REVIEW QUESTIONS
I. SECTION ONE
Choose the best answer per question:
1. What is a common result of poor project planning?
a) Wasted effort
b) Lost time
c) Increased cost
d) All of the above
2. You are a project manager newly assigned to a large project for your organization. The project charter
has been signed, and the stakeholders have been identified. What should you do next?
a) Ask appropriate team members to submit WBS input
b) Initiate the scope planning process
c) Start the develop project management plan process
d) Begin the activity definition process
3. As project manager, you are about to start the define scope process. You have the project charter and
the organizational process assets list. Because there are no change requests in your project at this point,
what must you have before you begin?
a) Product analysis
b) Requirements documentation
c) Updates to project documents
d) WBS
4. A project manager is leading a project to investigate the feasibility of constructing a dam to generate
hydroelectric power. The project needs to be analyzed from technical, economic, and social points of
view. The project manager has created the project charter on behalf of the project sponsor, and it is now
approved. Which of the following processes should be performed next?
a) Develop Project Management Plan
b) Identify Risks
c) Identify Stakeholders
d) Develop Project Charter
5. You are managing a software upgrade project for your company. Your project sponsor has a great deal
of authority regarding project decisions, but you recently discovered that he doesn't have much interest
in your project. To complete the project successfully, you need your project sponsor's continuous
support. What stakeholder management strategy should you use with your project sponsor?
a) Keep the sponsor satisfied
b) Manage the sponsor closely
c) Monitor the sponsor's actions
d) Keep the sponsor informed
6. You are a project manager for a new product development project that is in the planning stages. Your
project team has just finished creating the activities list and is now in the process of identifying and
documenting relationships among the project activities. While meeting with your project team, you
notice that a series of activities can be done in parallel but must finish in a specific sequence. Your team
is debating which type of activity sequencing method to use. What would you tell them?
a) Activities diagramming method
b) Precedence diagramming method
c) Project schedule network diagram
d) Critical path method
7. You are working with your team on estimating how much time each activity will take. One of the
documents you are using contains information on categories of labor, material, and equipment required
to complete your project. You are also interested to see skill levels of your labor, any certifications
required, and grade levels of your supplies. Which of the following documents would you primarily
refer to for this purpose?
a) Resource breakdown structure
b) Organizational breakdown structure
c) Work breakdown structure
d) Risk breakdown structure
8. During an inspection of a project deliverable, the team detects the same defect in the deliverable that
has already been identified during a previous inspection. The project manager is confused how this
could have happened since a change request was approved to correct the defect. After discussing the
issue with the team, the project manager learns that the team never implemented the approved change
request. What could have helped prevent this situation?
a) Manage Communications
b) Monitor Communications
c) Manage Stakeholder Engagement
d) Plan Communications Management
11. The project you have been managing for several years is now moving towards completion. Some of the
project deliverables have been contracted to vendors. You begin to close the project and want to make
sure all activities necessary for project closure are properly completed. Which of the following activities
would you not perform as part of this process?
a) The project manager should not have submitted the change request since the risk was
unknown.
b) The project manager did not account for all possible risks during project planning.
c) The project manager should not have included the schedule baseline in the change request.
d) The project manager used contingency reserves instead of management reserves.
13. You have recently been assigned to lead a project that is halfway into execution. The project has many
stakeholders, and you are trying to determine how to engage them effectively. Which of the following
will best help you in this effort?
15. You are managing the development of a new blood pressure cuff for a customer who provided you with
the objectives and description of the cuff. You and your team are decomposing the customer's high-
level requirements to the level of detail needed to design the blood pressure cuff and therefore define
the scope of the product. In what activity are you involved?
16. A project manager is conducting the initial process of identifying stakeholders for a new infrastructure
development project. The project manager has just compiled a list of potential stakeholders' names.
What should the project manager do next?
17. You are leading a project to develop a new web application. Together with your project team you
reprioritize the product backlog, determine velocity for the past iterations, and adapt your work plans
accordingly. Additionally, you facilitate retrospectives every two weeks. Which of the following
processes describes the work you are performing?
a) Monitor Risks
b) Manage Quality
c) Control Schedule
d) Develop Schedule
18. During a recession, a project manager posts a positive risk that in the current economic environment,
cheaper resources may become available. On the way into work, the project manager hears about a
competitor going out of business and contacts the competitor to acquire some equipment, materials,
and supplies at a fraction of their normal value. What is the project manager doing?
a) Assess any available project documentation and lessons learned from past projects
b) Perform stakeholder analysis to develop a list of stakeholders with relevant information
c) Submit a change request to update the stakeholder engagement plan
d) Categorize the stakeholders' stakes including interest, rights, ownership, and contribution
20. Your company was recently awarded a software development project, and you have just completed the
scope management plan. The sponsor reviews the plan and states that the client specified the use of
Scrum, while the plan indicates a waterfall approach. Which component of the project management
plan did you most likely overlook while developing the scope management plan?
28. The common technique used in project planning, scheduling and monitoring is PERT or CPM. Discuss
about each of their techniques.
34. Define the project management life cycle and clearly describe its functionalities
Success!
“Success provides a veritable arsenal of miracle solutions to increase
your productivity and minimize your stress. This will help you lower your internal
pressure cooker, eliminate the friction of any relationship and get more job satisfaction
than ever while building a level of calm and confidence that you have never experienced before”