Professional Documents
Culture Documents
Specs 2009 V1
Specs 2009 V1
BRICK WORK
CONTENTS
6.1 Bricks/ Brick Tiles/ Brick Bats/ Mechanized Autoclave Fly 208
Ash Lime Brick
6.7 Joining Old Brick Work with New Brick Work 221
Bond
The arrangement of the bricks in successive courses to tie the brick work together both longitudinally
and transversely. The arrangement is usually designed to ensure that no vertical joint of one course is
exactly over the one in the next course above or below it, and there is greatest possible amount of lap.
Bed Joint
Horizontal joint in brick work or masonry.
Closer
Any portion of a brick used in constructing a wall, to close up the bond next to the end brick of a
course (See Fig. 6.3).
Coping or Weathering
The cover applied over or the geometrical form given to a part of structure to enable it to shed rain
water.
Corbel
A cantilever projecting from the face of a wall to form a bearing (see Fig. 6.1D)
Cornice
Horizontal or ornamental feature projecting from the face of a wall (see Fig. 6.1D)
Course
A layer of bricks including bed mortar.
Cross joint
A joint other than a bed joint normal to the wall face.
Efflorescence
A powdery incrustment of salts left by evaporation. This may be visible on the surface or may be
below surface. In the latter case, this is termed as crypto Efflorescence.
Header
A brick laid with its length across the wall.
Indenting
The leaving recesses into which future work can be bonded.
Jamb
The part of the wall at the side of an opening.
Joint
A junction of bricks.
Jointing
The operation of finishing joints as the masonry work proceeds.
Pier
A thickened section forming integral part of the wall placed at intervals along the wall primarily to
increase the stiffness of the wall or to carry a vertical concentrated load. The thickness of a pier is the
over all thickness including the thickness of the wall, or when bonded into one leaf of a cavity wall the
thickness obtained by treating this leaf as an independent wall (see Fig. (6.1A, 6.1B)).
Quoin
An external corner in brick work, the term may also denote the brick used to form the quoin.
Scaffolding
A temporary erection of timber or steel work used in the construction, alteration, demolition or repairs
of a building to support or to attend of the hoisting or lowering of workmen, their tools and materials.
Scaffoldings are of two types, namely single and double scaffoldings. Single scaffolding consists of a
row of verticals connected to wall by horizontal supported on and tied to the structure. Double
scaffolding consists of two rows of verticals secured or leashed together with horizontal and diagonal
bracings forming essentially a structure independent of the building. It may also connect to the structure
at convenient points for the sake of better stability.
Sill
A brick work forming the lower boundary of door or window opening (see Fig. 6.1D).
Spandrel
The space between the haunches and the road decking of an arch.
Strecher
A brick laid with its length in the direction of the wall.
String course
A horizontal course projecting from a wall usually introduced at every floor level or windows or below
parapet for imparting architectural appearance to the structure and also keeping off the rain water. (see
Fig. 6.1D).
Templet
A pattern of sheet metal used as a guide for setting out specific section and shape.
Toothing
Bricks left projecting in alternate courses to bond with future work.
Wall joint
A joint parallel to the wall face.
(b) Fly Ash Lime Bricks (FALG Bricks) : The Fly Ash Lime Bricks (FALG Bricks) shall conform to
IS 12894. Visually the bricks shall be sound, compact and uniform in shape free from visible
cracks, warpage, flaws and organic matter. The bricks shall be solid and with or without frog on
one of its flat side.
Bottom ash used as replacement of sand shall not have more than 12% loss on ignition when tested.
Sand: Deleterious materials, such as clay and silt in the sand shall preferably be less than 5%.
Additives: Any suitable additive considered not detrimental to the durability of bricks may be used.
(c) Clay Fly Ash Bricks: The clay fly ash bricks shall conform to IS 13757. The bricks shall be
sound, compact and uniform in shape and colour. Bricks shall have smooth rectangular faces
with sharp and square corners. The bricks shall be free from visible cracks, flaws, warpage,
nodules of free lime and organic matter, the bricks shall be hand or machine moulded. The bricks
shall have frog of 100 mm in length 40 mm width and 10 to 20 mm deep on one of its flat sides. If
made by extrusion process may not be provided with frogs. Fly Ash shall conform to grade I or
grade II of IS 3812.
(d) Calcium Silicate Bricks: The bricks shall conform to IS 4139. The Calcium silicate bricks shall
be sound, compact and uniform in shape. Bricks shall be free from visible cracks, warpage,
organic matter, large pebbles and nodules of free lime. Bricks shall be solid and with or without
frog. The bricks shall be made of finely grounded sand siliceous rock and lime. In addition limited
quantity of fly ash conforming to IS 3812 may be used in the mix. These bricks are also known as
Fly Ash Sand Lime bricks in the construction industry.
(e) Tile Brick: The bricks of 4 cm height shall be moulded without frogs. Where modular tiles are not
freely available in the market, the tile bricks of F.P.S. thickness 44 mm (1-3/4") shall be used
unless otherwise specified.
(f) Brick Bats: Brick bats shall be obtained from well burnt bricks.
