Desarmado y Armado
345D, 349D and 349D2 Excavators and 345D MHPU and 349D MHPU Mobile Hydraulic Power
Units Machine Systems
Número de medio -RENR9574-09 Fecha de publicación -01/08/2014 Fecha de actualización -17/05/2017
i03474464
Removal Procedure
Table 1
Required Tools
Tool Part Number Part Description Qty
141-1785 Receiving Sleeve 1
3S-6224 Electric Hydraulic Pump 1
6V-3175 (2)
Hydraulic Cylinder Gp 1
1U-5197 (1)
Hydraulic Cylinder Gp 1
A
9U-6809 (1)
Fast Runner Nut Assembly (M36) 1
9U-6811 (1)
Puller Stud (M36) 1
9U-5346 (2)
Fast Runner Nut Assembly (M30) 1
137-8460 (2)
Puller Stud (M30) 1
B 140-7742 Sleeve 1
(1)
Used for the pin that connects the bucket to the control linkage and the pin that connects the bucket control linkage to the bucket
cylinder
(2)
Used for the pin that connects the bucket control linkage to the stick
When you are using hydraulic cylinders and puller studs, always ensure
that the rated capacity of the puller stud meets or exceeds the rated
capacity of the hydraulic cylinder. If the puller stud does not meet or
exceed the rated capacity of the hydraulic cylinder, a sudden failure of
the puller stud could occur. The sudden failure of the puller stud could
result in personal injury or death.
NOTICE
Do not use threaded rods that have not been hardened as tooling with
hydraulic cylinders. The maximum rated tonnage should be stamped
on one end of the puller studs. Do not use threaded rods that have not
been stamped with the rated tonnage.
1. Start the engine. Park the machine on a hard, level surface. Fully extend the stick. Position the bucket level
on the ground. Shut off the engine.
Illustration 1 g01212593
Illustration 2 g01212595
2. Slide O-ring seals (3) off the pin joints between the bucket and the power link and onto the flanges of the
bucket.
Note: Make sure that the threaded puller hole in pin assembly (1) is clean prior to installation of Tooling
(A).
3. Remove bolt (2). Fasten a suitable lifting device to Tooling (A). The weight of Tooling (A) is
approximately 136 kg (300 lb). Fasten Tooling (A) to pin assembly (1).
Note: Reposition the suitable lifting device during the removal of pin assembly (1).
4. Use Tooling (A) to remove pin assembly (1). The combined weight of Tooling (A) and pin assembly (1) is
approximately 191 kg (420 lb).
Illustration 3 g01212825
6. Start the engine. Extend the bucket cylinder. Use a suitable blocking in order to support the bucket
cylinder. Shut off the engine.
Illustration 4 g01212842
Illustration 5 g01213103
7. Attach a suitable lifting device and Tooling (B) to power link (4). The weight of power link (4) is
approximately 240 kg (529 lb). Raise power link (4) to a horizontal position.
Note: Some bucket control linkages are equipped with shims between the power link and the right hand
idler link.
8. Remove plate (5) from pin assembly (6). Install suitable cribbing in order to support the left hand idler link
and the right hand idler link. Use Tooling (A) to remove pin assembly (6). The weight of pin assembly (6)
is approximately 43 kg (95 lb).
9. Remove power link (4). If equipped, remove the shim between the right hand idler link and power link (4).
Illustration 6 g01213104
Illustration 7 g01213107
10. Attach a suitable lifting device to left hand idler link (7). The weight of left hand idler link (7) is
approximately 50 kg (110 lb). Remove plate (8).
11. Remove the grease fitting from pin assembly (9). Use Tooling (A) to partially remove pin assembly (9) in
order to remove left hand idler link (7). The weight of pin assembly (9) is approximately 43 kg (95 lb).
12. Attach a suitable lifting device to right hand idler link (10). The weight of right hand idler link (10) is
approximately 52 kg (115 lb). Use Tooling (A) to remove pin assembly (9) and right hand idler link (10).