 12.80 5.00 1075.20


Bridge shear key 2 16.80 (0.30+0.9)/2 0.60 12.10
Retaining wall left 1 8.70 12.80 5.00 556.80
Retaining wall right 1 8.70 12.80 5.00 556.80
Curtain wall (U/S) 1 16.80 1.50 2.10 52.92
Curtain wall (D/S) 1 16.80 1.85 2.60 80.81
Toe Wall Left 1 16.80 1.00 1.00 16.80
Toe Wall right 1 16.80 1.00 1.00 16.80
Stone Pitching Toe wall Left anf right 4 1/4*3.14*5.5**1.5*0.5 12.95
For GSB below raft 1 16.80 12.80 2.10 451.58
Total 2832.76 Cum 101.00 286108.81
4 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with smooth wheel roller to achieve
the desired density

Bridge 1 16.80 12.80 0.15 32.26


Bridge shear key 2 16.80 (0.30+0.9)/2 0.15 3.02
Retaining wall left 2 8.70 10.20 0.15 26.62
Retaining wall right 2 8.70 10.20 0.15 26.62
Curtain wall (U/S) 1 16.80 1.50 0.15 3.78
Curtain wall (D/S) 1 16.80 1.85 0.15 4.66
Toe Wall Left 1 11.15 1.00 0.15 1.67
Toe Wall right 1 11.15 1.00 0.15 1.67
For GSB below raft 1 16.80 1.50 0.15 3.78
Total 104.09 Cum 2882.69 300062.08
5 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-15, Nominal mix 1:3:6
Bridge 1 16.80 12.80 0.10 21.50
Bridge shear key 2 16.80 (0.30+0.9)/2 0.10 2.02
Retaining wall left 2 8.70 10.20 0.10 17.75
Retaining wall right 2 8.70 10.20 0.10 17.75
Curtain wall (U/S) 1 16.80 1.50 0.10 2.52
Curtain wall (D/S) 1 16.80 1.85 0.10 3.11
Toe Wall Left 1 11.15 1.00 0.10 1.12
Toe Wall right 1 11.15 1.00 0.10 1.12
For GSB below raft 1 16.80 1.50 0.10 2.52
Total 69.39 Cum 5265.17 365371.21
6 Stone masonry in 1:5 cement mortar for substructure complete
as per drawing & technical specification Clauses 702, 704, 1202
and 1204
Curtain wall (U/S) 1 16.80 0.50 1.50 12.60
Curtain wall (D/S) 1 16.80 0.50 1.50 12.60
Total 25.20 Cum 4750.55 119713.86
7 Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 and 1204 (M-30)
Box Upper and Bottom Slab 1 16.80 12.50 0.15 31.50

file:///conversion/tmp/scratch/454781501.xls16.8
S. Item of work No. Length Width Height Quantity Rate Amount
No (m) (m)
(m)
1 2 4 5 6 7 8 9
Shear Key 2 16.80 (0.30+0.9)/2 0.60 12.10
Bridge bottom Haunch 0.5*6 12.50 0.15 0.15 1.13
Retaining wall bottom slab 2 8.50 12.50 0.75 159.38
Retaining wall haunch 4*0.5 8.50 0.15 0.15 0.38
Total 204.48 Cum 6499.19 1328944.62
8 Providingpressure relief pipe, plain/ reinforced concrete with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 614, 709, 1204.3.7

30 30.00 Nos. 129.01 3870.30


9 Plain/reinforced cement concrete in super structure complete as
per drawings and technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 (M-30)
Box Top Slab 1 16.80 12.50 0.50 105.00
Abutment 2 12.50 0.55 5.00 68.75
Piers 2 12.50 0.35 5.00 43.75
Top Haunch 6*0.5 12.50 0.15 0.15 0.84
(12.5+5.50)/
Approach slab 2 3.50 0.30 18.90
2
Retaining walls 4 8.50 0.55 0.575 10.75
Retaining wall haunch 4*0.5 8.50 0.15 0.15 0.38
Crash barrier 2 33.80 0.32 0.25 5.41
Crash barrier 2 33.80 0.50 0.10 3.38
Crash barrier 2 33.80 0.20 0.75 10.14
Wearing coat 1 16.80 12.50 0.075 15.75
Total 283.06 Cum 6499.19 1839639.60
10 Suplying, Fixing, and placing HYPD bar reinforcement in
superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.0% of R.C.C. Work.
Total 452.89 Cum Excluding wearing coat

Total weight of Steel @1.0%= 355.51 Qtl 4197.95 1492435.29


11 Providing and fixing of drainage spout for disposal of rain water
6 6.00 Nos. 129.01 774.06
12 Cement Plum Concrete with 40% plum & 60% 1:3:6 Cement
Concrete including Supply of All material, labour,T&P etc.
required for proper completion of the work as per
drawing/Technical specifications clause 802,803,1202 & 1203
Bed protection 2 16.80 1.50 1.50 75.60
Total 75.60 Cum 3876.57 293068.69
13 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

Abutment 2 3x5 30 Nos.


Retaining wall 4 4x5 80 Nos.
4 110.00 Nos. 129.01 14191.10
14 Hand Packed stone filling in back of walls including cost of all
materials, royality, T&P etc complete as per direction of
Engineer-in-Charge
Behind abutment 2 11.15 0.60 5.50 73.59 Cum
Behind Retaining walls 4 8.50 0.60 5.50 112.20 Cum
Total 185.79 Cum 3876.57 720227.94
15 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301
U/S 1 16.80 3.00 1.00 50.40 Cum
D/S 1 16.80 6.00 1.00 100.80 Cum
Total 151.20 Cum 2501.59 378240.41
16 Providing and laying filter material underneath pitching in slopes
complete as per drawing and technical specifications Clause
1302
4 11.15 7.44 0.15 49.77 Cum
Total 49.77 Cum 2439.61 121428.17
17 Providing and laying pitching on slopes laid over prepared filter
media as per drawing and technical specifications Clause 1302
4 11.15 7.44 0.30 99.55 Cum
Toe wall 4 11.15 1.00 1.00 44.60 Cum

file:///conversion/tmp/scratch/454781501.xls16.8
S. Item of work No. Length Width Height Quantity Rate Amount
No (m) (m)
(m)
1 2 4 5 6 7 8 9
Total 144.15 Cum 2501.59 360597.19
Total 7692104.25

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra

file:///conversion/tmp/scratch/454781501.xls16.8
Construction of 16.80 m span of RCC Box culvert

S. Item of work No. Length Width Height Quantity Rate Amount


No (m) (m)
(m)
1 2 4 5 6 7 8 9
1 Dismantling of existing structures like culverts, bridges, retaining
walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with
all lifts and lead of 1000 m as per Technical Specification Clause
202.

1 27.50 5.00 1.00 137.50


Total 137.50 Cum 505.13 69455.38
2 Dewatering of water trenches during excavation, concreting,
masonary work upto sub soil/water level including hire charges of
5 HP Pump
1 1.00 Job
Total 1.00 Job 25000.00 25000.00
3 Earthwork in Excavation for structures as per Drawing and
technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps and
other deletorious material and disposal upto a lead of 50 metre,

Bridge 1 27.50 12.80 5.00 1760.00


Bridge shear key 2 27.50 (0.30+0.9)/2 0.60 19.80
Retaining wall left 1 8.70 12.80 5.00 556.80
Retaining wall right 1 8.70 12.80 5.00 556.80
Curtain wall (U/S) 1 27.50 1.50 2.10 86.63
Curtain wall (D/S) 1 27.50 1.85 2.60 132.28
Toe Wall Left 1 27.50 1.00 1.00 27.50
Toe Wall right 1 27.50 1.00 1.00 27.50
Stone Pitching Toe wall Left anf right 4 1/4*3.14*5.5**1.5*0.5 12.95
For GSB below raft 1 27.50 12.80 2.10 739.20
Total 3919.45 Cum 101.00 395864.70
4 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with smooth wheel roller to achieve
the desired density

Bridge 1 27.50 12.80 0.15 52.80


Bridge shear key 2 27.50 (0.30+0.9)/2 0.15 4.95
Retaining wall left 2 8.70 10.20 0.15 26.62
Retaining wall right 2 8.70 10.20 0.15 26.62
Curtain wall (U/S) 1 27.50 1.50 0.15 6.19
Curtain wall (D/S) 1 16.80 1.85 0.15 4.66
Toe Wall Left 1 11.15 1.00 0.15 1.67
Toe Wall right 1 11.15 1.00 0.15 1.67
For GSB below raft 1 27.50 1.50 0.15 6.19
Total 131.38 Cum 2882.69 378716.28
5 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-15, Nominal mix 1:3:6
Bridge 1 27.50 12.80 0.10 35.20
Bridge shear key 2 27.50 (0.30+0.9)/2 0.10 3.30
Retaining wall left 2 8.70 10.20 0.10 17.75
Retaining wall right 2 8.70 10.20 0.10 17.75
Curtain wall (U/S) 1 27.50 1.50 0.10 4.13
Curtain wall (D/S) 1 16.80 1.85 0.10 3.11
Toe Wall Left 1 11.15 1.00 0.10 1.12
Toe Wall right 1 11.15 1.00 0.10 1.12
For GSB below raft 1 27.50 1.50 0.10 4.13
Total 87.58 Cum 5265.17 461144.65
6 Stone masonry in 1:5 cement mortar for substructure complete
as per drawing & technical specification Clauses 702, 704, 1202
and 1204
Curtain wall (U/S) 1 27.50 0.50 1.50 20.63
Curtain wall (D/S) 1 16.80 0.50 1.50 12.60
Total 33.23 Cum 4750.55 157837.02
7 Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 and 1204 (M-30)
Box Upper and Bottom Slab 1 27.50 12.50 0.15 51.56

file:///conversion/tmp/scratch/454781501.xls27.5
S. Item of work No. Length Width Height Quantity Rate Amount
No (m) (m)
(m)
1 2 4 5 6 7 8 9
Shear Key 2 27.50 (0.30+0.9)/2 0.60 19.80
Bridge bottom Haunch 0.5*10 12.50 0.15 0.15 1.41
Retaining wall bottom slab 2 8.50 12.50 0.75 159.38
Retaining wall haunch 4*0.5 8.50 0.15 0.15 0.38
Total 232.53 Cum 6499.19 1511232.28
8 Providingpressure relief pipe, plain/ reinforced concrete with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 614, 709, 1204.3.7

30 30.00 Nos. 129.01 3870.30


9 Plain/reinforced cement concrete in super structure complete as
per drawings and technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 (M-30)
Box Top Slab 1 27.50 12.50 0.50 171.88
Abutment 2 12.50 0.55 5.00 68.75
Piers 2 12.50 0.35 5.00 43.75
Top Haunch 6*0.5 12.50 0.15 0.15 0.84
(12.5+5.50)/
Approach slab 2 3.50 0.30 18.90
2
Retaining walls 4 8.50 0.55 0.575 10.75
Retaining wall haunch 0.5*10 12.50 0.15 0.15 1.41
Crash barrier 2 33.80 0.32 0.25 5.41
Crash barrier 2 33.80 0.50 0.10 3.38
Crash barrier 2 33.80 0.20 0.75 10.14
Wearing coat 1 27.50 12.50 0.075 25.78
Total 360.99 Cum 6499.19 2346121.48
10 Suplying, Fixing, and placing HYPD bar reinforcement in
superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.0% of R.C.C. Work.
Total 548.83 Cum Excluding wearing coat

Total weight of Steel @1.0%= 430.83 Qtl 4197.95 1808616.80


11 Providing and fixing of drainage spout for disposal of rain water
6 6.00 Nos. 129.01 774.06
12 Cement Plum Concrete with 40% plum & 60% 1:3:6 Cement
Concrete including Supply of All material, labour,T&P etc.
required for proper completion of the work as per
drawing/Technical specifications clause 802,803,1202 & 1203
Bed protection 2 27.50 1.50 1.50 123.75
Total 123.75 Cum 3876.57 479725.54
13 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

Abutment 2 3x5 30 Nos.


Retaining wall 4 4x5 80 Nos.
4 110.00 Nos. 129.01 14191.10
14 Hand Packed stone filling in back of walls including cost of all
materials, royality, T&P etc complete as per direction of
Engineer-in-Charge
Behind abutment 2 11.15 0.60 5.50 73.59 Cum
Behind Retaining walls 4 8.50 0.60 5.50 112.20 Cum
Total 185.79 Cum 3876.57 720227.94
15 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301
U/S 1 27.50 3.00 1.00 82.50 Cum
D/S 1 27.50 6.00 1.00 165.00 Cum
Total 247.50 Cum 2501.59 619143.53
16 Providing and laying filter material underneath pitching in slopes
complete as per drawing and technical specifications Clause
1302
4 11.15 7.44 0.15 49.77 Cum
Total 49.77 Cum 2439.61 121428.17
17 Providing and laying pitching on slopes laid over prepared filter
media as per drawing and technical specifications Clause 1302
4 11.15 7.44 0.30 99.55 Cum
Toe wall 4 11.15 1.00 1.00 44.60 Cum

file:///conversion/tmp/scratch/454781501.xls27.5
S. Item of work No. Length Width Height Quantity Rate Amount
No (m) (m)
(m)
1 2 4 5 6 7 8 9
Total 144.15 Cum 2501.59 360597.19
Total 9473946.42

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra

file:///conversion/tmp/scratch/454781501.xls27.5
Construction of 7.5x5m span of 5 cells RCC Box culvert
Height
S. Length Width
Item of work No. Quantity Rate Amount
No (m) (m)
(m)
1 2 4 5 6 7 8 9
1 Dismantling of existing structures like culverts, bridges, retaining
walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with
all lifts and lead of 1000 m as per Technical Specification Clause
202.