(g) Mechanized Autoclave Fly Ash Lime Brick: These bricks shall be machine moulded and
prepared in plant by appropriate proportion of fly ash and lime. The autoclave fly ash bricks shall
conform to IS 12894. Visually, the bricks shall be sound, compact and uniform shape, free from
visible cracks, warpage and organic matters. The brick shall be solid with or without frog, and of
100/80 mm in length, 40 mm width and 10 to 20 mm deep one of its flat side as per IS 12894. The
brick shall have smooth rectangular faces with sharp corners and shall be uniform in shape and
colour. Fly ash shall conform to IS 3812 and lime shall conform to class ‘C’ hydrated lime of IS 712.
6.1.1 Dimensions
The brick may be modular or non-modular. Sizes for both types of bricks/tiles shall be as per Table
6.1. While use of modular bricks/tiles is recommended, non-modular (FPS) bricks/tiles can also be used
where so specified. Non-modular bricks/tiles of sizes other than the sizes mentioned in Table 6.1 may
also be used where specified.
TABLE 6.1
TABLE 6.2
Class Average compressive strength
Designation Not less than Less than
N/mm 2 (kgf/cm )2 N/mm 2 (Kgf/cm2)
12.5 (125) 12.5 (125) 15.0 150
10 (100) 10 (100) 12.5 125
7.5 (75) 7.5 (75) 10 100
5 (50) 5 (50) 7.5 75
3.5 (35) 3.5 (35) 5.0 50
The bricks shall have smooth rectangular faces with sharp corner and shall be uniform in colour and
emit clear ringing sound when struck.
(Note: Upper limits specified in Table 6.2 are for calculating the average compressive strength in
accordance with Appendix B of Chapter 6).
6.1.3.1 Sampling: For carrying out compressive strength, water absorption, efflorescence and
dimensional tests, the samples of bricks shall be taken at random according to the size of lot as given in
Table 6.3 below. The sample thus taken shall be stored in a dry place until tests are made. For the
purpose of sampling, the following definition shall apply.
(a) Lot: A collection of bricks of same class and size, manufactured under relatively similar conditions of
production. For the purpose of sampling a lot shall contain a maximum, of 50,000 bricks.
In case a consignment has bricks more than 50,000 of the same classification and size and
manufactured under relatively similar conditions of production, it shall be divided into lots of
50,000 bricks or part thereof.
(b) Sample: A collection of bricks selected for inspection and/or testing from a lot to reach the
decision regarding the acceptance or rejection of the lot.
(c) Defective: A brick failing to meet one or more of the specified requirements.
Scale of sampling and criteria for conformity for visual and dimensional characteristics:—
Visual characteristics: The bricks shall be selected and inspected for ascertaining their
conformity to the requirements of the relevant specification.
(ii) Visual Characteristics: All the bricks selected above in accordance with Col. 1 and 2 of Table
6.3 shall be examined for visual characteristics. If the number of defective bricks found in the
sample is less than or equal to the corresponding number as specified in Col. 3 of Table 6.3 the
lot shall be considered as satisfying the requirements of visual characteristics, otherwise the lot
shall be deemed as not having met the visual requirements.
(iii) Dimensional Characteristics: The number of bricks to be selected for inspecting the
dimensions and tolerance shall be in accordance with Col. 1 and 4 of Table 6.3. These bricks will
be divided into groups of 20 bricks at random and each of the group of 20 bricks thus formed will
be tested for all the dimensions and tolerances. A lot shall be considered having found meeting
the requirements of dimensions and tolerance if none of the groups of bricks inspected fails to
meet the specified requirements.
TABLE 6.3
Scale of Sampling and Permissible Number of Defectives for Visual and Dimensional
Characteristics
Note: In case the lot contains 2000 or less bricks the sampling shall be as per decision of the
Engineer-in-Charge.
(iv) Scale of Sampling and Criteria for Physical Characteristics: The lot which has been found
satisfactory in respect of visual and dimensional requirements shall be next tested for physical
characteristics like compressive strength, water absorption, efflorescence as specified in relevant
material specification. The bricks for this purpose shall be taken at random from those already
selected above. The number of bricks to be selected for each of these characteristics shall be in
accordance with relevant columns of Table 6.4.
TABLE 6.4
Scale of Sampling for Physical Characteristics
6.1.3.3 Dimensional Tolerances: The dimensions of, modular bricks when tested as described above
as per procedure described in Appendix A of Chapter 6 shall be within the following limits per 20 bricks
or locally available size as approved by Engineer-in-charge.
Brick Tiles
760 to 840 mm (800 ± 40 mm) for 40 mm high brick tiles
In case of non-modular bricks, % age tolerance will be ± 2% for group of 20 numbers of class 10
bricks, and ± 4% for other class of bricks.
6.1.3.4 Compressive Strength: The bricks, when tested in accordance with the procedure laid down in
Appendix B of Chapter 6 shall have a minimum average compressive strength for various classes as
given in Table 6.2. The compressive strength of any individual brick tested shall not fall below the min.
average compressive strength specified for the corresponding class of brick by more than 20%. In case
compressive strength of any individual brick tested exceeds the upper limit specified in Table 6.2 for the
corresponding class of bricks, the same shall be limited to upper limit of the class as specified in Table
6.2 for the purpose of calculating the average compressive strength.
