SCHEDULE “Q”
QUALITY ASSURANCE AND CONTROL, INSPECTION AND TESTING
1. GENERAL
1.1. For the purposes of this Schedule “Q”, SAUDI ARAMCO shall have
the same meaning as COMPANY for contracts with Aramco Services
Company and Aramco Overseas Company.
1.4. CONTRACTOR shall inspect, test and accept all parts of the WORK
as defined in Schedule “B”, including its subcontractors' work, in
conformance with all drawings, specifications and standards
applicable to the WORK.
Q-1 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
3.1. CONTRACTOR shall plan, organize, control and execute all WORK
in accordance with CONTRACTOR’s Quality Plan(s), Inspection and
Test Plans (ITP) and documented procedures. The Quality Plan(s)
Q-2 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
3.4. CONTRACTOR shall not place purchase orders for any equipment or
materials assigned an inspection level in Attachment VI of this
Schedule “Q” prior to SAUDI ARAMCO’s approval of the
Procurement Quality Plan.
3.8. The Quality Plan(s) shall contain organization charts that show
reporting relationships from the inspector through the level above the
Q-3 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
4.3. Within seven calendar days of the effective date of this Contract,
CONTRACTOR shall designate the QA or QA/QC Manager for this
Contract. The QA Manager shall be assigned to the WORK through
Mechanical Completion.
5. MANAGEMENT REVIEW
Q-5 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
Q-6 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
6.5.2. The location and the method of identification shall not affect
the function or quality of the item being identified. The
procedure shall require that verification of correct identification
of material, parts and components be made and documented
prior to installation.
6.7. Waivers
Q-9 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
Q-10 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
8.8. Welding rejection rate, reported on a per joint basis for piping,
structural, and alloy welds. A chart showing the historical
performance during the project shall be included.
Q-11 of 11
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
QUALIFICATION REQUIREMENTS
Q-I-3 of 4
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
14. Quality Control Manager: Shall have demonstrated knowledge and training
in the use of measuring and test equipment routinely used in conducting
inspections. He shall have a university degree or equivalent and seven
years inspection experience or a high school diploma with ten years
inspection experience directly relating to supervision of construction
activities in the oil, gas and petrochemical industries.
15. Procurement Quality Control Supervisor: Shall have demonstrated
knowledge and training in the use of measuring and test equipment routinely
used in conducting inspections at manufacturing and fabrication sites. He
shall have a university degree or equivalent and seven years inspection
experience or a high school diploma with ten years inspection experience
directly relating to supervision of vendor inspection activities in the oil, gas
and petrochemical industries.
16. Vendor Inspector: Shall have 10 years Quality Assurance/Quality Control
(QA/QC) inspection experience in manufacturing plants, including 4 years of
this inspection experience in the specific commodity and processes to be
inspected. He must understand national codes and fabrication methods;
and shall be qualified to perform specialized inspection and testing of
petrochemical processing materials, plant surveys as required to verify
supplier compliance with purchase order and SAUDI ARAMCO’s
Engineering Standards. Where NDT forms part of the WORK, and Inspector
is required to review, audit or ensure NDT programs and results, he shall
have been previously qualified and certified to a minimum ASNT Level II in
the relevant method(s). When performing, reviewing, ensuring or auditing
Nondestructive Testing in VT, MT, PT, RT or UT, he shall be certified to a
minimum ASNT Level II in the relevant method(s). When performing,
reviewing, ensuring or auditing Radiographic Testing Film Interpretation
(RTFI), Inspector shall be certified in RTFI.
17. Quality System Auditors: Shall have 10 years Quality Assurance/Quality
Control (QA/QC) inspection or auditing experience in manufacturing plants.
Auditors shall be qualified as stated in ISO-10011 and competent in the
discipline being audited, familiar with Quality System standards and be able
to exercise judgment against the criteria of the standards. Auditors must be
able to communicate clearly in writing and orally. Auditors shall have
satisfactorily completed a training course and passed the course
examination. Auditors shall have participated in a minimum of four audits for
a total of at least 20 days including documentation review, actual audit
activities and audit reporting.
END OF SCHEDULE “Q” ATTACHMENT I
Q-I-4 of 4
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
CONTRACTOR shall comply with all applicable SAUDI ARAMCO Material System
Specifications (SAMSS), SAUDI ARAMCO Engineering Standards (SAES), and
other SAUDI ARAMCO standards and specifications including, but not limited to the
following:
Q-II-1 of 1
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
3. CONTRACTOR shall prepare detailed Inspection and Test Plans (ITPs) for all
equipment and materials assigned a level 2, 3, or 4 in Attachment VI of this
Schedule “Q, and for any other equipment deemed necessary by
CONTRACTOR. CONTRACTOR shall review the QA/QC requirements in all
applicable SAUDI ARAMCO standards and procedures listed in Attachment II
to this Schedule “Q” and include appropriate QA/QC requirements in the ITPs.
Each ITP shall identify the inspection level and detail all witness, hold and
certification review points as specified in the each SAUDI ARAMCO Form175
(Inspection Requirements).
4. Supplier Selection
4.2. CONTRACTOR shall notify SAUDI ARAMCO at least two weeks ahead
of all planned supplier surveys.
Q-III-2 of 6
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
5.4. SAUDI ARAMCO shall have access to all purchase order inspection
report files.
Q-III-3 of 6
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
6.4. CONTRACTOR shall ensure that all suppliers and manufacturers have
and maintain acceptable QA/QC programs as identified in the relevant
ISO-9000 Series standards.
Q-III-4 of 6
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
8.2. CONTRACTOR or its approved third party inspector shall schedule and
perform source inspection at supplier and sub-supplier fabrication sites
as specified in the approved Inspection and Test Plans.