1 40.30 7.50 3.00 906.75


Total 906.75 Cum 510.66 463040.96
2 Dewatering of water trenches during excavation, concreting,
masonary work upto sub soil/water level including hire charges of
5 HP Pump
1 1.00 Job
Total 1.00 Job 25000.00 25000.00
3 Earthwork in Excavation for structures as per Drawing and
technical specification Clause -305.1 including setting out,
construction of shoring and bracing , removal of slumps and
other deletorious material and disposal upto a lead of 50 metre,

Bridge 1 40.30 12.80 1.98 1021.36


Bridge shear key 2 40.30 1.00 0.70 56.42
Retaining wall left 1 11.75 12.80 5.25 789.60
Retaining wall right 1 11.75 12.80 5.25 789.60
Curtain wall (U/S) 1 46.10 1.50 3.28 226.74
Curtain wall (D/S) 1 46.10 1.85 3.78 322.38
Toe Wall Left 1 46.10 1.00 1.00 46.10
Toe Wall right 1 46.10 1.00 1.00 46.10
Stone Pitching Toe wall Left anf right 2 11.16 1.00 1.05 23.44
For GSB below raft 1 40.30 12.80 0.20 103.17
Deduction For GSB below Shear Key -2 40.30 0.75 0.60 -36.27
For GSB below apron U/S 1 40.30 3.00 0.20 24.18
For GSB below apron D/S 1 40.30 5.00 0.20 40.30
Deduction For curtain wall -1 40.30 0.45 0.80 -14.51
-1 40.30 0.10 0.75 -3.02
-1 40.30 0.53 0.55 -11.75
-1 40.30 0.20 0.75 -6.05
-1 40.30 0.10 0.75 -3.02
Total 3414.77 Cum 110.00 375624.91
4 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-10, Nominal mix 1:3:6
Bridge 1 40.30 12.80 0.10 51.58
Bridge shear key 2 40.30 1.25 0.10 4.84
Below rigid apron (U/S) 1 46.80 4.80 0.10 22.46
Below rigid apron (D/S) 1 46.80 2.80 0.10 13.10
Retaining wall left 1 11.75 3.00 0.10 3.53
Retaining wall right 1 11.75 0.45 0.10 0.53
Curtain wall (Left) 1 46.10 0.10 0.10 0.46
Curtain wall (Right) 1 46.10 5.00 0.10 23.05
Toe Wall Left 1 40.30 0.10 0.10 0.40
Below Approach slab Left 1 8.70 5.80 0.10 5.05
Below Approach slab Left 1 8.70 5.80 0.10 5.05
Total 130.05 Cum 5265.17 684723.51
5 Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with smooth wheel roller to achieve
the desired density

RCC Raft of box 1 40.30 12.80 0.20 103.17


Deduct Bridge shear key -2 40.30 0.75 0.60 -29.02
For GSB Below Bridge 1 40.30 12.70 0.20 102.36
For GSB Below Apron U/S 1 40.30 3.00 0.20 24.18

Deuction for curtain wall -1 40.30 0.45 0.80 -14.51


-1 40.30 0.10 0.75 -3.02
For GSB below apron D/S 1 40.30 5.00 0.20 40.30
Deuction for curtain wall -1 40.30 0.55 0.53 -11.75
-1 40.30 0.20 0.75 -6.05
Toe Wall Left -1 40.30 0.10 0.75 -3.02
Total 202.65 Cum 3036.76 615395.01
6 Stone masonry in 1:5 cement mortar for substructure complete
as per drawing & technical specification Clauses 702, 704, 1202
and 1204 for water training
Curtain wall (U/S) 1 40.30 0.50 1.50 30.23
Curtain wall (D/S) 1 16.80 0.50 1.50 12.60
Total 42.83 Cum 4750.55 203442.30
7 Plain/reinforced cement concrete in substructure complete as per
drawings and technical specification Clauses 802, 804, 805, 806,
807, 1202 and 1204 (M-30)
Box Bottom Slab 1 40.30 12.50 0.70 352.63
Shear Key 2 40.30 0.60 0.60 29.02
Bridge bottom and upper Haunch 2*5 12.50 0.15 0.15 2.81
Retaining wall bottom slab left and right 2 11.55 12.50 0.90 259.88
Retaining wall haunch left and right 2*4 11.55 0.15 0.15 2.08
Total 646.41 Cum 6889.01 4453107.73
8 Providingpressure relief pipe, plain/ reinforced concrete with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 614, 709, 1204.3.7

60 60.00 Nos. 129.01 7740.60


9 Plain/reinforced cement concrete in super structure complete as
per drawings and technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 (M-30)
Box Top Slab 1 40.30 12.50 0.60 302.25
Abutment 2 12.50 0.60 5.00 75.00
Piers 4 12.50 0.35 5.00 87.50
Top Haunch 2*5*0.5 12.50 0.15 0.15 1.41
Approach slab 2 8.50 5.50 0.30 28.05
Retaining walls left 2 11.55 0.65 6.55 98.35
Retaining walls left 2 11.55 0.65 4.65 69.82
Retaining wall haunch 0.5*4 12.50 0.15 0.15 0.56
Crash barrier 2 33.80 0.32 0.25 5.41
Crash barrier 2 33.80 0.50 0.10 3.38
Crash barrier 2 33.80 0.20 0.75 10.14
Wearing coat 1 40.30 12.50 0.075 37.78
Total 719.65 Cum 6889.01 4957648.49
10 Suplying, Fixing, and placing HYSD bar reinforcement in
superstructure as per drawing and technical specifications
Clause 1002,1010,1202 @ 1.20% of R.C.C. Work.
Excluding wearing coat and
Total 1300.22 Cum
approach slab
Total weight of Steel @1.20%= 1224.81 Qtl 5289.47 6478593.59
11 Providing and fixing of drainage spout for disposal of rain water
6 6.00 Nos. 129.01 774.06
12 Cement Plum Concrete with 40% plum & 60% 1:3:6 Cement
Concrete including Supply of All material, labour,T&P etc.
required for proper completion of the work as per
drawing/Technical specifications clause 802,803,1202 & 1203
Bed protection 2 40.30 1.50 1.50 181.35
Total 181.35 Cum 3876.57 703015.97
13 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7

Abutment 2 3x5 30.00 Nos.


Retaining wall 4 4x5 80.00 Nos.
4 110.00 Nos. 129.01 14191.10
14 Hand Packed stone filling in back of walls including cost of all
materials, royality, T&P etc complete as per direction of
Engineer-in-Charge
Behind abutment
2 12.50 (0.6+2.0)/2 5.50 178.75 Cum

Behind Retaining walls


4 8.50 (0.6+2.0)/2 5.50 243.10 Cum
Total 421.85 Cum 435.00 183504.75
15 Providing and laying filter material underneath pitching in slopes
complete as per drawing and technical specifications Clause
1302
Behind abutment 2 40.30 0.60 5.50 265.98 Cum
Behind Retaining walls 4 8.50 0.60 5.50 112.20 Cum
Total 378.18 Cum 2439.61 922611.71
16 Bed protection of cement concrete flooring with flat stone flooring

U/S 1 40.10 8.00 0.10 32.08 Cum


D/S 1 40.10 8.00 0.10 32.08 Cum
Total 64.16 Cum 6015.28 385940.36
17 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-10, Nominal mix 1:3:6 for flooring
U/S 1 40.10 8.00 0.30 96.24 Cum
D/S 1 40.10 8.00 0.30 96.24 Cum
Total 192.48 Cum 5265.17 1013439.92
18 Suplying, Fixing, of expansion joint complete as per drawing and
technical specifications
20 mm asphalt plug Jont 5 12.50 62.50 RM
Total 62.50 RM 2500.00 156250.00
19 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301
U/S 1 40.30 3.00 1.00 120.90 Cum
D/S 1 40.30 6.00 1.00 241.80 Cum
Total 362.70 Cum 2501.59 907326.69
20 Providing and laying filter material underneath pitching in slopes
complete as per drawing and technical specifications Clause
1302
4 12.50 7.44 0.15 55.80 Cum
Total 55.80 Cum 2439.61 136130.24
21 Providing and laying pitching on slopes laid over prepared filter
media as per drawing and technical specifications Clause 1302
4 11.15 7.44 0.30 99.55 Cum
Toe wall 4 11.15 1.00 1.00 44.60 Cum
Total 144.15 Cum 2501.59 360597.19
22 Providing concrete Reinforced concrete in open foundation
complete , as per drawing and technical specification clause
802,803,1203 P.C.C. grade M-10, Nominal mix 1:3:6 for
Curtain wall U/S 1 46.10 1.30 0.80 47.94 Cum
1 46.10 0.45 0.75 15.56 Cum
1 46.10 0.20 0.45 4.15 Cum
D/S 1 46.10 0.75 0.75 25.93 Cum
1 46.10 0.45 0.75 15.56 Cum
1 46.10 0.20 0.45 4.15 Cum
Total 144.15 Cum 5265.17 758959.51
Total 23807058.60
Construction of 40.10 m span of RCC Box culvert

S. Item of work No. Length Width Height Quantity Rate Amount

1 2 4 5 6 7 8 9
1 Dismantling of existing structures like culverts,
bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work,
including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 m as per
Technical Specification Clause 202.

1 40.1 5 1 200.5
Total 200.5 Cum 505.13 101278.57
2 Dewatering of water trenches during excavation,
concreting, masonary work upto sub soil/water level
including hire charges of 5 HP Pump
1 1 Job
Total 1 Job 25000 25000
3 Earthwork in Excavation for structures as per Drawing
and technical specification Clause -305.1 including
setting out, construction of shoring and bracing ,
removal of slumps and other deletorious material and
disposal upto a lead of 50 metre,
Bridge 1 40.1 12.8 7.5 3849.6
Bridge shear key 2 40.1 (0.30+0.9)/ 0.6 28.872
Retaining wall left 1 11.75 12.8 7.5 1128
Retaining wall right 1 11.75 12.8 7.5 1128
Curtain wall (U/S) 1 40.1 1.5 2.1 126.315
Curtain wall (D/S) 1 40.1 1.85 2.6 192.881
Toe Wall Left 1 40.1 1 1 40.1
Toe Wall right 1 40.1 1 1 40.1
Stone Pitching Toe wall Left anf right 4 1/4*3.14*5.5**1.5*0.5 12.9525
For GSB below raft 1 40.1 12.8 2.1 1077.89
Total 7624.71 Cum 101 770095.56
4 Construction of granular sub-base by providing well
graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in
place method with rotavator at OMC, and compacting
with smooth wheel roller to achieve the desired
Bridge
density 1 40.1 12.8 0.15 76.992
Bridge shear key 2 40.1 (0.30+0.9)/ 0.15 7.218
Retaining wall left 2 8.7 10.2 0.15 26.622
Retaining wall right 2 8.7 10.2 0.15 26.622
Curtain wall (U/S) 1 40.1 1.5 0.15 9.0225
Curtain wall (D/S) 1 16.8 1.85 0.15 4.662
Toe Wall Left 1 11.15 1 0.15 1.6725
Toe Wall right 1 11.15 1 0.15 1.6725
For GSB below raft 1 40.1 1.5 0.15 9.0225
Total 163.506 Cum 2882.69 471337.11
5 Providing concrete Reinforced concrete in open
foundation complete , as per drawing and technical
specification clause 802,803,1203 P.C.C. grade M-15,
Nominal mix 1:3:6

Bridge 1 40.1 12.8 0.1 51.328


Bridge shear key 2 40.1 (0.30+0.9)/ 0.1 4.812
Retaining wall left 2 8.7 10.2 0.1 17.748
Retaining wall right 2 8.7 10.2 0.1 17.748
Curtain wall (U/S) 1 40.1 1.5 0.1 6.015
Curtain wall (D/S) 1 16.8 1.85 0.1 3.108
Toe Wall Left 1 11.15 1 0.1 1.115
Toe Wall right 1 11.15 1 0.1 1.115
For GSB below raft 1 40.1 1.5 0.1 6.015
Total 109.004 Cum 5265.17 573924.59

file:///conversion/tmp/scratch/454781501.xls40.1
S. Item of work No. Length Width Height Quantity Rate Amount

1 2 4 5 6 7 8 9
6 Stone masonry in 1:5 cement mortar for substructure
complete as per drawing & technical specification
Clauses 702, 704, 1202 and 1204

Curtain wall (U/S) 1 40.1 0.5 1.5 30.075


Curtain wall (D/S) 1 16.8 0.5 1.5 12.6
Total 42.675 Cum 4750.55 202729.72
7 Plain/reinforced cement concrete in substructure
complete as per drawings and technical specification
Clauses 802, 804, 805, 806, 807, 1202 and 1204 (M-
30)
Box Upper and Bottom Slab 1 40.1 12.5 0.15 75.1875
Shear Key 2 40.1 (0.30+0.9)/ 0.6 28.872
Bridge bottom Haunch 0.5*10 12.5 0.15 0.15 1.40625
Retaining wall bottom slab 2 11.55 12.5 0.75 216.563
Retaining wall haunch 4*0.5 11.55 0.15 0.15 0.51975
Total 322.548 Cum 6499.19 2096300.74
8 Providingpressure relief pipe, plain/ reinforced
concrete with 100 mm dia AC pipe extending through
the full width of the structures with slope of 1(V):20(H)
towards drawing face complete as per drawing and
technical specification Clauses 614, 709, 1204.3.7

30 30 Nos. 129.01 3870.3


9 Plain/reinforced cement concrete in super structure
complete as per drawings and technical specification
Clauses 802, 804, 805, 806, 807, 1202 and 1204 (M-
30)
Box Top Slab 1 40.1 12.5 0.6 300.75
Abutment 2 12.5 0.6 7.5 112.5
Piers 2 12.5 0.35 7.5 65.625
Top Haunch 6*0.5 12.5 0.15 0.15 0.84375
Approach slab 2 3.5 (12.5+5.50) 0.3 18.9
Retaining walls 4 8.5 0.6 0.675 13.77
Retaining wall haunch 0.5*10 12.5 0.15 0.15 1.40625
Crash barrier 2 33.8 0.32 0.25 5.408
Crash barrier 2 33.8 0.5 0.1 3.38
Crash barrier 2 33.8 0.2 0.75 10.14
Wearing coat 1 40.1 12.5 0.075 37.5938
Total 570.317 Cum 6499.19 3706596.92
10 Suplying, Fixing, and placing HYSD bar reinforcement
in superstructure as per drawing and technical
specifications Clause 1002,1010,1202 @ 1.0% of
R.C.C. Work.
Total 836.371 Cum Excluding wearing coat