6.1.3.5 Water Absorption: The average water absorption of bricks when tested in accordance with the
procedure laid down in Appendix C of Chapter 6 shall be not more than 20% by weight.
6.1.3.6 Efflorescence: The rating of efflorescence of bricks when tested in accordance with the
procedure laid down in Appendix D of Chapter 6 shall be not more than moderate.
For sewers of special shapes, such as the oval sewers, the bricks may have to be suitable
tapered to conform to the radii of curvature of the arches and barrels and sides of sewers.
Tolerance: The permissible tolerance on the dimensions specified in 6.1.4.2 shall be as follows :
6.1.4.3 Compressive Strength: The average compressive strength obtained on a sample of sewer
bricks when tested in accordance with the procedure laid down in IS 3495 (Part I) shall be not less than
17.5 N/mm2 (175 kgf/cm2 approximately) and the individual strength of any brick shall be not less than
16 N/mm2 (160 kgf/cm2 approximately).
6.1.4.4 Water Absorption: The average value of water absorption for five bricks after 24 h cold water
immersion test when tested in accordance with IS 3495 (Part 2) shall not exceed 10 per cent of the
average dry weight of the brick and the absorption for any individual brick shall not exceed 12 per cent.
6.1.4.5 Efflorescence: When the bricks are tested in accordance with the method laid down in IS 3495
(Part 3), the rating of efflorescence shall not be more than ‘slight’.
6.1.5.2 Dimensions and Tolerances: The standard size of burnt clay perforated bricks shall be as
follows:
Length Width Height
(L) (W) (H)
mm mm mm
Modular 190 90 90
Non 230 110 70
Modular
Dimension Tolerance
mm mm
70, 90 +4
110, 190 +7
230 + 10
Note: The tolerances specified above shall apply to measurements on individual bricks.
6.1.5.3 Perforations: The area of perforation shall be between 30% and 45% of the total area of the
corresponding face of the bricks.
The perforation shall be uniformly distributed over the surface. In the case of rectangular
perforations, the larger dimension shall be parallel to the longer side of the brick. The shorter side of the
perforation shall be less than 20 mm incase of rectangular perforations and less than 25 mm diameter in
case of circular perforations.
The thickness of any shell shall not be less then 15 mm and that of any web not less than 10 mm.
6.1.5.4 Compressive Strength: The bricks when tested in accordance with the procedure laid down in
IS 3495 (Parts 1 to 4) shall have a minimum average compressive strength of 7 N/ mm2 on net area.
The compressive strength of any individual brick tested shall not fall below the minimum
compressive strength specified for the corresponding class of bricks. The lot shall then be checked for
next lower class of brick.
6.1.5.5 Water Absorption: The bricks when tested in accordance with the procedure laid down in IS
3495 (parts 1 to 4): after immersion in cold water for 24 hours water absorption shall not be more than
20 percent by weight.
6.1.5.6 Efflorescence: The bricks when tested in accordance with the procedure laid down in IS 3495
(Parts 1 to 4) shall have a rating of efflorescence not more than ‘slight’.
6.1.5.7 Warpage: The bricks when tested in accordance with the procedure laid down in IS 3495 (parts
1 to 4) the average warpage shall not exceed 3%.
6.2.2 Mortar
The mortar for the brick work shall be as specified, and conform to accepted standards. Lime shall
not be used where reinforcement is provided in brick work.
Note I: The period of soaking may be easily found at site by a field test in which the bricks are
soaked in water for different periods and then broken to find the extent of water penetration. The least
period that corresponds to complete soaking will be the one to be allowed for in construction work.
Note II : If the bricks are soaked for the required time in water that is frequently changed the soluble
salt in the bricks will be leached out, and subsequently efflorescence will be reduced.
6.2.4 Laying
6.2.4.1 Bricks shall be laid in English Bond (Fig. 6.2, 6.3, 6.4) unless otherwise specified. For brick work
in half brick wall, bricks shall be laid in stretcher bond. Half or cut bricks shall not be used except as
closer where necessary to complete the bond. Closers in such cases, shall be cut to the required size
and used near the ends of the wall. Header bond shall be used preferably in all courses in curved plan
for ensuring better alignment.
Note: Header bond shall also be used in foundation footings unless thickness of walls (width of
footing) makes the use of headers impracticable. Where thickness of footing is uniform for a number of
courses, the top course of footing shall be headers.
6.2.4.2 All loose materials, dirt and set lumps of mortar which may be lying over the surface on which
brick work is to be freshly started, shall be removed with a wire brush and surface wetted. Bricks shall be
laid on a full bed of mortar, when laying, each brick shall, be properly bedded and set in position by
gently pressing with the handle of a trowel. Its inside face shall be buttered with mortar before the next
brick is laid and pressed against it. Joints shall be fully filled and packed with mortar such that no hollow
space are left inside the joints.
6.2.4.3 The walls shall be taken up truly in plumb or true to the required batter where specified. All
courses shall be laid truly horizontal and all vertical joints shall be truly vertical. Vertical joints in the
alternate course shall come directly one over the other. Quoin, Jambs and other angles shall be pro-
perly plumbed as the work proceeds. Care shall be taken to keep the perpends properly aligned within
following maximum permissible tolerances :
(a) Deviation from vertical within a storey shall not exceed 6 mm per 3 m height.
