Analysis of Cementing Turbulators
Analysis of Cementing Turbulators
Analysis of Cementing Turbulators
HENDRY HELMIYANTO
071001400073
http://sci-hub.se/https://doi.org/10.2118/19542-PA
http://sci-hub.se/https://doi.org/10.2118/950053-G
http://sci-hub.se/https://doi.org/10.2118/79907-MS
http://sci-hub.se/https://doi.org/10.2118/12454-MS
http://sci-hub.se/https://doi.org/10.2118/12603-MS
http://sci-hub.se/https://doi.org/10.2118/11981-PA
http://sci-hub.se/https://doi.org/10.2118/194186-MS
http://sci-hub.se/https://doi.org/10.2118/3809-MS
http://sci-hub.se/https://doi.org/10.2118/936187-G
http://sci-hub.se/https://doi.org/10.2118/11499-MS
http://sci-hub.se/https://doi.org/10.2118/25546-MS
http://sci-hub.se/https://doi.org/10.2118/904-PA
http://sci-hub.se/https://doi.org/10.2118/9597-PA
http://sci-hub.se/https://doi.org/10.2118/39005-MS
Analysis of Cementing Turbulators
hole.
http://sci-hub.se/https://doi.org/10.2118/19542-PA
Background
Casing turbulators were first evaluated in 1986. On the first well,19 turbulators
were run in three separate intervals; two are discussed here. These two intervals
were widely spaced in two different wellbore diameters. Fig. 2 shows the wellbore
arrangement and the cement-bond, sonic, and gamma ray logs for the first
interval. Thirteen turbulators with 6-in.-OD blades were run on 4th-in. casing.
One turbulator was run per 40-ft joint across 500 ft of open hole. The bottom
turbulator was at 18,762 ft, and casing was set at 19,602 ft. The pipe amplitude
curve on the CBL in Fig. 2 shows much better bonding opposite the turbulators
compared with the interval below 18,762 ft. The hole size throughout the interval,
as indicated by the caliper log, varied from 6 1/5 in. (bit size) to > 16 in. The best
bonding is achieved in the near-gauge hole for the 6- in.-OD turbulator blades,
demonstrating that the effect of the turbulator diminishes as the ratio of hole size
Three M4-in.-OD turbulators were also run farther up the hole in the same well. In
this case, the turbulators were inside a 7O/S-in. drilling liner with an approximate
ID of 6Ys in. The CBL pipe amplitude curve, shown in Fig. 3, indicates good
bonding in the 15,525- to 15,615-ft interval opposite the turbulators. Bonding was
poor above and below this interval where turbulators were not run. Prompted by
the good results obtained on the first well, turbulators were tested a second time
on another well (Fig. 4). On this second well, 3,500 ft of7-in. liner was run to
17,988 ft in 8lh-in. hole and equipped with 81 turbulators with 8I,4-in.-OD blades.
Turbulators were run one per 40-ftjoint from 14,454 to 17,956 ft. The CBL pipe
representative of the entire section where turbulators were used. In this case, good
bonding was realized even though the hole size ranged from 9 to 10 in. across the
interval.
The field evidence clearly indicates that use of casing turbulators on liners and
casing strings improves mud displacement and thus cement bonding. The
following sections outline the degree of influence the turbulator has on the cement
flow and provide techniques for proper turbulator placement and pump rates for
Introduction
around the casing by the blades, thereby flushing the narrow side
swirlflow.
flow passing the turbulator. The effective swirl length is the axial
distance along the casing annulus where the flow angle remains
efficiency
turbulator blade.
length
explained several analyzes and arguments well with several images and
I agree with the first argument because this has been proven in Evidence that the
field clearly shows that the use of a turbulator casing on the liner and casing string
increases the transfer of sludge and thus binds cement. The following section
describes the level of influence of the turbulator on cement flow and provides
techniques for proper turbulator placement and pump speed for maximum fluid
displacement. I agree with the second argument because it also aims to extend the
I disagree with the last opinion because indeed in increasing the level of
turbulence in the liquid immediately after the turbulator, the increase is not