Total weight of Steel @1.0 656.551 Qtl 4197.954 2756171.88


11 Providing and fixing of drainage spout for disposal of
rain water
6 6 Nos. 129.01 774.06
12 Cement Plum Concrete with 40% plum & 60% 1:3:6
Cement Concrete including Supply of All material,
labour,T&P etc. required for proper completion of the
work as per drawing/Technical specifications clause
802,803,1202 & 1203
Bed protection 2 40.1 1.5 1.5 180.45
Total 180.45 Cum 3876.57 699527.06
13 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return
wall with 100 mm dia AC pipe extending through the
full width of the structures with slope of 1(V):20(H)
towards drawing face complete as per drawing and
technical specification Clauses 614, 709, 1204.3.7

Abutment 2 3x5 30 Nos.

file:///conversion/tmp/scratch/454781501.xls40.1
S. Item of work No. Length Width Height Quantity Rate Amount

1 2 4 5 6 7 8 9
Retaining wall 4 4x5 80 Nos.
4 110 Nos. 129.01 14191.1
14 Hand Packed stone filling in back of walls including
cost of all materials, royality, T&P etc complete as per
direction of Engineer-in-Charge
Behind abutment 2 11.15 0.6 5.5 73.59 Cum
Behind Retaining walls 4 8.5 0.6 5.5 112.2 Cum
Total 185.79 Cum 3876.57 720227.94
15 Providing and laying boulder apron for bed protection
with stone boulders of minimum size and weight as
per Table 1300.1, no fragment weighing less than 25
kg laid dry complete as per drawing and technical
specifications Clause 1301
U/S 1 40.1 3 1 120.3 Cum
D/S 1 40.1 6 1 240.6 Cum
Total 360.9 Cum 2501.59 902823.83
16 Providing and laying filter material underneath pitching
in slopes complete as per drawing and technical
specifications Clause 1302
4 11.15 7.44 0.15 49.7736 Cum
Total 49.7736 Cum 2439.61 121428.17
17 Providing and laying pitching on slopes laid over
prepared filter media as per drawing and technical
specifications Clause 1302
4 11.15 7.44 0.3 99.5472 Cum
Toe wall 4 11.15 1 1 44.6 Cum
Total 144.147 Cum 2501.59 360597.19
Total 13526875

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra

file:///conversion/tmp/scratch/454781501.xls40.1
Analysis for Overlay on Causeway
Length= 1 Mtr Width= 7.5 Mtr
Sl.
No. Description of Item Unit No L (m) B (m) H (m) Qty. Rate (Rs.) Amount (Rs.)

1 Construction of un-reinforced, plain cement


concrete pavement, thickness as per design, over a
prepared sub base, with 43 grade cement or any
other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS:383,
maximum size of coarse aggregate not exceeding
25 mm, mixed in a concrete mixer of not less than
0.2 cum capacity and appropriate weigh batcher
using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of
125 micron thick polythene film, wedges, steel
plates including levelling the formwork as per
drawing), spreading the concrete with shovels,
rakes, compacted using needle, screed and plate
vibrators and finished in continuous operation
including provision of contraction and expansion,
construction joints, applying debonding strips,
primer, sealant, near approaches to bridge/culvert
and construction joints, admixtures as approved,
curing of concrete slabs for 14-days,using curing
compound (where specified) and water finishing to
lines and grade as per drawing and Technical
Specification Clause 1501

Base of causeway Cum 1 100 7.5 0.19 142.5


Total 142.5 6499.19 926134.575
Total (Rs.) 926134.575
5x1000mm Dia NP-3 RCC Hume Pipe Culvert

Sl. Description of Item Unit No L (m) B (m) H (m) Qty. Rate (Rs.) Amount (Rs.)
No.
Earthwork in excavation of trenches etc., as
per drawing and technical specification,
including setting out, construction of shoring
and bracing, removal of stumps and other
deleterious matter, dressing of sides and
1 bottom , backfilling excavated earth to the Cum 2 10.00 1.65 1.20 39.60 102.80 4070.88
extent required and utilising the remaining
earth locally for road work, as per MORD
Specifications No. 300 SL.No. 11.1

Providing concrete for plain/reinforced


concrete in open foundations complete as per
2 drawings and technical specifications Clause
802, 803, 1202 & 1203 M-10 (1:3:6)
In Foundation Cum 2 10.00 1.65 0.15 4.95
Under Hume Pipe Cum 1 10.00 7.8 0.20 15.60
Cum 1 10.00 (8.20+7.80)/2 1.25/2 50.00
Deduct for HP Cum 1x5x1/2x3.14x(1.25)/2x(1.25)/2x(8.6+7.8)/2 -25.14
Total 45.41 5491.60 249348.67
Stone masonry in cement mortar for
substructure complete as per drawing &
3 technical specification Clauses 702, 704,
1202 and 1204 (Coursed rubble masonry)
(1.45+1.1
Cum 2 10.00 1.05 26.78
0)/2
(1.10+0.6
Cum 2 10.00 1.44 24.48
0)/2
Deduct for HP Cum 2x5x3.14x(1.25/2)x(1.25/2)x(1.10+0.70)/2 -11.04
Total 40.22 3562.50 143269.28
Providing and laying reinforced cement
concrete pipe NP3 for culverts on first class
bedding of granular material in single row
4 including fixing collar with cement mortar 1:2
but excluding excavation, protection works,
backfilling, concrete and masonry works in
head walls and parapets Clause 1106.

Rm 5x4 2.50 50.00 4601.10 230055.00

Sand Fillling in foundation trenches as per


5 drawing and technical specification Clause
305.3.9
1x10x(8.60+7.80)/2x1/2x1.25 51.25
Deduct for HP 5x3.14x1.25/2x1.25/2x(8.6+7.8)/2x1.25/2 -31.43
Total 19.82 1846.60 36598.39
Providing and laying cement concrete M-30 in
superstructure as per drawing & technical
specifications Clauses 800, 1205.4 and
6 1205.5 Standard Data Book For Analysis Of Cum 1 10.00 10.00 0.19 19.00 7489.10 142292.9
Rates for Rural Roads,Sr No 13.1(iii), Pg-13 -
overlay on damaged causeways

Struck pointing with cement mortar consisting


of 1 part cement and 2 part of sand of 1.25
7 FM including supply of all materials, labour Sqm 2 10.00 1.44 28.80 120.00 3456
and T&P etc. required for proper campletion
of the work (as per SOR Item No. 574)

Total (Rs.) 809091.12


Say(Rs.) 8.09
Lacs
Junior Engineer Assistant Engineer Executive Engineer
PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
RCPLWEA (ADDITIONAL)

2x600mm Dia NP-3 Hume Pipe Culvert


UP67146
PACKAGE NO. :- Format F-7

SL Item of Work No L B H/D QTY. UNIT Rate Amount


1 Excavation for roadway in soil using manual
means for carrying of cut earth to
embankment site with a lift upto 1.5 m and
lead upto 50 m as per Technical Specification
Clause 302.3
2 5.30 1.40 0.85 12.61
Under Pipe 1 4.70 2.90 0.20 2.73
Total 15.34 cum 104.39 1601.34
2 Construction of granular sub-base by
providing well graded material, spreading in
uniform layers with motor grader on prepared
surface, mixing by mix in place method with
rotavator at OMC, and compacting with
smooth wheel roller to achieve the desired
density, complete as per Technical
Specification Clause 401. ( GSB Grade -
III) (Including Labour cess & Excluding GST)
Below Parapet 2 5.30 1.40 0.15 2.23 cum
Below Pipe 1 4.70 2.90 0.20 2.73 cum
Total 4.96 cum 2,882.69 14298.14
3 Plain cement concrete mix 1:3:6 C:CS
crushed stone aggregates 40mm nominal
size, placed in foundtion and compacted by
vibration including curing for 14 days as per
MORD Specification No. 800/1200[Sr. No.
11.41]

Below Parapet 2 5.30 1.40 0.15 2.23 cum


Below Pipe 1 4.70 2.90 0.20 2.73 cum
Total 4.96 cum 5,265.17 26115.24
3 Providing & Laying reinforced concrete pipe
NP3 for culvert on first class bedding of
granular material in single row including fixing
collar with cement mortar 1:2 (1 cement: 2
coarse sand) as per MORD Specifications No.
9.3-1100(B) for 600mm dia NP3 Hume pipe

2x3 2.50 15.00 Rm 2114.07 31711.05


4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
(1.2+1.0)/
2 5.00 0.65 7.15
2
(1.0+0.45
2 5.00 1.00 7.25
)/2
2 5.00 0.50 0.450 2.25

Deduction for pipe (area calculated in H/D column) 2x2 3.14x1.25/2x1.25/2x -3.93

Total 12.73 cum 4,750.55 60474.50


5 Pointing with cement mortar 1:3 C:CS deep
variety (cut or weather) on Brick & Tile work
including supply of all materials, labour and
T&P reqd. for proper completion of the work
as per drawing & Technical specification
clause 613.3 and 1204 standard Data Book
for analysis of rates for rural roads, Sr. No.
12.2 [MORD Specification 600]
(1.99+0.35
2 5.00 +0.35+1.1 38.00
1)
2x2 0.35 0.35 0.490
2x2 0.46 0.115 0.212
2x2 0.50 0.50 1.00
3.14x
Deduction for pipe (area calculated in H/D column) 2 1.25/ -4.91
2
Total 34.80 Sqm 57.06 1985.69
6 Plasster with cement mortar 1:4 C:CS 15 thick
on brick work in substructure as per Technical
specification clause 613.4 and 1204 standard
Data Book for analysis of rates for rural roads,
Sr. No. 12.3, Pg-12-4 [MORD Specification
600]

2x2 0.5 0.45 0.49


2x2 0.5 0.45 0.49
Total 0.98 Sqm 153.40 150.33
7 White washing two coats on parapet walls and
tree trunks including prepration of surface by
cleaning scrapping etc. as per Technical
specification clause 1915 Standard Data Book
for analysis of rates of rural roads Sr. No.
15.13, Pg-15-12 MORD specification 1900

Same as above item Pointing 34.80


Total 34.80 Sqm #REF! #REF!
8 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper completion
of work (Lump sump)
LS 1 Job 1 Job 5000.00 5000.00
Total (Rs.) #REF!

Assistant Engineer Executive Engineer


Junior Engineer PMGSY Division, PWD PMGSY Division, PWD
PMGSY Division, PWD Sonebhadra Sonebhadra
Sonebhadra
F7HP-450186
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF HP GULE WORKS
FORMAT F- 6
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

ROAD LENGTH :- 25.30 KM PACKAGE NO. :- UP67146


Construction of 450 mm NP-3 Hume Pipe Gule
D/H Amount in
S.No Description of Item No. L(m) B(M)
(M)
Quantity Unit Rate In Rs
Rs
1 2 3 4 5 6 7 8 9 10
1 Earth work in excavation in foundation of structure
up to depth 3m as per drg and technical clause 1104
including setting out , const. of shoring and bracing,
removal ofstumps and other deleterious matter,
dressing of sides and bottom and back fillingetc.
complete

For foundation 1 x 2 1.65 0.45 1.825 2.710 cum


For sand filling below pipe 1 x 1 6.600 1.530 0.850 8.583 cum
Total 11.293 cum 101.00 1140.64
2 Construction of granular sub-base by providing
well graded material, spreading in uniform
layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel
roller to achieve the desired density, complete
as per Technical Specification Clause 401.
( GSB Grade - III) (Including Labour cess &
Excluding GST)

Below Parapet 1 x 2 1.650 0.450 0.150 0.223 cum


Under Pipe 1 x 1 6.600 1.530 0.150 1.515 cum
Total 1.737 cum 2,882.69 5008.53
3 PCC in 1:3:6 Providing concrete for plain concrete in
open foundations complete as per drawings and
technical specifications Clause 802, 803, 1202 &
1203
Below Head wall 1 x 2 1.65 0.450 0.150 0.223 sqm
Total 0.223 sqm 5,265.17 1172.82
4 Stone masonry in 1:5 cement mortar for substructure
complete as per drawing & technical specification
Clauses 702, 704, 1202 and 1204
Parapet 1 2 1.500 0.350 1.500 1.575
deduction for hume pipe 1 x 2 3.140 0.076 0.350 -0.166
Total 1.409 cum 4,750.55 6692.46
6 Providing and laying 450mm reinforced cement
concrete pipe NP3 for culverts on first class bedding
of granular material in single row including fixing
collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets
Clause 1106.

1 x 3 2.500 7.500 Rm
Total 7.500 Rm #REF! #REF!
7 Pointing with cement mortar (1:3) on brickwork as
per drawing and technical specification Clauses
613.3 and 1204
2 x 2 1.500 2.450 14.700 sqm
sides 2 x 2 0.350 1.500 2.100 sqm
deduction for hume pipe 1 x 2 3.140 0.275 0.275 -0.475 sqm 0.000
Total 16.325 sqm 57.06 931.51
8 Colour washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915
1 x 2 1.500 0.350 1.050 Sqm #REF! #REF!
9 White washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915
1 x 2 1.500 1.500 4.500 sqm #REF! #REF!
10 Painting, writing, lettering etc. on number plates on
culverts including all materials, labour T&P etc.
required for proper completion of work (Lump sump)
LS 1 Job 5000.00 5000.000
Total cost of HP gule #REF!