(b) Deviation in verticality in total height of any wall of building more than one storey in height shall
not exceed 12.5 mm.
(c) Deviation from position shown on plan of any brick work shall not exceed 12.5 mm.
(d) Relative displacement between load bearing wall in adjacent storeys intended to be vertical
alignments shall not exceed 6 mm.
(e) A set of tools comprising of wooden straight edge, masonic spirit levels, square, 1 metre rule line
and plumb shall be kept on the site of work for every 3 masons for proper check during the
progress of work.
6.2.4.4 All quoins shall be accurately constructed and the height of brick courses shall be kept uniform.
This will be checked using graduated wooden straight edge or storey rod indicating height of each
course including thickness of joints. The position of damp proof course, window sills, bottom of lintels,
top of the wall etc. along the height of the wall shall be marked on the graduated straight edge or storey
rod. Acute and obtuse quoins shall be bonded, where practicable in the same way as square quoins.
Obtuse quoins shall be formed with squint showing three quarters brick on one face and quarter brick on
the other.
6.2.4.6 All pipe fittings and specials, spouts, hold fasts and other fixtures which are required to be built
into the walls shall be embedded, as specified, in their correct position as the work proceeds unless
otherwise directed by the Engineer-in-Charge.
6.2.4.7 Top courses of all plinths, parapets, steps and top of walls below floor and roof slabs shall be laid
with brick on edge, unless specified otherwise. Brick on edge laid in the top courses at corner of walls
shall be properly radiated and keyed into position to form cut (maru) corners as shown in Fig 6.4. Where
bricks cannot be cut to the required shape to form cut (maru) corners, cement concrete 1:2:4 (1 cement :
2 coarse sand : 4 graded stone aggregate 20 mm nominal size) equal to thickness of course shall be
provided in lieu of cut bricks.
6.2.4.8 Bricks shall be laid with frog (where provided) up. However, when top course is exposed, bricks
shall be laid with frog down. For the bricks to be laid with frog down, the frog shall be filled with mortar
before placing the brick in position.
6.2.4.9 In case of walls one brick thick and under, one face shall be kept even and in proper plane, while
the other face may be slightly rough. In case of walls more than one brick thick, both the faces shall be
kept even and in proper plane.
6.2.4.10 To facilitate taking service lines later without excessive cutting of completed work, sleeves
(to be paid separately) shall be provided, where specified, while raising the brick work. Such sleeves in
external walls shall be sloped down outward so as to avoid passage of water inside.
6.2.4.11 Top of the brickwork in coping and sills in external walls shall be slightly tilted. Where brick
coping and sills are projecting beyond the face of the wall, drip course/throating (to be paid separately)
shall be provided where indicated.
6.2.4.12 Care shall be taken during construction that edges of jambs, sills and projections are not
damaged in case of rain. New built work shall be covered with gunny bags or tarpoulin so as to prevent
the mortar from being washed away. Damage, if any, shall be made good to the satisfaction of the
Engineer-in-Charge.
6.2.4.13 Vertical reinforcement in the form of bars (MS or high strength deformed bars or thermo-
mechanically treated bars as per direction of Engineer-in-Charge)), considered necessary at the corners
and junction of walls and jamb opening doors, windows etc. shall be encased with cement mortar not
leaner than 1:4 (1 cement : 4 coarse sand), or cement concrete mix as specified. The reinforcement
shall be suitably tied, properly embedded in the foundation and at roof level. The dia. of bars shall not be
less than 8 mm and concrete grade shall be minimum 1:3:6 (1 cement : 3 coarse sand : 6 graded stone
aggregate 20 mm nominal size).
6.2.4.14 In retaining walls and the like, where water is likely to accumulate, weep holes, 50 to 75 mm
square shall be provided at 2 m vertically and horizontally unless otherwise specified. The lowest weep
hole shall be at about 30 cm above the ground level. All weep holes shall be surrounded by loose stones
and shall have sufficient fall to drain out the water quickly.
Note : Work of providing loose stone will be payable extra.
6.2.5 Joints
The thickness of all types of joints including brick wall joints and cross joints shall be such that four
course and three joints taken consecutively shall measure as follows:
(i) In case of modular bricks conforming to IS 1077 specification for common burnt clay buildings
bricks, equal to 39 cm.
(ii) In case of non-modular bricks, it shall be equal to 31 cm.
Note : Specified thickness of joints shall be of 1 cm. Deviation from the specified thickness of all
joints shall not exceed one-fifth of specified thickness.
6.2.5.1 Finishing of Joints: The face of brick work may be finished flush or by pointing. In flush
finishing either the face joints of the mortar shall be worked out while still green to give a finished surface
flush with the face of the brick work or the joints shall be squarely raked out to a depth of 1 cm while the
mortar is still green for subsequently plastering. The faces of brick work shall be cleaned with wire brush
so as to remove any splashes of mortar during the course of raising the brick work. In pointing, the joints
shall be squarely raked out to a depth of 1.5 cm while the mortar is still green and raked joints shall be
brushed to remove dust and loose particles and well wetted, and shall be later refilled with mortar to give
ruled finish. Some such finishes are ‘flush’, ‘weathered’, ruled, etc.