Q-III-5 of 6
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
10.2. In cases where the supplier is responsible for export packing, the final
disposition report shall be prepared after export packing has been
inspected and accepted by CONTRACTOR.
Q-III-6 of 6
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
2.1. One month prior to the start of the applicable WORK, CONTRACTOR
shall submit for review and approval a detailed Inspection and Test Plan
(ITP) for all construction processes to be executed by CONTRACTOR or
subcontractors. CONTRACTOR shall review the quality requirements in
all applicable SAUDI ARAMCO standards and procedures listed in
Attachment II to this Schedule “Q” and include appropriate QA/QC
requirements in each ITP. Each ITP shall detail all review, witness, hold
and certification review points for SAUDI ARAMCO, CONTRACTOR, and
subcontractors as specified in this Contract. It shall also include the
methods, extent and timing for examinations, measurements or tests.
2.3. Inspection and Test Plans and related procedures shall include
provisions to ensure that test prerequisites have been met, that adequate
Q-IV-1 of 4
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
2.4. Revision Control – CONTRACTOR shall revise each ITP and obtain
approval for such revisions from the Company Representative as needed
throughout the WORK. CONTRACTOR and subcontractor inspectors
shall maintain copies of every currently approved subcontractor ITP.
Personnel
Work Procedure Personnel
Qualification
Approval (A) or Qualification
Special Process Procedure
Review (R) Approval
Approval
Required Required
Required
Nondestructive
A Yes Yes
Testing/examination
Gasket Installation R No No
Q-IV-2 of 4
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
Concrete Installation R No No
Hydro-testing A No No
Heat Treatment A No No
Refractory Installation A No No
5.1. CONTRACTOR shall submit its test reports and its subcontractors test
reports to the Company Representative as specified by the applicable
SAUDI ARAMCO standards. The CONTRACTOR shall review and
approve its subcontractor’s test reports prior to submittal.
Q-IV-3 of 4
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
tests for each system, when it is scheduled, when it was completed, and
any non-conformances discovered during the test or inspection.
Inspection status reports shall be kept current and shall be available for
SAUDI ARAMCO’s review at all times.
6. Receiving Inspections
CONTRACTOR shall inspect all incoming equipment for damage and for
conformance to all applicable requirements, including the supplier inspection
release with verified Material Test Reports (MTR). If the equipment does not
have the required inspection release and MTR, CONTRACTOR shall verify and
document the compliance of the equipment with applicable standards and
specifications prior to release to be used as part of the WORK. Data concerning
receiving inspections shall be included on the Monthly Materials Procurement
Status Report as specified in Schedule “G”.
Q-IV-4 of 4
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
Subsequent
First Submittal to SAUDI
No. Title submittals to
ARAMCO
SAUDI ARAMCO
1. Quality Plan. 15 calendar days prior to the
Paragraph 3.2 of Schedule “Q” start of WORK or 45 calendar Within 7 calendar
days after the effective date of days of each
this Contract, whichever is revision
earlier
2. QA/QC Personnel or Agency Prior to bringing
Qualifications Prior to assignment of new QA/QC
Paragraph 4.4 of Schedule “Q” personnel on the project personnel on the
project.
3. Quality Audit Schedule.
Within 7 calendar
Paragraph 5.3.2 of Schedule Submitted with Quality Plan
days of revisions
“Q”
4. Audit Report Within fourteen (14) calendar
Paragraph 5.3.5 of Schedule days of completion of the
“Q” scheduled audit and re-audit.
5. Inspection Schedules Fourteen (14) calendar days
Paragraph 6.4 of Schedule “Q” before the start of any related Updated Weekly
activities
6. CONTRACTOR, Vendor and
Within 48 hours of reporting Notification of
Subcontractor NCR’s
each non-conformance clearance required
Paragraph 7.2 of Schedule “Q”
7. NCR Summary Weekly for the
Paragraph 7.2 of Schedule “Q” After the first NCR is issued Project Progress
Meeting
8. Quality Management Report Sixty (60) calendar days after
Paragraph 8 of Schedule “Q” the effective date of the Monthly
Contract
9. Inspection/Fabrication Status
One week after the first
Report
purchase order is awarded for Weekly
Paragraph 5.3 of Attachment
the Contract
III
10. Inspection Assignment
Twenty one (21) calendar days
Package Paragraph 8.1 of
prior to pre-inspection meeting
Attachment III
11. Preinspection Meeting
Ten (10) calendar days after
Reports Paragraph 8.3 of
preinspection meeting
Attachment III
12. Vendor Inspection Reports Ten (10) calendar days after Ten (10) calendar
Paragraph 8.3 of Attachment the first inspection visit for days after each
III each supplier inspection visit
Q-V-1 of 2
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
Q-V-2 of 2
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
1.1. The following system of coding the level of planned inspections shall be
used to define the inspection requirements. The inspection levels
specify the minimum amount of inspection coverage deemed necessary
by SAUDI ARAMCO to ensure that a product or service conforms to
specifications at a specific supplier’s and/or sub-supplier’s factory or
fabrication site. The following five levels of inspection shall be used:
1.2.1. For equipment items not identified on the Master Equipment List,
the following inspection levels apply:
1.2.2. For pipe, valves and fittings, the following inspection levels apply:
Q-VI-1 of 2
CR, MP-IK-LS, MP-IK-LSPB
OFF-IK-LSPB, OFF-OK-LSPB
OFF-IK-LS, OFF-OK-LS
09/00
CONTRACT NO.
Civil/Structural
Mechanical
Welding