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
RCPLWEA (ADDITIONAL)
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS
FORMAT F- 7
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

PACKAGE NO. :- UP67146


ROAD LENGTH :- 25.300 KM
Type of Cross drainage Works : Construction of 900 mm NP-3 Hume Pipe
L Culvert
B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
1 Excavation for roadway in soil using manual means for
carrying of cut earth to embankment site with a lift
upto 1.5 m and lead upto 50 m as per Technical
Specification Clause 302.3
For foundation 1 x 2 4.15 1.40 2.505 29.108 cum
For sand filling below pipe 1 x 1 4.850 1.530 1.900 14.099 cum
Total 43.207 cum 104.39 4510.38
2 Construction of granular sub-base by providing
well graded material, spreading in uniform layers
with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC,
and compacting with smooth wheel roller to
achieve the desired density, complete as per
Technical Specification Clause 401. ( GSB
Grade - III) (Including Labour cess & Excluding
GST)

Below Parapet 1 x 2 4.150 1.400 0.150 1.743 cum


Under Pipe 1 x 1 4.850 1.530 0.150 1.113 cum
Total 2.856 cum 2,882.69 8233.18
3 PCC in 1:3:6 Providing concrete for plain/reinforced
concrete in open foundations complete as per
drawings and technical specifications Clause 802,
803, 1202 & 1203
Below Head wall 1 x 2 4.15 1.400 0.150 1.743 sqm
Under Pipe 1 x 2 4.15 1.400 0.150 1.743 sqm
for haunching 1 x 1 6.30 0.356 2.244 sqm
Total 5.730 sqm 6,015.28 34469.47
4 Stone masonry in 1:5 cement mortar for substructure
complete as per drawing & technical specification
Clauses 702, 704, 1202 and 1204
Parapet 1 2 4.000 0.500 0.450 1.800
Head wall 1 2 4.000 0.825 2.505 16.533
deduction for hume pipe 1 x 2 3.140 0.378 0.755 -1.793
Total 16.540 cum 4,750.55 78572.60
5 Providing and laying 900mm reinforced cement
concrete pipe NP3 for culverts on first class bedding of
granular material in single row including fixing collar
with cement mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106.

1 x 3 2.500 7.500 Rm
Total 7.500 Rm 4,496.53 33723.98
6 Providing and laying M-20 plain cement concrete in 0.000
superstructure as per drawing and technical
specifications Clauses 800, 1205.4 and 1205.5
guard stone 1 x 4 0.200 0.200 0.500 0.080 cum
1 x 2 0.400 0.400 1.000 0.320 cum
Total 0.400 cum 6,015.28 2406.11
7 Pointing with cement mortar (1:3) on brickwork as per
drawing and technical specification Clauses 613.3 and
1204
1 x 2 6.000 3.755 45.060 sqm
sides 2 x 2 0.750 2.955 8.865 sqm
deduction for hume pipe 1 x 2 3.140 0.615 0.615 -2.375 sqm 0.000
Total 51.550 sqm 57.06 2941.43
L B D/H Unit Rate Amount
Sl No. Description of Item No. Quantity
(m) (m) (m) Rs Rs
1 2 3 4 5 6 7 8 9 10
8 Painting two coats including prime coat with epoxy
paint of approved brand on concrete/steel surfaces
after through cleaning of surface to give an even
shade as per drawing and Technical Specification
Clause 1701
5 x 2 0.400 0.400 1.600 sqm
5 x 4 0.200 0.200 0.800 sqm
Total 2.400 sqm 87.71 210.50
9 Colour washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915
Total 2 x 2 3.100 0.800 9.920 15.85 157.23
10 White washing two coats on parapet walls and tree
trunks including preparation of surface by cleaning
scraping etc. as per technical specifications Clause
1915
1 x 2 4.000 2.505 20.040 sqm
1 x 2 4.000 2.505 20.040 sqm
2 x 2 0.450 0.800 1.440 sqm
2 x 2 0.750 2.955 8.865 sqm
Total 50.385 sqm 15.85 798.60
10 Painting, writing, lettering etc. on number plates on
culverts including all materials, labour T&P etc.
required for proper completion of work (Lump sump)
LS 1 Job 5000.00 5000.000
Total cost of culvert 171023.48

Junior Engineer Assistant Engineer Executive Engineer


PMGSY Division, PWD PMGSY Division, PWD PMGSY Division, PWD
Sonebhadra Sonebhadra Sonebhadra
COST ESTIMATE FOR CONSTRUCTION BREAST WALL
UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
DISTRICT:- SONEBHADRA
Sl. Description of Item No. Length Width (m) Depth Unit Quanitity Rate (Rs.) Amount (Rs.)
No. (m) (m) (cum)
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and lead
upto 30 m and including filling,watering and
ramming of excavated earth into the trnches or
into the sapce between the building/ structure
and the side of fondation trenches or plinth and
removel and disposal of surface earth as
directed by Engineer in charge upto a distance
of 30 m from the foundation trenches including
all T& P and material etc complete as per
UPPWD specification SNo.1-251..

For breast wall


1×1 1.00 1.000 1.80 Cum 1.80
for K C drain
1×1 1.00 0.500 0.375 Cum 0.19
Total 1.99 101 200.99
2 Construction of granular sub-base by providing
well graded material, spreading in uniform
layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at
OMC, and compacting with smooth wheel
roller to achieve the desired density, complete
as per Technical Specification Clause 401.
( GSB Grade - III) (Including Labour cess &
Excluding GST)

For breast wall


1×1 1.00 1.00 0.10 Cum 0.10
for K C drain
1×1 1.00 0.50 0.10 Cum 0.05
Total 0.15 2882.69 432.40
3 Providing concrete for plain/reinforced concrete
in open foundations complete as per drawings
and technical specifications Clause 802, 803,
1202 & 1203 (PCC 1:3:6 concrete)
For breast wall 1×1 1.00 1.00 0.15 Cum 0.15
for K C drain 1×1 1.00 0.50 0.150 Cum 0.08
Total 0.230 5265.17 1210.99
4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
and 1204
For breast wall 1×1 1 (0.90+0.60 1.8 Cum 1.35
)/2
Total 1.35 4750.55 6413.24
5 Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 R.C.C. grade M 25

For breast wall 1×1 1 0.6 0.025 Cum 0.02

1×1 1 0.5 0.15 Cum 0.08

Total 0.1 6015.28 601.53


6 Pointing with cement mortar (1:3) on brickwork
as per drawing and technical specification
Clauses 613.3 and 1204
For breast wall 1×1 1.00 1 1.8 sqm 1.8
Total 1.8 57.06 102.71
7 Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical
specification Clauses 614, 709, 1204.3.7

For breast wall 1×1 1 Rm. 1


Total 1 129.01 129.01
Grand Total 9090.87
Rm. Say Rs. 9090.90
COST ESTIMATE FOR CONSTRUCTION RETAINING WALL

UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

DISTRICT:- SONEBHADRA
Sl. Description of Item No. Length Width Depth Unit Quanitity Rate (Rs.) Amount (Rs.)
No. (m) (m) (m) (cum)
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam 136.35
clay,sand) including filling upto 1.50 m and lead
upto 30 m and including filling,watering and
ramming of excavated earth into the trnches or
into the sapce between the building/ structure
1×1 1.00 1.350 1.00 Cum 1.35 101.00
and the side of fondation trenches or plinth and
2 Construction
removel andof disposal
granular sub-base
of surface by earth
providing
as 403.58
well graded
directed material,
by Engineer spreading
in charge upto in uniform
a distance
layers
of 30 mwith
frommotor grader on trenches
the foundation prepared including
surface,
mixing
all T& byP mix
andin material
place method with rotavator
etc complete as perat
OMC,
UPPWDand compacting
specification with smooth wheel
SNo.1-251..
roller to achieve the desired density, complete
as per Technical Specification Clause 401.
( GSB Grade - III) (Including Labour cess & 1×1 1.00 1.350 0.10 Cum 0.14 2882.69
3 Excluding concrete
Providing GST) for plain/reinforced concrete 526.52
in open foundations complete as per drawings
and technical specifications Clause 802, 803,
1202 & 1203 (PCC 1:3:6 concrete) 1×1 1.00 1.350 0.075 Cum 0.10 5265.17
4 Stone masonry in 1:3 cement mortar for 9786.13
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
1×1 1.00 0.825 2.50 Cum 2.06 4750.55
and 1204
5 Plain/reinforced cement concrete in 180.46
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 R.C.C. grade M 25 1×1 1.00 0.50 0.05 Cum 0.03 6015.28
6 Pointing with cement mortar (1:3) on Stone 142.65
work as per drawing and technical specification
Clauses 613.3 and 1204 1×1 1.00 2.50 Sqm 2.50 57.06
7 Providing weepholes in brick masonry/stone 129.01
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical 1×1 1.00 1.00 Rm. 1.00 129.01
6 specification
Hand PackedClauses
stone 614, 709,
filling in 1204.3.7
back of walls 71.06
including cost of all materials, royality, T&P etc
complete as per direction of Engineer-in-Charge 1×1 0.30 0.30 0.30 Cum 0.03 2368.82
Grand Total 11375.76
Rm. Say Rs. 11375.76
RCPLWEA (ADDITIONAL)
Format F-7
COST ESTIMATE FOR CONSTRUCTION PARAPET WALL
UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

DISTRICT:- SONEBHADRA
SI. Length Depth Amount
Description of Item Nos Width (m) Unit Quantity Rate (Rs.)
No. (m) (m) (Rs.)
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam 65.65
clay,sand) including filling upto 1.50 m and lead
upto 30 m and including filling,watering and
ramming of excavated earth into the trnches or
into the sapce between the building/ structure
and the side of fondation trenches or plinth and
removel and disposal of surface earth as
directed by Engineer in charge upto a distance
of 30 m from the foundation trenches including
all T& P and material etc complete as per
UPPWD specification SNo.1-251..
1x1 2.15 0.60 0.50 Cum 0.65 101.00
2 Construction of granular sub-base by providing 374.75
well graded material, spreading in uniform layers
with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC,
and compacting with smooth wheel roller to
achieve the desired density, complete as per
Technical Specification Clause 401. ( GSB
Grade - III) (Including Labour cess & Excluding
GST) 1x1 2.15 0.60 0.10 Cum 0.13 2882.69
3 Providing concrete for plain/reinforced concrete
in open foundations complete as per drawings
and technical specifications Clause 802, 803,
1202 & 1203 (PCC 1:3:6 concrete)

1x1 2.15 0.60 0.15 Cum 0.19


1x1 2.00 0.45 0.15 Cum 0.14
1x1 2.00 (0.45+0.25)/2 0.15 Cum 0.11
Total 0.44 5265.17 2316.67
4 White washing two coats on parapet walls
including prepration of surface by cleaning
scrapping etc. as per Technical specification
clause 1915 Standard Data Book for analysis of
rates of rural roads Sr. No. 15.13, Pg-15-12
MORD specification 1900

1x1 2.15 0.75 sqm 1.61


1x2 0.50 0.70 sqm 0.35
sqm 1.96 15.85 31.07
Total 2788.14
Say (Rs.) 2788.14
each
COST ESTIMATE FOR CONSTRUCTION TOE WALL

UP67146
PACKAGE NO. :-
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.

DISTRICT:- SONEBHADRA
Sl. Description of Item No. Lengt Width Depth Unit Quanitity Rate (Rs.) Amount (Rs.)
No. h (m) (m) (m) (cum)
1 2 3 4 5 6 7 8 9 10
1 Earthwork in fondation in ordinary soil (loam 54.54
clay,sand) including filling upto 1.50 m and lead
upto 30 m and including filling,watering and
ramming of excavated earth into the trnches or
into the sapce between the building/ structure
and the side of fondation trenches or plinth and
removel and disposal of surface earth as
directed by Engineer in charge upto a distance
of 30 m from the foundation trenches including
all T& P and material etc complete as per
UPPWD specification SNo.1-251..
1×1 1.00 0.90 0.60 Cum 0.54 101.00
2 Providing concrete for plain/reinforced concrete 473.87
in open foundations complete as per drawings
and technical specifications Clause 802, 803,
1202 & 1203 (PCC 1:3:6 concrete)
1×1 1.00 0.90 0.100 Cum 0.09 5265.17
3 Stone masonry in 1:5 cement mortar for 2850.33
substructure complete as per drawing &
technical specification Clauses 702, 704, 1202
1×1 1.00 0.60 1.00 Cum 0.60 4750.55
and 1204
4 Plain/reinforced cement concrete in 180.46
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 R.C.C. grade M 25 1×1 1.00 0.60 0.05 Cum 0.03 6015.28
Grand Total 3559.20
PER Rm. Say Rs. 3559.200
DRAWING OF 300MM DIA GULE

1500X1500X350 Stone Masonary


Hume pipe
6800 450

7500
750
DRAWING OF 450MM DIA GULE

1500X1500X350 Stone Masonary


Hume pipe
6800 550

7500
750
G(1X1000)195

CONSTRUCTION OF 1 M DIA HUMEPIPE CULVERT

DETAILS OF CALCULATION OF GRANULAR MATERIAL BELOW HUMEPIPES

1000 MM DIA NP3 HUMEPIPES


1230 MM OUTER DIA

Outer radius of pipe = 615


AC = 300
Hence , CD = 536.9

Angle a= 60.8
A

Area of sector ABD = PI/4 X OUTER DIA X OUTER DIA X 2 X a /360


= 0.402 SQM
B D

A Area of triangle ABD = 0.5 x BD X AC


= 0.161 SQM
J K
B C D B D
0.2 Hence area of segment = sector ABD - triangle ABD
0.12 0.39 E = 0.240
E
0.075 M L

Area of JKLM = 0.39 x 1.53


1.53 = 0.597

Hence X-sectional area of granular work = 0.356 sqm


DRG(1X1000)196

CONSTRUCTION OF 1 M DIA HUMEPIPE CULVERT


pipe
thickness
7.5

0.40 x 0.40 x 1.0 guard stone one each side 0.20 x 0.20 x 0.5 guard stone @ 1.5 c/c

brickwork in multiples of
brick units
2.73 ###

0.35 4
CUSHION

NP-3 HUMEPIPE
0.45 1:5 ?
0.115
1

GL GROUND LEVEL

0.115 BW 1:4
GRANULAR MATERIAL BELOW PIPES 1.05

SECTION AT 'A - A' SECTION AT 'B - B'


ELEVATION 0.15

CC 1:3:6 IN FOUNADATION
1.25
4.3

1.4

SIDE ELEVATION

0.15 0.075

invert of pipe min


150 - 132 of 20 GL

0.2
0.39

0.115
0.075 GRANULAR MATERIAL

1.53 SECTION OF GRANULAR MATERIAL

1 ALL DIMENSIONS ARE IN METERS , UNLESS OTHERWISE SPECIFIED .

2 FOUNDATION CONCRETING TO BE IN PCC 1 : 3 : 6 C:CS: 40 MM STONE AGGREGATE.


4.3
3 BRICK MASONRYIN HEADWALL TO BE IN 1:4 C:FS .
4
4 LONGITUDENAL SLOPE OF THE PIPE TO BE MINIMUM OF 1 : 1000 .
A A
5 EARTH/METALLING CUSHION SHALL BE PROVIDED MINIMUM OF 1.0 M .