6.2.6 Curing
The brick work shall be constantly kept moist on all faces for a minimum period of seven days. Brick
work done during the day shall be suitably marked indicating the date on which the work is done so as to
keep a watch on the curing period.
6.2.7.1 Single Scaffolding: Where plastering, pointing or any other finishing has been indicated for
brick work, single scaffolding may be provided, unless otherwise specified. In single scaffolding, one end
of the put-logs/pole shall rest in the hole provided in the header course of brick masonry. Not more than
one header for each put-log/pole shall be left out. Such holes shall not be allowed in the case of pillars,
brick work less than one metre in length between the openings or near the skew backs of arches or
immediately under or near the structural member supported by the walls. The holes for putlogs/poles
shall be made good with brick work and wall finishing as specified.
6.2.7.2 Double Scaffolding: Where the brick work or tile work is to be exposed and not to be finished with
plastering etc. double scaffolding having two independent supports, clear of the work, shall be provided.
6.2.8 Measurements
6.2.8.1 Brick work shall be measured in cubic metres unless otherwise specified. Any extra work over
the specified dimensions shall be ignored. Dimensions shall be measured correct to the nearest 0.01 m
i.e. 1 cm. Areas shall be calculated to the nearest 0.01 sq mtrs and the cubic contents shall be worked
out to the nearest 0.01 cubic metres.
6.2.8.3 No deductions or additions shall be done and no extra payment made for the following :
Note : Where minimum area is defined for deduction of an opening, void or both, such areas shall
refer only to opening or void within the space measured.
(a) Ends of dissimilar materials (that is, joists, beams, lintels, posts, girders, rafters, purlins, trusses,
corbels, steps, etc.); up to 0.1 m2 in section;
(b) Opening up to 0.1 m2 in area (see Note);
(c) Wall plates, bed plates, and bearing of slabs, chajjas and the like, where thickness does not
exceed 10 cm and bearing does not extend over the full thickness of wall;
(d) Cement concrete blocks as for hold fasts and holding down bolts;
(e) Iron fixtures, such as wall ties, pipes upto 300 mm diameter and hold fasts for doors and
windows; and
(f) Chases of section not exceeding 50 cm in girth.
(g) Bearing portion of drip course, bearing of moulding and cornice.
Note : In calculating area of an opening, any separate lintel or sills shall be included with the size of
the opening but end portions of lintel shall be excluded. Extra width of rebated reveals, if any, shall also
be excluded.
6.2.8.4 Walls half brick thick and less shall each be measured separately in square metres stating
thickness.
Where fractions of half brick occur due to architectural or other reasons, measurement shall be as follows :
6.2.8.6 String courses, projecting pilasters, aprons, sills and other projections shall be fully described
and measured separately in running metres stating dimensions of each projection.
6.2.8.7 Square or rectangular pillars shall be measured separately in cubic metres in multiple of half brick.
6.2.8.8 Circular pillars shall be measured separately in cubic metres as per actual dimensions.
6.2.8.9 Brick work curved on plan shall be measured like the brick work in straight walls and shall
include all cutting and wastage of bricks, tapered vertical joints and use of extra mortar, if any. Brick
work curved on plan to a mean radius not exceeding six metres shall be measured separately and extra
shall be payable over the rates for brick work in straight walls. Nothing extra shall be payable if the mean
radius of the brick work curved in plan exceeds six metres.
6.2.8.10 Tapered walls shall be measured net as walls and extra payment shall be allowed for making
tapered surface for brick work in walls.
6.2.8.11 Brick work with brick tiles shall be measured and paid for separately.
6.2.9 Rate
The rate shall include the cost of materials and labour required for all the operations described above
except the vertical reinforcement and its encasement in cement mortar or cement concrete. The rate
shall also include the following :
(a) Raking out joints or finishing joints flush as the work proceeds;
(b) Preparing tops of existing walls and the like for raising further new brick work.
(c) Rough cutting and waste for forming gables, splays at eaves and the like.
(d) Leaving holes for pipes upto 150 mm dia. and encasing hold fasts etc.
(e) Rough cutting and waste for brick work curved in plan and for backing to stone or other types of
facing.
(f) Embedding in ends of beams, joists, slabs, lintels, sills, trusses etc.
(g) Bedding wall plates, lintels, sills, roof tiles, corrugated sheets, etc. in or on walls if not covered in
respective items and
(h) Leaving chases of section not exceeding 50 cm in girth or 350 sq cm in cross-section.
(i) Brick on edge courses, cut brick corners, splays reveals, cavity walls, brick works curved on plan
to a mean radius exceeding six metres.
6.3.0 The detailed specifications for brick work mentioned in 6.2 shall apply, in so far as these are
applicable. Arch work shall include masonry for both gauged as well as plain arches. In gauged arches,
cut or moulded bricks shall be used. In plain arches, uncut bricks shall be used.
Brick forming skew-backs shall be dressed or cut so as to give proper radial bearing to the end
voussiors. Defects in dressing of bricks shall not be covered by extravagant use of mortar, nor shall the
use of chips or bats etc. be permitted.
After the arch is completed, the haunches shall be loaded by filling up the spandrels upto the crown
level of the arch. Care shall be taken to load the haunches on two sides of the spandrels.
When the arch face is to be pointed (and not plastered), the face bricks shall be cut to proper shape
or moulded, so as to have the joints not more than 5 mm thick. These shall be laid with radial joints to
the full depth of the arch. The voussoirs shall break joints to the full depth of the arch.
In flat arches, bricks shall be laid with radial joints to the full depth of arch and voussoirs breaking
joints with each other. The arch work shall be carried up from both ends simultaneously and keyed in the
centre. The thickness of the joints shall not exceed 5 mm. Flat arches may be used for the sake of
appearance but for purpose of carrying loads of the wall above, these shall be used in conjunction with
relieving arches, lintels placed below.
The shuttering shall be tightened with hard wood wedged or sand boxes, so that the same could be
eased without jerks being transmitted to the arch. The sequence of easing the shuttering shall be got
approved from the Engineer-in-Charge. The shuttering shall be struck within 48 hours of the completion
of the arch but not before 24 hours. This shall be done after the spandrel has been filled in and the arch
loaded.
6.3.4 Measurements
The length of the arch shall be measured as the mean of the extrados and intrados of the arch
correct to a cm. The thickness of the arch shall be measured in multiples of the half brick.
The breadth in the direction of the thickness of wall shall be measured as specified.
The cubical contents shall be calculated in cubic metre, correct to two places of decimal.
For arches exceeding 6 m in spans extra payment shall be made on the actual area of the soffit for
additional cost of centring including all strutting, bolting, wedging, easing, striking and its removal.
6.3.5 Rate
The rate is inclusive of the cost of the materials and labour required for all the operations described
above.
The mortar interposed between the reinforcement bars and the brick shall not be less than 5 mm.
The mortar covering in the direction of joints shall not be less than 15 mm.
6.4.1 Measurements
The length and height of the wall shall be measured correct to a cm. The area shall be calculated in
sq.m. where half brick wall is joined to the main walls of one brick or greater thickness and
measurements for half brick wall shall be taken for its clear length from the face of the thicker wall.
6.4.2 Rate
The rate includes the cost of the materials and labour involved in all the operations described above
except reinforcement which is to be paid for separately.
6.5.0 The work shall be done in the same manner as described in 6.2.4 except that brick tile shall be
used instead of bricks. The measurement and rate shall be same as specified under 6.2.
The thickness of the brick honeycomb work shall be half-brick only, unless otherwise specified.
Openings shall be equal and alternate with half brick laid with a bearing of 2 cm on either side.
6.6.1 Measurements
The length and height shall be measured correct to a cm. Area shall be calculated in square metres
correct to two places of decimal. Honeycomb openings shall not be deducted.
6.6.2 Rate
The rate includes the cost of materials and labour involved in all the operations described above.
6.7.1 In case the height of the bricks of old as well as new work is same, the old work shall be toothed to
the full width of the new wall and to the depth of a quarter of brick in alternate courses. In case the
height of the bricks is unequal, then the height of each course of new work shall be made equal to the
height of the old work by adjusting thickness of horizontal mortar joints in the new wall. Where
necessary, adjustment shall be made equal to thickness of old wall by adjusting the thickness of vertical
joints.
6.7.2 For joining new cross wall to old main walls, a number of rectangular recesses of width equal to
the thickness of cross wall, three courses in height and half a brick in depth shall be cut in the main
6.7.3 Joining of old brick work with the new brick work shall be done in such a way that there shall not be
any hump or projection at the joint.
6.7.4 Measurement
The height and thickness of vertical face in contact with new work shall be measured to the nearest
0.01 m and the area shall be calculated to the nearest 0.01 sqm.
6.7.5 Rate
The rate includes the cost of labour and material involved in all the operations described above.
6.8.0 The specifications described under 6.2 shall apply in so far these are applicable. Mouldings and
cornices shall be made with bricks as specified for brick work. The bricks shall be cut and dressed to the
required shape as shown in the architectural drawings.
6.8.1 Cornices shall not ordinarily project by more than 15 cm to 20 cm and this projection shall be
obtained by projecting each brick course by more than one fourth of the length. For cornices projecting
more than 20 cm and requiring more than quarter bricks projection, metal cramps shall be used and paid
for separately.
6.8.2 Corbelling shall be brought roughly to shape by plastering with the specified mortar. When the
mortar is still green, the mouldings shall be finished straight and true with the help of metal templates.
6.8.4 Measurements
For the purpose of measurements, the sectional periphery of mouldings and cornices (excluding the
portion in contact with wall) shall be measured in centimetres and length in metres (fig. below). The girth
and length shall be measured correct to a cm. No deduction shall be made from the masonry of wall for
the bearing of the moulding and cornices.
Note: Tolerance and Dimensions for selected hand moulded bricks + 4 mm in length and + 3 mm in
width and thickness).
6.10.3 Sampling
As per Para 6.1.3 and 6.1.3.2.
Mortar, Soaking of Bricks and laying shall be as specified in Para 6.2.2, 6.2.3 and 6.2.4 respectively.
6.10.5 Joints in the exposed brick work shall be truly horizontal and vertical and kept uniform with the
help of wooden or steel strips. The thickness of joints shall be as per 6.2.5.