6 DRAWING NOT TO THE SCALE .

7 GRANULAR MATERIAL TO BE OF GRANULAR MATERIAL PASSING 5.6 MM SIEVE

GOVERNMENT OF UTTAR PRADESH

PUBLIC WORKS DEPARTMENT

CODE
B
FOR RES
TYPICAL DRAWING OF 1000 MM DIA NP-3 HUMEPIPE CULVERT
B
1
PLAN

CONSTRUCTION DIVISION NO - 3 ( P P )

LUCKNOW
AE EE SE
G(1X1200)197

CONSTRUCTION OF 1 M DIA HUMEPIPE CULVERT

DETAILS OF CALCULATION OF GRANULAR MATERIAL BELOW HUMEPIPES

1200 MM DIA NP3 HUMEPIPES


1250 MM OUTER DIA

Outer radius of pipe = 625


AC = 300
Hence , CD = 548.3

Angle a= 61.3
A

Area of sector ABD = PI/4 X OUTER DIA X OUTER DIA X 2 X a /360


= 0.418 SQM
B D

A Area of triangle ABD = 0.5 x BD X AC


= 0.164 SQM
J K
B C D B D
0.2 Hence area of segment = sector ABD - triangle ABD
0.13 0.4 E = 0.254
E
0.075 M L

Area of JKLM = 0.4 x 1.55


1.55 = 0.620

Hence X-sectional area of granular work = 0.366 sqm


DRG(1X1200)198

CONSTRUCTION OF 1 M DIA HUMEPIPE CULVERT


pipe
thickness
7.5

0.40 x 0.40 x 1.0 guard stone one each side 0.20 x 0.20 x 0.5 guard stone @ 1.5 c/c

brickwork in multiples of
brick units
2.75 ###

0.35 4
CUSHION

NP-3 HUMEPIPE
0.45 1:5 ?
0.125
1

GL GROUND LEVEL

0.125 BW 1:4
GRANULAR MATERIAL BELOW PIPES 1.05

SECTION AT 'A - A' SECTION AT 'B - B'


ELEVATION 0.15

CC 1:3:6 IN FOUNADATION
1.25
4.3

1.4

SIDE ELEVATION

0.15 0.075

invert of pipe min


150 - 132 of 20 GL

0.2
0.4

0.125
0.075 GRANULAR MATERIAL

1.55 SECTION OF GRANULAR MATERIAL

1 ALL DIMENSIONS ARE IN METERS , UNLESS OTHERWISE SPECIFIED .

2 FOUNDATION CONCRETING TO BE IN PCC 1 : 3 : 6 C:CS: 40 MM STONE AGGREGATE.


4.3
3 BRICK MASONRYIN HEADWALL TO BE IN 1:4 C:FS .
4
4 LONGITUDENAL SLOPE OF THE PIPE TO BE MINIMUM OF 1 : 1000 .
A A
5 EARTH/METALLING CUSHION SHALL BE PROVIDED MINIMUM OF 1.0 M .

6 DRAWING NOT TO THE SCALE .

7 GRANULAR MATERIAL TO BE OF GRANULAR MATERIAL PASSING 5.6 MM SIEVE

GOVERNMENT OF UTTAR PRADESH

PUBLIC WORKS DEPARTMENT

CODE
B
FOR RES
TYPICAL DRAWING OF 1000 MM DIA NP-3 HUMEPIPE CULVERT
B
1
PLAN

CONSTRUCTION DIVISION NO - 3 ( P P )

LUCKNOW
AE EE SE
CONSTRUCTION OF " U " DRAIN

50CM 50CM

30CM

30CM

7.5CM

GSB 150 mm

7.5CM

81CM
9.3.1 VEHICLE CLASS
Date Cars , Motorised , Light Trucks Agricultu Buses Cycles Cycles Animal Total
Vans two Commer ral Rickshaw Drawn
Jeeps , Wheelers cial Tractors , Vehicles
Three Vehicles Trailers
Wheelers
1 2 3 4 5 6 7 8 9 10 11
07-03-2019 10 31 7 2 11 4 90 0 0 155
08-03-2019 11 70 4 2 7 4 101 0 0 199
09-03-2019 15 49 7 2 12 4 100 0 0 189
Total for 3 36 150 18 6 30 12 291 0 0 543
days
Average daily 12 50 6 2 10 4 97 0 0 181
traffic
PCU factor 1 0.5 1.5 3 4.5 3 0.5 2 6
Average daily 12 25 9 6 45 12 49 0 0 158
PCU

9.3.2 Crust Design

Sl. No. AverageTraffic Data Mainly Consider Appendix A,B to check your ESAL count.

Motorised
1 Pkg. 67146 Cars, jeeps, vans, 3 12 ADT

Name of R WindhamganjMotorised two wheel 50 ADT lean 181

LCVs 6 ADT peak 362

Trucks laden
0 Period : Trucks unladen 1 AADT=(T+1.2 226
nTt/365)
Enter if Trucks overloded 1 AADT*(1.06)2 254
Peak = 1, (2 years after
opening to
Lean = 0 Traffic)

6 Growth rate Agri Tractor Trolley Factor=AADT 1.4


adopted(%) x(1.06) /ADT
2

10 Design life Agri Tractor Trolley 4 Overloaded 12.01


in years HCV*factor*2.
86
2 No. of Agri Tractor Trolley 6 Loaded 0
Harvesting HCV*factor*2.
seasons 58
75 No. of days Bus laden - Unloaded 1.3
in each HCV*factor*0.
Harvesting 31
season
Bus unladen 2 Overloaded 2.86
MCV*factor*0
.34
Bus over loaded 2 Loaded 0
MCV*factor x
0.31
Non-motorised Unloaded 0.11
MCV*factor*
x 0.02
Cycles 97 Total=To 16.28
Cycle rickshaws 0 ESAL=To*481 78333
1*Lane
Distribution
Factor

16 Total CVPD Animal driven Solid 0

Animal driven pneuma 0 S2 T3


According to Fig 4 of IRC :SP:72-2015 following crust
The thickness
crust composition
is adopted against this req
REQUIRED

CBR 3.64% Required MM Provided MM


Wearing Course (PC) 20 BT(20 mm PMC with Seal Coat) 20
Binder Course - - Binder Course (BM) -
Granular Base (G-III) 75 WBM Top Layer,G 3 75
Base of Gravel (G-II) 2x75 75 WBM,G 2 75
GB - GSB Overlay on Exist Crust -
GSB 175 GSB/Existing Crust 175
Mod Subgrade 0 0
Total 325 Total_PROVIDED 325

Ch. 0.00 to 4.850


PC - 20mm.
G-3 - 75mm

Ch. 4.850 to 25.300


PC - 20mm
G3 -
75mm.
G2 -
75mm.
GSB - 175
mm.
Cost for Widening of Causeway 200m length & 4m width and 800 Sqm.
Sl.
No. Description of Item Unit No L (m) B (m) H (m) Qty. Rate (Rs.) Amount (Rs.)

1 Dewatering of water trenches during


excavation, concreting, masonary work upto
sub soil/water level including hire charges of 5 Hrs 840 840 200.00 168000.00
HP Pump
2 Earthwork in fondation in ordinary soil (loam
clay,sand) including filling upto 1.50 m and
lead upto 30 m and including filling,watering Cum 2 200.00 2.0 1.98 1584.00 131.25 207900.00
and ramming of excavated earth into the
trnches or into the sapce between the
3 Random Rubble Stone
building/ structure and theMasonry laid in 1:5
side of fondation
cement
trenches and sand
or plinth andmortar,
removelinandbreast walls,
disposal
retaining walls,as parapets,
of surface earth directed by scuppers,
Engineer in etc.
including
charge uptosupply of all of
a distance material, labour,
30 m from the T&P
and
foundation trenches including all T& P drawing
royaltiies etc. complete as per and
and technical
material specifications
etc complete Clauses 702,
as per UPPWD
704,1202 & 1203 of MORD
specification SNo.1-251.. Specifiction

Section-1 Cum 2 200.00 2.05 820.00


Section-2 Cum 2 315.00 0.55 346.50
Total 1166.50 2398.50 2797850.25
4 Providing and laying cement concrete M-30 in
superstructure as per drawing & technical
specifications Clauses 800, 1205.4 and
1205.5 Standard Data Book For Analysis Of
Rates for Rural Roads,Sr No 13.1(iii), Pg-13 -
overlay on damaged causeways

Section-1 Cum 2 200.00 10.00 0.19 760.00


Section-2 Cum 2 315.00 10.00 0.19 1197.00
Total 1957.00 7489.10 14656168.70
5 Concrete with cement, coarse sand and 40
mm gauge stone ballast in proportion 1:4:8 in
foundations and floors including supply of au·
material, labour and T&P etc. requited for
proper completion of the work as per
drawings and technical specifications Clause
802, 803, 1202 & 1203

Section-1 (Below Retaing wall) Cum 2 200.00 1.54 0.10 61.60


Section-2 (Below Retaing wall) Cum 2 315.00 0.75 0.10 47.25
Section-1 (Below PQC) Cum 2 200.00 2.00 0.10 80.00
Section-2 (Below PQC) Cum 2 315.00 2.50 0.10 157.50
Total 188.85 4580.90 865102.97
6 Construction of granular sub-base by
providing Well graded material grade-
I,spreading in uniform layers with motor
grader on prepared surface mixing by mix in
place method with rotavator at OMC,and
compacted with smooth wheel roller to
achieve the desired

Section-1 Cum 2 200.00 2.00 0.15 120.00


Section-2 Cum 2 315.00 2.50 0.15 236.25
Total 356.25 2586.50 921440.63
7 Hand Packed stone filling in back of wallis
including cost' of all materials, royality, T&P
e.t. c. complete as per direction of Engineer-in Cum 2 200.00 2.00 2.16 1728.00 1828.80 3160166.4
charge.
8 Making provision for weep holes with 100mm
dia polymer pipes fixed at an angle of 45 No 160.00 - - 160.00 60.00 9600.00
degrees placed 2.5m c/c
9 Cement Plum Concrete with 40% plum & 60%
1:3:6 Cement Concrete including Supply of All
material,labour,T&P etc. required for proper
completion of the work as per
drawing/Technical specifications clause
802,803,1202 & 1203 of MORD specification

Section-1 Cum 2 200.00 1.20 1.25 600.00


Section-2 Cum 2 315.00 1.15 1.25 905.63
Total 1505.63 4720.00 7106550.00
10 Providing and laying boulder pitching as per
drawing and technical specifications Clause
1302 (25-40 Kg)
Section-1 Cum 1 200.00 8.00 0.30 480.00
Section-2 Cum 1 315.00 8.00 0.30 756.00
Total 1236.00 832.00 1028352.00
Cost For 800 Sqm area Total (Rs.) 30921130.95
Say(Rs.) 309.21
Lacs

Assistant Engineer Executive Engineer


Junior Engineer PMGSY Division, PWD PMGSY Division, PWD
PMGSY Division, PWD Sonebhadra Sonebhadra
Sonebhadra
PACKAGE NO :- UP67146
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
ROAD LENGTH :- 25.300 K.M.
L
Sl No. Description of Item No.
(m)
1 2 3 4
A Pavement Components
1 Clearing and grubbing road land including
uprooting wild vegetation, grass, bushes,
shrubs, saplings and trees of girth upto
300 mm, removal of stumps of such trees
cut earlier and disposal of unserviceable
materials and stacking of serviceable
material to be used or auctioned, upto a
lead of 1000 m including removal and
disposal of top organic soil not exceeding
150 mm in thickness as per Technical
Specification Clause 201.

TOTAL 1 x 1 4850.000
3.00 M BT Ch. 4.850 to 18.300, Ch.
21.800 to 25.300 1 x 2 3500.000
EARTHEN PORTION Ch. 18.300 to
21.800 1 x 1 4850.000
Deduct culverts portion and causeway
,minor bridge -1 x 2 12.000
Total
2 Providing and fixing of reference/ level
pillars on ether side of the road @ 50 m
C/C as per standered drawing
(150mmx150mmX900mm) and also 1 x 2 506.000
including
Total reused on high
embankment,sharp curves and safe
3 Scarifying existing bitumenus
guard on structure surface toall
etc and inclunding a
depth of 50
material, mmand
t&p andlabours
disposaland
of scarified
proper
material
completion ,asasper
perTechnical
direction Specification
of Engineer-
Clause
incharge.301.4. Reusable material shall be
sorted out from scarified material and
shall be compacted as per specifications.

TOTAL
1 x 90% 4850.000
3.00 M BT Ch. 4.850 to 18.300, Ch.
21.800 to 25.300 1 x 70% 16950.000
Total
4 Construction of embankment with
approved material obtained from availble
land as permitted and approved by
Engineer-in-Charge and as per Technical
Specitaion Clause 301.3.4.1, with all lifts
and leads, spreading, grading to required
slope and compacting to meet
requirement of Tables 300.1and 300.2 as
per Technical Specification clause 301.5
(Local earth)
As per calculation sheet

Deduct qty of excavation as per Item No.


60% OF EXCAVATION
7
Deduct for hard rock cutting as item No 8
(50%) -1 x 1 1200.000
Total
5 Construction of embankment with
approved material obtained from borrow
pits with a lift upto 1.5 m, transporting to
site, spreading, grading to required slope
and compacting to meet requirement of
Tables 300.1 and 300.2 with a Carted
upto 1000 m as per Technical
Specification Clause 301.5 (Carted)

Qty of earth work for Junction ch 0.00

Qty of earth work for Junction of


Chakroads 1 x 39 1.350
As per calculation sheet

Deduct qty of excavation as per Item No.


7 40% OF EXCAVATION
Total
6 Construction of embankment with
approved materials deposited at site from
roadway cutting and excavation from
drain and foundation of other structures
graded and compacted to meet
requirement of Tables 300.1 and 300.2 as
per Technical Specification Clause 301.5

AS per itm no 7
Total
7 Excavation for roadwork in soil with
hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in
tippers, trimming bottom and side slopes,
in accordance with requirements of lines,
grades and cross-sections, and
transporting to the embankment location
with a lift upto 1.5 m and lead upto 1000
m as per Technical Specification Clause
302.3

in widening
EXISTING SURFACE 1 x 2 16950.000
3.00 M BT 1 x 2 0.000
in T-junction 1 x 32,965 0.000
Deduct culverts portion and causeway
and minor bridge -1 x 2 12.000
in widening of curves Area = 4.43
Deduction for Retaining Wall/Toe 1 x 1 1200.000
Wall/Breast wall

Total
8 Excavation for roadway in hard rock
(blasting prohibited) with rock breakers
including breaking rock, loading in tippers
and disposal with a lift upto 1.5 m and
lead upto 1000 metres, trimming bottom
and side slopes in accordance with
requirements of lines, grades and cross-
sections as per Technical Specification
Clause 302.3.5

For smoothing of verticle curves 1 x 1 1200.000


Total
9 Construction of embankment in shoulder
with approved material obtained from
availble land as permitted and approved
by Engineer-in-Charge and as per
Technical Specitaion Clause 301.3.4.1,
with all lifts and leads, spreading,
grading to required slope and compacting
to meet requirement of Tables 300.1and
300.2 as per Technical Specification
clause 301.5 (LOcal earth)
1 x 2 #VALUE!
Total
10 Construction of embankment in shoulder
with approved material obtained from
borrow pits with a lift upto 1.5 m,
transporting to site, spreading, grading to
required slope and compacting to meet
requirement of Tables 300.1 and 300.2
with a lead upto 1000 m as per Technical
Specification Clause 301.5 (Carted)

1 x 2 0.000
Total
11 Construction of granular sub-base by
providing well graded material, spreading
in uniform layers with motor grader on
prepared surface, mixing by mix in place
method with rotavator at OMC, and
compacting with smooth wheel roller to
achieve the desired density, complete as
per Technical Specification Clause 401.
( GSB Grade - III)

3.00 M BT Ch. 4.850 to 18.300, Ch.


21.800 to 25.300
1 x 2 16950.000

EARTHEN PORTION Ch. 18.300 to


21.800 1 x 1 4850.000
deduct qty. of cutting length -1 x 2 1200.000
for smoothing of vrticle curves 1 x 1 1200.000

In widening of T-junctions 1 x 32965 0.000


In widening of curves Area = 1858.28
Extra Qty of for Junction ch 0.00 1 x 1 49.231
Deduct culverts portion and causeway
,minor bridge
-1 x 2 12.000
Total
12 Providing, laying, spreading and
compacting stone aggregates of specific
sizes to water bound macadam
specification including spreading in
uniform thickness, hand packing, rolling
with smooth wheel roller 80-100 kN in
stages to proper grade and camber,
applying and brooming, stone
screening/binding materials to fill-up the
interstices of coarse aggregate, watering
and compacting to the required density
grading 2 as per Technical Specification
Clause 405.Grading -II Material (63-45
mm size ) in base course with screening
material Type B and binding material, 75
mm thick by Mechanical means.

For Pot holes and undulation filling


1 x 10% 16950.000
3.00 M BT Ch. 4.850 to 18.300, Ch.
21.800 to 25.300 1 x 1 16950.000
EARTHEN PORTION Ch. 18.300 to
21.800
1 x 1 4850.000
For correction of super elevation upto 7%
1 x 49.2307 50.00
In widening of T-junctions 1 x 32965 0.000
In widening of curves Area = 1858.28
Extra Qty of for Junction ch 0.00 1 x 1 49.231
Deduct culverts portion and causeway
,minor bridge -1 x 1 12.000
Total
13 Providing, laying, spreading and
compacting stone aggregates of specific
sizes to water bound macadam
specification including spreading in
uniform thickness, hand packing, rolling
with smooth wheel roller 80-100 kN in
stages to proper grade and camber,
applying and brooming, stone
screening/binding materials to fill-up the
interstices of coarse aggregate, watering
and compacting to the required density
grading 2 as per Technical Specification
Clause 405 Grading -III Material (53-22.4
mm size ) in base course with screening
material Type B , 75 mm thick by
Mechanical means.

For Pot holes and undulation filling


x 10% 4850.000
For Strenthening coat Ch. 0.00 to 25.300
Km.
1 x 1 3500.000
In widening of T-junctions 1 x 32965 0.000
In widening of curves Area = 1858.28
Extra Qty of for Junction ch 0.00 1 x 1 49.231
Deduct culverts portion and causeway
,minor bridge
-1 x 1 12.000
Total
14 Prime Coat : Preparing and applying of
water for bitumen emulsion application,
IRC approved with cationic bitumen
emulsion-SS1 and water (<1000 ppm
TDS) in the ratio of 1 kg silane : 100 kg
cationic bitumen emulsion and add 200
liter water while filling water in
tanker/drum and then add 100 kg cationic
bitumen emulsion under circulation. Mix
the solution completely. Spray the
solution at the rate of 1 liter per sqm on
compacted stone base. Check quality of
bitumen emulsion before bulk use.

1 x 1 3500.000
In widening of T-junctions 1 x 32965 0.000
In widening of curves Area = 1858.28
Extra Qty of for Junction ch 0.00 1 x 1 49.231
Deduct culverts portion and causeway
and CC roads
-1 x 1 12.000
Total
15 Providing and applying Tack Coat with
Bitumen -VG-30 mixed with organo silane
nano technology and water in the ratio of
1.4:100:200 (Organo silane nano-
technology ) with pressure distributor at
the rate of 0.30 kg per sqm on the
prepared granular/bituminous surfaces
treated with primer & cleaned with
Hydraulic broom as per Technical
Specification Clause 503.

1 x 1 3500.000
In widening of T-junctions 1 x 32965 0.000
In widening of curves Area = 1858.28
Extra Qty of for Junction ch 0.00 1 x 1 49.231
Deduct culverts portion and causeway
,minor bridge -1 x 1 12.000
Total
16 Providing, laying and rolling of Open-
Graded Premix Carpet of 20 mm
thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration
grade bitumenVG-30 Mixed with Nano
Technology Based Organo Silane
Compound @ 0.1% by the weight of
bitumen for enhansed performance and
durability to required line, grade and level
to serve as wearing course on a
previously prepared base, including
mixing in a suitable plant, laying and
rolling with a three wheel 80-100 kN static
roller capacity, finished to required level
and grades to be followed by seal coat of
either Type A or Type B or Type C as per
Technical Specification Clause 508.

1 x 1 3500.000
In widening of T-junctions 1 x 32965 0.00
In widening of curves Area = 1858.28
Extra Qty of for Junction ch 0.00
1 x 1 49.231
Deduct culverts portion and causeway
,minor bridge
-1 x 1 12.000
Total
17 Providing and laying Seal Coat with
nano technology based organo silane
@ 0.1% by the weight of bitumen-VG-30,
sealing the voids in a bituminous surface
laid to the specified levels, grade and
cross fall using Type B as per Technical
Specification Clause 510

1 x 1 3500.000
In widening of T-junctions 1 x 32965 0.000
In widening of curves 1 x 1 1858.280
Extra Qty of for Junction ch 0.00
1 x 1 49.231
Deduct culverts portion and causeway
,minor bridge
-1 x 1 12.000
Total
18 Providing and Laying brick edging with
first class brick 8 cm wide and 12 cm
deep laid on either side of the mettaled
surface as per direction of Engineer-in-
charge including of all materials, labour,
T&P etc required for proper completion of
work ( as per SI 765 of Shedule of Rate
of UPPWD)

WINDHAMG
ANJ
PIPARKHAR
1 x 1 R ROAD
Deduct culverts portion and causeway
,minor bridge
-1 x 1 12.000
Total
B- CD Works
Repair of old Culverts

19 Repairof old existing culverts


1 x 1
Construction of New Culverts

20 Providing/ Laying of 1x350mm dia NP-3


RCC hume pipe goole as per approved
drawing& design
1 x 0
21 Providing/ Laying of 1x600mm dia NP-3
RCC hume pipe as per approved
drawing& design

1 x 3
22 Providing/ Laying of 1x1000mm dia NP-3
RCC hume pipe as per approved
drawing& design

1 x 2
23 Construction of 1x5.0 m span RCC
culvert as per drawing and technical
specification 1 x 0
24 OVER LAY ON EXISTING CAUSEWAY
1 249.00
Total 249.00
25 CONSTRUCTION OF BOX CULVERT in
Cause way
0 1 0.00
Size 1 NO
4x2x2 M 1 0.00
4x3x3 M 1 0.00
Total 0.00
C- Protection Works
26 CONSTRUCTION OF PARAPET WALL
1 38
Total 38
27 CONSTRUCTION OF TOE WALL
1 401.00
Total 401.00
28 CONSTRUCTION OF RETAINING WALL

1 804.00
Total 804.00
29 CONSTRUCTION OF BREAST WALL
1 200.00
Total 200.00
30 CONSTRUCTION OF PLUM
CONCRETE BLOCKS
100 3.00

D- Side Drains
31 Construction of KC Drain on both side of
abadi portionfor draiange of water
KC DRAIN 1 x 2 50.000
NAME 1 x 2 LENGTH
KUDWA VILLAGE 1 x 2 100.000
KUDWA YADAV BASTI 1 x 2 70.000
KUDWA TUNIYA BASTI 1 x 2 100.000
PANDU CHATAW VILLAGE 1 x 2 120.000
GHICHORWA VILLAGE 1 x 2 0.000
NIMIYA SUKAR (KHARAIYA) VILL. 1 x 2 0.000
NIMIYA SUKAR (KHARAIYA) VILL. 1 x 2 50.000
KARIYA VILLAGE 1 x 2 0.000
Total 490.000
32 Construction of U-Type Drain on both
side of abadi portionfor draiange of water
U- TYPE DEEP DRAIN
1 x 1 50.000
NAME
1 x 1 LENGTH
KUDWA VILLAGE
1 x 1 100.000
KUDWA YADAV BASTI
1 x 2 50.000
KUDWA TUNIYA BASTI
1 x 2 50.000
PANDU CHATAW VILLAGE
1 x 2 0.000
GHICHORWA VILLAGE
1 x 2 0.000
NIMIYA SUKAR (KHARAIYA) VILL. 1 x 2 0.000
GULARIYA 1 x 2 0.000
KARIYA VILLAGE 1 x 2 0.000
Total 250.000
E- Road furniture and signage

33 Road furniture and signage


a 5TH KM Stone 1 x 1 272
b KM Stone 1 x 1 1858
c Hectometer Stones 1 x 1 100
d Traffic Signs 1 x 1 25
e Direction and Place Identification signs
with size more than 0.9 sqm size board 1 x 1 24
f Logo board with diamond 1 x 1 13
g Informatory boards with Logo 1 x 1 2
i citizen information board 1 x 1 2
i Maintenance Board 1 x 1 1

ROAD LENGTH :- 25.30 KM


Construction of 350 mm NP-3 Hume Pi
S.No Description of Item No. L(m)
1 2 3 4
1 Earthwork in fondation in ordinary soil
(loam clay,sand) including filling upto 1.50
m and lead upto 30 m and including
filling,watering and ramming of excavated
earth into the trnches or into the sapce
For foundation
between the building/ structure and the 1 x 2 2.55
side
belowofpipe
fondation trenches or plinth and 1 x 1 6.300
removel and disposal of surface earth as
Total
directed by Engineer in charge upto a
2 distance
Constructionof 30of m from the
granular foundation
sub-base by
trenches including all T& P and material
providing well graded material,
etc complete as per UPPWD specification
spreading
SNo.1-251.. in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and Below Parapet
compacting 1 x 2 2.550
with smooth wheel rollerUnder
to achieve
Pipe 1 x 1 6.300
the desired density, complete as per
Technical Specification Clause 401.
( GSB Grade - III) (Including
Labour cess & Excluding GST)
3 Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC
1:3:6 concrete)
Below Head wall 1 x 2 2.55
Total
4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical
Head Wallspecification Clauses 702, 704, 1 x 2 2.400
1202 and 1204
Parapet 1 2 2.400
deduction for hume pipe 1 x 2 3.140
Total
5 Providing and laying 350mm reinforced
cement concrete pipe NP3 for culverts on
first class bedding of granular material in
single row including fixing collar with 1 x 3 2.500
cement mortar 1:2 but excluding
Total
excavation, protection works, backfilling,
6 concrete with
Pointing andcement
masonry works
mortar (1:3) in
on head
walls
Stoneandworkparapets Clause 1106.
as per drawing and technical
specification
Head Wall back Clauses 613.3
side with and 1204
Parapet 1 x 2 2.400
Parapet Top 1 x 2 2.400
Parapet inner face 1 x 2 2.400
Parapet sides 2 x 2
deduction for hume pipe 1 x 2 0.785
Total
7 White washing two coats on parapet walls
and tree trunks including preparation of
surface by cleaning scraping etc. as per 1 x 2 2.400
technical specifications Clause 1915
8 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper LS
completion of work (Lump sump)
Total cost of HP gule

600
SL Item of Work No L B H/D
1 E/W IN EXACAVATION
Head Wall 2 4.20 1.14 0.95
Under Pipe 1 5.40 1.05 1.80
Total
2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and compacting
with smooth wheel rollerFor to achieve
Head Wall 2 4.20 1.14 0.15
the desired density, complete as per
Under Pipe 1 5.40 1.05 0.15
Technical Specification Clause 401.
( GSB Grade - III) (Including Total
3 Labour
1.3.6 cess & Excluding GST)
For Head Wall 2 4.20 1.05 0.15
Below Pipe 1 5.40 1.05 0.15
Total
4 Providing and laying 600mm
reinforced cement concrete pipe NP3
for culverts on first class bedding of
granular material in single row
including fixing collar with cement
mortar 1:2 but excluding excavation,
protection works, backfilling, concrete
and masonry works in head walls
and parapets Clause 1106.