6.10.6 Curing and scaffolding shall be as specified in 6.2.6 and 6.2.7 to 6.2.7.2 respectively.
6.10.7 Measurements
Exposed brick work in face using machine moulded bricks and selected hand moulded bricks shall
be measured separately and the measurement shall be as specified in 6.2.8.
Length of the Bonding units will be sum of thickness of both leaves plus width of cavity if the leaves
are 75 mm or 115 mm. If the leaves are more than 115 mm thick, then the length of a unit will be 2 ×
115 + width of cavity as shown in Fig. 6 of Chapter 6. Precast RCC units shall be provided with 2 no., 6
mm mild steel reinforcement bars tied with 2 no. 3 mm. dia. M.S. wire/hard drawn wire cross bars (As
shown in Fig. 6 of Chapter 6) placed in the centre of units.
Cement concrete used in the bonding units shall not be leaner than 1:3:6 (1 cement : 3 coarse sand :
6 graded stone aggregate 20 mm nominal size).
6.11.3 Spacing
Metal ties/bonding units shall be spaced not more than 90 cm apart horizontally and 45 cm vertically
and staggered in each course. Additional ties shall be used near openings.
6.11.4 Restrictions
Cavity walls shall not normally be built more than 7.5 metres in height and 9 metres in length. Where
large lengths and heights are desired, the wall shall be divided into panels with strengthening measures
such as pillars etc. Cavity shall be covered at the top with at least two courses of masonry unit and/or a
coping over it.
Adoption of cavity walls is not recommended when heavy concentrated load from beam etc. are to
be supported by walls.
6.12.2 Dimensions
As per the item nomenclature.
6.12.3 Laying
(i) Panels are stored in a dry place and water should not come in contact with panels during or after
construction. If the panels get wet, they should be dried before use.
(ii) The floor should be perfectly level before laying the first course. All panels must be properly
aligned to the plumb. Successive layer of panels must be alternatively staggered so that vertical
joints are not in the same line.
(iii) The recommended quantity of Gypsum Bonding Plaster must be used for joints and filling the
grooves made for conduits, pipelines, etc. Excess Bonding Plaster must be scooped and
removed, so that the joints and the places where the grooves are filled in are flush and even.
(iv) The walls should be dry and sanding done properly especially at joints before the primer is
applied so that the surface is even and joints will not be visible after painting. Avoid chasing with
chisel and hammer. Use electrical saw or grooving tools for conduiting etc.
(v) The recommended span of walls is maximum 6 meters and maximum height is 4.5 meters.
(vi) Gypsum panel can easily be cut with coarse tooth hand saw, electric jigsaw, etc. The panels can
be cut, sawn, drilled, milled or dowelled on the job. For concealed piping and conduit, the depth
of groove should not exceed 50 mm. Hammer and chisel techniques to form chases must be
avoided.
(vii) Sanding: This application is to make the surface level without undulations. To make the gypsum
wall surface level (in particular at joints, where there is excess bonding plaster), do sanding with
sand paper at joints and other places, wherever you find uneven surface, otherwise joints will be
visible after painting. It is important to sand all joints uniformly.
(viii) Primer Application: The purpose of the primer is to give a better adhesion to the paint and also
to reduce consumption of paint on the wall. Water thinable primers shall be used only.
6.12.4 Measurements
The length and height shall be measured correct to a cm. Area shall be calculated in square meters
correct to two place of decimal. No deduction shall be made for ducts, opening made from the standard
size of panel.
6.12.5 Rate
The rate shall include the cost of materials and labour involved in all the operations described above.
6.13.1 The edging shall be of bricks of class specified in the item. The specifications of bricks shall be
as described in 6.1. Trenches of required depth and width shall first be made along the edge of the plinth
protection to receive the bricks for edging. The bed of trenches shall be compacted to a firm and even
surface. The brick shall be laid true to line in cement mortar 1:4 (1 cement: 4 fine sand) with length
parallel and butting the plinth protection. The top face of the brick edging shall be in one level to conform
to the finished level of the plinth protection adjacent to the edging. After the concreting is done, no
portion of the brick edging shall project above the adjacent concrete surface. Cement mortar shall
conform to the specification described in chapter 3.0.
6.13.2 Measurements
The brick edging shall be measured in running metere correct a cm.
6.13.3 Rate
Rate shall include the cost of materials and labour involved in all operations.
Non-Modular Bricks
For class 10
Length (4520 to 4680) mm (4600 ± 80 mm)
Width (2240 to 2160) mm (2200 ± 40 mm)
Height (1440 to 1360) mm (1400 ± 40 mm) for 70 mm high bricks
(640 to 560) mm (600 ± 40 mm) for 30 mm high bricks
1 to 2 CM
4 CM
'A' Measurement of Length
10 CM
B-1. Specimen
Five whole bricks shall be taken from the samples as specimens for this test. Length and width of
each specimen shall be measured correct to 1 mm.
B-2. Apparatus
The apparatus consists of compression testing machine, the compression plate of which shall have a
ball seating in the form of portion of a sphere the centre of which shall coincide with the centre of the
plate.