600mm dia NP3 Hume pipe 3 2.50


4 Stone masonry in 1:3 cement mortar
for substructure complete as per
drawing & technical specification
Clauses 702, 704, 1202 and 1204
For Head Wall 2 4.00 0.67 2.15
Parapet wall rect. Portion 2 4.00 0.40 0.45

Deduction for pipe 1X2X 3.14x0.75x0.75x0.69/4


Total
5 PLASTER
Outside 2 4.00 1.50
Inside 2 4.00 0.45
Top 2 4.00 0.40

Deductions 1X2X 3.14x0.75x0.75/4


Total
6 Plastering with cement mortar (1:4),
15 mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204
4 0.40 0.45
Total
7 0
Same as above item Pointing
Total
8 Painting, writing, lettering etc. on
number plates on culverts including
all materials, labour T&P etc.
required for proper completion of
work (Lump sump)

LS

Type of Cross drainage Works :


L
Sl No. Description of Item No.
(m)
1 2 3 4
1 E/W INEXCAVATION
For foundation 1 x 2 4.20
For sand filling below pipe 1 x 1 5.400
Total
2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and compacting
with smooth wheel roller to achieve
the desired density, complete as per
Technical Specification Clause 401.
( GSB Grade - III) (Including
Labour cess & Excluding GST)

Below Parapet 1 x 2 4.200


Under Pipe 1 x 1 5.400

3 0
Below head wall 1 x 2 4.20
Under Pipe 1 x 2 5.40

Total
4 Stone masonry in 1:3 cement mortar for
substructure complete as per drawing &
technical specification Clauses 702, 704,
1202 and 1204
parapet wall 1 x 2 4.000
Head wall 1 2 4.000
deduction for hume pipe 1 x 2 3.140
Total
5 Providing and laying 1000mm reinforced
cement concrete pipe NP3 for culverts on
first class bedding of granular material in
single row including fixing collar with
cement mortar 1:2 but excluding
excavation, protection works, backfilling,
concrete and masonry works in head
walls and parapets Clause 1106.

1 x 3 2.500
Total
6 Providing and laying M-25 plain cement
concrete in superstructure as per drawing
and technical specifications Clauses 800,
1205.4 and 1205.5
guard stone 1 x 4 0.200
1 x 2 0.400
Total
7 0
out side 1 x 2 4.000
inside 1 x 2 4.000
Top 1 x 2 4.000
deduction for hume pipe 1 x 2 3.140
Total
8 Plastering with cement mortar (1:4),
15 mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204
1 x 4 0.400

9 White washing two coats on parapet walls


including preparation of surface by
cleaning scraping etc. as per technical
specifications Clause 1915
1 x 2 4.000
Total
10 Painting, writing, lettering etc. on number
plates on culverts including all materials,
labour T&P etc. required for proper
completion of work (Lump sump)
LS
Total cost of culvert

COST ESTIMATE FOR CONSTRUCTION BREAST WALL


PACKAG
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
DISTRICT:- SONEBHADRA
Sl. No. Description of Item No. Length (m) Width (m) Depth
(m)
1 2 3 4 5 6
1 Earthwork in fondation in ordinary
soil (loam clay,sand) including filling
upto 1.50 m and lead upto 30 m and
including filling,watering and
ramming of excavated earth into the
trnches or into the sapce between
the building/ structure and the side of
fondation trenches or plinth and
removel and disposal of surface
earth as directed by Engineer in
charge upto a distance of 30 m from
the foundation trenches including all
T& P and material etc complete as
per UPPWD specification SNo.1-
251..

For breast wall 1×1 1.00 1.000 1.80


for K C drain 1×1 1.00 0.500 0.375
Total
2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and compacting
with smooth wheel roller to achieve
the desired density, complete as per
Technical Specification Clause 401.
( GSB Grade - III) (Including
Labour cess & Excluding GST)

For breast wall 1×1 1.00 1.00 0.15


for K C drain 1×1 1.00 0.50 0.15
Total
3 Providing concrete for
plain/reinforced concrete in open
foundations complete as per
drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC
1:3:6 concrete)

For breast wall 1×1 1.00 1.00 0.075


for K C drain 1×1 1.00 0.50 0.075
Total
4 Stone masonry in 1:3 cement mortar
for substructure complete as per
drawing & technical specification
Clauses 702, 704, 1202 and 1204
For breast wall 1×1 1 (0.90+0.60)/ 1.8
2
Total
5 Plain/reinforced cement concrete in
substructure complete as per
drawings and technical specification
Clauses 802, 804, 805, 806, 807,
1202 and 1204 R.C.C. grade M 25

For breast wall 1×1 1 0.6 0.025


1×1 1 0.5 0.15
Total
6 Pointing with cement mortar (1:3) on
brickwork as per drawing and
technical specification Clauses 613.3
and 1204
For breast wall 1×1 1.00 1 1.8
Total
7 Providing weepholes in brick
masonry/stone masonry,
plain/reinforced concrete abutment,
wing wall, return wall with 100 mm
dia AC pipe extending through the full
width of the structures with slope of
1(V):20(H) towards drawing face
complete as per drawing and
technical specification Clauses 614,
709, 1204.3.7

For breast wall 1×1 1


Total

COST ESTIMATE FOR CONSTRUCTION PARAPET WALL


PACKAG
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
DISTRICT:- SONEBHADRA
SI. Length Depth
Description of Item Nos Width (m)
No. (m) (m)
1 2 3 4 5 6
1 Earthwork in fondation in ordinary
soil (loam clay,sand) including
filling upto 1.50 m and lead upto
30 m and including filling,watering
and ramming of excavated earth
into the trnches or into the sapce
between the building/ structure
and the side of fondation trenches
or plinth and removel and
disposal of surface earth as
directed by Engineer in charge
upto a distance of 30 m from the
foundation trenches including all
T& P and material etc complete
as per UPPWD specification
SNo.1-251..
1x1 2.15 0.60 0.10
2 Construction of granular sub-base
by providing well graded material,
spreading in uniform layers with
motor grader on prepared
surface, mixing by mix in place
method with rotavator at OMC,
and compacting with smooth
wheel roller to achieve the
desired density, complete as per
Technical Specification Clause
401. ( GSB Grade - III)
(Including Labour cess &
Excluding GST)
1x1 2.15 0.60 0.10
3 Providing concrete for
plain/reinforced concrete in open
foundations complete as per
drawings and technical
specifications Clause 802, 803,
1202 & 1203 (PCC 1:3:6
concrete)
1x1 2.15 0.60 0.10
1x1 2.00 0.45 0.15
1x1 2.00 (0.45+0.25)/2 0.35

4 White washing two coats on


parapet walls including prepration
of surface by cleaning scrapping
etc. as per Technical specification
clause 1915 Standard Data Book
for analysis of rates of rural roads
Sr. No. 15.13, Pg-15-12 MORD
specification 1900

1x1 2.15 0.75


1x2 0.50 0.70

COST ESTIMATE FOR CONSTRUCTION RETAINING WALL


PACKAG
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
DISTRICT:- SONEBHADRA
Sl. No. Description of Item No. Length (m) Width (m) Depth
(m)
1 2 3 4 5 6
1 Earthwork in fondation in ordinary
soil (loam clay,sand) including filling
upto 1.50 m and lead upto 30 m and
including filling,watering and
ramming of excavated earth into the
trnches or into the sapce between
the building/ structure and the side of
fondation trenches or plinth and
removel and disposal of surface
earth as directed by Engineer in
charge upto a distance of 30 m from
the foundation trenches including all
T& P and material etc complete as
per UPPWD specification SNo.1-
251..

1×1 1.00 1.350 1.00


2 Construction of granular sub-base by
providing well graded material,
spreading in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and compacting
with smooth wheel roller to achieve
the desired density, complete as per
Technical Specification Clause 401.
( GSB Grade - III) (Including
Labour cess & Excluding GST)
1×1 1.00 1.350 0.10
3 Providing concrete for
plain/reinforced concrete in open
foundations complete as per
drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC
1:3:6 concrete)
1×1 1.00 1.350 0.075
4 Stone masonry in 1:3 cement mortar
for substructure complete as per
drawing & technical specification
Clauses 702, 704, 1202 and 1204 1×1 1.00 0.825 2.50
5 Plain/reinforced cement concrete in
substructure complete as per
drawings and technical specification
Clauses 802, 804, 805, 806, 807,
1202 and 1204 R.C.C. grade M 25
1×1 1.00 0.50 0.05
6 Pointing with cement mortar (1:3) on
Stone work as per drawing and
technical specification Clauses 613.3
and 1204 1×1 1.00 2.50
7 Providing weepholes in brick
masonry/stone masonry,
plain/reinforced concrete abutment,
wing wall, return wall with 100 mm
dia AC pipe extending through the full
width of the structures with slope of
1(V):20(H) towards drawing face
complete as per drawing and
technical specification Clauses 614,
709, 1204.3.7
1×1 1.00 1.00
6 Hand Packed stone filling in back of
walls including cost of all materials,
royality, T&P etc complete as per
direction of Engineer-in-Charge 1×1 1.00 0.30 1.00

COST ESTIMATE FOR CONSTRUCTION TOE WALL


PACKAG
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
DISTRICT:- SONEBHADRA
Sl. No. Description of Item No. Length (m) Width (m) Depth
(m)
1 2 3 4 5 6
1 Earthwork in fondation in ordinary
soil (loam clay,sand) including filling
upto 1.50 m and lead upto 30 m and
including filling,watering and
ramming of excavated earth into the
trnches or into the sapce between
the building/ structure and the side of
fondation trenches or plinth and
removel and disposal of surface
earth as directed by Engineer in
charge upto a distance of 30 m from
the foundation trenches including all
T& P and material etc complete as
per UPPWD specification SNo.1-
251..

1×1 1.00 0.90 0.60


2 Providing concrete for
plain/reinforced concrete in open
foundations complete as per
drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC
1:3:6 concrete)
1×1 1.00 0.90 0.075
3 Stone masonry in 1:5 cement mortar
for substructure complete as per
drawing & technical specification
Clauses 702, 704, 1202 and 1204 1×1 1.00 0.60 1.00
4 Plain/reinforced cement concrete in
substructure complete as per
drawings and technical specification
Clauses 802, 804, 805, 806, 807,
1202 and 1204 R.C.C. grade M 25
1×1 1.00 0.60 0.05

PER

Analysis for Overlay on Causeway


Length= 100 Mtr
Sl. No.
Description of Item Unit No L (m) B (m)
1 Construction of un-reinforced, plain
cement concrete pavement,
thickness as per design, over a
prepared sub base, with 43 grade
cement or any other type as per
Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates
conforming to IS:383, maximum size
of coarse aggregate not exceeding
25 mm, mixed in a concrete mixer of
not less than 0.2 cum capacity and
appropriate weigh batcher using
approved mix design, laid in
approved fixed side formwork (steel
channel, laying and fixing of 125
micron thick polythene film, wedges,
steel plates including levelling the
formwork as per drawing), spreading
the concrete with shovels, rakes,
compacted using needle, screed and
plate vibrators and finished in
continuous operation including
provision of contraction and
expansion, construction joints,
applying debonding strips, primer,
sealant, near approaches to
bridge/culvert and construction joints,
admixtures as approved, curing of
concrete slabs for 14-days,using
curing compound (where specified)
and water finishing to lines and grade
as per drawing and Technical
Specification Clause 1501

Base of causeway Cum 1 100 7.5

CONSTRUCTION OF KC- DRAIN


NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
Sl. No. Description of Item Unit No L (m) B (m)
1 Earthwork in fondation in ordinary soil
(loam clay,sand) including filling upto 1.50
m and lead upto 30 m and including
filling,watering and ramming of excavated
earth into the trnches or into the sapce
between the building/ structure and the
side of fondation trenches or plinth and
removel and disposal of surface earth as
directed by Engineer in charge upto a
distance of 30 m from the foundation
trenches including all T& P and material
etc complete as per UPPWD specification
SNo.1-251..