B-3. Procedure
(a) Pre-conditioning: The specimen shall be immersed in the water for 24 hours at 25º to 29ºC. Any
surplus moisture shall be allowed to drain at room temperature. The frog of the bricks should be
filled flush with mortar 1:3 (1 cement : 3 clean coarse sand of grade 3 mm and down) and shall
be kept under damp jute bags for 24 hours, after that these shall be immersed in clean water for
three days.
After removal from water, the bricks shall be wiped out of any traces of moisture.
(b) Actual Testing: Specimen shall be placed with flat faces horizontal and mortar filled face upward
between three 3 ply plywood sheets each of thickness 3 mm and carefully centred between
plates of the testing machine. Plaster of Paris can also be used in place of plywood sheets to
ensure a uniform surface.
Load shall be applied carefully axially at uniform rate of 14 N/mm2 per minute till the failure of the
specimen occurs.
In case the compressive strength of any individual brick tested exceeds the upper limit of the
average compressive strength specified for the corresponding class of brick, the same shall be limited to
the upper limit of the class specified in 6.1.2 for the purpose of calculating the average compressive
strength. Compressive strength of all the individual bricks comprising the sample shall be averaged and
reported.
C-2. Apparatus
A balance required for this test shall be sensitive to weigh 0.1 percent of the weight of the specimen.
C-3. Procedure
(a) Pre-conditioning: The specimen shall be allowed to dry in a ventilated oven at a 110°C to 115°C
till it attains a substantially constant weight. If the specimen is known to be relatively dry, this
would be accomplished in 48 hours, if the specimen is wet, several additional hours may be
required to attain a constant weight. It shall be allowed to cool at room temperature. In a
ventilated room, properly separated bricks will require four hours for cooling, unless electric fan
passes air over them continuously in which case two hours may suffice.
The cooled specimen shall be weigh (W1) a warm specimen shall not be used for this purpose.
(b) Actual Testing: Specimen shall be completely dried before immersion in the water. It shall be
kept in clean water at a temperature of 27°C ± 2°C for 24 hours. Specimen shall be wiped out of
the traces of water with a damp cloth after removing from the water and then shall be weighed
within three minutes after removing from water (W2).
⎛ W − W1 ⎞
WaterAbsorption = ⎜ 2 ⎟ ×100
⎝ W1 ⎠
D-2. Apparatus
Apparatus required for this test shall be a shallow flat bottom dish containing distilled water.
(b) SLIGHT: When not more than 10 per cent of the area of the brick is covered with a thin deposit of
salts.
(c) MODERATE: When there is heavier deposit and covering upto 50% of the area of the brick
surface but unaccompanied by powdering or flaking of the surface.
(d) HEAVY: When there is a heavy deposit of salts covering 50% or more of the brick surface but
unaccompanied by powdering or flaking of the surface.
(e) SERIOUS: When there is heavy deposit of salts, accompanied powdering and/or flaking of the
surface and tending to increase in the repeated wetting of the specimen.
COPING
OVERSAILING COURSE
MUD PHUSKA
TILES
SLAB
CORNICE
CORBLES
STRING COURSE
WINDOW SILL
A. PIER (1)
B. PIER (2)
FLOORING
DPC
100 150
100
200
1 X 1½ BRICK
50 100 200
100
200
1 X 2 BRICK
200
1 X 2 ½ BRICK
100
50 100 200
300
1 ½ X 2 BRICK
100
100 50 200
100 50
400
2 X 2 BRICK
150 100
150
300
100
1 ½ X 1 ½ BRICK
200
100
1 BRICK WALL
200 100
100
Q UEEN
CLOSER
200
1½ BRICK WALL
200
200
2 BRICK WALL
200
100 Q UEEN
CLOSER
200
1 BRICK WALL
200 100
100
300
200
1½ BRICK WALL
100 200 100
100
400
200
2 BRICK WALL
200 300
70 20
300
70 50
60 40
200
70 80
70
60 150
200 60 70 70 70 60 70
SPANDREL KEY
EXTRADOS
OR BACK
T SOFFIT OR
ES S SPRINGING INTRADOS
O W SOI R POINT
FACE JOINTS NOT L OU S JOINTS VARYING
V FROM 5 TO 15 MM
MORE THAN 5 MM
THICK THICK
ABUTMENT.
PIER SPAN
CIRCULAR ARCH
SPAN
SPAN
Coping
roof level
M M
Metal Tie or
bonding unit
Metal tie of
bonding unit
Cavity
(c) PLAN AT MM
115 mm 75 mm or less
outside face
(d) PLAN AT MM
75 mm 75 mm
(e) PLAN AT MM
Note :
(1) Only one of the alternative a, b, c, d or e shall be applicable in each case.
(2) Ties shall be placed sloping towards exterior side.
Drawing not to Scale
All dimensions are in mm
Fig. 6.6 : Brick Work in Cavity Walls
(Fig. 6.6 Contd.)
450
450
450
450
900 mm 900 mm
(f) ELEVATION
Course
Height
20 cm
W id
th
6 mm
M.S. Bar
L
L = Thickness of Walls + Cavity L = Sum of Two Leaves + Cavity
> 2 x 115 + Cavity (for walls 115 mm or more) > 2 x 115 + Cavity (for walls 115 mm or more)
STONE WORK