Cum 1 1.00 1.10

2 Construction of granular sub-base by


providing well graded material,
spreading in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and compacting
with smooth wheel roller to achieve
the desired density, complete as per
Technical Specification Clause 401.
( GSB Grade - III) (Including
Labour cess & Excluding GST)

Cum 1 1.00 1.10

3 Providing concrete for


plain/reinforced concrete in open
foundations complete as per
drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC
1:3:6 concrete)

Cum 1 1.00 1.10

4 Stone masonry in 1:3 cement mortar


for substructure complete as per
drawing & technical specification
Clauses 702, 704, 1202 and 1204
Cum 1 1.00 0.50

5 Plain/reinforced cement concrete in


substructure complete as per
drawings and technical specification
Clauses 802, 804, 805, 806, 807,
1202 and 1204 R.C.C. grade M 25

bottom Cum 1 1.00 0.60


top Cum 1 1.00 0.50

6 Plastering with cement mortar (1:4),


15 mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204
Sqm 1 1.00 0.20
Cost For 1.00 m

CONSTRUCTION OF U-DRAIN
NAME OF ROAD :- WINDHAMGANJ PIPARKHARR ROAD TO AURADAR.
Sl. No.
Description of Item Unit No L (m) B (m)

1 Earthwork in fondation in ordinary soil


(loam clay,sand) including filling upto 1.50
m and lead upto 30 m and including
filling,watering and ramming of excavated
earth into the trnches or into the sapce
between the building/ structure and the
side of fondation trenches or plinth and
removel and disposal of surface earth as
directed by Engineer in charge upto a
distance of 30 m from the foundation
trenches including all T& P and material
etc complete as per UPPWD specification
SNo.1-251..

Cum 1 1.00 1.65

2 Construction of granular sub-base by


providing well graded material,
spreading in uniform layers with
motor grader on prepared surface,
mixing by mix in place method with
rotavator at OMC, and compacting
with smooth wheel roller to achieve
the desired density, complete as per
Technical Specification Clause 401.
( GSB Grade - III) (Including
Labour cess & Excluding GST)

Cum 1 1.00 1.65

3 Providing concrete for


plain/reinforced concrete in open
foundations complete as per
drawings and technical specifications
Clause 802, 803, 1202 & 1203 (PCC
1:3:6 concrete)

Cum 1 1.00 1.65

4 Stone masonry in 1:3 cement mortar


for substructure complete as per
drawing & technical specification
Clauses 702, 704, 1202 and 1204
Cum 2 1.00 0.50
5 Plain/reinforced cement concrete in
substructure complete as per
drawings and technical specification
Clauses 802, 804, 805, 806, 807,
1202 and 1204 R.C.C. grade M 25

bottom Cum 1 1.00 0.45


top Cum 2 1.00 0.50

6 Plastering with cement mortar (1:4),


15 mm thick on stone masonary in
substructure as per technical
specification Clauses 613.4 & 1204
Sqm 2 1.00 0.60

7 Plain/reinforced cement concrete in


substructure complete as per
drawings and technical specification
Clauses 802, 804, 805, 806, 807, cum 1 1 1.45
1202 and 1204 (M-25)(40% of total
length) for drain cover.

8 Suplying, Fixing, and placing HYSD 0.087*1.5%*7850


bar reinforcement in superstructure
as per drawing and technical
specifications Clause Qtl
1002,1010,1202 @ 1.5% of R.C.C.
Work.

Cost For 1.00 m


RADAR.

B D/H Quantity Unit Rate Amount


(m) (m) ( Rs) Rs
5 6 7 8 9 10

2.000 9700.000 sqm

2.000 14000.000 sqm

8.000 38800.000 sqm

2.000 -48.000 sqm


62452.000 sqm 4.22 263547.44

1012.000 No
1012 No 343.90 348026.8

3.750 16368.750 sqm

3.000 35595.000 sqm


51963.750 sqm 18.51 961849.01

11.615 Cum

N -4879.982 Cum

10.000 1.500 -9000.000 sqm


25240.578 Cum 86.50 2183310.00
49.231 Cum

52.650 Cum

13.685 Cum

N -3253.321 Cum
13471.030 Cum 165.82 2233766.19

8133.303 Cum
8133.303 Cum 55.62 452374.31

0.000 Crust 0.000 Cum


1.050 0.000 0.000 Cum
Crust 0.000 Cum
0.000
0.000 Crust sqm
Sqm Crust 4.425 Cum
1/2*1.90x3.8 4332.000
0

8133.303 Cum 36.72 298654.89

10.000 1.500 18000.000


18000.000 Cum 457.25 8230500.00
(1.875+2.0)/2 0.150 7492.540
7492.540 Cum 86.5 648104.71

(1.875+2.0)/2 0.150 6359.210


6359.210 Cum 165.82 1054484.20

0.000
0.000 Crust Cum

0.000
0.000 0.000 Cum
0.525 0.175 -220.500 Cum
4.050 0.175 850.500 Cum

0.000 Crust #VALUE! Cum


Sqm Crust 1858.280 Cum
Crust 49.231 Cum
0.000
0.000 Crust sqm
6961.158 Cum 3036.76 21139366.17
0.00

Width 0.075 127.125 cum

3.000 0.075 3813.750 cum

Proposed Proposed #VALUE!


Width Prime Width G-2 Cum

2.00 0.023 114.872 Cum


0.075 0.000 Cum
Sqm 0.075 139.371 Cum
0.075 3.692 Cum
Proposed
Width Prime 0.075 -0.900 sqm
7012.761 cum 3089.700 21667327.66

3.000 0.075 109.125 cum

Proposed 0.00
Width Prime 0.075 262.500 Cum
0.075 0 Cum
Sqm 0.075 139.371 Cum
0.075 3.692 Cum

Proposed
Width Prime 0.075 -0.900 sqm
7497.188 cum 3206.420 24039133.55
0.00

Proposed
Width Prime 3500.000 sqm
0.000 sqm
Sqm 1858.280 sqm
49.231 sqm

Proposed
Width Prime -12.000 sqm
98143.761 sqm 35.670 3500787.95
0.00

Proposed
Width Prime 3500.000 sqm
0.000 sqm
Sqm 1858.280 sqm
49.231 sqm
Proposed
Width Prime -12.000 sqm
98143.761 sqm 12.380 1215019.76
0.00

Proposed
Width Prime 3500.00 sqm
0.00 sqm
Sqm 1858.280 sqm

49.231 sqm

Proposed
Width Prime -12.000 sqm
98143.761 sqm 137.25 13470231.20
0.00

Proposed
Width Prime 3500.000
0.000
Sqm 1858.280

49.231 sqm

Proposed
Width Prime -12.000 sqm
98143.761 sqm 42.02 4124000.84

1.000 Km

-0.012 Km
25.039 Km 75000.00 1877925.00

1.000 Job 133463.63 133463.63


54799.99

0.000 No 0.00

3.000 No 0.00 0.00


0

2.000 No 0.00

0.000 No 2667545.14 0.00


0.00
249.00 RM
249.00 RM 926134.58 230607509.18
0.00

0.00 NO
1.00 NO
0.00 NO
0.00 NO
1.00 NO 0.00 0.00

0.00
38 NO
38 NO 31.07 1180.66
0.00
401.00 RM
401.00 RM 180.46 72364.46
0.00
804.00 RM
804.00 RM 71.06 57132.24
0.00
200.00 RM
200.00 RM 9090.90 1818180.00

1.250 1.250 468.75 Cum


43.50 20390.63

0.00

100.000 RM
2.000 RM
200.000 RM
140.000 RM
200.000 RM
240.000 RM
0.000 RM
0.000 RM
100.000 RM
0.000 RM
982.000 RM 0.00 0.00
0.00

50.000 RM

1.000 RM

100.000 RM

100.000 RM

100.000 RM
0.000 RM
0.000 RM
0.000 RM
0.000 RM
0.000 RM
351.000 RM 6165.52 2164098.82

272 No. 20.72 5634.93


1858 No. 14.22 26421.56
100 No. 2.53 252.80
25 No. 3,098.29 77457.25

24 No. 8.87 212.89


13 No. 3176.59 41295.67
2 No. 13.31 26.61
2 No. 28.51 57.02
1 No. 13.31 13.31

PACKAGE NO. :- UP67146


350 mm NP-3 Hume Pipe Gule
B(M) D/H (M) Quantity Unit Rate In Rs Amount in Rs
5 6 7 8 9 10

0.91 0.750 3.481 cum


0.750 0.850 4.016 cum
7.497 cum 101.00 757.20

0.910 0.150 0.696 cum


0.750 0.150 0.709 cum
Total 1.405 cum 0.00 0.00
0.910 0.150 0.696 sqm
0.696 sqm 5,265.17 3665.35

0.850 1.800 7.344


0.400 0.450 0.864
0.45*0.45/4 0.625 -0.199
8.009 cum 0.00 0.00

7.500 Rm
7.500 Rm 2,467.33 18505.00

2.250 10.800
0.400 1.920
0.450 2.160 sqm
0.400 0.450 0.720 sqm
0.450 0.450 -0.318 sqm 0.000
15.282 sqm 0.00 0.00

4.800 sqm 0.00 0.000

LS 1 Job 500.00 500.000


23427.54

QTY. UNIT Rate Amount

9.10 cum
10.21 cum
19.31 cum 0.00 0.00

1.44 cum
0.85 cum
2.29 cum 0.00 0.00

1.32 cum
0.85
2.17 cum 5,265.17 11425.42
7.50 Rm 2114.07 15855.53

11.52
1.44

-0.61
12.35 cum 0.00 0.00

12.00
3.60
3.20

-0.88
17.92 Sqm 0.00 0.00

0.72
0.72 Sqm 0.00 0

6.80 Sqm
6.80 Sqm 15.85 107.78

1 Job 1 Job 500.00 500.00


Total (Rs.) 27888.70

Construction of 1000 mm NP-3 Hume Pipe Culvert


B D/H Unit Rate Amount
Quantity
(m) (m) Rs Rs
5 6 7 8 9 10
1.25 0.950 9.975 cum
1.500 1.900 15.390 cum
25.365 cum 0.00 0.00

1.250 0.150 1.575 cum


1.500 0.150 1.215 cum
Total 2.790 cum 0.00 0.00

1.250 0.150 1.575 cum


1.500 0.150 2.430 cum

4.005 cum 1,050.00 4205.25

0.400 0.450 1.440


0.730 2.600 15.184
1.2*1.2*.73/4 -1.650
14.974 cum 22.50 336.91

7.500 Rm
7.500 Rm 0.00 0.00
0.000

0.200 0.500 0.080 cum


0.400 1.000 0.320 cum
0.400 cum 7.42 2.97

1.950 15.600 sqm


0.450 3.600 sqm
0.400 3.200 sqm
1.2*1.2/4 -2.261 sqm 0.000
20.139 sqm 0.00 0.00
0.450 0.720 sqm
0.720 sqm 0.00 0.00

1.950 15.600 sqm


15.600 sqm 0.00 0.00

LS 1 Job 500.00 500.000


5045.1250771

BREAST WALL
UP67146
PACKAGE NO. :-
O AURADAR.

Unit Quanitity Rate (Rs.) Amount


(cum) (Rs.)
7 8 9 10

Cum 1.80
Cum 0.19
1.99 0.00 0.00
Cum 0.15
Cum 0.08
0.23 0.00 0.00

Cum 0.075
Cum 0.038
0.113 0 0.000

Cum 1.35

1.35 0.0000 0.00

Cum 0.015
Cum 0.075
0.09 0 0

sqm 1.8
1.8 0 0
N0 1
1 0 0
Grand Total 0.00
Rm. Say Rs. 0.00

PARAPET WALL
UP67146
PACKAGE NO. :-
O AURADAR.

Amount
Unit Quantity Rate (Rs.)
(Rs.)
7 8 9 10

Cum 0.13 0.00 0.00


Cum 0.13 0.00 0.00

Cum 0.13
Cum 0.14
Cum 0.25
Total 0.51 5265.17 2679.97

sqm 1.61
sqm 0.35
sqm 1.96 15.85 31.11
Total 2711.08
Say (Rs.) 2711.00

RETAINING WALL
UP67146
PACKAGE NO. :-
O AURADAR.

Unit Quanitity Rate (Rs.) Amount


(cum) (Rs.)
7 8 9 10
Cum 1.35 0.00 0.00

Cum 0.14 0.00 0.00

Cum 0.10 5265.17 533.10

Cum 2.06 0.00 0.00

Cum 0.03 0.00 0.00

Sqm 2.50 0.00 0.00

N0 1.00 129.01 129.01


Cum 0.30 2368.82 710.65
Grand Total 1372.75
Rm. Say Rs. 1372.800

ON TOE WALL
UP67146
PACKAGE NO. :-
O AURADAR.

Unit Quanitity Rate (Rs.) Amount


(cum) (Rs.)
7 8 9 10

Cum 0.54 2.93 1.58

Cum 0.07 0.00 0.00

Cum 0.60 0.00 0.00

Cum 0.03 0.00 0.00


Grand Total 1.58
Rm. Say Rs. 1.600

seway
Width= 7.5 Mtr
Amount
H (m) Qty. Rate (Rs.)
(Rs.)
0.19 142.5
Total 142.5 6499.19 926134.575
Total (Rs.) 926134.6
Rate per RM 9261.346

C- DRAIN
PACKAGE NO. :- UP67146
O AURADAR.
H (m) Qty. Rate (Rs.) Amount (Rs.)
0.50 0.55
Total 0.55 101.00 55.55

0.15 0.17
Total 0.165 0.00 0.00

0.075 0.08
Total 0.0825 5265.17 434.38

0.35 0.18
Total 0.18 4750.55 831.35

0.15 0.090
0.050 0.025
Total 0.115 3530.02 405.95

0.20
Total 0.20 0.00 0.00
Total (Rs.) 1727.23

U-DRAIN
UP67146
PACKAGE NO. :-
O AURADAR.
Amount
H (m) Qty. Rate (Rs.)
(Rs.)

0.83 1.36
Total 1.36 0.00 0.00

0.10 0.17
Total 0.165 0.00 0.00

0.075 0.12
Total 0.12375 0.00 0.00

0.65 0.65
Total 0.65 0.00 0.00
0.05 0.023
0.025 0.025
Total 0.048 0.00 0.00

1.20
Total 1.20 0.00 0.00

0.15 0.087 0.8 0.07

0.1024425 0 0.00

Total (Rs.) 0.07

You might also like